TECH-6 CURRICULUM VITAE (CV) FOR PROPOSED PROFESSIONAL STAFF
Position Title & No. Highway Engineer 3
Name of Firm Hung Nghiep Construction Consulting Co., Ltd.
Name of Expert: NGUYEN Ngoc Duong
Date of birth: 22 June 1985
Citizenship Vietnamese
Education:
 Engineer degree in Bridge and Highway Engineering, University of Transport and Communication , Hochiminh
city – VietNam, 2008.
 Training courses in Supervising for Constructing Traffic Projects, 2012.
 Certification of Construction Design, MOC, 2013.
Employment record relevant to the assignment:
Period
Employing organization and your
title/position.
Contact information forreferences
Country
Summary of activities performed relevant to the
Assignment
08. 2012~
Present
Hung Nghiep Construction Consulting
Co., Ltd
Position: Highway Engineer/Highway
Team leader
Contact: DUONGVan Hiep
Tel: +84 9 1374 2295
E-mail: hiepdv@hungnghiep.com
Viet Nam
Prepare schedule of works for the projects of design
departments. Design road, bridge and infrastructure systems for
several projects in Vietnam. Reviewed engineering design and
drawings of all infrastructures. Prepared cost estimate on the
basis of the design & drawings.
03. 2011~
08. 2012
Katahira Engineering Co., Ltd.
Position: Highway/ Interchange Engineer
Contact: LE Ngoc Hieu
Tel: +84 9 3738 0768
E-mail: hieu.kei@gmail.com
Viet Nam
Design road alignment, profile, interchange, culvert for projects
in Vietnam. Prepared quantity tables.
06. 2010~
01. 2011
Nippon KoeiEngineering Co., Ltd.
Position: Highway/ Interchange Engineer
Contact: NGUYEN Manh Chung
Tel: +84 9 8913 2389
E-mail: manhchung.hwe@gmail.com
Viet Nam
Design road alignment, profile, interchange, culvert for projects
in Vietnam. Prepared quantity tables.
07. 2007~
05. 2010
Transport Engineering consulting joint
stock company No.553 (TECCO 533)
Position: Highway/ bridge Engineer
Contact: NGO Anh Sang
Tel: +84 9 8324 0176
Viet Nam
Design road, bridge, culvert, retaining wall, etc for projects in
Vietnam. Prepared quantity and cost estimate on the basis of the
design & drawings.
Membership in Professional Associations and Publications:
 Bridge, Road and Port Association ofHo Chi Minh city
Language Skills (indicate only languages in which you can work) :
Language Reading Writing Speaking
Vietnamese Native Native Native
English Good Good Good
Adequacy for the Assignment:
Detailed Tasks Assigned on
Consultant’s Team of Experts:
Reference to Prior Work/Assignments that Best Illustrates Capability to Handle the
AssignedTasks
Fulfill the relevant work on FS in
coordination with international
specialist in his absence.
Coordinate with other project team
members. Support the Deputy
Team Leader with design and
ensuring compliance with
Vietnamese specifications, laws
and requirements.
(1) Name of assignment or project: Feasibility Study for Constructing Province Road
DT852B projects, section from DT849 to Sa Dec city, Dong Thap province, Viet Nam
Year: October 2015 – present
Location: Dong Thap, Vietnam
Client: PMUDongThap
Main Project Features: Feasibility study to construct new road DT852B to connect
from DT849 to Sa Dec city. Total road length: 20.8km (including 1.81km urban road
W=25m), width=12m. Totalestimation cost of theproject is about VND 1,450 billion.
Positions held: Highway Engineer
TECHNICAL PROPOSAL
Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of
BEN LUC – NH22 and NH22 – BINH CHUAN Section under
Ho Chi Minh City Third Ring Road Technical Assistance Project
TECH-6 HighwayEngineer 3
NGUYEN Ngoc Duong
Page 2
Play a key contributing role in the
following tasks:
- Prepare detailed designs of
structureworks;
- Preparation of technical
specifications and bills of
quantities;
- Assist others with technical
details in reports;
- Analysis and design of road and
bridge. Including alignment,
profile, cross sections,
pavement, hydrological and
drainage system, embankment
structure, soil mechanics, earth
retaining wall structures based
on topography survey dataand
soil investigation.
- Using modern software such as
Civil 3D, Infraworks 360,
Revit, Viasys VDC,
Navisworks to make modelling
for roads, intersections,
interchanges and infrastructure
system. Then divide and assign
work in part for road team
members to work in interactive
digital environment.
- On-Site visits.
- Working with stakeholders to
collect data for projects.
Activities performed: Using modern software such as Civil 3D, Infraworks 360,
Revit, Viasys VDC, Navisworks to make modelling for roads, intersections and
infrastructure system. Then divide and assign work in part for road team members to
work in interactive digital environment.
- Detail design for alignment, plan and profile
- Detail design for interchanges.
- Design cross section.
- Design drainage.
- Calculation quantities.
(2) Name of assignment or project: Detailed Design for Mekong Delta Region Urban
Upgrading Project - Ca Mau City Sub-Project - Funded by World Bank (WB).
Year: December 2013 – June 2015
Location: Ca Mau province, Vietnam
Client: CaMau city Urban Upgrading Project Management Unit
Main Project Features:
Implement embankment against erosion, construct walkways, pavements and concrete
sewers, plant trees and arrange green grass beds along the river and arroyo banks in
LIAs 10, 12, 17, 18. Total embankment length is 3,147 m (of which reinforced concrete
embankment is 1,033m long in LIA 17, LIA 18, embankment’s length is 2,114m in the
remaining LIAs).
Construct new road which serves as main route to LIA 9 and residential quarters of
ward 8 in Tinh doi channel. Total length of the road construction is 863.8 m, road
width is 12m (including 2 lanes of 6m wide each), pavement’s width is 6.5m at two
sides.
Positions held: Highway Engineer
Activities performed: Using modern software such as Civil 3D, Infraworks 360 to
make modelling for roads, intersections and infrastructure system. Then divide and
