The Cinder Bed Road Realignment Project in Fairfax County, VA was substantially completed in July 2017. The project realigned a portion of Cinder Bed Road and installed a triple box culvert to improve traffic flow and access to the Newington DVS Maintenance Facility. It also included stream restoration, construction of a sidewalk, trail, and drainage improvements. The project team consisted of members from the Department of Transportation, Land Acquisition Division, and Utilities Design and Construction Division.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Cinder Bed Road Realignment
Contract No. CN15304081
Project No. 5G25-054-000
Lee District
August 31, 2017
2. Cinder Bed Road Realignment
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
3. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Completed Stream Channel Restoration
Cinder Bed Road Realignment
4. Project Details
Cinder Bed Road Realignment
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Description:
The Cinder Bed Road Realignment Project was substantially completed on July 31, 2017. This
project consisted of construction of a triple box culvert, concrete sidewalk, asphalt trail, curb &
gutter, water line relocation, stream channel restoration and realignment of a portion of Cinder
Bed Road with new access into the Newington DVS Maintenance Facility.
Project Overview:
• Realignment of Cinder Bed Road for better traffic flow and access to the Newington DVS
Maintenance Facility
• Installation of triple box culvert over Long Branch Creek
• Installation RCP concrete pipe to improve drainage flow
• Stream Restoration
Project Team:
• Department of Transportation – Brook Khorashadi, Bob Ayers
• Land Acquisition Division – Beth Shubert
• Utilities Design and Construction Division (UDCD) – Ben Samiyi
• Project Inspector, UDCD – Howard Champ
5. Cinder Bed Road Realignment
Lee District, Tax Map No. 99-2 & 99-4
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Project
Location
Cinder Bed Road Realignment
6. Cinder Bed Road Realignment
Construction of Realigned Cinder Bed Road
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
7. Cinder Bed Road Realignment
Installation of Final Pavement and Striping
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
8. Cinder Bed Road Realignment
Construction of New DVS Access Road
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
9. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Cinder Bed Road Realignment
Stream Channel Restoration under Construction
10. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Cinder Bed Road Realignment
Triple Box Culvert under Construction
11. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Cinder Bed Road Realignment
Construction of Drainage Pipe
12. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Cinder Bed Road Realignment
Intersection of Cinder Bed Road & DVS Access Road
13. Before After
Cinder Bed Road Realignment
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
14. Before After
Intersection of Cinder Bed Road Realignment
and Newington Road
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
15. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Matthew Kaiser, Public Information Officer
703-324-5034, TTY 711
Matthew.Kaiser@fairfaxcounty.gov