PMO – DELIVERY
METHODOLOGY OVERVIEW
Daniel Brody © 2014
TABLE OF CONTENTS
 PMO Overview	4
 PMO Roles & Responsibilities6
 PMO Phases9
 Key Performance Indicators 10
 PMO Tools 12
 Statement of Work/Contract 14
 Project Charter 15
 Project Workplan 17
 Project Calendar 18
 Deliverables Inventory 19
 Risk Management 20
05/22/14 2
TABLE OF CONTENTS
 Issue Management 22
 Change Request Management 25
 Decision Log 28
 Weekly Status Reports 29
 Monthly Steering Committee Meetings 30
 Meeting Agenda and Minutes 31
 Project QA Process 32
 Document Naming and Storage 33
 Client / Employee Satisfaction Processes 36
 Implementation Methodology Overview	 44
05/22/14 3
PMO OVERVIEW
What is a Project Management Office (PMO)?
 The PMO is composed of project leadership and administrative support (as required).
 The specific size and composition w	ill vary from project to project based on project size,
complexity, client involvement and project management capabilities
 The objective of the PMO is to ensure a successful project delivery:
 On time/on budget and overall control of Scope, Time & Cost
 Excellent client satisfaction
 Excellent employee/team satisfaction
 The benefits of a PMO include:
 Promotion of standard and repeatable delivery processes and deliverables
 Early identification and management of Issues and Risks
 Continual communication throughout the project team and client leadership
05/22/14 4
PMO OVERVIEW (CONT’D)
 Specific responsibilities of the PMO include:
 Project w	orkplan development and maintenance
 Regular time tracking, including identification of estimates to complete and
variances to budget
 Scope Change Management
 Status Reporting
 Deliverable review	
 Project operational and financial analysis
 Risk Management
 Issue Management
 Steering Committee Reporting
 Quality Review	s
05/22/14 5
PMO ROLES AND
RESPONSIBILITIES
05/22/14 6
The Project Management Office consists of project leadership and administrative
support staff as appropriate for the engagement. Factors such as project team size, risks
and complexity will determine the need for full or part-time Project Office and
Administrative Support.
Managing Director
Project Office
& Admin
Team Leads Team Leads
Project Manager
PMO ROLES AND
RESPONSIBILITIES
 Managing Director – The role of the Managing Director is to w	ork closely w	ith
senior client leadership to ensure a successful delivery process. The Managing
Director is focused on project delivery, successful adoption by user community, and
client satisfaction. The Managing Director w	ill serve on the Project Steering
Committee.
 Project Manager – The Project Manager has primary day-to-day responsibility for
the engagement. The PM w	ill be responsible for providing w	eekly status updates
to the client and for conducting monthly Steering Committee meetings. The PM is
also responsible for Risk Management and Issue Management.
 PMO Manager – The PMO Manager has day-to-day operational responsibility for
managing the PMO and overall quality assurance responsibility for the project.
This individual w	ill perform thorough QA assessments, assuring that projects meet
the defined business requirements, identifying risk areas and mitigating actions at
multiple points in the implementation cycle, and producing consolidated reports
from the PMO on all Programs and component projects. The PMO Manager is also
responsible for assessing actual project team time and expense utilization and
estimates to complete, relative to project budgets. The PMO Manager may be a
full or part-time role on the engagement.
05/22/14 7
PMO ROLES AND
RESPONSIBILITIES
 Project Administration – Depending on the project, resources may be assigned on a full and/or part-
time basis to assist w	ith administrative activities. The Project Administrator has direct responsibility
for maintaining the master project plans, resource schedules, and issue/change logs. This individual
w	ill issue the w	eekly task sheets, collect w	eekly time & estimate to complete reports, apply actuals to
the project plans, and produce w	eekly productivity and progress reports. The PA w	ill ensure that the
resource schedules are kept current, that standard meeting schedules are maintained, and w	ill
facilitate and maintain meeting minutes as required. Offsite IT Solutions personnel w	ill be
responsible for entry of financial information, accounts receivable, generation of financial reports,
etc. If Administrative support staff is not assigned to an engagement, these responsibilities may be
allocated amongst the other PMO team members.
 Team Leads – Depending on the engagement, individual team leads w	ill be responsible for
developing and managing the project plans associated w	ith their specific portions of the project.
These plans w	ill roll up into a summary w	orkplan. Team leads may also be responsible for preparing
status reports, participating in Steering Committee meetings and risk and issue management.
05/22/14 8
PMO PHASES
05/22/14 9
Initiation
(1 week)
Planning
(2 weeks)
Execution
(Project
Duration)
Closure
(1-2 weeks)
• Gather all available
background info (RFP,
proposal, discovery notes,
estimating models, timelines)
• Determine magnitude of
effort
• Schedule review with
@CIOBRODY leadership
• Set-up project (client codes,
project codes, accounting,
etc.)
• Develop detailed scope
statement with client
• Create Project Charter
• Create Project Schedule
• Create a consolidated project
workplan
• Conduct initial Risk
Assessment
• Conduct kickoff meeting(s)
• Obtain stakeholder buy-in of
plans, budget and scope
• Ensure resource availability
• Ongoing workplan
management
• Phase Reviews (QA & Risk
Assessment)
• Assist in management of
Issues and Risks
• Project performance analysis
• Client Satisfaction reviews
• Employee Satisfaction
Reviews
• Change control management
• Final project plan updates
• Communicate project
closure (charge codes
closed, accounting, etc.)
• Ensure @CIOBRODY
Staffing aware of resource
rolloff dates
• Generate Project Report
• Archive documentation
(soft and hard copies)
• Conduct debriefing
• Celebrate
DELIVERABLES
Sales Inputs
• RFP
• Proposal
• Discovery Notes
• Work level estimates
• Project codes
• Initial timelines
• Staffing requests
• Statement of
Work/Contract
• Project Charter
• Project Schedule
• Consolidated Workplan
• Resource Assignments
• Risk Assessment
• Initial Risk Log
• Kickoff presentation
• Updated workplan
• QA Assessment(s)
• Issues Logs
• Risk Assessment(s)
• Risk Logs
• Client Sat Surveys
• Employee Sat Surveys
• Change Logs
• Project performance
reports
• Final workplan
• Final performance/
profitability assessment
• Staff evaluations
• Project Report
• Documentation archives
• Client Sat Survey
• Client sign-off
• Employee Sat Survey
• Archived deliverables
• Follow-on Work
KEY PERFORMANCE INDICATORS
05/22/14 10
The chart on the following pages presents potential metrics that can be used by IT Solutions to assess its
performance. KPI’s have been organized by Financial, Operational and Administrative. The chart also indicates
whether the metric can be used to measure Business Development performance and/or to assess the delivery of an
individual project. Oracle will be used to provide these metrics where possible. Where Peoplesoft does not
capture the data needed, the TEMPLATE - Project Performance.xls spreadsheet may be used.
Metric Comment
Financial Metrics Refer to TEMPLATE - Project Performance.xls for details
Project Revenue Variance Broken down by Fees/Expenses and Totals. Calculate by dividing Estimate at
Completion (To Date + ETCs) - Budget. Report by Total as well as % of Budget.
Profitability Margin Broken down by Fees/Expenses and Totals. Calculate by taking fees (expenses and
total) realized per period and subtracting costs. Calculated in dollars as well as %.
Calculate variance vs. original budget.
Efficiency Measures Fees Earned (Budget Fees – ETC Fees). More relative on Fixed Fee
engagements than on T&M since Fees Earned = Hours Worked * Bill Rate.
Change Orders as % of Initial Budget Should not exceed x% of original budget. Measures effectiveness of
discovery/proposal process.
Follow-On Opportunities Proposed $ as well as closed $
Charge-Off % Project Write-Offs (0$ Change Orders, Expense Write-offs, Bill Reductions) as a %
of Total Budget
KEY PERFORMANCE INDICATORS
05/22/14 11
Metric Comment
Operational Metrics
Project Hourly Variance Calculate by dividing Estimate at Completion (To Date + ETCs) - Budget.
Report by Total as well as % of Budget.
Efficiency Measures Hours Earned (Budget Hours – ETC) against workplan.
Change Orders as % of Initial Budget Should not exceed x% of original budget. Measures effectiveness of
discovery/proposal process.
Client Satisfaction See TEMPLATE – Client Sat Results.xls and TEMPLATE – Client Sat
Survey.doc for survey form and summary spreadsheet
Project QA Results QA Survey form Form layout shown in TEMPLATE – QA Checklist
Administrative
Overtime %
Days Outstanding Timely payment by clients contributes to cash flow. Often an indicator of client
satisfaction.
Employee Satisfaction Refer to TEMPLATE – Employee Sat.doc
Utilization
Performance Reviews Outstanding Timely feedback critical to Employee Development
PMO TOOLSThe follow	ing slides present the standard tools w	hich w	ill be used by the PMO to provide quality delivery
oversight. Use of these tools is required and their application w	ill be review	ed as part of the project QA process.
05/22/14 12
PMO Deliverable Frequency/When Prepared By Inputs Template
Statement of
Work/Contract
Prior to kickoff Sales Team, Project
Manager, Managing Director
Proposal, Client feedback TEMPLATE – SOW.doc
Project Charter At project kickoff PM or PMO Manager with
input from Sales, Mng. Dir.
Proposal, Contract/SOW TEMPLATE – Project
Charter.doc
Project Workplan Created at kickoff, updated
at least weekly
PM or Team Leads with
input from team
SOW/Contract, Estimating
Models, Methodology
TEMPLATE – Project
Workplan.mpp
Project Calendar Created at kickoff, updated
at least weekly
PM or Project Admin. Workplan, Vacation Calendar
Deliverables Inventory Created at kickoff, updated
as workplan changes
PM Workplan, Methodology TEMPLATE –
Deliverables
Inventory.doc
Risk Assessment Art kickoff and at key
milestones
PMO Manager and/or
Managing Director
Proposal, Contract, Workplan,
Project deliverables, Client Sat
Surveys, Employee Sat Survey
TEMPLATE – Risk
Management Tool.xls
Risk Log Throughout project PM with input from Team
Leads
Risk Assessment TEMPLATE – Risk
Log.xls
Issues Log Throughout project PM or Team Leads with
input from team
IssueTrak www.issuetrak.com/@CI
OBRODY
Change Control Form &
Log
Throughout project PM or Team Leads with
input from team
Client Change Requests, Issues
Log
TEMPLATE – Project
Change Request
Form.doc
Template – Project
Change Request Log
PMO TOOLS
05/22/14 13
PMO Deliverable Frequency/When Prepared By Inputs Template
Decision Log Throughout project PM with input from
team leads
Significant client decisions that
should be highlighted and
communicated
TEMPLATE – Decision
Log.xls
Status Reports & Meeting
Minutes
Weekly throughout project PM and Team Leads Issues Log, Risk Log, Change
Request Log, Decision Log, Updated
Workplan
TEMPLATE – Weekly
Status Report.doc
Steering Committee
Presentation & Meeting
Minutes
Monthly throughout
project
Managing Director and
PM
Issues Log, Risk Log, Change
Request Log, Decision Log, Updated
Workplan
TEMPLATE – Steering
Committee
Presentation.ppt
Quality Assurance Checklist At phase/key milestone
completion
PMO Manager or
Managing Director
Proposal, Contract, Workplan, Project
deliverables, Client Sat Surveys,
Employee Sat Surveys, Status reports,
Steering Committee presentations
TEMPLATE – QA
Checklist.xls
Document Naming & Storage
Standards
Throughout sales cycle and
engagement
Sales and project
teams
Directory Structure.xls
Client Satisfaction Survey At kickoff and at
completion of phases/key
milestones
Managing Director or
PMO Manager
Client interviews TEMPLATE.Client
Satisfaction Survey.doc
TEMPLATE – Client
Satisfaction Results.xls
Employee Satisfaction Survey At least quarterly and at
project completion
Managing Director or
PMO Manager
Employee surveys (TEMPLATE –
Employee Satisfaction
Survey)
TEMPLATE –
Employee Sat
Results.xls
STATEMENT OF
WORK/CONTRACT
Before beginning any work for a client, a contract or Statement of Work (SOW) will be prepared by the Sales
Team, the Managing Director and the Project Manager. This document should be signed prior to sending any
team members to a client site, although exceptions may be appropriate for existing clients, follow-on
engagements or where the client has agreed to interim funding while the contract details are being finalized.
While the client may have their own standard contract formats, @CIOBRODY should ensure the following
information is presented within the SOW/Contract:
• Scope Definition – this should be a very detailed description of the services and deliverables @CIOBRODY is being engaged
to provide the client. It should describe the underlying business issues, the proposed solution, any integration
requirements, training to be provided, data conversion requirements, etc. in clear and concise terms.
• Assumptions – The SOW/Contract should also detail any assumptions made which impact scope (number or reports to be
written, location of project team members, resources to be provided by the client (people, workspace, computer
equipment, servers, access, project start dates , etc.).
• Timeline – A high-level overview of the key milestones of the engagement should be included in the SOW.
• Change Management – The contract/SOW should include a description of the process for identifying, documenting and
approving changes to scope.
• Project Organization – While specific names in the project organization may not be assigned, the SOW should include an
organization chart which shows the types and levels of client, @CIOBRODY and any vendor or other third party project
team and Steering Committee members. It should also include brief descriptions of key roles and responsibilities.
• Project Financials – The contract/SOW Should include the financial terms, payment schedule, expense policies, etc.
A sample Statement of Work is project in TEMPLATE – SOW.doc
05/22/14 14
PROJECT CHARTER
The Project Charter is a governance document. It will be developed during the project’s planning phase and
must be jointly approved by Client and @CIOBRODY Project Management prior to project execution phases.
The Project Charter documents:
 Project objectives, scope, and critical success factors
 Project approach
 Assumptions and planning principles
 Risks and constraints
 Key project resources
 Project workplan, responsibilities, and status reporting
 Project Management, Schedule Reviews, and Status Reporting
 Steering Committee Meetings
 Risk Management Reviews
 Quality Assurance Reviews
 Weekly Financial Reporting
 Time Entry
 Status Reporting
 Project Team Schedules
 Meeting Schedules, Agendas, and Meeting Minutes
 Client Contacts and Communications
05/22/14 15
05/22/14 16
PROJECT CHARTER
The Project Charter continued …
– General and Administrative policies
• Client Transmittals and Approval Documents
• Project Document Storage
• Standard work day
• Travel and Expense Reporting
• Dress Code
• Vacation and time-off requests
• Safety and health
PROJECT WORKPLAN
A detailed, task level project workplan will be prepared by the Project Manager and Team Leads. The
workplan will identify milestones, inter-task dependencies and any deliverables associated with each
task. It will also identify individual team members responsible for completing each task, the time
allocated to each team member for the task and the Start and Completion Dates. The workplan should
also include resource loading so that individual team members vacation or other time away from the
project is incorporated.
Microsoft Project will be used as the standard tool for developing workplans, project calendars, time
sheets and for recording time spent, ETCs, etc. It will then provide the data necessary for determining
project efficiency, budget variances and other performance metrics.
Team members will receive weekly (or bi-weekly) time tracking sheets so that they can record the time
spent on each task, the estimate to complete (or % complete) and any revisions to Start/End Dates.
This information should foot to the time sheets submitted to @CIOBRODY so that hours charged to the
project from a billing perspective equal those on the workplan. Reference the PMO Time Entry
Process.doc or Time Entry section of the Project Charter.
This data will also be loaded into the TEMPLATE - Project Performance.xls spreadsheet to calculate
Efficiency Ratios, Margins and Variances.
The workplan should be kept current with any changes to tasks, timelines or resource loadings due to
changes in scope, staffing or other factors.
05/22/14 17
PROJECT CALENDAR
A calendar which incorporates project milestones and key deliverable dates from the project workplan,
along with meetings and vacation or other time away for key project team members and clients will be
maintained. This calendar should be incorporated into the Weekly Status Reports to provide management
an ongoing short-term (4-5 week) window of upcoming events.
05/22/14 18
Monday Tuesday Wednesday Thursday Friday
8/12 8/13
 
