Enviar búsqueda
Cargar
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
•
1 recomendación
•
6,366 vistas
Fairfax County
Seguir
Little Hunting Creek Sewer Replacement Community Meeting: 12-1-2017
Leer menos
Leer más
Noticias y política
Vista de diapositivas
Denunciar
Compartir
Vista de diapositivas
Denunciar
Compartir
1 de 18
Descargar ahora
Descargar para leer sin conexión
Recomendados
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
Fairfax County
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Fairfax County
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Fairfax County
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
Fairfax County
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Fairfax County
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
Fairfax County
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
Fairfax County
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community Meeting
Fairfax County
Recomendados
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
Fairfax County
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Fairfax County
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Fairfax County
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
Fairfax County
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Fairfax County
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
Fairfax County
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
Fairfax County
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community Meeting
Fairfax County
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Fairfax County
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
Fairfax County
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
Fairfax County
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Fairfax County
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
Fairfax County
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
Fairfax County
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency Repair
Fairfax County
Belle View Pump Station Rehabilitation
Belle View Pump Station Rehabilitation
Fairfax County
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration Project
Fairfax County
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
Fairfax County
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
Fairfax County
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
Fairfax County
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
Fairfax County
Stormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
Fairfax County
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Fairfax County
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Fairfax County
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
Fairfax County
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Fairfax County
Summerton Way Pond Retrofit
Summerton Way Pond Retrofit
Fairfax County
North Shore Sidewalk Improvements
North Shore Sidewalk Improvements
Fairfax County
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
Fairfax County
Negdc presentation december 2013
Negdc presentation december 2013
carsoncorporation
Más contenido relacionado
La actualidad más candente
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Fairfax County
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
Fairfax County
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
Fairfax County
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Fairfax County
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
Fairfax County
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
Fairfax County
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency Repair
Fairfax County
Belle View Pump Station Rehabilitation
Belle View Pump Station Rehabilitation
Fairfax County
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration Project
Fairfax County
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
Fairfax County
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
Fairfax County
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
Fairfax County
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
Fairfax County
Stormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
Fairfax County
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Fairfax County
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Fairfax County
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
Fairfax County
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Fairfax County
Summerton Way Pond Retrofit
Summerton Way Pond Retrofit
Fairfax County
North Shore Sidewalk Improvements
North Shore Sidewalk Improvements
Fairfax County
La actualidad más candente
(20)
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency Repair
Belle View Pump Station Rehabilitation
Belle View Pump Station Rehabilitation
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration Project
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
Stormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Summerton Way Pond Retrofit
Summerton Way Pond Retrofit
North Shore Sidewalk Improvements
North Shore Sidewalk Improvements
Similar a Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
Fairfax County
Negdc presentation december 2013
Negdc presentation december 2013
carsoncorporation
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Fairfax County
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Fairfax County
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Florida Public Works Expo - 2016 - Tampa, Florida
Senior Design Presentation - Winter Term
Senior Design Presentation - Winter Term
Steven E. Kreeley, EIT
The permitting advantages and challenges of green infrastructure
The permitting advantages and challenges of green infrastructure
Southern New England American Planning Association
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
Northeast Ohio Regional Sewer District
Ahmedabad srfdcl
Ahmedabad srfdcl
Jigar Prajapati
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Fairfax County
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Fairfax County
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland
Final Design Presentation
Final Design Presentation
Brian Weaver
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Fairfax County
Rick Guenther Jr Resume
Rick Guenther Jr Resume
Rick Guenther
Dead Run Force Main Rehabilitation Project
Dead Run Force Main Rehabilitation Project
Fairfax County
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
Fairfax County
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
VDOT Northern Virginia
Pipe Bursting
Pipe Bursting
2014 Florida Public Works Expo
Similar a Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
(20)
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
Negdc presentation december 2013
Negdc presentation december 2013
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Senior Design Presentation - Winter Term
Senior Design Presentation - Winter Term
The permitting advantages and challenges of green infrastructure
The permitting advantages and challenges of green infrastructure
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
Ahmedabad srfdcl
Ahmedabad srfdcl
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Final Design Presentation
Final Design Presentation
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Rick Guenther Jr Resume
Rick Guenther Jr Resume
Dead Run Force Main Rehabilitation Project
Dead Run Force Main Rehabilitation Project
Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
Pipe Bursting
Pipe Bursting
Más de Fairfax County
Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
Fairfax County
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Fairfax County
Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Fairfax County
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Fairfax County
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station #19
Fairfax County
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Fairfax County
Sully Community Center Construction Progress
Sully Community Center Construction Progress
Fairfax County
Burke VRE Connector Phase IV
Burke VRE Connector Phase IV
Fairfax County
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Fairfax County
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Fairfax County
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Fairfax County
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Fairfax County
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Fairfax County
Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Fairfax County
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Fairfax County
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Fairfax County
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Fairfax County
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Fairfax County
Más de Fairfax County
(20)
Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station #19
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Sully Community Center Construction Progress
Sully Community Center Construction Progress
Burke VRE Connector Phase IV
Burke VRE Connector Phase IV
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Último
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
bhavenpr
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
NaveedKhaskheli1
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest2
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
FIRST INDIA
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
AbdulGhani778830
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
Gerald Furnkranz
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
Fabwelt
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
FIRST INDIA
Último
(8)
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
1.
LITTLE HUNTING CREEK SEWER
REPLACEMENT Community Meeting December 11, 2017
2.
© Arcadis 2017 •
Project Location and Background • Site Study and Alternatives Analysis • Design • Construction Agenda 2
3.
© Arcadis 2017 Project
Location 3
4.
