SlideShare una empresa de Scribd logo
1 de 17
Descargar para leer sin conexión
1
CHAPTER 1
INTRODUCTION
1.0 INTRODUCTION
Gas insulated substations (GIS) have been used in power systems
over the last three decades because of their high reliability, easy
maintenance, small ground space requirement etc. In India also, a few
GIS units are under various stages of installation.
The basic insulation level (BIL) required for a gas insulated substation
(GIS) is different from that of the conventional substation because of
certain unique properties of the former. Gas insulated bus has a surge
impedance (70Ω) more than that of the conventional oil filled cables, but
much less than that of an over head line (300Ω - 400Ω). Further, the
average bus run for a compact GIS is much less than that for the
conventional station. In addition, the GIS is totally enclosed and
therefore is free from any atmospheric contamination. Hence, in general
the GIS permit lower BIL rating than the conventional one. However the
life of GIS is affected by several factors such as: conductive particles,
particle discharges and contamination (decomposition products,
moisture, etc.). Conductive particles inside the enclosure are known to
reduce the breakdown level of Gas insulated systems. Partial discharges
can develop from conductive particles, contamination, and defects during
the manufacturing process, etc.
2
The GIS require less number of lightning arresters than a
conventional one. This is mainly because of its compactness. The basic
consideration for insulation coordination is V-T characteristic. The V-T
characteristic of SF6 is considerably flat compared to that of air. Air can
withstand to very high voltages for very short time. However, as the
duration of voltage increases, the withstand voltage falls off considerably.
On the other hand, SF6 exhibits a flat characteristic, thus the ratio of
basic lightning impulse level is close to unity for GIS, whereas for the
conventional substations this ratio varies between 0.6 and 0.86.
Although GIS has been in operation for several years, a lot of
problems encountered in practice need further understanding. Some of
the problems studied are:
a. Switching operations generate very fast transient over
voltages (VFTOS)
b. VFTOS may cause secondary breakdowns inside a GIS and
Transient Enclosure Voltages (TEV) outside the GIS
c. Prolonged arcing may produce corrosive / toxic by products
d. Support spacers can be weak points when arc by products
and metallic particles are present
e. From the reliability point of view, partial discharge detection
is important. The methods of detection are of acoustic
system and electric systems etc. These methods lack quality
control.
3
For these reasons, VFTOS generated in a GIS should be considered as
an important factor in the insulation design. In a GIS, Very Fast
Transient Overvoltages (VFTOS) are caused by two ways:
a. Due to switching operations and
b. Line to enclosure faults.
The switching operations may be dis-connector switch, circuit breaker
or earth switch. Since, the contact speed of disconnector switches are
low, restriking occurs many times before the interruption is completed.
Each restrike generates very fast transient over voltages with different
levels of magnitude. Further, disconnector switches are used primarily to
isolate the operating sections of an HV installation from each other as a
safety measure. Beyond this, they must also be able to perform certain
switching duties, such as load transferred from one bus bar to another
or disconnection of bus sections, circuit breakers etc.
During switching operations, voltage collapse across the contacts take
place within 3 to 20 nanoseconds depending on the system voltage, gas
pressure, field intensity etc. Once this short time rise pulse starts at
switching contacts, it travels along gas bus duct in either direction and
gets reflected at different terminations. The superimposition of system
with reflected pulse develops over voltages in GIS. These over voltages
have been called as Very Fast Transient Over voltages (VFTOS), because
of their very high frequency components in the range of MHz. The main
problems associated with the VFTOS are as follows:
4
1. Flash over to ground at the disconnector switch contacts
2. Failure of electronic control circuits connected to GIS due to
electro magnetic interference of VFTOS
3. Di-electric strength is reduced under VFTOS, if non-uniform
electric field is formed by the particles (mainly metallic)
4. Effect on equipments such as bushing, power transformer
and instrument transformers
5. Transient Enclosure Voltage (TEV) on external surface of the
sheath. This may cause flashovers to nearby grounded
objects
For the above reasons, VFTOS generated in GIS should be considered
as an important factor in the insulation design of not only gas-insulated
components, but also for the entire substation. The levels and waveforms
of VFTOS are determined by the design of the substation. To calculate
the levels and waveforms of VFTOS, the Pspice/MATLAB is used. In
Pspice/MATLAB simulation, a suitable equivalent circuit is necessary for
each component of the substation.
1.1 GAS INSULATED SUBSTATIONS
SF6 gas insulated high voltage switchgear has been in commercial
operation for more than 30 years. Continuous technological and design
improvements of all the components during the course of the time are
characterized by appreciable savings in area and volume occupied by the
substation. Gas insulated substations are in service up to the highest
5
voltage of 800 kV, meeting almost all the requirements in urban,
industrial as well as rural areas. In the initial stages, the new SF6 gas
insulated substations were almost exclusively used where space
limitations, site restrictions or exponential ambient conditions made it
difficult to use conventional air insulated substations. However, over the
last 30 years, GIS at voltage up to 800 kV in various station
configurations and with various performance requirements, have been
installed in increasing numbers worldwide.
The modular of design of GIS offers a high degree of flexibility to meet
layout requirements of both substations, as well as power station
switchgear, making efficient use of available space. GIS technology has
reached a stage of application and a wide range of GIS equipment up to
highest voltage of 800 kV is available with many unique features. They
are:
1. Wide spread application of aluminum enclosure materials for
standardized component models for all voltage ranges
2. The light weight enclosures have good conductivity, low
eddy-current losses and a high resistance to corrosion
3. Easy handling, as well as reduced stresses on foundation
and support structure are additional features
4. Standard arrangements can be easily modified and extended
with good co-ordination between the manufacturer and the
user.
6
5. A gas- tight barrier insulator in switchgear serve for the
separation of gas compartments and prevents neighbouring
switchgear parts from being affected during maintenance.
A typical Gas insulated substation is shown in Fig.1.1.
Fig.1.1 Gas Insulated Substation
The Gas insulated substation shown in above figure comprises the
following components:
1 Circuit breaker
2 Disconnector switch
3 Earthing switch
4 Current transformer
5 Voltage transformer
6 Bus bar & connectors
7
7 Power transformer
8 Surge arrester
9 Cable termination
10 SF6 / air or SF6 / oil bushing
1.1.1 Advantages of GIS over the conventional open air substation
The application of GIS during the last fifteen years has been very
rapid. The rapid growth in GIS application is due to the following special
advantages:
1. Area and volume saving in construction for over or underground
applications. Therefore they offer saving in land area and
construction costs.
2. Insensitivity to external influences because of grounded metal
enclosures.
3. Greatly improved safety and reliability due to earthed metal housing
of all high voltage parts and much higher intrinsic strength of SF6 gas
as insulation.
4. Short on site erection times, based on large factory assembled and
tested shipping units
5. Fulfillment of aesthetic requirements with indoor applications
6. High service reliability due to non-exposure of the use of high voltage
parts to atmosphere influences
7. Reduction in radio interference with the use of earthed metal
enclosures
8
8. Use as mobile substations for transportation to load centers on
standard tracks. These substations can be located closer to load
centers thereby reducing transmission losses and expenditure in the
distribution network.
9. More optimal life cycle costs because of lesser maintenance, down
time and repair costs.
10. It is not necessary that high voltage or extra high voltage
switchgear has to be installed out doors.
1.1.2 Disadvantages of GIS
Although GIS has been in operation for several years, a lot of
problems encountered in practice need fuller understanding. Some of the
problems being studied are:
1. Switching operation generate Very Fast Transients Over Voltages
(VFTOS).
2. VFTOS may cause secondary breakdown inside a GIS and Transient
Enclosure Voltages (TEV) outside the GIS.
3. Field non-uniformities reduce withstanding levels of a GIS.
4. Prolonged arcing may produce corrosive/toxic by-products.
5. Support spacers can be weak points when arc by-products and
metallic particles are present.
1.2 GENERATION OF VERY FAST TRANSIENT OVER VOLTAGES
(VFTOS) IN A GIS
Fast transient over voltages in GIS are mainly due to two reasons
9
1. Disconnector switch operation
2. Faults between bus bar and enclosure
In case of line-to-earth faults, the voltage collapse at the fault location
occurs in a similar way as in disconnector gap during restriking. By this
event, step shape-travelling surges are injected. When SF6 gas
breakdown occurs, it extinguishes very quickly, since it has a high
electro-negative property. Breakdown in SF6 starts initially by avalanche,
starting with an initiatory electron due to cosmic radiation, field emission
or several other phenomenon producing electrons. These electrons are
accelerated by electric field, thereby increasing its kinetic energy. As a
result, number of electrons increase due to collisions. According to
streamer criteria, first avalanche occurs followed by chain of avalanches
bridging the gap between the electrodes and thus forming the streamer.
Thus, to have the breakdown there should be sufficient electric field to
produce sequence of avalanches and there should be at least one
primary electron to initiate first avalanche. In the above sequence of
events, there exits a time lag for initiating electron to be available in the
gap after the voltage is applied. This time lag is termed as statistical time
lag. Similarly, the formation of spark channel takes definite time known
as formative time lag (tr) and is defined below,