8/14
1-2 – Status Meeting
 
8/15
 
8/16
Detail Design Sign-
Off
8/19
 
8/20 8/21
1-2 – Status Meeting
8/22
 
8/23
1-2 Steering 
Committee
8/26
CRP
8/27
CRP
8/28
CRP
1-2 – Status Meeting
8/29
2-3 Steering
Committee Mtg.
8/30
9/2
LABOR DAY
9/3
PM on Vacation
9/4
PM on Vacation
1-2 – Status Meeting
9/5
PM on Vacation
9/6
PM on Vacation
DELIVERABLES INVENTORY
Every project, regardless of size or complexity, should maintain an inventory of deliverables. This should
be generated as part of the workplan development process so that team members understand the specific
deliverables they are to produce and that clients understand what deliverables will be produced and when.
A standard file naming convention will be implemented to ensure consistency and allow for easy archival
and retrieval. Additionally, a standard set of file folders will be set up on the server to ensure deliverables
are stored in a common, secured, archived location (vs. individual hard drives) and that team members
know where to look for a specific document, vs. having to search multiple folders.
05/22/14 19
Deliverable Name Description Responsible Milestone
Date
Workpaper X-Ref
System Schematic PowerPoint or Visio drawing
presenting the Inputs, Processes
and Outputs of the system
Technical Architect 11/1/02 ISG.DD.System
Schematic.v1.doc
Test Scripts Word or Excel documents which
present test cases, test inputs and
expected results.
Test Team 12/1/02 ISG. ST.Test
Script.Cycle1.2.v1.doc
Training Plan Word document which provides a
high level summary of training
requirements and over timeline
for training.
Training Team 11/1/02 ISG.TR.Training Plan.IH.
v1.doc
RISK MANAGEMENT
Risk Management is an important element of successful project sales and delivery. Early identification
and continual management of serious issues and potential threats to a project is critical to ensuring
client satisfaction and an on-time, on-budget delivery.
Sales Process - During the Business Development cycle, it is important to conduct a thorough
discovery process to identify potential scope, client, technical and/or resource risks. Identifying these
risks early in the process will allow mitigation through reductions in scope or caveats and assumptions
clearly noted in the proposal and contract. This process will also demonstrate to the client a firm
understanding of the complexities of the engagement. The Risk Management Tool should be used by
the person who is responsible for writing the proposal as an initial Risk Assessment mechanism.
Delivery Process – Once an engagement is underway, Risk Identification and Management takes on
two distinct forms.
 Part of the Project Audit/QA process should include periodic risk assessments using the Risk Management Tool that
was also used during the Sales process as described above. This tool allows assessment of threats and risks that
are common to all projects. Conducting this assessment at key milestones/checkpoints throughout the
engagement will allow monitoring of mitigating and contingency plans to ensure their effectiveness and to allow
alternate resolutions to be pursued as appropriate.
 Throughout the engagement, it is the responsibility of senior project leadership to be continually aware of
potential threats to the project’s success. Use of the Risk Log to identify, manage and track all Risks is critical.
Updates on the status of new and previously identified Risks should be part of weekly status reporting and should
be a primary component of Steering Committee discussions.
05/22/14 20
RISK MANAGEMENT TOOLS
05/22/14 21
TOOL WHEN USED USED BY COMMENT
Risk Management Tool
(TEMPLATE – Risk
Management Tool.xls)
During proposal process
Project QA’s and Key
Milestone Checkpoints
Sales Lead
Managing Director
Project Manager
PMO Manager
Managing Director
Project Manager
Risks identified during these
reviews should be recorded in the
Risk Log to be tracked and
managed by senior project
management.
Risk Log
(TEMPLATE – Risk Log.xls)
Throughout project Project Manager
Senior project leads
All risks are recorded, tracked and
managed. Internal risks are
reported to @CIOBRODY
management, external risks are
reported on status reports and
discussed at Steering Committee
meetings.
ISSUE MANAGEMENT
An Issue is a situation, action, problem, or question arising during the performance of
the project which may or may not be efficiently or effectively resolved. Left un-
resolved, an issue will impede or prohibit project related progress or development by
delaying or suspending work effort. The purpose of issue resolution management is
to ensure issues are identified, logged, and tracked using an established format in
order to facilitate full issue disclosure, timely solutions, minimized project delays, and
minimize budget impacts.
@CIOBRODY has purchased an online Issue Tracking database tool. Issue Traker
allows project team members to record issues. Project management can then assign
responsibility to team members for analysis and manage the resolution process.
The PMO will:
 Maintain the Issue Traker Issue Management Tool and Database
 Assure proper submission and logging of identified issues
 Assure timely assignment of responsibilities for analysis, alternative development, and action planning
 Facilitate daily Issue Log Review Meetings with a “Zero Sum” focus
 Obtain necessary approvals for issue resolution action plans
 Log the approved actions and communicate decisions
 Update project plans and budgets
05/22/14 22
ISSUE RESOLUTION PROCESS
05/22/14 23
IssueTrak escalates
issues when
thresholds are missed
Client or team
member identifies
issue
IssueTrak
Issue Document
Assignment
Emails
PM / team lead assess
issue validity and
completes issue form in
Issuetrak
PM/team lead
coordinates analysis
of issue and
alternative
development
• Description
• Issue type
• Priority
• Assignment
• Open Issues
• Un-assigned Issues
• Resolved Issues
• Zero-Sum Focus
Daily Issue Log
PM / team leads
reviews issues log
daily
Escalation Email
to PM
IssueTrak
Issue Resolved,
Added to Project
Plan, Change
Request, or Closed
CHANGE REQUEST
MANAGEMENT
On any engagement, management of scope is an important component to the project’s success and to client
satisfaction. On fixed fee engagements, scope control is critical to ensure project profitability. On T&M
engagements, scope control will help ensure an on time, on budget delivery and will avoid potential client
conflicts. While it is not practical to assume a project’s scope will not change over the course of an engagement,
capturing change requests, fully analyzing them to identify potential workarounds and to assess their impact in
terms of costs and timeline changes, as obtaining appropriate client sign-off for any changes is an important
component of project management.
There are two primary components of the Change Request process – the Change Request form which details
individual change requests and a Change Request log which summarizes all requests. The Change Request form
(TEMPLATE – Change Request Form.doc) will be completed once a change to the project scope or agree-upon
requirements has been identified. Changes may result from system or user testing, pilot rollout or from issues
identified as processes and products change.
The person who identifies a potential change should complete a Change Request form, providing a description,
a priority assessment and identifying the impact of not implementing the requested change (workaround).
Once the initial request information has been completed, the project manager should coordinate obtaining the
necessary work level estimates and timeline impacts to assess the change. Based on the work level estimates,
they should provide cost impacts (fees and associated expenses) and review with the client to obtain approval or
to decide to table the change.
The Change Request log should be kept current throughout this process. All open and newly approved change
requests should be presented in the weekly status reports and reviewed in the monthly Steering Committee
meetings.
05/22/14 24
CHANGE REQUEST
MANAGEMENT
A Project Change Request is generated to document, track, and control adjustments to scope of work
including the addition or removal of requirements, date changes, resource changes, and budget
changes. The change may or may not impact project schedules or costs. These change requests will
provide a documented trail which will:
 Update revisions to the original definition of expected activities
 Provide information for the assessment of time, resource availability, and cost impact of the
requested change
A Project Change Request will be issued when:
 There may be a delay in obtaining required information or where the delay would impact the
project schedule commitments
 A decision or approval is required which could have a broad impact on business policies, processes,
or procedures
 An issue could impact the scope of work
 Change is the result of the removal of functionality or reduction in project costs
The PMO will ensure that Project Change Requests are fully documented, reviewed, tracked, and that
project impacts are appropriately assessed. The PMO will further ensure that these requests are
approved or rejected in a timely manner.
05/22/14 25
CHANGE REQUEST PROCESS
05/22/14 26
Project Admin
updates CR Log
Client (or team
member) identifies
issue
Client (or team
member) identifies
change
IssueTrak
Client (or team member)
determines change is
needed
Change Request
Form
Client (or PM/team lead)
completes Change
Request Form
PM/team lead
coordinates analysis
of request, reviews
with client
• Description
• Priority
• Workarounds
• Solution Alternatives
• Estimate of Effort
• Workplan impact
Change Request
Form
PM provides cost
estimate and obtains
client approval,
updates CR log
Change Request
Log
CR log presented in
weekly status and
monthly Steering
Committee meetings
DECISION LOG
A Decision Log is a valuable tool to be used on large, complex projects where client
resources are organizationally or geographically decentralized. It is to be used to help
ensure buy-in and accountability throughout the project team by communicating
decisions which impact the project’s scope or which may cause potential conflict.
Many of the items on the Decision Log will also be documented elsewhere (i.e., test plans,
design documents,etc.), but having a central repository noting significant decisions will
highlight potential conflict areas to ensure full communication and avoid later rework.
All new decisions should be included in the weekly status report and summarized in the
Steering Committee presentation. The Decision Log template and instructions for
completing each field is found in TEMPLATE – Decision Log.xls.
05/22/14 27
# Functional
Area
Description Made
By
Date Approved By Date
Approved
Date
Reported in
Status Mtg.
Impact
WEEKLY STATUS REPORTS
As part of the project charter, clients will commit to participating in
weekly status meetings. These meetings should include project
leadership representing @CIOBRODY (PM and Team Leads), vendors (if
appropriate) and the client (key client leads, client PM).
These meetings will ensure the client is continually updated on project
status, project risks, open issues, decisions, scope change requests and
upcoming milestones or project activities. It will also provide project
leadership the opportunity to identify cross-team issues or risks. A
status report will be prepared in advance using the template presented
in TEMPLATE-Weekly Status Report.doc. This pulls in information
from several sources including the workplan, Issues database, Risk Log,
Decision Log and Project Calendar.
During the meeting, minutes should be taken to capture any relevant
discussion or follow-up points. These meeting minutes, along with the
updated status report and supporting documents, should be
redistributed following the meeting.
05/22/14 28
MONTHLY STEERING COMMITTEE
MEETINGS
Another component of the project charter will be the establishment of a Steering Committee composed of
senior project leadership (@CIOBRODY, Vendor and Client) and other @CIOBRODY or Client management as
appropriate.