assign work in part for road team members to work in interactive digital environment.
- Detail design for alignment, plan and profile
- Design cross section.
- Design drainage
- Calculation quantities.
(3) Name of assignment or project: Feasibility Study for Intermodal Transportation Strengthening Project (Ben Thanh - Suoi
Tien Section – HCM city Urban Railway Construction Project – Funded by JICA.
Year: December 2013 – July 2014
Location: Ho Chi Minh city, Vietnam
Client: Japan InternationalCooperation Agency (JICA)
Main Project Features:
The HCMC UMRT Line 1 project is a mass rapid transit construction project between Ben Thanh and Suoi Tien along the
Hanoi Highway. The total route length is 19.7 km long which consists of a 2.2 km long underground section and a 17.5 km
long elevated section. The study are to develop an implementation plan of a feeder bus network along the HCMC UMRT Line
1 and to conduct a feasibility study and basic design of intermodal facilities in station areas of the HCMC UMRT Line 1. The
design includes:
- Design station plazafor 10 stations of the project.
- Design bus station, car station, bus parking, car parking, motorcycle’s parking for passengers for 10 stations.
- Design additional pedestrian bridges as well as elevator, escalator,… to connect to thedesigned stations.
- Design landscape for the area.
Positions held: Highway Engineer
Activities performed:
- Detail design for alignment, plan and profile
- Design cross section.
- Design drainage
- Calculation quantities.
(4) Name of assignment or project: Feasibility Study for Second GMS Southern Coastal Corridor Project expressway project –
Funded by ADB.
Year: 8/2012 – 6/2013
Location: Kien Giang, Vietnam
Client: Cuu Long CIPM
Main Project Features:
The Second Greater Mekong Sub-region (GMS) Southern Coastal Corridor Project (Second GMS-SCCP) is proposed to
construct the missing sections of this GMSroad corridor in Kien Giang province in the southern coastal area of Viet Nam.
The proposed Second GMS-SCCP will construct the remaining 84km (between Ha Tien to Rach Gia) of QL80 route in Viet
Nam; construct the new 7.5km Minh Luong T-junction bypass from the end of the Rach Gia bypass at Rach Soi to the start of
the Tac Cau bypass; and (iii) upgrade Ha Tien (formerly Xa Xia) cross border facilities and streamline border crossing
procedures. In tune with one of the strategic thrusts of the GMS Strategic Framework (2012-2022), the proposed Second
TECHNICAL PROPOSAL
Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of
BEN LUC – NH22 and NH22 – BINH CHUAN Section under
Ho Chi Minh City Third Ring Road Technical Assistance Project
TECH-6 HighwayEngineer 3
NGUYEN Ngoc Duong
Page 3
GMS-SCCP is a necessary precondition for promoting broader economic corridor development.
Positions held: Highway Engineer
Activities performed: Using modern software such as Civil 3D and Infraworks 360 to make modelling for roads,
intersections, interchanges and infrastructure system. Then divide and assign work in part for road team members to work in
interactive digital environment.
- Detail design for alignment, plan and profile
- Design cross section.
- Design drainage
- Calculation quantities.
(5) Name of assignment orproject: Technical Design for GMSBen Luc – Long Thanh expressway project – Funded by ADB.
Year: 02/2011 - 08/ 2012
Location: Ho Chi Minh City and Long An province, Vietnam
Client: Vietnam Expressway Company (VEC)
Main Project Features:
Ben Luc-Long Thanh Expressway is one of 16 expressways under Eastern North-South Expressway according to
“Development planning of Vietnam expressway network toward 2020 and the vision after 2020”. Project Scale:
- Total length of the whole route is about 58.5Km. Location of the project: Long An province ( Ben Luc, Can Giuoc
districts); Ho Chi Minh City (Districts of Binh Chanh, Nha Be, Can Gio) and Dong Nai province (districts of Nhon Trach,
Dong Nai).
- Starting point of the project: The intersection point between Ho Chi Minh City- Trung Luong expressway and Ring Road
3 project (at about Km12+100 – Station of HCM –Trung Luong Expressway).
- Ending point of the project: The intersection point with Bien Hoa- Vung Tau expressway, phase 1, the ending point of the
project is located at the interchange with National Highway QL51 (at about Km35+350 – Station of National Highway
51).
Positions held: Highway Engineer
Activities performed: Using Civil 3D to:
- Detail design for alignment, plan and profile.
- Detail design for 11 interchanges.
- Design cross section.
- Design drainage system.
- Calculation quantities.
(6) Name of assignment or project: Technical Design for HCM - Long Thanh – Dau Giay expressway project – Funded by
ADB.
Year: 06/2010 to 01/2012
Location: Ho Chi Minh city and Dong Nai province, Vietnam
Client: Vietnam Expressway Company (VEC)
Main Project Features:
HCM - Long Thanh – Dau Giay expressway is one of 16 expressways under Eastern North-South Expressway according to
“Development planning of Vietnam expressway network toward 2020 and the vision after 2020”. Project Scale:
- Total length of the whole route is about 53Km. Location of the project: Ho Chi Minh City and Dong Nai province. This
expressway will connect with planned Long Thanh’s airport which will help create a part of the Southern Economic
Corridor under Greater Mekong Subregion (GMS) from Bangkok to Phnom Penh – Ho Chi Minh
- Starting point of theproject: The intersection point with East – West highway (An Phu district 2, Ho Chi Minh City)
- Ending point of the project: Theintersection point with Dau Giay, Dong Nai province.
Positions held: Highway Engineer
Activities performed:
- Detail design for 02 interchanges: Do Xuan Hop and An Phu
- Design alignment, plan, profile and cross section.
- Design traffic safety.
- Design drainage system.
- Calculation quantities.
(7) Name of assignment or project: Feasibility Study and Basic design for Improvement and expand highway No.1A project,
