Ingredients for success deployment of Earned-Value Management in projects
Culture shift is essential – every Project Team  must understand the working of EVM model Also, culture shift needs to be managed and supported well
Besides  accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
Replanning the work at every change is critical. Use of automated tools will ease out this process
Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
 

More Related Content

What's hot

What's hot (16)

Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Seven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company NeedsSeven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company Needs
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
Cost analysis
Cost analysisCost analysis
Cost analysis
 
Value management presentation
Value management presentationValue management presentation
Value management presentation
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Cost
CostCost
Cost
 
Standard costing
Standard costingStandard costing
Standard costing
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Pm0015 summer-2016
Pm0015 summer-2016Pm0015 summer-2016
Pm0015 summer-2016
 
Cost management
Cost managementCost management
Cost management
 
factors affecting prodution
factors affecting produtionfactors affecting prodution
factors affecting prodution
 
Odoo experience 2015 earned value management
Odoo experience 2015   earned value managementOdoo experience 2015   earned value management
Odoo experience 2015 earned value management
 
Methods
MethodsMethods
Methods
 
Project cost control system in SAP
Project cost control system in SAPProject cost control system in SAP
Project cost control system in SAP
 

Similar to Vijay Prasad’S Views On Earned Value Management In Project

Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 

Similar to Vijay Prasad’S Views On Earned Value Management In Project (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Cost
CostCost
Cost
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Project mgt
Project mgtProject mgt
Project mgt
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Updated Resume - Veena Kumar
Updated Resume - Veena KumarUpdated Resume - Veena Kumar
Updated Resume - Veena Kumar
 

Recently uploaded

Structuring Teams and Portfolios for Success
Structuring Teams and Portfolios for SuccessStructuring Teams and Portfolios for Success
Structuring Teams and Portfolios for Success
UXDXConf
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Peter Udo Diehl
 

Recently uploaded (20)

What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024What's New in Teams Calling, Meetings and Devices April 2024
What's New in Teams Calling, Meetings and Devices April 2024
 
THE BEST IPTV in GERMANY for 2024: IPTVreel
THE BEST IPTV in  GERMANY for 2024: IPTVreelTHE BEST IPTV in  GERMANY for 2024: IPTVreel
THE BEST IPTV in GERMANY for 2024: IPTVreel
 
Structuring Teams and Portfolios for Success
Structuring Teams and Portfolios for SuccessStructuring Teams and Portfolios for Success
Structuring Teams and Portfolios for Success
 
The UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, OcadoThe UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, Ocado
 
How we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdfHow we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdf
 
Designing for Hardware Accessibility at Comcast
Designing for Hardware Accessibility at ComcastDesigning for Hardware Accessibility at Comcast
Designing for Hardware Accessibility at Comcast
 
The Metaverse: Are We There Yet?
The  Metaverse:    Are   We  There  Yet?The  Metaverse:    Are   We  There  Yet?
The Metaverse: Are We There Yet?
 
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxUnpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
 
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo DiehlFuture Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
Future Visions: Predictions to Guide and Time Tech Innovation, Peter Udo Diehl
 
Introduction to FDO and How It works Applications _ Richard at FIDO Alliance.pdf
Introduction to FDO and How It works Applications _ Richard at FIDO Alliance.pdfIntroduction to FDO and How It works Applications _ Richard at FIDO Alliance.pdf
Introduction to FDO and How It works Applications _ Richard at FIDO Alliance.pdf
 
Simplified FDO Manufacturing Flow with TPMs _ Liam at Infineon.pdf
Simplified FDO Manufacturing Flow with TPMs _ Liam at Infineon.pdfSimplified FDO Manufacturing Flow with TPMs _ Liam at Infineon.pdf
Simplified FDO Manufacturing Flow with TPMs _ Liam at Infineon.pdf
 
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdfLinux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
 
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
 
A Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System StrategyA Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System Strategy
 
ECS 2024 Teams Premium - Pretty Secure
ECS 2024   Teams Premium - Pretty SecureECS 2024   Teams Premium - Pretty Secure
ECS 2024 Teams Premium - Pretty Secure
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM Performance
 
Top 10 Symfony Development Companies 2024
Top 10 Symfony Development Companies 2024Top 10 Symfony Development Companies 2024
Top 10 Symfony Development Companies 2024
 
IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024IoT Analytics Company Presentation May 2024
IoT Analytics Company Presentation May 2024
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
 

Vijay Prasad’S Views On Earned Value Management In Project

  • 1. Ingredients for success deployment of Earned-Value Management in projects
  • 2. Culture shift is essential – every Project Team must understand the working of EVM model Also, culture shift needs to be managed and supported well
  • 3. Besides accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
  • 4. It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
  • 5. To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
  • 6. Replanning the work at every change is critical. Use of automated tools will ease out this process
  • 7. Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
  • 8. It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
  • 9.