Whereas the weekly status meetings focus on progress to date and open items, the Steering Committee
presentations should generally address open risks, significant issues and scope changes. The format of the
presentations may change, but should include copies of the Risk Logs, Scope Change Logs and Issues Logs (high
priority/impact issues only).
As with the Weekly Status meetings, minutes should be taken during the Steering Committee meetings and
distributed to all participants and Steering Committee members. @CIOBRODY project management should
ensure client participation in these meetings. If clients are not regularly attending the meetings, it should be
documented as a project risk.
While some of the specific agenda items for Steering Committee meetings will vary based on the engagement,
the status of the project and the phase being completed, every Steering Committee should include the
following discussion topics (see TEMPLATE – Steering Committee Presentation.ppt):
 Status Update
 Open and Recently Resolved Risks
 Significant Issues Requiring Senior Management Attention
 Decision Log
 Upcoming milestones
05/22/14 29
05/22/14 30
MEETING AGENDA AND MINUTES
Meeting Agendas will be prepared by the meeting chairperson for all meetings, and distributed to expected
attendees prior to the scheduled time. The agenda should identify items for review and discussion
including who is responsible and expected discussion result, (ie: agreement, decision, direction, or
assignment). Meeting minutes will be recorded by the meeting chairperson or that person’s designee.
Action items and or decisions will be recorded in the IssueTrak data base. Items identified as decisions will
be recorded in the Decision Log. A template and instructions are presented in the TEMPLATE – Meeting
Agenda and Minutes.doc. The template includes:
– Title of Meeting
– Expectations
– Meeting called by
– Date / Time
– Place
– Attendees
– Please Bring
– Agenda Topics, Durations, and Owner
– Special Notes
– Minutes
– Action Items
PROJECT QA PROCESS
A Managing Director or other IT Solutions Executive not directly involved in the
project should conduct quarterly Quality Assurance reviews. The object of these
reviews is to ensure the project is being delivered according to @CIOBRODY’s
methodology and standards and that the project is not exposed to significant risk
that could impact its successful completion.
The QA template can be found in TEMPLATE – QA Checklist.xls. The checklist
identifies 53 individual checkpoints addressing items such as:
 Are the Risk and Issues Logs current and are being worked in a timely manner?
 Does the workplan have accurate ETCs?
 Are deliverables in standard format and of good quality?
 Do team members understand their upcoming tasks and responsibilities?
 Is there a test plan?
 Are there sufficient skills on the team?
The individual completing the QA assessment will rate each of the criteria (Good,
Fair, Poor and N/A). The spreadsheet will then calculate a QA score. Once the QA is
completed, the reviewer will work with project leadership (and the client if
appropriate) to develop action plans to address weaknesses identified in the review.
05/22/14 31
DOCUMENT NAMING AND
STORAGE
An important component of successful delivery organizations is their knowledge capital. Knowledge capital is
composed of the skills and experiences of individual team members but more importantly, the collective skills
and experience those team members gain within the organization. The ability to use repeatable deliverables
substantially simplifies work effort on subsequent engagements. Therefore, it is important that standard
deliverable formats and hard and soft-copy naming conventions and storage procedures be implemented. This
will allow team members to quickly locate documents and files, promote version control and backup, and will
support other teams who may be engaged in projects with similar characteristics, allowing them to reuse your
deliverables.
• Deliverable Templates – Deliverable template formats will be developed and stored on the shared drive.
Each template will be named with the prefix TEMPLATE – {Template name}.ext. Some templates have
already been created for use, particularly those supporting the PMO; others will be created as a standard
methodology is developed.
• File Naming – All files should be named using the following standard. ISG.{Doc Init}.{Doc Name}v.1.ext:
 ISG – Client Initials
 {Doc Initials} – 2 or 3 letter code indicating then document type. This code is found in the Directory Structure.xls
spreadsheet. Status report = “SR”, Steering Committee presentation = “SC”, etc.
 {Doc Name} – a unique identifier of the document being created. For instance – “Hennepin Sales Order Returns Process
Flow” or “Indiana Harbor Shipping System test Script”.
 v.x – Version. Use v.1, v.2, etc.
 ext – document extension assigned by the application used to create the document (doc, xls, ppt, mpp).
05/22/14 32
DOCUMENT NAMING AND
STORAGE
• Header/Footer – In addition to the naming standards, every document should have a standard header and
footer. The header should be formatted in bold font, centered at the top of the page and should include
{Client Name}: {Project Name}
{Document Title}
Subtitle (i.e., Excel tab) if applicable
The footer of every page should be in a small (8 or 10 point) font, and include the following:
{Directory/File Name} Page # Date Created: {mm/dd/yy}
Created By: {Author} Date Modified: {mm/dd/yy}
• Hard Copy retention – at the end of each phase, or whenever a client has signed-off on a document, a
printout should be stored in a deliverables folder. The deliverables should be stored according to the
hierarchy presented in the Directory Structure.xls spreadsheet.
• Original versions of documents which require client sign-off should be forwarded to Pittsburgh. A copy of
any client-signed document should be provided to the client and another retained by the project team.
Documents requiring client sign-off include:
 Contract/Statement of work
 Change requests
 Client satisfaction surveys
 Phase completion/deliverable sign-offs
05/22/14 33
DOCUMENT NAMING AND
STORAGE
 Network retention – Every project should have secured file server space for storing project
deliverables. Individual hard drives are not to be used to store any deliverable including work in
process, drafts or final versions, unless the team member is working from a remote location and does
not have access to the server. The server space should be backed up daily, with an offsite backup
made at least weekly. Individual team members should not create their own folders for work in
process or final deliverables. All deliverables should be stored in common folders according to the
hierarchy presented in the Directory Structure.xls spreadsheet.
05/22/14 34
CLIENT SATISFACTION PROCESS
The Client Satisfaction Survey process is a key component of @CIOBRODY IT Solutions’
success. Client satisfaction drives the ability to obtain repeat business at existing
clients, to provide additional services such as support agreements and to use clients as
references in obtaining new business. It provides feedback on our consulting skills and
the value we are perceived to provide to clients. It also helps project team members
understand what the client values and expects from us throughout an engagement so
that we can frame our efforts accordingly.
The process is composed of three primary components:
 A Pre-Survey conducted prior to, or shortly after, project kickoff. The Pre-Survey will introduce
the client to the Client Satisfaction survey form and process and will solicit input from the
client. The client will be asked to review the standard satisfaction criteria on our form and to
provide any additional, client-specific criteria that they consider important components of a
successful engagement. The client will also be asked to assign weightings to all the evaluation
criteria. Soliciting this information upfront will allow us to focus our energies accordingly and
to identify any potential issues early on.
 At the completion of each project phase (or at the end of shorter engagements), the client will
be asked to rate us using the standard criteria as well as the additional criteria they may have
added in the first step. They may also provide additional, free-form commentary. If the survey
is being conducted at the end of a phase (vs. end of the project), the client may also change
their assessment criteria and weightings obtained earlier.
 The final step in the review process is logging the results into a spreadsheet which will calculate
an overall client satisfaction index. This will allow for reporting by PM, by client, by line of
business, organization-wide or other criteria.
05/22/14 35
CLIENT SATISFACTION SURVEY
FORM
05/22/14 36
Survey Criteria Step 1 – Relative Importance
(Rank 1-Critical to
5-Unimportant
Step 2 – Hudson Score
(1 – Greatly Exceeded
to 5 – Dissatisfied)
Communication Skills
Project Management
Business Understanding
Technical Expertise
Professionalism
Quality of Work
Price/Value
Client Specific Criteria
Where did we greatly exceed your
expectations?
Where did we not exceed your
expectations?
Would you use Hudson Global
Resources IT Solutions for a future
project?
Would you recommend Hudson
Global Resources IT Solutions to
other potential clients?
The Client Satisfaction Survey is very straightforward to ensure client understanding and usage. The table
below summarizes the survey form, which is formatted differently for client distribution and completion.
CLIENT SATISFACTION SURVEY
RESULTS
The next slide shows the format of the spreadsheet to be used for entering survey results and
calculating the over Client Satisfaction Survey Score. The PMO Manager or Managing Director
should obtain the survey forms from the client and fill in the yellow-shaded fields with the survey
results.
Additional columns can be added to support extended engagements. This data could also be
extracted into a database for summary reporting by line item/criteria client, by sales person, by
project manager or other criteria as defined by IT Solutions management.
Analysis of the survey results will identify areas where @CIOBRODY may want to focus staff
development efforts or it may highlight areas where individual project manager performance
excels or needs improvement. It may also identify Business Development opportunities.
05/22/14 37
EMPLOYEE SATISFACTION
PROCESS
Employee Satisfaction is a key component to being able to attract and retain top talent. Given the
costs to recruit and train resources, keeping existing staff challenged and rewarded can help
manage costs, particularly in an economy where profitability is challenged by shrinking revenue.
Staff turnover rates are also reviewed by stock analysts to assess a company’s stability. High
turnover rates may be an indication of internal issues and may impact the ability to deliver
projects.
The Survey forms should be distributed to all project team members at least quarterly and at the
completion of a project. Employee Satisfaction surveys should be anonymous to allow team
members to be candid in their responses. The PMO Manager or Managing Director responsible
for the engagement (vs. the Project Manager) should be responsible for distributing and collecting
surveys.
The Survey questions and the spreadsheet used to tabulate the results and calculate results are
shown on the following page. The yellow-shaded cells are to be used by the PMO Manager to
enter survey results. Like the Client Satisfaction surveys, summary results may be analyzed by
Managing Director, Director, Manager, Line Item, Client or other criteria to identify areas for
improvement or potential counseling of team leadership.
05/22/14 38
@CIOBRODY RESOURCES
IMPLEMENTATION METHODOLOGY
OVERVIEW
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 40
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 41
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 42
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 43
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 44
IMPLEMENTATION METHODOLOGY
OVERVIEW
05/22/14 45