Khanh Hoa & Ninh Thuan province
Year: 03/2010 to 06/2010
Location: Khanh Hoa and Ninh Thuan provinces, Vietnam
Client: Department of Transportation of Khanh Hoa &Ninh thuan province
Main Project Features: Expansion project to upgrade National Highway 1A section from Cam Ranh - Phan Rang has a total
length of over 51 km is a part of the upgrading and expansion of National Highway 1A full part in ensuring traffic demand in
the coming years
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
TECHNICAL PROPOSAL
Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of
BEN LUC – NH22 and NH22 – BINH CHUAN Section under
Ho Chi Minh City Third Ring Road Technical Assistance Project
TECH-6 HighwayEngineer 3
NGUYEN Ngoc Duong
Page 4
(8) Name of assignment orproject: Construction drawing design for Vinh Hy – Ninh Chu project, Ninh Thuan province
Year: 01/2010 to 03/2010
Location: Ninh Thuan province, Vietnam
Client: Department of Transportation of Ninh thuan province
Main Project Features: The project corridor Vinh Hy – Ninh Chu has a total coastal length of over 30 km to help develop the
local economy and tourismof the province.
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
(9) Name of assignment or project: Construction drawing design for Improvement and expand road No.915 project, Dong nai
province,
Year: 09/2009 to 03/2010
Location: Dong Nai province, Vietnam
Client: Department of Transportation of Dong Nai province
Main Project Features: The project has a total coastal length of over 21 km to help develop the local economy and tourism
of the province.
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
(10) Name of assignment or project: Construction drawing design New construction of 2 bridges on NH1A (Package 2a) –
Funded by JBIC
Year: 2008-2009
Location: Hau Giang province, Vietnam
Client: PMUNo.2 - MOT
Main Project Features: Design construction drawings for Cai Huu bridge at Km2196+680 on NH1A. To avoid different
settlement between existing NH1A road and new embankment, approaching roads near abutments have to be treated by soft
soil treatment methods as PVD or SD.
Positions held: Highway Engineer.
Activities performed: Design approaching road for 2 bridges.
(11) Name of assignment or project: Technical Design for Improvement and expand highway No.53 project, Vinh Long and Tra
Vinh province
Year: 04/2009 to 09/2009
Location: Ho Chi Minh city, Vietnam
Client: Department of Transportation of Vinh Long and Tra Vinh province
Main Project Features: The project has a total coastal length of over 35 km to help develop the local economy and tourism
of the province.
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
(12) Name of assignment orproject: Technical Design for NamCan – Dat Muiproject, Ca Mau province
Year: 01/2009 to 04/2009
Location: Ca Mau province, Vietnam
Client: PMU46
Main Project Features: The project has a total coastal length of over 25 km to help develop the local economy and tourism
of the province.
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
(13) Name of assignment orproject: Feasibility Study for Rung Sac Road Project, Ho Chi Minh city, Viet nam
Year: 2007 to 2008
Location: Ho Chi Minh city, Vietnam
Client: Project Management Unit Can Gio District
Main Project Features: The Project involved the construction of the Rung Sac road, include 36.5 Km highway and 07
TECHNICAL PROPOSAL
Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of
BEN LUC – NH22 and NH22 – BINH CHUAN Section under
Ho Chi Minh City Third Ring Road Technical Assistance Project
TECH-6 HighwayEngineer 3
NGUYEN Ngoc Duong
Page 5
bridges: Long Giang Xay bridge, Rach Don bridge, An Nghia bridge, Ha Thanh bridge, Loi Giang bridge, Rach La bridge,
Nong Truong Q.5 bridge.
Positions held: Highway Engineer
Activities performed:
- Design alignment, plan, profile and cross section.
- Design traffic safety
- Design drainage
- Calculation quantities.
Expert’s contact information : duongnn@hungnghiep.com; Phone : +84 9 8664 2736
Certification:
I, the undersigned,certify to the best of my knowledge and belief that
(i) This CV correctly describes my qualifications and experience
(ii) I am not a current employee of the Executing or the Implementing Agency
(iii) In the absence of medical incapacity, I will undertake this assignment for the duration and in terms of the inputs specified for me in
TECH 6 provided team mobilization takes place within the validity of this proposal.
(iv) I was not part of the team who wrote the terms of reference for this consulting services assignment
(v) I am not currently debarred by a multilateral development bank
(vi) I certify that I have been informed by the firm that it is including my CV in the Proposal for the “Package 01: Consulting
Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section
under Ho Chi Minh City Third Ring Road Technical Assistance Project”. I confirm that I will be available to carry out the
assignment for which my CV has been submitted in accordance with the implementation arrangements and schedule set out in the
Proposal.
If CV is signed by the firm’s authorized representative:
(vii) I, as the authorized representative of the firm submitting this Proposal for the “Package 01: Consulting Services For
Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi
Minh City Third Ring Road Technical Assistance Project”, certify that I have obtained the consent of the named expert to submit
his/her CV, and that s/he will be available to carry out the assignment in accordance with the implementation arrangements and
schedule set out in the Proposal, and confirm his/her compliance with paras (i) to (v) above.
I understand that any willful misstatement described herein may lead to my disqualification or dismissal, if engaged.
Full name of the Expert : NGUYEN Ngoc Duong Date: 15/01/2016
Day/Month/Year
Full name of authorized representative: DUONG Van Hiep