Rise time tr = 4.4 (S. Kr / U) nano seconds (1.1)
U = Ignition voltage in kV
10
S = spark length in mm
Kr = Toepler’s constant
This time lag is of order of nanoseconds for SF6 gas. The above
phenomenon suggests that the VFTOS are generated due to the voltage
collapse, which occurs in few nano seconds.
1.3 TRAPPED CHARGE
Several authors have described the effects of trapped charge on
occurrence of VFTOS. When a disconnector switch is opened on a
floating section of switchgear, a trapped charge may be left on the
floating section. The potential caused by this charge will decay very
slowly as a result of leakage through spacers. Particle motion under d.c
conditions is much more severe than that for a.c excitation and may lead
to scattering of particles onto insulating surfaces. However, such particle
motion leads to appreciable (µA) d.c currents which will discharge the
normally floating section in a relatively short time.
The asymmetry in breakdown voltages leads to the “falling” pattern
near the end of Disconnector Switch operation which continues until the
potential is low enough that breakdown cannot occur during the rising
portion of a power frequency cycle as shown in Fig.1.2.
11
V(p.u)
→ t (micro seconds)
Fig.1.2 Load side voltage waveform during opening of Disconnector
switch.
The end point is inevitably a transition from a large negative potential
to a slightly positive potential at a gap distance for which the positive
breakdown potential is 1.1 p.u (peak) and the negative breakdown
potential is 1.2 p.u (peak). At this point, another positive and negative
breakdown cannot occur, as a result 0.1-0.2 p.u (peak) is left on the
floating switchgear.
The salient features, which lead to this small trapped charge, are the
asymmetry in breakdown potential and relatively long arcing time. This
trapped charge can be controlled through careful design of contact
geometry.
The concept of using compressed SF6 gas, as the principal insulating
media in metal clad substations was first implemented in the early
1970’s. The overall techno-economic advantages such as higher
reliability, personal safety, compactness, ease of maintenance, improved
aesthetics etc. over air insulated substations have led to an increased
12
demand for Gas Insulated Metal Enclosed Switchgear (GIMES) or gas
insulated substations (GIS) over the last three decades. They are now
available worldwide up to a voltage of 800kV. In our country too, in order
to fulfill the needs of technological up gradation, a few GIS units have
already gone into operation or are in various stages of installation.
In a GIMES system, all energized or live parts are enclosed inside a
grounded metallic encapsulation, which shields them from the
environment. Compressed SF6 gas, which has excellent dielectric
properties, is used as the insulating medium between the live parts and
the enclosure. Early designs of GIMES followed a cautions approach and
complete segregation of the three phases i.e. separate chambers were
provided for each functional component such as circuit breakers, current
transformers etc., of each phase.
However, after gaining sufficient service experience and ability to
maintain dielectric integrity three phases in one or phase integrated
modules are now available. The three phase’s construction has the added
advantage of having only a reduced number of gas and moving parts.
Gas insulated substations occupy only about ten percent of the space
required by conventional substations. They also offer saving in land area
and construction costs. Their modular design provides higher degree of
flexibility in the substation layout and efficient use of space. These
substations can be located closer to load centers thereby reducing
transmission losses and expenditure in the distribution network. Since
13
they are hermetically sealed units and hence are not affected by
atmospheric contamination. As associated costs are reduced, when
designing typical cases for which GIMES offers a more economic solution
are following:
a. Urban and industrial areas (space, pollution)
b. Mountain areas (site preparation, altitude)
c. Coastal areas (salt associated problems)
d. Underground substations.
e. Areas where aesthetics are of major concern.
However, a transition from air insulated to gas insulated technology
should require recognition of certain aspects with respect to design. The
bus scheme, for example, used for GIMES is quite different from what is
used for AIS. In GIMES, enclosure is the nearest earth surface with
respect to the conductor. Therefore switching devices in metal enclosed
systems have to fulfill their duties under conditions, which are different
from those prevailing in conventional systems. More clearly, they are
influenced by their close spatial neighborhood in the form of electrostatic
interactions.
The switching device considered under the current study is an
Isolator or disconnecting switch (DS). Several of which are generally
present in a GIMES.
High frequency surges are generated in GIS during the operation of
dis-connectors. These are steep fronted oscillatory over voltages in the
14
frequency ranges of several Mega hertz and known as Very Fast over
Voltages (VFO). It is necessary to investigate the level of over voltages in
order to assess their effect on the insulation characteristics of GIS. Even
though the dielectric strength of a clean GIS may be adequate under
clean conditions, under particle contaminated conditions, the dielectric
strength for over voltages may become lower resulting in bus-bar to
enclosure flashovers.
1.4 VFTOSS ACROSS TRANSFORMER
Very fast transient over voltages (VFTOS) occur in Gas Insulated
Substation (GIS) due to the operation of the disconnector switch. It has
very short rise time of less than 5 nano seconds, and an oscillatory
component of several MHz lasting for few microseconds. There are
concerns about a possibility that the VFTOS sets of a resonance in the
winding of the transformer in the system, particularly if the transformer
is connected to the GIS through a gas insulated bus.
The voltage oscillations in transformer winding have always been
troublesome. Using the concept of ‘on-resonance’ or ‘surge-proof’
transformer, it is intended to suppress the oscillations by controlling the
initial voltage distribution or capacitive voltage distribution. The device
works against ordinary lighting impulses, but it may not necessarily be
effective for oscillatory pulses such as VFTOS originated in GIS. It is of
prime importance to investigate the underlying mechanism of VFTOS
15
phenomena in the transformer and to provide a means to accurately
predict the over voltages in the winding.
Two kinds of induced voltages are reported in transformers, one is
high frequency component induced electro statically and the other is
lower frequency component traveling along the winding. Initially this
phenomenon was analyzed using simple ladder circuit network model.
They have showed that the inter turn voltage can be explained by a
simple transmission line model. They have developed a generalized
analytical method applying the single transmission line model.
They have successfully applied this model to the VFTOS phenomena in
transformer winding. Since the analysis requires a large scale
computation, they have limited the computation area by the use of a
terminal admittance representing the rest of the winding. Most of the
time overvoltages cause a flashover from the winding to core or between
the turns. The inter turn voltage is particularly vulnerable to the high
frequency oscillation and therefore the study of over voltages is of
interest. The VFTOS produced by switching in GIS depend not only on
connection between the GIS and transformer, but also on the
transformer parameters and type of the winding.
1.5 VFTOSS ACROSS BUSHING
The distribution of voltage across the layers of SF6 / air
capacitively graded bushing is not uniform under these fast transients,
particularly the voltage across the first few layers. Further, the voltage
16
distribution across the layers depends on frequency components of the
VFTOS. Hence work has been carried out, to estimate the effect of
different rise time step pulse on SF6 / air capacitively graded bushing
connected to GIS.
1.6 VFTOSS ACROSS DISCONNECTOR SWITCH
The basic function of disconnecting switches is to isolate sections
of a GIS for ensuring safety of the operations. In the process of isolations,
trapped charges may be left on certain sections of the GIS on the
capacitance to ground sections, resulting in large differential voltages
across the disconnecting switches and also in the presence of AC-DC
conditions across the poles of the switches. A switching operation such
as re-energisation under such condition leads to switching charging
current results in steeper oscillations which travel through the
components of the system and suffer multiple reflections. These surges
may cause internal flashovers to nearby grounded objects. Therefore
overvoltages generated in GIS is a major parameter to be considered in
insulation designs as it has bearing on many vital components of the
installation such as insulating spacers, bushings, transformers etc. The
electromagnetic interference (EMI) caused by overvoltages in electronic
control circuitry is another problem to reckon with.
Discussed under the present scope is a study of switching overvoltages
under trapped charge or AC-DC conditions across the disconnector, the
17
magnitude and rise time of overvoltages generated and a method of
controlling them.
For the above reasons, VFTOS generated in a GIS should be
considered as an important factor in the insulation design. For designing
a substation it is essential to know the maximum value of VFTOS.
Moreover, this VFTOS in turn generates Transient Enclosure Voltages
(TEV) outside the GIS, hence studies are carried out on estimation of the
VFTOS and TEV levels. Since the contact speed of disconnect switches is
low, re-striking occurs many times before the interruption is completed.
Each re-strike generates VFTOS with different levels of magnitude.
Disconnect switches are used primarily to isolate the opening sections of
an HV installation from each other as a safety measure. Beyond this,
they must also be able to perform certain switching duties, such as load
transfer from one busbar to another or disconnection of bus bar, circuit
breaker etc., step shaped traveling wave generated between the
disconnect switch contacts propagates in the both directions, reflecting
at the components of GIS, thus resulting in a complex waveform.
1.7 SUPPRESSION OF VFTOSS ACROSS FLANGE
Discussed under the present scope is a study of transient enclosure
voltages across insulating flange and enclosure using MATLAB. The
magnitudes of over voltages across flange and enclosure are suppressed
by various techniques such as by the use of capacitors, shunting bars
(copper strips) etc.