More Related Content

What's hot

ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiAli Kaabi
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)Dilawar Abbas
 
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth Infographic - How a PMO/PPM tool like PM3 gives one version of the truth
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth Bestoutcome
 
PMO - Added value instead of administration
PMO - Added value instead of administrationPMO - Added value instead of administration
PMO - Added value instead of administrationAndreas Splett
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmocrmackenzie
 
Implementing PMO
Implementing PMOImplementing PMO
Implementing PMOTURKI , PMP
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises Ghayas Mansoor
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMOfficers PMOAcademy
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1ken martin
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 

What's hot (20)

Real example of PMO deployment
Real example of PMO deploymentReal example of PMO deployment
Real example of PMO deployment
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
ePMO Workshop - Ali Kaabi
ePMO Workshop - Ali KaabiePMO Workshop - Ali Kaabi
ePMO Workshop - Ali Kaabi
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth Infographic - How a PMO/PPM tool like PM3 gives one version of the truth
Infographic - How a PMO/PPM tool like PM3 gives one version of the truth
 
PMO - Added value instead of administration
PMO - Added value instead of administrationPMO - Added value instead of administration
PMO - Added value instead of administration
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
PMO-Framework
PMO-FrameworkPMO-Framework
PMO-Framework
 
Implementing PMO
Implementing PMOImplementing PMO
Implementing PMO
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises Skeleton for EPMO roll out for large enterprises
Skeleton for EPMO roll out for large enterprises
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts Overview
 
Oim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure CoxOim Pmo It Governance Structure Cox
Oim Pmo It Governance Structure Cox
 
Pmo Why?
Pmo Why?Pmo Why?
Pmo Why?
 