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
Vishu resume new (1)
Vishu resume new (1)Vishu resume new (1)
Vishu resume new (1)
 
Curriculum Vitae-Zuber
Curriculum Vitae-ZuberCurriculum Vitae-Zuber
Curriculum Vitae-Zuber
 
Civil Engineer (Roads) with photo - Final
Civil Engineer (Roads) with photo - FinalCivil Engineer (Roads) with photo - Final
Civil Engineer (Roads) with photo - Final
 
(Highway Engineer) Raj singh
(Highway  Engineer) Raj singh(Highway  Engineer) Raj singh
(Highway Engineer) Raj singh
 
Cv of rafique 2020 cad
Cv of rafique 2020 cadCv of rafique 2020 cad
Cv of rafique 2020 cad
 
CV Sriinivas 1i doc
CV Sriinivas 1i docCV Sriinivas 1i doc
CV Sriinivas 1i doc
 
CV_KUSUM
CV_KUSUMCV_KUSUM
CV_KUSUM
 
Engr. Mohammed Alauddin CV
Engr. Mohammed Alauddin CVEngr. Mohammed Alauddin CV
Engr. Mohammed Alauddin CV
 
Cv mallikarjuna rao venkata bhadriraju 1 july 2019 consolidated
Cv mallikarjuna rao venkata  bhadriraju 1 july 2019 consolidatedCv mallikarjuna rao venkata  bhadriraju 1 july 2019 consolidated
Cv mallikarjuna rao venkata bhadriraju 1 july 2019 consolidated
 
USM-28-6-16
USM-28-6-16USM-28-6-16
USM-28-6-16
 
CV of M Saidul Islam.os
CV of M Saidul Islam.osCV of M Saidul Islam.os
CV of M Saidul Islam.os
 
Fawad cv a
Fawad cv aFawad cv a
Fawad cv a
 
CV-Rabiul Islam-2016
CV-Rabiul Islam-2016CV-Rabiul Islam-2016
CV-Rabiul Islam-2016
 
AECOM BAH-Madhava.Kulal.P
AECOM BAH-Madhava.Kulal.PAECOM BAH-Madhava.Kulal.P
AECOM BAH-Madhava.Kulal.P
 
Baba Lalin.B -Bridge Structural Engineer
Baba Lalin.B -Bridge Structural EngineerBaba Lalin.B -Bridge Structural Engineer
Baba Lalin.B -Bridge Structural Engineer
 
CV_Bavanam Veenadhari_July_16
CV_Bavanam Veenadhari_July_16CV_Bavanam Veenadhari_July_16
CV_Bavanam Veenadhari_July_16
 
Musammil -CV - 10-07-2016
Musammil  -CV - 10-07-2016Musammil  -CV - 10-07-2016
Musammil -CV - 10-07-2016
 
Ahmed saied cv_2016
Ahmed saied cv_2016Ahmed saied cv_2016
Ahmed saied cv_2016
 
PK_Thakore_New_CV
PK_Thakore_New_CVPK_Thakore_New_CV
PK_Thakore_New_CV
 

Destacado

L'omosessualità nelle scienze della salute mentale
L'omosessualità nelle scienze della salute mentaleL'omosessualità nelle scienze della salute mentale
L'omosessualità nelle scienze della salute mentaleAda Moscarella
 
Tarea 3 fisiologia conductual
Tarea 3 fisiologia conductualTarea 3 fisiologia conductual
Tarea 3 fisiologia conductualyenniffer22
 
MaiVanBinh_CV
MaiVanBinh_CVMaiVanBinh_CV
MaiVanBinh_CVBINH MAI
 
CURRICULUMVITAE ĐẶNG HOÀI LINH
CURRICULUMVITAE ĐẶNG HOÀI LINH CURRICULUMVITAE ĐẶNG HOÀI LINH
CURRICULUMVITAE ĐẶNG HOÀI LINH ĐẶNG Linh
 
Cv nguyen thi khanh ngoc - recherche de stage
Cv   nguyen thi khanh ngoc - recherche de stageCv   nguyen thi khanh ngoc - recherche de stage
Cv nguyen thi khanh ngoc - recherche de stageNGUYEN Thi Khanh Ngoc
 
CV_ Tran anh Tuan - EN (17122014)
CV_ Tran anh Tuan  - EN (17122014)CV_ Tran anh Tuan  - EN (17122014)
CV_ Tran anh Tuan - EN (17122014)Tr?n Tuan
 
My Resume (Agricultural Engineer)
My Resume (Agricultural Engineer)My Resume (Agricultural Engineer)
My Resume (Agricultural Engineer)Hưng Bùi
 
CV of Mr. NGUYEN VAN TRANG.doc
CV of Mr. NGUYEN VAN TRANG.docCV of Mr. NGUYEN VAN TRANG.doc
CV of Mr. NGUYEN VAN TRANG.docNguyenvan Trang
 
CV.PhamVoThanhDat
CV.PhamVoThanhDatCV.PhamVoThanhDat
CV.PhamVoThanhDatDat Pham
 
Phung Tran Resume
Phung Tran ResumePhung Tran Resume
Phung Tran ResumePhung Tran
 
CV _ Ha Van_310588 - LT
CV _ Ha Van_310588 - LTCV _ Ha Van_310588 - LT
CV _ Ha Van_310588 - LTnguyen ha van
 

Destacado (20)