Más contenido relacionado

La actualidad más candente

Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstationraja sukumar
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationMOHDFAIZAN75
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3Ronal Parmar
 
GIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & ShanniGIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & ShanniBHARATKUMAR RATHOD
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONsujitmandalsk
 
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,Sameer Kumar
 
Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)MANASB72
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1Ronal Parmar
 
Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)sujay sahu
 
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
End of-life factors in high voltage gas insulated switchgear with sf6 or with...End of-life factors in high voltage gas insulated switchgear with sf6 or with...
End of-life factors in high voltage gas insulated switchgear with sf6 or with...Ali Sepehri
 
27072013140225 gas-insulated-substations
27072013140225 gas-insulated-substations27072013140225 gas-insulated-substations
27072013140225 gas-insulated-substationsMugdha Jhanjhote
 
Modern substation design
Modern substation designModern substation design
Modern substation designrajesh18001 R
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARashwini kumar
 

La actualidad más candente (20)

Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
GIS(GAS INSULATED SUBSTATION)
GIS(GAS  INSULATED  SUBSTATION) GIS(GAS  INSULATED  SUBSTATION)
GIS(GAS INSULATED SUBSTATION)
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Deepak kumar
Deepak kumarDeepak kumar
Deepak kumar
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
 
GIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & ShanniGIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & Shanni
 
Gagan
GaganGagan
Gagan
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
 
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
 
Ppt
PptPpt
Ppt
 
Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)
 
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
End of-life factors in high voltage gas insulated switchgear with sf6 or with...End of-life factors in high voltage gas insulated switchgear with sf6 or with...
End of-life factors in high voltage gas insulated switchgear with sf6 or with...
 