What is a PMO
What is a PMOWhat is a PMO
What is a PMO
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Pmo Concept
Pmo ConceptPmo Concept
Pmo Concept
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 

Similar to @CIOBRODY PMO Methodology Overview

Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbTa Ngoc
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI ApproachZaur Ahmadov, PMP
 
Applying Project Management in the workplace(1)
Applying Project Management in the workplace(1)Applying Project Management in the workplace(1)
Applying Project Management in the workplace(1)Demilade Adewumi
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdfapoorvaguptaspn27
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbngocjos
 
Project Management
Project ManagementProject Management
Project ManagementPrarthan P
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management FundamentalsInsaf Ali Soomro PMP
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing managementDhamo daran
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creepOnkar Tendulkar
 

Similar to @CIOBRODY PMO Methodology Overview (20)

The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
Applying Project Management in the workplace(1)
Applying Project Management in the workplace(1)Applying Project Management in the workplace(1)
Applying Project Management in the workplace(1)
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Project Management
Project ManagementProject Management
Project Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
Pmipmo
PmipmoPmipmo
Pmipmo
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing management
 
Work plan and Scope creep
Work plan and Scope creepWork plan and Scope creep
Work plan and Scope creep
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
 

More from Daniel Brody

Launch180 Early adopters guide Incubator Case Study
Launch180 Early adopters guide Incubator Case StudyLaunch180 Early adopters guide Incubator Case Study
Launch180 Early adopters guide Incubator Case StudyDaniel Brody
 
Dan Brody Information and Technology Coach for Hire
Dan Brody Information and Technology Coach for HireDan Brody Information and Technology Coach for Hire
Dan Brody Information and Technology Coach for HireDaniel Brody
 
Voice To Text Solution
Voice To Text SolutionVoice To Text Solution
Voice To Text SolutionDaniel Brody
 
Managing the Warehouse Management
Managing the Warehouse ManagementManaging the Warehouse Management
Managing the Warehouse ManagementDaniel Brody
 
ITIL Best Practice for Software Companies
ITIL Best Practice for Software CompaniesITIL Best Practice for Software Companies
ITIL Best Practice for Software CompaniesDaniel Brody
 
ERP Fabrication Module Design Overview
ERP Fabrication Module Design OverviewERP Fabrication Module Design Overview
ERP Fabrication Module Design OverviewDaniel Brody
 
Yield Technology Marketing Automation Software
Yield Technology Marketing Automation SoftwareYield Technology Marketing Automation Software
Yield Technology Marketing Automation SoftwareDaniel Brody
 
Technology Guru Brody
Technology Guru BrodyTechnology Guru Brody
Technology Guru BrodyDaniel Brody
 
Steelman SEMS EBS Addon for Mills
Steelman SEMS EBS Addon for MillsSteelman SEMS EBS Addon for Mills
Steelman SEMS EBS Addon for MillsDaniel Brody
 

More from Daniel Brody (10)

Launch180 Early adopters guide Incubator Case Study
Launch180 Early adopters guide Incubator Case StudyLaunch180 Early adopters guide Incubator Case Study
Launch180 Early adopters guide Incubator Case Study
 
Dan Brody Information and Technology Coach for Hire
Dan Brody Information and Technology Coach for HireDan Brody Information and Technology Coach for Hire
Dan Brody Information and Technology Coach for Hire
 
Voice To Text Solution
Voice To Text SolutionVoice To Text Solution
Voice To Text Solution
 
Managing the Warehouse Management
Managing the Warehouse ManagementManaging the Warehouse Management
Managing the Warehouse Management
 
ITIL Best Practice for Software Companies
ITIL Best Practice for Software CompaniesITIL Best Practice for Software Companies
ITIL Best Practice for Software Companies
 
ERP Fabrication Module Design Overview
ERP Fabrication Module Design OverviewERP Fabrication Module Design Overview
ERP Fabrication Module Design Overview
 
Yield Technology Marketing Automation Software
Yield Technology Marketing Automation SoftwareYield Technology Marketing Automation Software
Yield Technology Marketing Automation Software
 
Technology Guru Brody
Technology Guru BrodyTechnology Guru Brody
Technology Guru Brody
 
Steelman SEMS EBS Addon for Mills
Steelman SEMS EBS Addon for MillsSteelman SEMS EBS Addon for Mills
Steelman SEMS EBS Addon for Mills
 
Steelman Sems 4.5
Steelman Sems 4.5Steelman Sems 4.5
Steelman Sems 4.5
 

Recently uploaded

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for LearningCIToolkit
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 

Recently uploaded (20)