Project Details
Project DetailsProject Details
Project Details
 
Cancer de mama
Cancer de mamaCancer de mama
Cancer de mama
 
L'omosessualità nelle scienze della salute mentale
L'omosessualità nelle scienze della salute mentaleL'omosessualità nelle scienze della salute mentale
L'omosessualità nelle scienze della salute mentale
 
La comunicazione
La comunicazioneLa comunicazione
La comunicazione
 
Tarea 3 fisiologia conductual
Tarea 3 fisiologia conductualTarea 3 fisiologia conductual
Tarea 3 fisiologia conductual
 
MaiVanBinh_CV
MaiVanBinh_CVMaiVanBinh_CV
MaiVanBinh_CV
 
CURRICULUMVITAE ĐẶNG HOÀI LINH
CURRICULUMVITAE ĐẶNG HOÀI LINH CURRICULUMVITAE ĐẶNG HOÀI LINH
CURRICULUMVITAE ĐẶNG HOÀI LINH
 
Cv nguyen thi khanh ngoc - recherche de stage
Cv   nguyen thi khanh ngoc - recherche de stageCv   nguyen thi khanh ngoc - recherche de stage
Cv nguyen thi khanh ngoc - recherche de stage
 
CV_ Tran anh Tuan - EN (17122014)
CV_ Tran anh Tuan  - EN (17122014)CV_ Tran anh Tuan  - EN (17122014)
CV_ Tran anh Tuan - EN (17122014)
 
SON-HONG-PHUC-CV
SON-HONG-PHUC-CVSON-HONG-PHUC-CV
SON-HONG-PHUC-CV
 
My Resume (Agricultural Engineer)
My Resume (Agricultural Engineer)My Resume (Agricultural Engineer)
My Resume (Agricultural Engineer)
 
Cv tai
Cv taiCv tai
Cv tai
 
CV of Mr. NGUYEN VAN TRANG.doc
CV of Mr. NGUYEN VAN TRANG.docCV of Mr. NGUYEN VAN TRANG.doc
CV of Mr. NGUYEN VAN TRANG.doc
 
CV_NGUYEN HON
CV_NGUYEN HONCV_NGUYEN HON
CV_NGUYEN HON
 
CV
CVCV
CV
 
CURRICULUM
CURRICULUMCURRICULUM
CURRICULUM
 
CV.PhamVoThanhDat
CV.PhamVoThanhDatCV.PhamVoThanhDat
CV.PhamVoThanhDat
 
CV_Anh Hào
CV_Anh HàoCV_Anh Hào
CV_Anh Hào
 
Phung Tran Resume
Phung Tran ResumePhung Tran Resume
Phung Tran Resume
 
CV _ Ha Van_310588 - LT
CV _ Ha Van_310588 - LTCV _ Ha Van_310588 - LT
CV _ Ha Van_310588 - LT
 

Similar a Highway Engineer Designs Roads

(2015-CV) Le Phuoc China (Eng)
(2015-CV) Le Phuoc China (Eng)(2015-CV) Le Phuoc China (Eng)
(2015-CV) Le Phuoc China (Eng)China Le Phuoc
 
Hays Highways CV
Hays Highways CVHays Highways CV
Hays Highways CVSa Ga
 
2016 AEC Excellence - Infrastructure Submissions
2016 AEC Excellence - Infrastructure Submissions 2016 AEC Excellence - Infrastructure Submissions
2016 AEC Excellence - Infrastructure Submissions Teresa Elliott
 
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...IRJET Journal
 
CV Transport Expert_Vu Anh Tuan (2015)
CV Transport Expert_Vu Anh Tuan (2015)CV Transport Expert_Vu Anh Tuan (2015)
CV Transport Expert_Vu Anh Tuan (2015)VU Anh Tuan
 
GM CV-Nov16
GM CV-Nov16 GM CV-Nov16
GM CV-Nov16 Babu Mama
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 

Similar a Highway Engineer Designs Roads (20)

(2015-CV) Le Phuoc China (Eng)
(2015-CV) Le Phuoc China (Eng)(2015-CV) Le Phuoc China (Eng)
(2015-CV) Le Phuoc China (Eng)
 
Hays Highways CV
Hays Highways CVHays Highways CV
Hays Highways CV
 
2016 AEC Excellence - Infrastructure Submissions
2016 AEC Excellence - Infrastructure Submissions 2016 AEC Excellence - Infrastructure Submissions
2016 AEC Excellence - Infrastructure Submissions
 
_Mohamad Bendary_Jan-2015
_Mohamad Bendary_Jan-2015_Mohamad Bendary_Jan-2015
_Mohamad Bendary_Jan-2015
 
Vijay banga
Vijay banga Vijay banga
Vijay banga
 
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...
COMPARATIVE ANALYSIS OF GEOMETRIC DESIGN OF HIGHWAY USING AUTOCAD CIVIL 3D AN...
 
CV Transport Expert_Vu Anh Tuan (2015)
CV Transport Expert_Vu Anh Tuan (2015)CV Transport Expert_Vu Anh Tuan (2015)
CV Transport Expert_Vu Anh Tuan (2015)
 
Muhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CVMuhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CV
 
Vijay banga
Vijay banga Vijay banga
Vijay banga
 
GM CV-Nov16
GM CV-Nov16 GM CV-Nov16
GM CV-Nov16
 
Detailed Experiance - REV01
Detailed Experiance - REV01Detailed Experiance - REV01
Detailed Experiance - REV01
 
CV_MPS_Elango_Vadiveloo
CV_MPS_Elango_VadivelooCV_MPS_Elango_Vadiveloo
CV_MPS_Elango_Vadiveloo
 
1a.Curriculum Vitae _English_.pdf
1a.Curriculum Vitae _English_.pdf1a.Curriculum Vitae _English_.pdf
1a.Curriculum Vitae _English_.pdf
 
CV_Anil Malagi
CV_Anil MalagiCV_Anil Malagi
CV_Anil Malagi
 
Shibendra_Kumar_Patel.
Shibendra_Kumar_Patel.Shibendra_Kumar_Patel.
Shibendra_Kumar_Patel.
 