27072013140225 gas-insulated-substations
27072013140225 gas-insulated-substations27072013140225 gas-insulated-substations
27072013140225 gas-insulated-substations
 
GIS-NESCL-6
GIS-NESCL-6GIS-NESCL-6
GIS-NESCL-6
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
 

Destacado

Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationseSAT Journals
 
2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substationRemigiusz Joeck
 
Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationSupardi Amaludin
 
Alok ppt new 13 aprl
Alok ppt new 13 aprlAlok ppt new 13 aprl
Alok ppt new 13 aprlNitesh Prasad
 
Gas insulated sub station 2
Gas insulated sub station 2Gas insulated sub station 2
Gas insulated sub station 2Ronal Parmar
 
System and method for generating electric power
System and method for generating electric powerSystem and method for generating electric power
System and method for generating electric powershalsub
 
Power generation from railway track
Power generation from railway trackPower generation from railway track
Power generation from railway trackManojkumar Mishra
 
Automatic Vehicle Locator(AVL) Seminar report
 Automatic Vehicle Locator(AVL) Seminar report Automatic Vehicle Locator(AVL) Seminar report
Automatic Vehicle Locator(AVL) Seminar reportRohit Kumar patel
 
Power generation through railway track
Power generation through railway trackPower generation through railway track
Power generation through railway trackMuhammad Aleem
 
Steam power plant
Steam power plant Steam power plant
Steam power plant msrao1
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report19saurabh89
 
Wireless+power+transmission+via+solar+power+satellite
Wireless+power+transmission+via+solar+power+satelliteWireless+power+transmission+via+solar+power+satellite
Wireless+power+transmission+via+solar+power+satelliteniteshmishra05
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substationsbhanu lucky
 

Destacado (20)

Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substations
 
2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation2003 09-08 joeck icefa fuse protection in transformer pole substation
2003 09-08 joeck icefa fuse protection in transformer pole substation
 
Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substation
 
Speed
SpeedSpeed
Speed
 
Alok ppt new 13 aprl
Alok ppt new 13 aprlAlok ppt new 13 aprl
Alok ppt new 13 aprl
 
Gas insulated sub station 2
Gas insulated sub station 2Gas insulated sub station 2
Gas insulated sub station 2
 
System and method for generating electric power
System and method for generating electric powerSystem and method for generating electric power
System and method for generating electric power
 
Automatic Vehicle Locator
Automatic Vehicle LocatorAutomatic Vehicle Locator
Automatic Vehicle Locator
 
contributor
contributorcontributor
contributor
 
electrical engineering
electrical engineeringelectrical engineering
electrical engineering
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
Vivek harmonics
Vivek harmonicsVivek harmonics
Vivek harmonics
 
Power generation from railway track
Power generation from railway trackPower generation from railway track
Power generation from railway track
 
Automatic Vehicle Locator(AVL) Seminar report
 Automatic Vehicle Locator(AVL) Seminar report Automatic Vehicle Locator(AVL) Seminar report
Automatic Vehicle Locator(AVL) Seminar report
 
Power generation through railway track
Power generation through railway trackPower generation through railway track
Power generation through railway track
 
Steam power plant
Steam power plant Steam power plant
Steam power plant
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
Amit
AmitAmit
Amit
 
Wireless+power+transmission+via+solar+power+satellite
Wireless+power+transmission+via+solar+power+satelliteWireless+power+transmission+via+solar+power+satellite
Wireless+power+transmission+via+solar+power+satellite
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substations
 

Similar a substation 101

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptxBasavarajbanakar6
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptxSatish Pydimarla
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxborapring
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid SubstationAng Sovann
 
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationIRJET Journal
 
Design of Nanoscale 3-T DRAM using FinFET
Design of Nanoscale 3-T DRAM using FinFETDesign of Nanoscale 3-T DRAM using FinFET
Design of Nanoscale 3-T DRAM using FinFETIOSR Journals
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Torben Haagh
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyMahesh Chandra Manav
 
GIS and Over voltages.ppt
GIS and Over voltages.pptGIS and Over voltages.ppt
GIS and Over voltages.pptrajnikanthp
 
IRJET- Simulation of 10nm Double Gate MOSFET using Visual TCAD Tool
IRJET-  	  Simulation of 10nm Double Gate MOSFET using Visual TCAD ToolIRJET-  	  Simulation of 10nm Double Gate MOSFET using Visual TCAD Tool
IRJET- Simulation of 10nm Double Gate MOSFET using Visual TCAD ToolIRJET Journal
 
IRJET- Liquid Power Supply (L P S)
IRJET- Liquid Power Supply (L P S)IRJET- Liquid Power Supply (L P S)
IRJET- Liquid Power Supply (L P S)IRJET Journal
 
Catalog busbar ls 05. busduct catalogue e series ver 6.5
Catalog busbar ls 05. busduct catalogue e series ver 6.5Catalog busbar ls 05. busduct catalogue e series ver 6.5
Catalog busbar ls 05. busduct catalogue e series ver 6.5Dien Ha The
 

Similar a substation 101 (20)

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptx
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptx
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
 
GIS PRESENTATION.pdf
GIS PRESENTATION.pdfGIS PRESENTATION.pdf
GIS PRESENTATION.pdf
 
Substation
Substation Substation
Substation
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
 
Design of Nanoscale 3-T DRAM using FinFET
Design of Nanoscale 3-T DRAM using FinFETDesign of Nanoscale 3-T DRAM using FinFET
Design of Nanoscale 3-T DRAM using FinFET
 
INTER PHASE SPACERS
INTER PHASE SPACERS INTER PHASE SPACERS
INTER PHASE SPACERS
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periorty
 
Nc342352340
Nc342352340Nc342352340
Nc342352340
 
Gis91
Gis91Gis91
Gis91
 
GIS and Over voltages.ppt
GIS and Over voltages.pptGIS and Over voltages.ppt
GIS and Over voltages.ppt
 
IRJET- Simulation of 10nm Double Gate MOSFET using Visual TCAD Tool
IRJET-  	  Simulation of 10nm Double Gate MOSFET using Visual TCAD ToolIRJET-  	  Simulation of 10nm Double Gate MOSFET using Visual TCAD Tool
IRJET- Simulation of 10nm Double Gate MOSFET using Visual TCAD Tool
 