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 

@CIOBRODY PMO Methodology Overview

  • 1. PMO – DELIVERY METHODOLOGY OVERVIEW Daniel Brody © 2014
  • 2. TABLE OF CONTENTS  PMO Overview 4  PMO Roles & Responsibilities6  PMO Phases9  Key Performance Indicators 10  PMO Tools 12  Statement of Work/Contract 14  Project Charter 15  Project Workplan 17  Project Calendar 18  Deliverables Inventory 19  Risk Management 20 05/22/14 2
  • 3. TABLE OF CONTENTS  Issue Management 22  Change Request Management 25  Decision Log 28  Weekly Status Reports 29  Monthly Steering Committee Meetings 30  Meeting Agenda and Minutes 31  Project QA Process 32  Document Naming and Storage 33  Client / Employee Satisfaction Processes 36  Implementation Methodology Overview 44 05/22/14 3
  • 4. PMO OVERVIEW What is a Project Management Office (PMO)?  The PMO is composed of project leadership and administrative support (as required).  The specific size and composition w ill vary from project to project based on project size, complexity, client involvement and project management capabilities  The objective of the PMO is to ensure a successful project delivery:  On time/on budget and overall control of Scope, Time & Cost  Excellent client satisfaction  Excellent employee/team satisfaction  The benefits of a PMO include:  Promotion of standard and repeatable delivery processes and deliverables  Early identification and management of Issues and Risks  Continual communication throughout the project team and client leadership 05/22/14 4
  • 5. PMO OVERVIEW (CONT’D)  Specific responsibilities of the PMO include:  Project w orkplan development and maintenance  Regular time tracking, including identification of estimates to complete and variances to budget  Scope Change Management  Status Reporting  Deliverable review  Project operational and financial analysis  Risk Management  Issue Management  Steering Committee Reporting  Quality Review s 05/22/14 5
  • 6. PMO ROLES AND RESPONSIBILITIES 05/22/14 6 The Project Management Office consists of project leadership and administrative support staff as appropriate for the engagement. Factors such as project team size, risks and complexity will determine the need for full or part-time Project Office and Administrative Support. Managing Director Project Office & Admin Team Leads Team Leads Project Manager
  • 7. PMO ROLES AND RESPONSIBILITIES  Managing Director – The role of the Managing Director is to w ork closely w ith senior client leadership to ensure a successful delivery process. The Managing Director is focused on project delivery, successful adoption by user community, and client satisfaction. The Managing Director w ill serve on the Project Steering Committee.  Project Manager – The Project Manager has primary day-to-day responsibility for the engagement. The PM w ill be responsible for providing w eekly status updates to the client and for conducting monthly Steering Committee meetings. The PM is also responsible for Risk Management and Issue Management.  PMO Manager – The PMO Manager has day-to-day operational responsibility for managing the PMO and overall quality assurance responsibility for the project. This individual w ill perform thorough QA assessments, assuring that projects meet the defined business requirements, identifying risk areas and mitigating actions at multiple points in the implementation cycle, and producing consolidated reports from the PMO on all Programs and component projects. The PMO Manager is also responsible for assessing actual project team time and expense utilization and estimates to complete, relative to project budgets. The PMO Manager may be a full or part-time role on the engagement. 05/22/14 7
  • 8. PMO ROLES AND RESPONSIBILITIES  Project Administration – Depending on the project, resources may be assigned on a full and/or part- time basis to assist w ith administrative activities. The Project Administrator has direct responsibility for maintaining the master project plans, resource schedules, and issue/change logs. This individual w ill issue the w eekly task sheets, collect w eekly time & estimate to complete reports, apply actuals to the project plans, and produce w eekly productivity and progress reports. The PA w ill ensure that the resource schedules are kept current, that standard meeting schedules are maintained, and w ill facilitate and maintain meeting minutes as required. Offsite IT Solutions personnel w ill be responsible for entry of financial information, accounts receivable, generation of financial reports, etc. If Administrative support staff is not assigned to an engagement, these responsibilities may be allocated amongst the other PMO team members.  Team Leads – Depending on the engagement, individual team leads w ill be responsible for developing and managing the project plans associated w ith their specific portions of the project. These plans w ill roll up into a summary w orkplan. Team leads may also be responsible for preparing status reports, participating in Steering Committee meetings and risk and issue management. 05/22/14 8
  • 9. PMO PHASES 05/22/14 9 Initiation (1 week) Planning (2 weeks) Execution (Project Duration) Closure (1-2 weeks) • Gather all available background info (RFP, proposal, discovery notes, estimating models, timelines) • Determine magnitude of effort • Schedule review with @CIOBRODY leadership • Set-up project (client codes, project codes, accounting, etc.) • Develop detailed scope statement with client • Create Project Charter • Create Project Schedule • Create a consolidated project workplan • Conduct initial Risk Assessment • Conduct kickoff meeting(s) • Obtain stakeholder buy-in of plans, budget and scope • Ensure resource availability • Ongoing workplan management • Phase Reviews (QA & Risk Assessment) • Assist in management of Issues and Risks • Project performance analysis • Client Satisfaction reviews • Employee Satisfaction Reviews • Change control management • Final project plan updates • Communicate project closure (charge codes closed, accounting, etc.) • Ensure @CIOBRODY Staffing aware of resource rolloff dates • Generate Project Report • Archive documentation (soft and hard copies) • Conduct debriefing • Celebrate DELIVERABLES Sales Inputs • RFP • Proposal • Discovery Notes • Work level estimates • Project codes • Initial timelines • Staffing requests • Statement of Work/Contract • Project Charter • Project Schedule • Consolidated Workplan • Resource Assignments • Risk Assessment • Initial Risk Log • Kickoff presentation • Updated workplan • QA Assessment(s) • Issues Logs • Risk Assessment(s) • Risk Logs • Client Sat Surveys • Employee Sat Surveys • Change Logs • Project performance reports • Final workplan • Final performance/ profitability assessment • Staff evaluations • Project Report • Documentation archives • Client Sat Survey • Client sign-off • Employee Sat Survey • Archived deliverables • Follow-on Work
  • 10. KEY PERFORMANCE INDICATORS 05/22/14 10 The chart on the following pages presents potential metrics that can be used by IT Solutions to assess its performance. KPI’s have been organized by Financial, Operational and Administrative. The chart also indicates whether the metric can be used to measure Business Development performance and/or to assess the delivery of an individual project. Oracle will be used to provide these metrics where possible. Where Peoplesoft does not capture the data needed, the TEMPLATE - Project Performance.xls spreadsheet may be used. Metric Comment Financial Metrics Refer to TEMPLATE - Project Performance.xls for details Project Revenue Variance Broken down by Fees/Expenses and Totals. Calculate by dividing Estimate at Completion (To Date + ETCs) - Budget. Report by Total as well as % of Budget. Profitability Margin Broken down by Fees/Expenses and Totals. Calculate by taking fees (expenses and total) realized per period and subtracting costs. Calculated in dollars as well as %. Calculate variance vs. original budget. Efficiency Measures Fees Earned (Budget Fees – ETC Fees). More relative on Fixed Fee engagements than on T&M since Fees Earned = Hours Worked * Bill Rate. Change Orders as % of Initial Budget Should not exceed x% of original budget. Measures effectiveness of discovery/proposal process. Follow-On Opportunities Proposed $ as well as closed $ Charge-Off % Project Write-Offs (0$ Change Orders, Expense Write-offs, Bill Reductions) as a % of Total Budget
  • 11. KEY PERFORMANCE INDICATORS 05/22/14 11 Metric Comment Operational Metrics Project Hourly Variance Calculate by dividing Estimate at Completion (To Date + ETCs) - Budget. Report by Total as well as % of Budget. Efficiency Measures Hours Earned (Budget Hours – ETC) against workplan. Change Orders as % of Initial Budget Should not exceed x% of original budget. Measures effectiveness of discovery/proposal process. Client Satisfaction See TEMPLATE – Client Sat Results.xls and TEMPLATE – Client Sat Survey.doc for survey form and summary spreadsheet Project QA Results QA Survey form Form layout shown in TEMPLATE – QA Checklist Administrative Overtime % Days Outstanding Timely payment by clients contributes to cash flow. Often an indicator of client satisfaction. Employee Satisfaction Refer to TEMPLATE – Employee Sat.doc Utilization Performance Reviews Outstanding Timely feedback critical to Employee Development
  • 12. PMO TOOLSThe follow ing slides present the standard tools w hich w ill be used by the PMO to provide quality delivery oversight. Use of these tools is required and their application w ill be review ed as part of the project QA process. 05/22/14 12 PMO Deliverable Frequency/When Prepared By Inputs Template Statement of Work/Contract Prior to kickoff Sales Team, Project Manager, Managing Director Proposal, Client feedback TEMPLATE – SOW.doc Project Charter At project kickoff PM or PMO Manager with input from Sales, Mng. Dir. Proposal, Contract/SOW TEMPLATE – Project Charter.doc Project Workplan Created at kickoff, updated at least weekly PM or Team Leads with input from team SOW/Contract, Estimating Models, Methodology TEMPLATE – Project Workplan.mpp Project Calendar Created at kickoff, updated at least weekly PM or Project Admin. Workplan, Vacation Calendar Deliverables Inventory Created at kickoff, updated as workplan changes PM Workplan, Methodology TEMPLATE – Deliverables Inventory.doc Risk Assessment Art kickoff and at key milestones PMO Manager and/or Managing Director Proposal, Contract, Workplan, Project deliverables, Client Sat Surveys, Employee Sat Survey TEMPLATE – Risk Management Tool.xls Risk Log Throughout project PM with input from Team Leads Risk Assessment TEMPLATE – Risk Log.xls Issues Log Throughout project PM or Team Leads with input from team IssueTrak www.issuetrak.com/@CI OBRODY Change Control Form & Log Throughout project PM or Team Leads with input from team Client Change Requests, Issues Log TEMPLATE – Project Change Request Form.doc Template – Project Change Request Log
  • 13. PMO TOOLS 05/22/14 13 PMO Deliverable Frequency/When Prepared By Inputs Template Decision Log Throughout project PM with input from team leads Significant client decisions that should be highlighted and communicated TEMPLATE – Decision Log.xls Status Reports & Meeting Minutes Weekly throughout project PM and Team Leads Issues Log, Risk Log, Change Request Log, Decision Log, Updated Workplan TEMPLATE – Weekly Status Report.doc Steering Committee Presentation & Meeting Minutes Monthly throughout project Managing Director and PM Issues Log, Risk Log, Change Request Log, Decision Log, Updated Workplan TEMPLATE – Steering Committee Presentation.ppt Quality Assurance Checklist At phase/key milestone completion PMO Manager or Managing Director Proposal, Contract, Workplan, Project deliverables, Client Sat Surveys, Employee Sat Surveys, Status reports, Steering Committee presentations TEMPLATE – QA Checklist.xls Document Naming & Storage Standards Throughout sales cycle and engagement Sales and project teams Directory Structure.xls Client Satisfaction Survey At kickoff and at completion of phases/key milestones Managing Director or PMO Manager Client interviews TEMPLATE.Client Satisfaction Survey.doc TEMPLATE – Client Satisfaction Results.xls Employee Satisfaction Survey At least quarterly and at project completion Managing Director or PMO Manager Employee surveys (TEMPLATE – Employee Satisfaction Survey) TEMPLATE – Employee Sat Results.xls
  • 14. STATEMENT OF WORK/CONTRACT Before beginning any work for a client, a contract or Statement of Work (SOW) will be prepared by the Sales Team, the Managing Director and the Project Manager. This document should be signed prior to sending any team members to a client site, although exceptions may be appropriate for existing clients, follow-on engagements or where the client has agreed to interim funding while the contract details are being finalized. While the client may have their own standard contract formats, @CIOBRODY should ensure the following information is presented within the SOW/Contract: • Scope Definition – this should be a very detailed description of the services and deliverables @CIOBRODY is being engaged to provide the client. It should describe the underlying business issues, the proposed solution, any integration requirements, training to be provided, data conversion requirements, etc. in clear and concise terms. • Assumptions – The SOW/Contract should also detail any assumptions made which impact scope (number or reports to be written, location of project team members, resources to be provided by the client (people, workspace, computer equipment, servers, access, project start dates , etc.). • Timeline – A high-level overview of the key milestones of the engagement should be included in the SOW. • Change Management – The contract/SOW should include a description of the process for identifying, documenting and approving changes to scope. • Project Organization – While specific names in the project organization may not be assigned, the SOW should include an organization chart which shows the types and levels of client, @CIOBRODY and any vendor or other third party project team and Steering Committee members. It should also include brief descriptions of key roles and responsibilities. • Project Financials – The contract/SOW Should include the financial terms, payment schedule, expense policies, etc. A sample Statement of Work is project in TEMPLATE – SOW.doc 05/22/14 14
