2. BENNING PARK COMMUNITY CENTER07/28/2016
AGENDA
1. Introduction
2. Design Team Overview
3. Design Process
4. Schedule
5. Comments/Next Steps
3. BENNING PARK COMMUNITY CENTER07/28/2016
MOODY NOLAN
• Local Success
• National Sports Consultant
• 145 Design Citations
• Responsive Design
4. BENNING PARK COMMUNITY CENTER07/28/2016
JAMES JORDAN, AIA, NCARB
• Principal/Owner - Millennium
Design Architects
• Associate Architect
• Ward 7 Business & Resident
– Former Benning Heights/ Ft.
Dupont Park Resident
• Community Service
– Served on Marshall Heights
Community Development
Organization Board of
Directors
– Served on 11th Street Bridge
Park
– Design Review Committee
• Multiple Projects in Wards 7
& 8 East of the River
Communities
5. BENNING PARK COMMUNITY CENTER07/28/2016
DESIGN PROCESS
• Program/Scope of Work
– Requirements and Goals
• Community Meeting
• Feedback
6. GROUND FLOOR PLANS
BENNING PARK COMMUNITY CENTER
EXISTING PLANPROGRESS PLAN
Upgrades
-Life Safety
-ADA/Elevator
-Roof
-MEP Systems
-Windows
-Boxing
07/28/2016
7. FIRST FLOOR PLANS
BENNING PARK COMMUNITY CENTER
EXISTING PLANPROGRESS PLAN
Upgrades
-Life Safety
-ADA/Elevator
-Roof
-MEP Systems
-Windows
-Boxing
07/28/2016
8. BENNING PARK COMMUNITY CENTER07/28/2016
SCHEDULE
• Design Development: Fall ‘16
• Bidding/Award: Winter ‘16
• Construction: Spring ’17
• Anticipated Completion: Fall
or Winter ‘17
9. BENNING PARK COMMUNITY CENTER07/28/2016
COMMENTS/ NEXT STEPS
THANK YOU
Contacts:
Jackie Stanley, DGS:
jackie.stanley@dc.gov
Peter Nohrden, DPR:
peter.nohrden@dc.gov
• Agency Review:
• Design Development:
• Next Meeting: Fall ’16
• Q & A / Comments
Refreshments by:
104 Rhode Island Avenue NE
202-629-2040
orders@grassrootsgourmet.org