IRJET- Liquid Power Supply (L P S)
IRJET- Liquid Power Supply (L P S)IRJET- Liquid Power Supply (L P S)
IRJET- Liquid Power Supply (L P S)
 
Catalog busbar ls 05. busduct catalogue e series ver 6.5
Catalog busbar ls 05. busduct catalogue e series ver 6.5Catalog busbar ls 05. busduct catalogue e series ver 6.5
Catalog busbar ls 05. busduct catalogue e series ver 6.5
 

Último

Soviet pilot Yuri Gagarin was the first person to ever orbit the Earth
Soviet pilot Yuri Gagarin was the first person to ever orbit the EarthSoviet pilot Yuri Gagarin was the first person to ever orbit the Earth
Soviet pilot Yuri Gagarin was the first person to ever orbit the EarthChristina Parmionova
 
What is the career path of a VFX artist?
What is the career path of a VFX artist?What is the career path of a VFX artist?
What is the career path of a VFX artist?santoshjadhav126
 
LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024Bruce Bennett
 
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptxwaghmare9860lavin
 
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作rpb5qxou
 
APSC Motor Vechile Inspector 18 Posts.pdf
APSC Motor Vechile Inspector 18 Posts.pdfAPSC Motor Vechile Inspector 18 Posts.pdf
APSC Motor Vechile Inspector 18 Posts.pdfsoumita869
 
Bobby singh - Digital Marketing Service
Bobby singh -  Digital Marketing ServiceBobby singh -  Digital Marketing Service
Bobby singh - Digital Marketing ServiceBobby singh
 
Abanoub Ghobrial, Planning Team Leader.pdf
Abanoub Ghobrial, Planning Team Leader.pdfAbanoub Ghobrial, Planning Team Leader.pdf
Abanoub Ghobrial, Planning Team Leader.pdfAbanoubGhobrial1
 
How to prepare yourself for a job interview.pptx
How to prepare yourself for a job interview.pptxHow to prepare yourself for a job interview.pptx
How to prepare yourself for a job interview.pptxJohnreyFalsarioBasid
 
Design, Desire and Demand Presentation.pptx
Design, Desire and Demand Presentation.pptxDesign, Desire and Demand Presentation.pptx
Design, Desire and Demand Presentation.pptxaaronbasko1
 
Jumark Morit Diezmo- Career portfolio- BPED 3A
Jumark Morit Diezmo- Career portfolio- BPED 3AJumark Morit Diezmo- Career portfolio- BPED 3A
Jumark Morit Diezmo- Career portfolio- BPED 3Ajumarkdiezmo1
 
Banged Dubai Call Girls O525547819 Call Girls Dubai
Banged Dubai Call Girls O525547819 Call Girls DubaiBanged Dubai Call Girls O525547819 Call Girls Dubai
Banged Dubai Call Girls O525547819 Call Girls Dubaikojalkojal131
 
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024Hector Del Castillo, CPM, CPMM
 
The Next Things To Immediately Do About Mating Press
The Next Things To Immediately Do About Mating PressThe Next Things To Immediately Do About Mating Press
The Next Things To Immediately Do About Mating Pressmatingpress170
 
dentinalhypersensitivity, classification and material used
dentinalhypersensitivity,  classification and material useddentinalhypersensitivity,  classification and material used
dentinalhypersensitivity, classification and material usedaishwaryakhare5
 
Human Rights are notes and helping material
Human Rights are notes and helping materialHuman Rights are notes and helping material
Human Rights are notes and helping materialnadeemcollege26
 
Complete Benefits of career counseling in India
Complete Benefits of career counseling in IndiaComplete Benefits of career counseling in India
Complete Benefits of career counseling in IndiaMere Mentor
 
Chapter 4 - Promoting Inclusive Culture.ppt
Chapter 4 - Promoting   Inclusive Culture.pptChapter 4 - Promoting   Inclusive Culture.ppt
Chapter 4 - Promoting Inclusive Culture.pptmoytopo
 
Get to know about Raquel Thompson Barbados.pdf
Get to know about Raquel Thompson Barbados.pdfGet to know about Raquel Thompson Barbados.pdf
Get to know about Raquel Thompson Barbados.pdfRaquel Thompson Barbados
 
Senior IT Professional with Master’s Degree with 21+ years of experience is...
Senior IT Professional with Master’s Degree with 21+ years of experience   is...Senior IT Professional with Master’s Degree with 21+ years of experience   is...
Senior IT Professional with Master’s Degree with 21+ years of experience is...Anas Acharath Parakat
 

Último (20)

Soviet pilot Yuri Gagarin was the first person to ever orbit the Earth
Soviet pilot Yuri Gagarin was the first person to ever orbit the EarthSoviet pilot Yuri Gagarin was the first person to ever orbit the Earth
Soviet pilot Yuri Gagarin was the first person to ever orbit the Earth
 
What is the career path of a VFX artist?
What is the career path of a VFX artist?What is the career path of a VFX artist?
What is the career path of a VFX artist?
 
LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024LinkedIn for Your Job Search in April 2024
LinkedIn for Your Job Search in April 2024
 
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx
401799841-Increasing-Crimes-and-Suicides-Among-Youth.pptx
 
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作
加拿大MUN学位证,纽芬兰纪念大学毕业证书1:1制作
 
APSC Motor Vechile Inspector 18 Posts.pdf
APSC Motor Vechile Inspector 18 Posts.pdfAPSC Motor Vechile Inspector 18 Posts.pdf
APSC Motor Vechile Inspector 18 Posts.pdf
 
Bobby singh - Digital Marketing Service
Bobby singh -  Digital Marketing ServiceBobby singh -  Digital Marketing Service
Bobby singh - Digital Marketing Service
 
Abanoub Ghobrial, Planning Team Leader.pdf
Abanoub Ghobrial, Planning Team Leader.pdfAbanoub Ghobrial, Planning Team Leader.pdf
Abanoub Ghobrial, Planning Team Leader.pdf
 
How to prepare yourself for a job interview.pptx
How to prepare yourself for a job interview.pptxHow to prepare yourself for a job interview.pptx
How to prepare yourself for a job interview.pptx
 
Design, Desire and Demand Presentation.pptx
Design, Desire and Demand Presentation.pptxDesign, Desire and Demand Presentation.pptx
Design, Desire and Demand Presentation.pptx
 