  • 15. PROJECT CHARTER The Project Charter is a governance document. It will be developed during the project’s planning phase and must be jointly approved by Client and @CIOBRODY Project Management prior to project execution phases. The Project Charter documents:  Project objectives, scope, and critical success factors  Project approach  Assumptions and planning principles  Risks and constraints  Key project resources  Project workplan, responsibilities, and status reporting  Project Management, Schedule Reviews, and Status Reporting  Steering Committee Meetings  Risk Management Reviews  Quality Assurance Reviews  Weekly Financial Reporting  Time Entry  Status Reporting  Project Team Schedules  Meeting Schedules, Agendas, and Meeting Minutes  Client Contacts and Communications 05/22/14 15
  • 16. 05/22/14 16 PROJECT CHARTER The Project Charter continued … – General and Administrative policies • Client Transmittals and Approval Documents • Project Document Storage • Standard work day • Travel and Expense Reporting • Dress Code • Vacation and time-off requests • Safety and health
  • 17. PROJECT WORKPLAN A detailed, task level project workplan will be prepared by the Project Manager and Team Leads. The workplan will identify milestones, inter-task dependencies and any deliverables associated with each task. It will also identify individual team members responsible for completing each task, the time allocated to each team member for the task and the Start and Completion Dates. The workplan should also include resource loading so that individual team members vacation or other time away from the project is incorporated. Microsoft Project will be used as the standard tool for developing workplans, project calendars, time sheets and for recording time spent, ETCs, etc. It will then provide the data necessary for determining project efficiency, budget variances and other performance metrics. Team members will receive weekly (or bi-weekly) time tracking sheets so that they can record the time spent on each task, the estimate to complete (or % complete) and any revisions to Start/End Dates. This information should foot to the time sheets submitted to @CIOBRODY so that hours charged to the project from a billing perspective equal those on the workplan. Reference the PMO Time Entry Process.doc or Time Entry section of the Project Charter. This data will also be loaded into the TEMPLATE - Project Performance.xls spreadsheet to calculate Efficiency Ratios, Margins and Variances. The workplan should be kept current with any changes to tasks, timelines or resource loadings due to changes in scope, staffing or other factors. 05/22/14 17
  • 18. PROJECT CALENDAR A calendar which incorporates project milestones and key deliverable dates from the project workplan, along with meetings and vacation or other time away for key project team members and clients will be maintained. This calendar should be incorporated into the Weekly Status Reports to provide management an ongoing short-term (4-5 week) window of upcoming events. 05/22/14 18 Monday Tuesday Wednesday Thursday Friday 8/12 8/13   8/14 1-2 – Status Meeting   8/15   8/16 Detail Design Sign- Off 8/19   8/20 8/21 1-2 – Status Meeting 8/22   8/23 1-2 Steering  Committee 8/26 CRP 8/27 CRP 8/28 CRP 1-2 – Status Meeting 8/29 2-3 Steering Committee Mtg. 8/30 9/2 LABOR DAY 9/3 PM on Vacation 9/4 PM on Vacation 1-2 – Status Meeting 9/5 PM on Vacation 9/6 PM on Vacation
  • 19. DELIVERABLES INVENTORY Every project, regardless of size or complexity, should maintain an inventory of deliverables. This should be generated as part of the workplan development process so that team members understand the specific deliverables they are to produce and that clients understand what deliverables will be produced and when. A standard file naming convention will be implemented to ensure consistency and allow for easy archival and retrieval. Additionally, a standard set of file folders will be set up on the server to ensure deliverables are stored in a common, secured, archived location (vs. individual hard drives) and that team members know where to look for a specific document, vs. having to search multiple folders. 05/22/14 19 Deliverable Name Description Responsible Milestone Date Workpaper X-Ref System Schematic PowerPoint or Visio drawing presenting the Inputs, Processes and Outputs of the system Technical Architect 11/1/02 ISG.DD.System Schematic.v1.doc Test Scripts Word or Excel documents which present test cases, test inputs and expected results. Test Team 12/1/02 ISG. ST.Test Script.Cycle1.2.v1.doc Training Plan Word document which provides a high level summary of training requirements and over timeline for training. Training Team 11/1/02 ISG.TR.Training Plan.IH. v1.doc
  • 20. RISK MANAGEMENT Risk Management is an important element of successful project sales and delivery. Early identification and continual management of serious issues and potential threats to a project is critical to ensuring client satisfaction and an on-time, on-budget delivery. Sales Process - During the Business Development cycle, it is important to conduct a thorough discovery process to identify potential scope, client, technical and/or resource risks. Identifying these risks early in the process will allow mitigation through reductions in scope or caveats and assumptions clearly noted in the proposal and contract. This process will also demonstrate to the client a firm understanding of the complexities of the engagement. The Risk Management Tool should be used by the person who is responsible for writing the proposal as an initial Risk Assessment mechanism. Delivery Process – Once an engagement is underway, Risk Identification and Management takes on two distinct forms.  Part of the Project Audit/QA process should include periodic risk assessments using the Risk Management Tool that was also used during the Sales process as described above. This tool allows assessment of threats and risks that are common to all projects. Conducting this assessment at key milestones/checkpoints throughout the engagement will allow monitoring of mitigating and contingency plans to ensure their effectiveness and to allow alternate resolutions to be pursued as appropriate.  Throughout the engagement, it is the responsibility of senior project leadership to be continually aware of potential threats to the project’s success. Use of the Risk Log to identify, manage and track all Risks is critical. Updates on the status of new and previously identified Risks should be part of weekly status reporting and should be a primary component of Steering Committee discussions. 05/22/14 20
  • 21. RISK MANAGEMENT TOOLS 05/22/14 21 TOOL WHEN USED USED BY COMMENT Risk Management Tool (TEMPLATE – Risk Management Tool.xls) During proposal process Project QA’s and Key Milestone Checkpoints Sales Lead Managing Director Project Manager PMO Manager Managing Director Project Manager Risks identified during these reviews should be recorded in the Risk Log to be tracked and managed by senior project management. Risk Log (TEMPLATE – Risk Log.xls) Throughout project Project Manager Senior project leads All risks are recorded, tracked and managed. Internal risks are reported to @CIOBRODY management, external risks are reported on status reports and discussed at Steering Committee meetings.
  • 22. ISSUE MANAGEMENT An Issue is a situation, action, problem, or question arising during the performance of the project which may or may not be efficiently or effectively resolved. Left un- resolved, an issue will impede or prohibit project related progress or development by delaying or suspending work effort. The purpose of issue resolution management is to ensure issues are identified, logged, and tracked using an established format in order to facilitate full issue disclosure, timely solutions, minimized project delays, and minimize budget impacts. @CIOBRODY has purchased an online Issue Tracking database tool. Issue Traker allows project team members to record issues. Project management can then assign responsibility to team members for analysis and manage the resolution process. The PMO will:  Maintain the Issue Traker Issue Management Tool and Database  Assure proper submission and logging of identified issues  Assure timely assignment of responsibilities for analysis, alternative development, and action planning  Facilitate daily Issue Log Review Meetings with a “Zero Sum” focus  Obtain necessary approvals for issue resolution action plans  Log the approved actions and communicate decisions  Update project plans and budgets 05/22/14 22
  • 23. ISSUE RESOLUTION PROCESS 05/22/14 23 IssueTrak escalates issues when thresholds are missed Client or team member identifies issue IssueTrak Issue Document Assignment Emails PM / team lead assess issue validity and completes issue form in Issuetrak PM/team lead coordinates analysis of issue and alternative development • Description • Issue type • Priority • Assignment • Open Issues • Un-assigned Issues • Resolved Issues • Zero-Sum Focus Daily Issue Log PM / team leads reviews issues log daily Escalation Email to PM IssueTrak Issue Resolved, Added to Project Plan, Change Request, or Closed
  • 24. CHANGE REQUEST MANAGEMENT On any engagement, management of scope is an important component to the project’s success and to client satisfaction. On fixed fee engagements, scope control is critical to ensure project profitability. On T&M engagements, scope control will help ensure an on time, on budget delivery and will avoid potential client conflicts. While it is not practical to assume a project’s scope will not change over the course of an engagement, capturing change requests, fully analyzing them to identify potential workarounds and to assess their impact in terms of costs and timeline changes, as obtaining appropriate client sign-off for any changes is an important component of project management. There are two primary components of the Change Request process – the Change Request form which details individual change requests and a Change Request log which summarizes all requests. The Change Request form (TEMPLATE – Change Request Form.doc) will be completed once a change to the project scope or agree-upon requirements has been identified. Changes may result from system or user testing, pilot rollout or from issues identified as processes and products change. The person who identifies a potential change should complete a Change Request form, providing a description, a priority assessment and identifying the impact of not implementing the requested change (workaround). Once the initial request information has been completed, the project manager should coordinate obtaining the necessary work level estimates and timeline impacts to assess the change. Based on the work level estimates, they should provide cost impacts (fees and associated expenses) and review with the client to obtain approval or to decide to table the change. The Change Request log should be kept current throughout this process. All open and newly approved change requests should be presented in the weekly status reports and reviewed in the monthly Steering Committee meetings. 05/22/14 24
  • 25. CHANGE REQUEST MANAGEMENT A Project Change Request is generated to document, track, and control adjustments to scope of work including the addition or removal of requirements, date changes, resource changes, and budget changes. The change may or may not impact project schedules or costs. These change requests will provide a documented trail which will:  Update revisions to the original definition of expected activities  Provide information for the assessment of time, resource availability, and cost impact of the requested change A Project Change Request will be issued when:  There may be a delay in obtaining required information or where the delay would impact the project schedule commitments  A decision or approval is required which could have a broad impact on business policies, processes, or procedures  An issue could impact the scope of work  Change is the result of the removal of functionality or reduction in project costs The PMO will ensure that Project Change Requests are fully documented, reviewed, tracked, and that project impacts are appropriately assessed. The PMO will further ensure that these requests are approved or rejected in a timely manner. 05/22/14 25
  • 26. CHANGE REQUEST PROCESS 05/22/14 26 Project Admin updates CR Log Client (or team member) identifies issue Client (or team member) identifies change IssueTrak Client (or team member) determines change is needed Change Request Form Client (or PM/team lead) completes Change Request Form PM/team lead coordinates analysis of request, reviews with client • Description • Priority • Workarounds • Solution Alternatives • Estimate of Effort • Workplan impact Change Request Form PM provides cost estimate and obtains client approval, updates CR log Change Request Log CR log presented in weekly status and monthly Steering Committee meetings