Gaurav Kumar
Gaurav KumarGaurav Kumar
Gaurav Kumar
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
ToR
ToRToR
ToR
 
CV (1).doc
CV (1).docCV (1).doc
CV (1).doc
 
CURRICULAM VITAE - M
CURRICULAM VITAE - MCURRICULAM VITAE - M
CURRICULAM VITAE - M
 

Highway Engineer Designs Roads

  • 1. TECHNICAL PROPOSAL Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project TECH-6 HighwayEngineer 3 NGUYEN Ngoc Duong Page 1 TECH-6 CURRICULUM VITAE (CV) FOR PROPOSED PROFESSIONAL STAFF Position Title & No. Highway Engineer 3 Name of Firm Hung Nghiep Construction Consulting Co., Ltd. Name of Expert: NGUYEN Ngoc Duong Date of birth: 22 June 1985 Citizenship Vietnamese Education:  Engineer degree in Bridge and Highway Engineering, University of Transport and Communication , Hochiminh city – VietNam, 2008.  Training courses in Supervising for Constructing Traffic Projects, 2012.  Certification of Construction Design, MOC, 2013. Employment record relevant to the assignment: Period Employing organization and your title/position. Contact information forreferences Country Summary of activities performed relevant to the Assignment 08. 2012~ Present Hung Nghiep Construction Consulting Co., Ltd Position: Highway Engineer/Highway Team leader Contact: DUONGVan Hiep Tel: +84 9 1374 2295 E-mail: hiepdv@hungnghiep.com Viet Nam Prepare schedule of works for the projects of design departments. Design road, bridge and infrastructure systems for several projects in Vietnam. Reviewed engineering design and drawings of all infrastructures. Prepared cost estimate on the basis of the design & drawings. 03. 2011~ 08. 2012 Katahira Engineering Co., Ltd. Position: Highway/ Interchange Engineer Contact: LE Ngoc Hieu Tel: +84 9 3738 0768 E-mail: hieu.kei@gmail.com Viet Nam Design road alignment, profile, interchange, culvert for projects in Vietnam. Prepared quantity tables. 06. 2010~ 01. 2011 Nippon KoeiEngineering Co., Ltd. Position: Highway/ Interchange Engineer Contact: NGUYEN Manh Chung Tel: +84 9 8913 2389 E-mail: manhchung.hwe@gmail.com Viet Nam Design road alignment, profile, interchange, culvert for projects in Vietnam. Prepared quantity tables. 07. 2007~ 05. 2010 Transport Engineering consulting joint stock company No.553 (TECCO 533) Position: Highway/ bridge Engineer Contact: NGO Anh Sang Tel: +84 9 8324 0176 Viet Nam Design road, bridge, culvert, retaining wall, etc for projects in Vietnam. Prepared quantity and cost estimate on the basis of the design & drawings. Membership in Professional Associations and Publications:  Bridge, Road and Port Association ofHo Chi Minh city Language Skills (indicate only languages in which you can work) : Language Reading Writing Speaking Vietnamese Native Native Native English Good Good Good Adequacy for the Assignment: Detailed Tasks Assigned on Consultant’s Team of Experts: Reference to Prior Work/Assignments that Best Illustrates Capability to Handle the AssignedTasks Fulfill the relevant work on FS in coordination with international specialist in his absence. Coordinate with other project team members. Support the Deputy Team Leader with design and ensuring compliance with Vietnamese specifications, laws and requirements. (1) Name of assignment or project: Feasibility Study for Constructing Province Road DT852B projects, section from DT849 to Sa Dec city, Dong Thap province, Viet Nam Year: October 2015 – present Location: Dong Thap, Vietnam Client: PMUDongThap Main Project Features: Feasibility study to construct new road DT852B to connect from DT849 to Sa Dec city. Total road length: 20.8km (including 1.81km urban road W=25m), width=12m. Totalestimation cost of theproject is about VND 1,450 billion. Positions held: Highway Engineer
  • 2. TECHNICAL PROPOSAL Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project TECH-6 HighwayEngineer 3 NGUYEN Ngoc Duong Page 2 Play a key contributing role in the following tasks: - Prepare detailed designs of structureworks; - Preparation of technical specifications and bills of quantities; - Assist others with technical details in reports; - Analysis and design of road and bridge. Including alignment, profile, cross sections, pavement, hydrological and drainage system, embankment structure, soil mechanics, earth retaining wall structures based on topography survey dataand soil investigation. - Using modern software such as Civil 3D, Infraworks 360, Revit, Viasys VDC, Navisworks to make modelling for roads, intersections, interchanges and infrastructure system. Then divide and assign work in part for road team members to work in interactive digital environment. - On-Site visits. - Working with stakeholders to collect data for projects. Activities performed: Using modern software such as Civil 3D, Infraworks 360, Revit, Viasys VDC, Navisworks to make modelling for roads, intersections and infrastructure system. Then divide and assign work in part for road team members to work in interactive digital environment. - Detail design for alignment, plan and profile - Detail design for interchanges. - Design cross section. - Design drainage. - Calculation quantities. (2) Name of assignment or project: Detailed Design for Mekong Delta Region Urban Upgrading Project - Ca Mau City Sub-Project - Funded by World Bank (WB). Year: December 2013 – June 2015 Location: Ca Mau province, Vietnam Client: CaMau city Urban Upgrading Project Management Unit Main Project Features: Implement embankment against erosion, construct walkways, pavements and concrete sewers, plant trees and arrange green grass beds along the river and arroyo banks in LIAs 10, 12, 17, 18. Total embankment length is 3,147 m (of which reinforced concrete embankment is 1,033m long in LIA 17, LIA 18, embankment’s length is 2,114m in the remaining LIAs). Construct new road which serves as main route to LIA 9 and residential quarters of ward 8 in Tinh doi channel. Total length of the road construction is 863.8 m, road