© Arcadis 2017 Project
Background • Sanitary Sewer Crossing 789 LF of Little Hunting Creek • 12” Cast Iron Pipe • Constructed in 1961 • Extends from west end Woodland Lane to the east by Thomas J Stockton Parkway • Serves approximately 480 residences 4
5.
© Arcadis 2017 Condition
Assessment of Sewer • Site visit • Review of available information • Review maintenance history and records • Review of pipe video • Plan and Profile Survey 5
6.
© Arcadis 2017 Sewer
Pipe Profile 6
7.
© Arcadis 2017
7 Alternative Pro's Con's Viable Next Steps Pipe Bursting Utilizes the existing alignment along a known easement. Employs technology suitable for older cast iron pipe. Does not allow for the pipe to be adequately corrected in profile – pipe could still have sags. No Recommend no further evaluation. Cured in Place Pipe Lining Utilizes the existing alignment along a known easement. Employs a rehabilitation method suitable for a pipe of this diameter and material. Does not allow for the pipe to be adequately corrected in profile – pipe could still have sags. No Recommend no further evaluation. New Pump Station Eliminates need for work in the creek. Provides abandonment of the old line. New pumping station will need to be maintained. Requires constructing a new small force main as described in sub-alternatives. Requires building pump station within HOA property. Yes May require flow metering to confirm flow and flow peaking quantities. Need to consider effects of flow to the downstream pump station. New 6-inch Force Main Inside the Existing 12-inch Pipe Minimizes extensive permitting. Uses existing easement. Eliminates creek crossing construction work Requires cleaning existing pipe prior to pulling smaller pipe through. Need to determine if sag slopes are too steep to accommodate HDPE pipe. Yes Re-CCTV existing pipe with elevation readings to make sure pipe can act as a good conduit for a smaller pipe inside. Tie-Into Existing 30-inch” DIP Force Main on West Side of Creek Reduces length of force main construction. Eliminates creek crossing construction work. Risk of 30” pipe integrity issues to accommodate pipe tapping. Yes Investigate pipe integrity. If early phase of construction finds pipe is not suitable, direct contractor to alternative options. New Pump Station for a New Force Main on West Side of Street, Tie-In where Existing Force Main becomes a Gravity Sewer Eliminates creek crossing construction work. Requires community disruption along a significant distance. No Cost out linear footage of pipe and street repairs. Jack and Bore Minimizes any work in the creek Creates options for realignment and depth of alignment. Too long of a reach for most contracting methods. No No further evaluation. Horizontal Directional Drilling Creates options for realignment and depth of alignment. Minimizes any work in the creek. In order to achieve sufficient long-term bedding/stability, a deeper profile may be necessary that creates a siphon condition. Entire 789’ has to be fused ahead of time. HDD permit is more stringent. No Will need to know more about the bed of the creek to determine depth of drilling Should be explored and costed out as a viable alternative for comparison. Open Cut Pipe Replacement with Dam Allows best assessment of bedding of pipe during construction. Reduces the amount of on-shore work in proximity of residences. Provides a long life expectancy. Requires significant detailed permitting. Requires coffer-damming and related impacts in the creek. May require restoration of impacted wetlands. Yes Requires exploring permitting challenges Should be explored and costed-out as a viable alternative for comparison. Do Nothing Eliminates construction in the creek. No disruption to the community. Continued maintenance for cleaning and inspection. Asset remains in poor condition and stays on the high-risk list. No Will be developed only as a baseline alternative for cost comparison. Alternatives Analysis
8.
© Arcadis 2017 Criteria
Matrix: Open Cut with Pipe Replacement 8
9.
© Arcadis 2017 Conceptual
Replacement Design Layout 9
10.
© Arcadis 2017 Key
Design Investigations Vegetation SurveyWetlands Delineation Field Survey 10 Geotechnical Investigation
11.
© Arcadis 2017 Development
of Design Plans and Specification • Alignment • Pipe support • Construction: dam, dewatering, trench support - Specialty contractor • Contract documents 11
12.
© Arcadis 2017 Permitting •
Goals ‒ Provide appropriate solution and meet basic design criteria ‒ Environmental stewardship • Process ‒ Early engagement ‒ Permit development ‒ Permit submissions ‒ Review by agencies ‒ Approval 12
13.
© Arcadis 2017 Design
Schedule • Design: December 2017 – April 2019 – Permit Development February 2018 - March 2018 – Permit Review November 2018 – March 2019 13
14.
© Arcadis 2017 Permitting Regulatory
Entity Permit Virginia Department of Environmental Quality (DEQ) Virginia Marine Resource Commission (VMRC) Virginia Pollutant Discharge Elimination System (VPDES), CWA Sec. 404/401, VSMP-Stormwater Pollution Prevention Plan United States Army Corps of Engineers (USACE) CWA Sec. 404/401, Nationwide Permit #6 DEQ, VMRC, USACE Tidal Water Joint Permit Application VDOT Various Fairfax County Compliance with Chesapeake Bay Preservation Ordinance DPWES Land Development Site and Building Permits Virginia Department of Environmental Quality (DEQ) Certificate to Construct (CTC) United States Army Corps of Engineers Nationwide Permit #12 14
15.
© Arcadis 2017 Construction
Considerations • Creek construction – 2-stage coffer dam • Minimize impact to the park and boat ramp (off-site staging, construction parking and traffic) • Schedule will minimize interference with recreational creek activities and consider time of year restrictions Portadam Brochure 15
16.
© Arcadis 2017 Construction
Schedule • Estimated start: May 2019 • Anticipated time of year restriction: February 15 – June 30 • Construction: July 2019 – November 2019 • Construction Costs: $1.2 – 1.6 million dollars 16
17.
© Arcadis 2017 Schedule 17
18.
© Arcadis 2017 Questions/Comments 18