  • 27. DECISION LOG A Decision Log is a valuable tool to be used on large, complex projects where client resources are organizationally or geographically decentralized. It is to be used to help ensure buy-in and accountability throughout the project team by communicating decisions which impact the project’s scope or which may cause potential conflict. Many of the items on the Decision Log will also be documented elsewhere (i.e., test plans, design documents,etc.), but having a central repository noting significant decisions will highlight potential conflict areas to ensure full communication and avoid later rework. All new decisions should be included in the weekly status report and summarized in the Steering Committee presentation. The Decision Log template and instructions for completing each field is found in TEMPLATE – Decision Log.xls. 05/22/14 27 # Functional Area Description Made By Date Approved By Date Approved Date Reported in Status Mtg. Impact
  • 28. WEEKLY STATUS REPORTS As part of the project charter, clients will commit to participating in weekly status meetings. These meetings should include project leadership representing @CIOBRODY (PM and Team Leads), vendors (if appropriate) and the client (key client leads, client PM). These meetings will ensure the client is continually updated on project status, project risks, open issues, decisions, scope change requests and upcoming milestones or project activities. It will also provide project leadership the opportunity to identify cross-team issues or risks. A status report will be prepared in advance using the template presented in TEMPLATE-Weekly Status Report.doc. This pulls in information from several sources including the workplan, Issues database, Risk Log, Decision Log and Project Calendar. During the meeting, minutes should be taken to capture any relevant discussion or follow-up points. These meeting minutes, along with the updated status report and supporting documents, should be redistributed following the meeting. 05/22/14 28
  • 29. MONTHLY STEERING COMMITTEE MEETINGS Another component of the project charter will be the establishment of a Steering Committee composed of senior project leadership (@CIOBRODY, Vendor and Client) and other @CIOBRODY or Client management as appropriate. Whereas the weekly status meetings focus on progress to date and open items, the Steering Committee presentations should generally address open risks, significant issues and scope changes. The format of the presentations may change, but should include copies of the Risk Logs, Scope Change Logs and Issues Logs (high priority/impact issues only). As with the Weekly Status meetings, minutes should be taken during the Steering Committee meetings and distributed to all participants and Steering Committee members. @CIOBRODY project management should ensure client participation in these meetings. If clients are not regularly attending the meetings, it should be documented as a project risk. While some of the specific agenda items for Steering Committee meetings will vary based on the engagement, the status of the project and the phase being completed, every Steering Committee should include the following discussion topics (see TEMPLATE – Steering Committee Presentation.ppt):  Status Update  Open and Recently Resolved Risks  Significant Issues Requiring Senior Management Attention  Decision Log  Upcoming milestones 05/22/14 29
  • 30. 05/22/14 30 MEETING AGENDA AND MINUTES Meeting Agendas will be prepared by the meeting chairperson for all meetings, and distributed to expected attendees prior to the scheduled time. The agenda should identify items for review and discussion including who is responsible and expected discussion result, (ie: agreement, decision, direction, or assignment). Meeting minutes will be recorded by the meeting chairperson or that person’s designee. Action items and or decisions will be recorded in the IssueTrak data base. Items identified as decisions will be recorded in the Decision Log. A template and instructions are presented in the TEMPLATE – Meeting Agenda and Minutes.doc. The template includes: – Title of Meeting – Expectations – Meeting called by – Date / Time – Place – Attendees – Please Bring – Agenda Topics, Durations, and Owner – Special Notes – Minutes – Action Items
  • 31. PROJECT QA PROCESS A Managing Director or other IT Solutions Executive not directly involved in the project should conduct quarterly Quality Assurance reviews. The object of these reviews is to ensure the project is being delivered according to @CIOBRODY’s methodology and standards and that the project is not exposed to significant risk that could impact its successful completion. The QA template can be found in TEMPLATE – QA Checklist.xls. The checklist identifies 53 individual checkpoints addressing items such as:  Are the Risk and Issues Logs current and are being worked in a timely manner?  Does the workplan have accurate ETCs?  Are deliverables in standard format and of good quality?  Do team members understand their upcoming tasks and responsibilities?  Is there a test plan?  Are there sufficient skills on the team? The individual completing the QA assessment will rate each of the criteria (Good, Fair, Poor and N/A). The spreadsheet will then calculate a QA score. Once the QA is completed, the reviewer will work with project leadership (and the client if appropriate) to develop action plans to address weaknesses identified in the review. 05/22/14 31
  • 32. DOCUMENT NAMING AND STORAGE An important component of successful delivery organizations is their knowledge capital. Knowledge capital is composed of the skills and experiences of individual team members but more importantly, the collective skills and experience those team members gain within the organization. The ability to use repeatable deliverables substantially simplifies work effort on subsequent engagements. Therefore, it is important that standard deliverable formats and hard and soft-copy naming conventions and storage procedures be implemented. This will allow team members to quickly locate documents and files, promote version control and backup, and will support other teams who may be engaged in projects with similar characteristics, allowing them to reuse your deliverables. • Deliverable Templates – Deliverable template formats will be developed and stored on the shared drive. Each template will be named with the prefix TEMPLATE – {Template name}.ext. Some templates have already been created for use, particularly those supporting the PMO; others will be created as a standard methodology is developed. • File Naming – All files should be named using the following standard. ISG.{Doc Init}.{Doc Name}v.1.ext:  ISG – Client Initials  {Doc Initials} – 2 or 3 letter code indicating then document type. This code is found in the Directory Structure.xls spreadsheet. Status report = “SR”, Steering Committee presentation = “SC”, etc.  {Doc Name} – a unique identifier of the document being created. For instance – “Hennepin Sales Order Returns Process Flow” or “Indiana Harbor Shipping System test Script”.  v.x – Version. Use v.1, v.2, etc.  ext – document extension assigned by the application used to create the document (doc, xls, ppt, mpp). 05/22/14 32
  • 33. DOCUMENT NAMING AND STORAGE • Header/Footer – In addition to the naming standards, every document should have a standard header and footer. The header should be formatted in bold font, centered at the top of the page and should include {Client Name}: {Project Name} {Document Title} Subtitle (i.e., Excel tab) if applicable The footer of every page should be in a small (8 or 10 point) font, and include the following: {Directory/File Name} Page # Date Created: {mm/dd/yy} Created By: {Author} Date Modified: {mm/dd/yy} • Hard Copy retention – at the end of each phase, or whenever a client has signed-off on a document, a printout should be stored in a deliverables folder. The deliverables should be stored according to the hierarchy presented in the Directory Structure.xls spreadsheet. • Original versions of documents which require client sign-off should be forwarded to Pittsburgh. A copy of any client-signed document should be provided to the client and another retained by the project team. Documents requiring client sign-off include:  Contract/Statement of work  Change requests  Client satisfaction surveys  Phase completion/deliverable sign-offs 05/22/14 33
  • 34. DOCUMENT NAMING AND STORAGE  Network retention – Every project should have secured file server space for storing project deliverables. Individual hard drives are not to be used to store any deliverable including work in process, drafts or final versions, unless the team member is working from a remote location and does not have access to the server. The server space should be backed up daily, with an offsite backup made at least weekly. Individual team members should not create their own folders for work in process or final deliverables. All deliverables should be stored in common folders according to the hierarchy presented in the Directory Structure.xls spreadsheet. 05/22/14 34
  • 35. CLIENT SATISFACTION PROCESS The Client Satisfaction Survey process is a key component of @CIOBRODY IT Solutions’ success. Client satisfaction drives the ability to obtain repeat business at existing clients, to provide additional services such as support agreements and to use clients as references in obtaining new business. It provides feedback on our consulting skills and the value we are perceived to provide to clients. It also helps project team members understand what the client values and expects from us throughout an engagement so that we can frame our efforts accordingly. The process is composed of three primary components:  A Pre-Survey conducted prior to, or shortly after, project kickoff. The Pre-Survey will introduce the client to the Client Satisfaction survey form and process and will solicit input from the client. The client will be asked to review the standard satisfaction criteria on our form and to provide any additional, client-specific criteria that they consider important components of a successful engagement. The client will also be asked to assign weightings to all the evaluation criteria. Soliciting this information upfront will allow us to focus our energies accordingly and to identify any potential issues early on.  At the completion of each project phase (or at the end of shorter engagements), the client will be asked to rate us using the standard criteria as well as the additional criteria they may have added in the first step. They may also provide additional, free-form commentary. If the survey is being conducted at the end of a phase (vs. end of the project), the client may also change their assessment criteria and weightings obtained earlier.  The final step in the review process is logging the results into a spreadsheet which will calculate an overall client satisfaction index. This will allow for reporting by PM, by client, by line of business, organization-wide or other criteria. 05/22/14 35
  • 36. CLIENT SATISFACTION SURVEY FORM 05/22/14 36 Survey Criteria Step 1 – Relative Importance (Rank 1-Critical to 5-Unimportant Step 2 – Hudson Score (1 – Greatly Exceeded to 5 – Dissatisfied) Communication Skills Project Management Business Understanding Technical Expertise Professionalism Quality of Work Price/Value Client Specific Criteria Where did we greatly exceed your expectations? Where did we not exceed your expectations? Would you use Hudson Global Resources IT Solutions for a future project? Would you recommend Hudson Global Resources IT Solutions to other potential clients? The Client Satisfaction Survey is very straightforward to ensure client understanding and usage. The table below summarizes the survey form, which is formatted differently for client distribution and completion.
  • 37. CLIENT SATISFACTION SURVEY RESULTS The next slide shows the format of the spreadsheet to be used for entering survey results and calculating the over Client Satisfaction Survey Score. The PMO Manager or Managing Director should obtain the survey forms from the client and fill in the yellow-shaded fields with the survey results. Additional columns can be added to support extended engagements. This data could also be extracted into a database for summary reporting by line item/criteria client, by sales person, by project manager or other criteria as defined by IT Solutions management. Analysis of the survey results will identify areas where @CIOBRODY may want to focus staff development efforts or it may highlight areas where individual project manager performance excels or needs improvement. It may also identify Business Development opportunities. 05/22/14 37
  • 38. EMPLOYEE SATISFACTION PROCESS Employee Satisfaction is a key component to being able to attract and retain top talent. Given the costs to recruit and train resources, keeping existing staff challenged and rewarded can help manage costs, particularly in an economy where profitability is challenged by shrinking revenue. Staff turnover rates are also reviewed by stock analysts to assess a company’s stability. High turnover rates may be an indication of internal issues and may impact the ability to deliver projects. The Survey forms should be distributed to all project team members at least quarterly and at the completion of a project. Employee Satisfaction surveys should be anonymous to allow team members to be candid in their responses. The PMO Manager or Managing Director responsible for the engagement (vs. the Project Manager) should be responsible for distributing and collecting surveys. The Survey questions and the spreadsheet used to tabulate the results and calculate results are shown on the following page. The yellow-shaded cells are to be used by the PMO Manager to enter survey results. Like the Client Satisfaction surveys, summary results may be analyzed by Managing Director, Director, Manager, Line Item, Client or other criteria to identify areas for improvement or potential counseling of team leadership. 05/22/14 38