width is 12m (including 2 lanes of 6m wide each), pavement’s width is 6.5m at two sides. Positions held: Highway Engineer Activities performed: Using modern software such as Civil 3D, Infraworks 360 to make modelling for roads, intersections and infrastructure system. Then divide and assign work in part for road team members to work in interactive digital environment. - Detail design for alignment, plan and profile - Design cross section. - Design drainage - Calculation quantities. (3) Name of assignment or project: Feasibility Study for Intermodal Transportation Strengthening Project (Ben Thanh - Suoi Tien Section – HCM city Urban Railway Construction Project – Funded by JICA. Year: December 2013 – July 2014 Location: Ho Chi Minh city, Vietnam Client: Japan InternationalCooperation Agency (JICA) Main Project Features: The HCMC UMRT Line 1 project is a mass rapid transit construction project between Ben Thanh and Suoi Tien along the Hanoi Highway. The total route length is 19.7 km long which consists of a 2.2 km long underground section and a 17.5 km long elevated section. The study are to develop an implementation plan of a feeder bus network along the HCMC UMRT Line 1 and to conduct a feasibility study and basic design of intermodal facilities in station areas of the HCMC UMRT Line 1. The design includes: - Design station plazafor 10 stations of the project. - Design bus station, car station, bus parking, car parking, motorcycle’s parking for passengers for 10 stations. - Design additional pedestrian bridges as well as elevator, escalator,… to connect to thedesigned stations. - Design landscape for the area. Positions held: Highway Engineer Activities performed: - Detail design for alignment, plan and profile - Design cross section. - Design drainage - Calculation quantities. (4) Name of assignment or project: Feasibility Study for Second GMS Southern Coastal Corridor Project expressway project – Funded by ADB. Year: 8/2012 – 6/2013 Location: Kien Giang, Vietnam Client: Cuu Long CIPM Main Project Features: The Second Greater Mekong Sub-region (GMS) Southern Coastal Corridor Project (Second GMS-SCCP) is proposed to construct the missing sections of this GMSroad corridor in Kien Giang province in the southern coastal area of Viet Nam. The proposed Second GMS-SCCP will construct the remaining 84km (between Ha Tien to Rach Gia) of QL80 route in Viet Nam; construct the new 7.5km Minh Luong T-junction bypass from the end of the Rach Gia bypass at Rach Soi to the start of the Tac Cau bypass; and (iii) upgrade Ha Tien (formerly Xa Xia) cross border facilities and streamline border crossing procedures. In tune with one of the strategic thrusts of the GMS Strategic Framework (2012-2022), the proposed Second
  • 3. TECHNICAL PROPOSAL Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project TECH-6 HighwayEngineer 3 NGUYEN Ngoc Duong Page 3 GMS-SCCP is a necessary precondition for promoting broader economic corridor development. Positions held: Highway Engineer Activities performed: Using modern software such as Civil 3D and Infraworks 360 to make modelling for roads, intersections, interchanges and infrastructure system. Then divide and assign work in part for road team members to work in interactive digital environment. - Detail design for alignment, plan and profile - Design cross section. - Design drainage - Calculation quantities. (5) Name of assignment orproject: Technical Design for GMSBen Luc – Long Thanh expressway project – Funded by ADB. Year: 02/2011 - 08/ 2012 Location: Ho Chi Minh City and Long An province, Vietnam Client: Vietnam Expressway Company (VEC) Main Project Features: Ben Luc-Long Thanh Expressway is one of 16 expressways under Eastern North-South Expressway according to “Development planning of Vietnam expressway network toward 2020 and the vision after 2020”. Project Scale: - Total length of the whole route is about 58.5Km. Location of the project: Long An province ( Ben Luc, Can Giuoc districts); Ho Chi Minh City (Districts of Binh Chanh, Nha Be, Can Gio) and Dong Nai province (districts of Nhon Trach, Dong Nai). - Starting point of the project: The intersection point between Ho Chi Minh City- Trung Luong expressway and Ring Road 3 project (at about Km12+100 – Station of HCM –Trung Luong Expressway). - Ending point of the project: The intersection point with Bien Hoa- Vung Tau expressway, phase 1, the ending point of the project is located at the interchange with National Highway QL51 (at about Km35+350 – Station of National Highway 51). Positions held: Highway Engineer Activities performed: Using Civil 3D to: - Detail design for alignment, plan and profile. - Detail design for 11 interchanges. - Design cross section. - Design drainage system. - Calculation quantities. (6) Name of assignment or project: Technical Design for HCM - Long Thanh – Dau Giay expressway project – Funded by ADB. Year: 06/2010 to 01/2012 Location: Ho Chi Minh city and Dong Nai province, Vietnam Client: Vietnam Expressway Company (VEC) Main Project Features: HCM - Long Thanh – Dau Giay expressway is one of 16 expressways under Eastern North-South Expressway according to “Development planning of Vietnam expressway network toward 2020 and the vision after 2020”. Project Scale: - Total length of the whole route is about 53Km. Location of the project: Ho Chi Minh City and Dong Nai province. This expressway will connect with planned Long Thanh’s airport which will help create a part of the Southern Economic Corridor under Greater Mekong Subregion (GMS) from Bangkok to Phnom Penh – Ho Chi Minh - Starting point of theproject: The intersection point with East – West highway (An Phu district 2, Ho Chi Minh City) - Ending point of the project: Theintersection point with Dau Giay, Dong Nai province. Positions held: Highway Engineer Activities performed: - Detail design for 02 interchanges: Do Xuan Hop and An Phu - Design alignment, plan, profile and cross section. - Design traffic safety. - Design drainage system. - Calculation quantities. (7) Name of assignment or project: Feasibility Study and Basic design for Improvement and expand highway No.1A project, Khanh Hoa & Ninh Thuan province Year: 03/2010 to 06/2010 Location: Khanh Hoa and Ninh Thuan provinces, Vietnam Client: Department of Transportation of Khanh Hoa &Ninh thuan province Main Project Features: Expansion project to upgrade National Highway 1A section from Cam Ranh - Phan Rang has a total length of over 51 km is a part of the upgrading and expansion of National Highway 1A full part in ensuring traffic demand in the coming years Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities.