Jumark Morit Diezmo- Career portfolio- BPED 3A
Jumark Morit Diezmo- Career portfolio- BPED 3AJumark Morit Diezmo- Career portfolio- BPED 3A
Jumark Morit Diezmo- Career portfolio- BPED 3A
 
Banged Dubai Call Girls O525547819 Call Girls Dubai
Banged Dubai Call Girls O525547819 Call Girls DubaiBanged Dubai Call Girls O525547819 Call Girls Dubai
Banged Dubai Call Girls O525547819 Call Girls Dubai
 
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024
How To Land Your Next PM Dream Job - PMISSC Meeting - April 2024
 
The Next Things To Immediately Do About Mating Press
The Next Things To Immediately Do About Mating PressThe Next Things To Immediately Do About Mating Press
The Next Things To Immediately Do About Mating Press
 
dentinalhypersensitivity, classification and material used
dentinalhypersensitivity,  classification and material useddentinalhypersensitivity,  classification and material used
dentinalhypersensitivity, classification and material used
 
Human Rights are notes and helping material
Human Rights are notes and helping materialHuman Rights are notes and helping material
Human Rights are notes and helping material
 
Complete Benefits of career counseling in India
Complete Benefits of career counseling in IndiaComplete Benefits of career counseling in India
Complete Benefits of career counseling in India
 
Chapter 4 - Promoting Inclusive Culture.ppt
Chapter 4 - Promoting   Inclusive Culture.pptChapter 4 - Promoting   Inclusive Culture.ppt
Chapter 4 - Promoting Inclusive Culture.ppt
 
Get to know about Raquel Thompson Barbados.pdf
Get to know about Raquel Thompson Barbados.pdfGet to know about Raquel Thompson Barbados.pdf
Get to know about Raquel Thompson Barbados.pdf
 
Senior IT Professional with Master’s Degree with 21+ years of experience is...
Senior IT Professional with Master’s Degree with 21+ years of experience   is...Senior IT Professional with Master’s Degree with 21+ years of experience   is...
Senior IT Professional with Master’s Degree with 21+ years of experience is...
 

