The Dolley Madison sidewalk project included 345 linear feet of concrete sidewalk, pedestrian ramps, curb and gutter, modification of existing median, pavement marking and signage, pavement mill and overlay and other associated work.

  • Sé el primero en comentar

  • Sé el primero en recomendar esto

Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Dolley Madison Sidewalk Chain Bridge Road to Kurtz Road Contract No. CN17304122 Task Order No. 48 Project No. 5G25-060-015 Dranesville District Tax Map No. 30-2 December 7, 2018
  2. 2. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
  3. 3. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Project Site Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd Tax Map No. 30-2
  4. 4. Project Details Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Description: The Dolley Madison Sidewalk: Chain Bridge Road to Kurtz Road was substantially completed on November 20, 2018. The project included 345 LF concrete sidewalk, pedestrian ramps, curb and gutter, modification of existing median, pavement marking & signage, pavement mill and overlay and other associated work. Project Overview: • Project Delivery: Annual Contract • Contract: Unit Price Project Team: • Contractor • Ashburn Contracting Corporation • Fairfax County • Department of Transportation – Shahla Zahirieh • Utilities Design and Construction Division - Sanjala Bajracharya • Project Inspector, UDCD – Jim Cooper • Land Survey Branch, UDCD – Cody Harp-Taylor Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
  5. 5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd Installation of Sidewalk and Curb & Gutter Concrete Forming
  6. 6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd Installation of Concrete Sidewalk
  7. 7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd Soil Retention Mat (Jute Mesh)
  8. 8. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
  9. 9. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.kaiser@fairfaxcounty.gov

×