  • 4. TECHNICAL PROPOSAL Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project TECH-6 HighwayEngineer 3 NGUYEN Ngoc Duong Page 4 (8) Name of assignment orproject: Construction drawing design for Vinh Hy – Ninh Chu project, Ninh Thuan province Year: 01/2010 to 03/2010 Location: Ninh Thuan province, Vietnam Client: Department of Transportation of Ninh thuan province Main Project Features: The project corridor Vinh Hy – Ninh Chu has a total coastal length of over 30 km to help develop the local economy and tourismof the province. Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities. (9) Name of assignment or project: Construction drawing design for Improvement and expand road No.915 project, Dong nai province, Year: 09/2009 to 03/2010 Location: Dong Nai province, Vietnam Client: Department of Transportation of Dong Nai province Main Project Features: The project has a total coastal length of over 21 km to help develop the local economy and tourism of the province. Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities. (10) Name of assignment or project: Construction drawing design New construction of 2 bridges on NH1A (Package 2a) – Funded by JBIC Year: 2008-2009 Location: Hau Giang province, Vietnam Client: PMUNo.2 - MOT Main Project Features: Design construction drawings for Cai Huu bridge at Km2196+680 on NH1A. To avoid different settlement between existing NH1A road and new embankment, approaching roads near abutments have to be treated by soft soil treatment methods as PVD or SD. Positions held: Highway Engineer. Activities performed: Design approaching road for 2 bridges. (11) Name of assignment or project: Technical Design for Improvement and expand highway No.53 project, Vinh Long and Tra Vinh province Year: 04/2009 to 09/2009 Location: Ho Chi Minh city, Vietnam Client: Department of Transportation of Vinh Long and Tra Vinh province Main Project Features: The project has a total coastal length of over 35 km to help develop the local economy and tourism of the province. Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities. (12) Name of assignment orproject: Technical Design for NamCan – Dat Muiproject, Ca Mau province Year: 01/2009 to 04/2009 Location: Ca Mau province, Vietnam Client: PMU46 Main Project Features: The project has a total coastal length of over 25 km to help develop the local economy and tourism of the province. Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities. (13) Name of assignment orproject: Feasibility Study for Rung Sac Road Project, Ho Chi Minh city, Viet nam Year: 2007 to 2008 Location: Ho Chi Minh city, Vietnam Client: Project Management Unit Can Gio District Main Project Features: The Project involved the construction of the Rung Sac road, include 36.5 Km highway and 07
  • 5. TECHNICAL PROPOSAL Package 01:Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project TECH-6 HighwayEngineer 3 NGUYEN Ngoc Duong Page 5 bridges: Long Giang Xay bridge, Rach Don bridge, An Nghia bridge, Ha Thanh bridge, Loi Giang bridge, Rach La bridge, Nong Truong Q.5 bridge. Positions held: Highway Engineer Activities performed: - Design alignment, plan, profile and cross section. - Design traffic safety - Design drainage - Calculation quantities. Expert’s contact information : duongnn@hungnghiep.com; Phone : +84 9 8664 2736 Certification: I, the undersigned,certify to the best of my knowledge and belief that (i) This CV correctly describes my qualifications and experience (ii) I am not a current employee of the Executing or the Implementing Agency (iii) In the absence of medical incapacity, I will undertake this assignment for the duration and in terms of the inputs specified for me in TECH 6 provided team mobilization takes place within the validity of this proposal. (iv) I was not part of the team who wrote the terms of reference for this consulting services assignment (v) I am not currently debarred by a multilateral development bank (vi) I certify that I have been informed by the firm that it is including my CV in the Proposal for the “Package 01: Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project”. I confirm that I will be available to carry out the assignment for which my CV has been submitted in accordance with the implementation arrangements and schedule set out in the Proposal. If CV is signed by the firm’s authorized representative: (vii) I, as the authorized representative of the firm submitting this Proposal for the “Package 01: Consulting Services For Feasibility and Social/Safeguards Studies of BEN LUC – NH22 and NH22 – BINH CHUAN Section under Ho Chi Minh City Third Ring Road Technical Assistance Project”, certify that I have obtained the consent of the named expert to submit his/her CV, and that s/he will be available to carry out the assignment in accordance with the implementation arrangements and schedule set out in the Proposal, and confirm his/her compliance with paras (i) to (v) above. I understand that any willful misstatement described herein may lead to my disqualification or dismissal, if engaged. Full name of the Expert : NGUYEN Ngoc Duong Date: 15/01/2016 Day/Month/Year Full name of authorized representative: DUONG Van Hiep