substation 101

  • 1. 1 CHAPTER 1 INTRODUCTION 1.0 INTRODUCTION Gas insulated substations (GIS) have been used in power systems over the last three decades because of their high reliability, easy maintenance, small ground space requirement etc. In India also, a few GIS units are under various stages of installation. The basic insulation level (BIL) required for a gas insulated substation (GIS) is different from that of the conventional substation because of certain unique properties of the former. Gas insulated bus has a surge impedance (70Ω) more than that of the conventional oil filled cables, but much less than that of an over head line (300Ω - 400Ω). Further, the average bus run for a compact GIS is much less than that for the conventional station. In addition, the GIS is totally enclosed and therefore is free from any atmospheric contamination. Hence, in general the GIS permit lower BIL rating than the conventional one. However the life of GIS is affected by several factors such as: conductive particles, particle discharges and contamination (decomposition products, moisture, etc.). Conductive particles inside the enclosure are known to reduce the breakdown level of Gas insulated systems. Partial discharges can develop from conductive particles, contamination, and defects during the manufacturing process, etc.
  • 2. 2 The GIS require less number of lightning arresters than a conventional one. This is mainly because of its compactness. The basic consideration for insulation coordination is V-T characteristic. The V-T characteristic of SF6 is considerably flat compared to that of air. Air can withstand to very high voltages for very short time. However, as the duration of voltage increases, the withstand voltage falls off considerably. On the other hand, SF6 exhibits a flat characteristic, thus the ratio of basic lightning impulse level is close to unity for GIS, whereas for the conventional substations this ratio varies between 0.6 and 0.86. Although GIS has been in operation for several years, a lot of problems encountered in practice need further understanding. Some of the problems studied are: a. Switching operations generate very fast transient over voltages (VFTOS) b. VFTOS may cause secondary breakdowns inside a GIS and Transient Enclosure Voltages (TEV) outside the GIS c. Prolonged arcing may produce corrosive / toxic by products d. Support spacers can be weak points when arc by products and metallic particles are present e. From the reliability point of view, partial discharge detection is important. The methods of detection are of acoustic system and electric systems etc. These methods lack quality control.
  • 3. 3 For these reasons, VFTOS generated in a GIS should be considered as an important factor in the insulation design. In a GIS, Very Fast Transient Overvoltages (VFTOS) are caused by two ways: a. Due to switching operations and b. Line to enclosure faults. The switching operations may be dis-connector switch, circuit breaker or earth switch. Since, the contact speed of disconnector switches are low, restriking occurs many times before the interruption is completed. Each restrike generates very fast transient over voltages with different levels of magnitude. Further, disconnector switches are used primarily to isolate the operating sections of an HV installation from each other as a safety measure. Beyond this, they must also be able to perform certain switching duties, such as load transferred from one bus bar to another or disconnection of bus sections, circuit breakers etc. During switching operations, voltage collapse across the contacts take place within 3 to 20 nanoseconds depending on the system voltage, gas pressure, field intensity etc. Once this short time rise pulse starts at switching contacts, it travels along gas bus duct in either direction and gets reflected at different terminations. The superimposition of system with reflected pulse develops over voltages in GIS. These over voltages have been called as Very Fast Transient Over voltages (VFTOS), because of their very high frequency components in the range of MHz. The main problems associated with the VFTOS are as follows:
  • 4. 4 1. Flash over to ground at the disconnector switch contacts 2. Failure of electronic control circuits connected to GIS due to electro magnetic interference of VFTOS 3. Di-electric strength is reduced under VFTOS, if non-uniform electric field is formed by the particles (mainly metallic) 4. Effect on equipments such as bushing, power transformer and instrument transformers 5. Transient Enclosure Voltage (TEV) on external surface of the sheath. This may cause flashovers to nearby grounded objects For the above reasons, VFTOS generated in GIS should be considered as an important factor in the insulation design of not only gas-insulated components, but also for the entire substation. The levels and waveforms of VFTOS are determined by the design of the substation. To calculate the levels and waveforms of VFTOS, the Pspice/MATLAB is used. In Pspice/MATLAB simulation, a suitable equivalent circuit is necessary for each component of the substation. 1.1 GAS INSULATED SUBSTATIONS SF6 gas insulated high voltage switchgear has been in commercial operation for more than 30 years. Continuous technological and design improvements of all the components during the course of the time are characterized by appreciable savings in area and volume occupied by the substation. Gas insulated substations are in service up to the highest
  • 5. 5 voltage of 800 kV, meeting almost all the requirements in urban, industrial as well as rural areas. In the initial stages, the new SF6 gas insulated substations were almost exclusively used where space limitations, site restrictions or exponential ambient conditions made it difficult to use conventional air insulated substations. However, over the last 30 years, GIS at voltage up to 800 kV in various station configurations and with various performance requirements, have been installed in increasing numbers worldwide. The modular of design of GIS offers a high degree of flexibility to meet layout requirements of both substations, as well as power station switchgear, making efficient use of available space. GIS technology has reached a stage of application and a wide range of GIS equipment up to highest voltage of 800 kV is available with many unique features. They are: 1. Wide spread application of aluminum enclosure materials for standardized component models for all voltage ranges 2. The light weight enclosures have good conductivity, low eddy-current losses and a high resistance to corrosion 3. Easy handling, as well as reduced stresses on foundation and support structure are additional features 4. Standard arrangements can be easily modified and extended with good co-ordination between the manufacturer and the user.
  • 6. 6 5. A gas- tight barrier insulator in switchgear serve for the separation of gas compartments and prevents neighbouring switchgear parts from being affected during maintenance. A typical Gas insulated substation is shown in Fig.1.1. Fig.1.1 Gas Insulated Substation The Gas insulated substation shown in above figure comprises the following components: 1 Circuit breaker 2 Disconnector switch 3 Earthing switch 4 Current transformer 5 Voltage transformer 6 Bus bar & connectors
  • 7. 7 7 Power transformer 8 Surge arrester 9 Cable termination 10 SF6 / air or SF6 / oil bushing 1.1.1 Advantages of GIS over the conventional open air substation The application of GIS during the last fifteen years has been very rapid. The rapid growth in GIS application is due to the following special advantages: 1. Area and volume saving in construction for over or underground applications. Therefore they offer saving in land area and construction costs. 2. Insensitivity to external influences because of grounded metal enclosures. 3. Greatly improved safety and reliability due to earthed metal housing of all high voltage parts and much higher intrinsic strength of SF6 gas as insulation. 4. Short on site erection times, based on large factory assembled and tested shipping units 5. Fulfillment of aesthetic requirements with indoor applications 6. High service reliability due to non-exposure of the use of high voltage parts to atmosphere influences 7. Reduction in radio interference with the use of earthed metal enclosures
  • 8. 8 8. Use as mobile substations for transportation to load centers on standard tracks. These substations can be located closer to load centers thereby reducing transmission losses and expenditure in the distribution network. 9. More optimal life cycle costs because of lesser maintenance, down time and repair costs. 10. It is not necessary that high voltage or extra high voltage switchgear has to be installed out doors. 1.1.2 Disadvantages of GIS Although GIS has been in operation for several years, a lot of problems encountered in practice need fuller understanding. Some of the problems being studied are: 1. Switching operation generate Very Fast Transients Over Voltages (VFTOS). 2. VFTOS may cause secondary breakdown inside a GIS and Transient Enclosure Voltages (TEV) outside the GIS. 3. Field non-uniformities reduce withstanding levels of a GIS. 4. Prolonged arcing may produce corrosive/toxic by-products. 5. Support spacers can be weak points when arc by-products and metallic particles are present. 1.2 GENERATION OF VERY FAST TRANSIENT OVER VOLTAGES (VFTOS) IN A GIS Fast transient over voltages in GIS are mainly due to two reasons
  • 9. 9 1. Disconnector switch operation 2. Faults between bus bar and enclosure In case of line-to-earth faults, the voltage collapse at the fault location occurs in a similar way as in disconnector gap during restriking. By this event, step shape-travelling surges are injected. When SF6 gas breakdown occurs, it extinguishes very quickly, since it has a high electro-negative property. Breakdown in SF6 starts initially by avalanche, starting with an initiatory electron due to cosmic radiation, field emission or several other phenomenon producing electrons. These electrons are accelerated by electric field, thereby increasing its kinetic energy. As a result, number of electrons increase due to collisions. According to streamer criteria, first avalanche occurs followed by chain of avalanches bridging the gap between the electrodes and thus forming the streamer. Thus, to have the breakdown there should be sufficient electric field to produce sequence of avalanches and there should be at least one primary electron to initiate first avalanche. In the above sequence of events, there exits a time lag for initiating electron to be available in the gap after the voltage is applied. This time lag is termed as statistical time lag. Similarly, the formation of spark channel takes definite time known as formative time lag (tr) and is defined below, Rise time tr = 4.4 (S. Kr / U) nano seconds (1.1) U = Ignition voltage in kV
  • 10. 10 S = spark length in mm Kr = Toepler’s constant This time lag is of order of nanoseconds for SF6 gas. The above phenomenon suggests that the VFTOS are generated due to the voltage collapse, which occurs in few nano seconds. 1.3 TRAPPED CHARGE Several authors have described the effects of trapped charge on occurrence of VFTOS. When a disconnector switch is opened on a floating section of switchgear, a trapped charge may be left on the floating section. The potential caused by this charge will decay very slowly as a result of leakage through spacers. Particle motion under d.c conditions is much more severe than that for a.c excitation and may lead to scattering of particles onto insulating surfaces. However, such particle motion leads to appreciable (µA) d.c currents which will discharge the normally floating section in a relatively short time. The asymmetry in breakdown voltages leads to the “falling” pattern near the end of Disconnector Switch operation which continues until the potential is low enough that breakdown cannot occur during the rising portion of a power frequency cycle as shown in Fig.1.2.
  • 11. 11 V(p.u) → t (micro seconds) Fig.1.2 Load side voltage waveform during opening of Disconnector switch. The end point is inevitably a transition from a large negative potential to a slightly positive potential at a gap distance for which the positive breakdown potential is 1.1 p.u (peak) and the negative breakdown potential is 1.2 p.u (peak). At this point, another positive and negative breakdown cannot occur, as a result 0.1-0.2 p.u (peak) is left on the floating switchgear. The salient features, which lead to this small trapped charge, are the asymmetry in breakdown potential and relatively long arcing time. This trapped charge can be controlled through careful design of contact geometry. The concept of using compressed SF6 gas, as the principal insulating media in metal clad substations was first implemented in the early 1970’s. The overall techno-economic advantages such as higher reliability, personal safety, compactness, ease of maintenance, improved aesthetics etc. over air insulated substations have led to an increased
  • 12. 12 demand for Gas Insulated Metal Enclosed Switchgear (GIMES) or gas insulated substations (GIS) over the last three decades. They are now available worldwide up to a voltage of 800kV. In our country too, in order to fulfill the needs of technological up gradation, a few GIS units have already gone into operation or are in various stages of installation. In a GIMES system, all energized or live parts are enclosed inside a grounded metallic encapsulation, which shields them from the environment. Compressed SF6 gas, which has excellent dielectric properties, is used as the insulating medium between the live parts and the enclosure. Early designs of GIMES followed a cautions approach and complete segregation of the three phases i.e. separate chambers were provided for each functional component such as circuit breakers, current transformers etc., of each phase. However, after gaining sufficient service experience and ability to maintain dielectric integrity three phases in one or phase integrated modules are now available. The three phase’s construction has the added advantage of having only a reduced number of gas and moving parts. Gas insulated substations occupy only about ten percent of the space required by conventional substations. They also offer saving in land area and construction costs. Their modular design provides higher degree of flexibility in the substation layout and efficient use of space. These substations can be located closer to load centers thereby reducing transmission losses and expenditure in the distribution network. Since
  • 13. 13 they are hermetically sealed units and hence are not affected by atmospheric contamination. As associated costs are reduced, when designing typical cases for which GIMES offers a more economic solution are following: a. Urban and industrial areas (space, pollution) b. Mountain areas (site preparation, altitude) c. Coastal areas (salt associated problems) d. Underground substations. e. Areas where aesthetics are of major concern. However, a transition from air insulated to gas insulated technology should require recognition of certain aspects with respect to design. The bus scheme, for example, used for GIMES is quite different from what is used for AIS. In GIMES, enclosure is the nearest earth surface with respect to the conductor. Therefore switching devices in metal enclosed systems have to fulfill their duties under conditions, which are different from those prevailing in conventional systems. More clearly, they are influenced by their close spatial neighborhood in the form of electrostatic interactions. The switching device considered under the current study is an Isolator or disconnecting switch (DS). Several of which are generally present in a GIMES. High frequency surges are generated in GIS during the operation of dis-connectors. These are steep fronted oscillatory over voltages in the
  • 14. 14 frequency ranges of several Mega hertz and known as Very Fast over Voltages (VFO). It is necessary to investigate the level of over voltages in order to assess their effect on the insulation characteristics of GIS. Even though the dielectric strength of a clean GIS may be adequate under clean conditions, under particle contaminated conditions, the dielectric strength for over voltages may become lower resulting in bus-bar to enclosure flashovers. 1.4 VFTOSS ACROSS TRANSFORMER Very fast transient over voltages (VFTOS) occur in Gas Insulated Substation (GIS) due to the operation of the disconnector switch. It has very short rise time of less than 5 nano seconds, and an oscillatory component of several MHz lasting for few microseconds. There are concerns about a possibility that the VFTOS sets of a resonance in the winding of the transformer in the system, particularly if the transformer is connected to the GIS through a gas insulated bus. The voltage oscillations in transformer winding have always been troublesome. Using the concept of ‘on-resonance’ or ‘surge-proof’ transformer, it is intended to suppress the oscillations by controlling the initial voltage distribution or capacitive voltage distribution. The device works against ordinary lighting impulses, but it may not necessarily be effective for oscillatory pulses such as VFTOS originated in GIS. It is of prime importance to investigate the underlying mechanism of VFTOS
  • 15. 15 phenomena in the transformer and to provide a means to accurately predict the over voltages in the winding. Two kinds of induced voltages are reported in transformers, one is high frequency component induced electro statically and the other is lower frequency component traveling along the winding. Initially this phenomenon was analyzed using simple ladder circuit network model. They have showed that the inter turn voltage can be explained by a simple transmission line model. They have developed a generalized analytical method applying the single transmission line model. They have successfully applied this model to the VFTOS phenomena in transformer winding. Since the analysis requires a large scale computation, they have limited the computation area by the use of a terminal admittance representing the rest of the winding. Most of the time overvoltages cause a flashover from the winding to core or between the turns. The inter turn voltage is particularly vulnerable to the high frequency oscillation and therefore the study of over voltages is of interest. The VFTOS produced by switching in GIS depend not only on connection between the GIS and transformer, but also on the transformer parameters and type of the winding. 1.5 VFTOSS ACROSS BUSHING The distribution of voltage across the layers of SF6 / air capacitively graded bushing is not uniform under these fast transients, particularly the voltage across the first few layers. Further, the voltage
  • 16. 16 distribution across the layers depends on frequency components of the VFTOS. Hence work has been carried out, to estimate the effect of different rise time step pulse on SF6 / air capacitively graded bushing connected to GIS. 1.6 VFTOSS ACROSS DISCONNECTOR SWITCH The basic function of disconnecting switches is to isolate sections of a GIS for ensuring safety of the operations. In the process of isolations, trapped charges may be left on certain sections of the GIS on the capacitance to ground sections, resulting in large differential voltages across the disconnecting switches and also in the presence of AC-DC conditions across the poles of the switches. A switching operation such as re-energisation under such condition leads to switching charging current results in steeper oscillations which travel through the components of the system and suffer multiple reflections. These surges may cause internal flashovers to nearby grounded objects. Therefore overvoltages generated in GIS is a major parameter to be considered in insulation designs as it has bearing on many vital components of the installation such as insulating spacers, bushings, transformers etc. The electromagnetic interference (EMI) caused by overvoltages in electronic control circuitry is another problem to reckon with. Discussed under the present scope is a study of switching overvoltages under trapped charge or AC-DC conditions across the disconnector, the
  • 17. 17 magnitude and rise time of overvoltages generated and a method of controlling them. For the above reasons, VFTOS generated in a GIS should be considered as an important factor in the insulation design. For designing a substation it is essential to know the maximum value of VFTOS. Moreover, this VFTOS in turn generates Transient Enclosure Voltages (TEV) outside the GIS, hence studies are carried out on estimation of the VFTOS and TEV levels. Since the contact speed of disconnect switches is low, re-striking occurs many times before the interruption is completed. Each re-strike generates VFTOS with different levels of magnitude. Disconnect switches are used primarily to isolate the opening sections of an HV installation from each other as a safety measure. Beyond this, they must also be able to perform certain switching duties, such as load transfer from one busbar to another or disconnection of bus bar, circuit breaker etc., step shaped traveling wave generated between the disconnect switch contacts propagates in the both directions, reflecting at the components of GIS, thus resulting in a complex waveform. 1.7 SUPPRESSION OF VFTOSS ACROSS FLANGE Discussed under the present scope is a study of transient enclosure voltages across insulating flange and enclosure using MATLAB. The magnitudes of over voltages across flange and enclosure are suppressed by various techniques such as by the use of capacitors, shunting bars (copper strips) etc.