DESIGN OF AIR PRE HEATER
AND ECONOMIZER
Submitted by
J.SHANMUKA VENKATA GOPICHAND (101FA08133)
L.SURYA TEJA (101FA08141)
Under the guidance of(Internal)
N.B.PRAKASH TIRUVEEDULA
ASSISTANT PROFESSOR
VIGNAN UNIVERSITY
Under the guidance of(External)
Mr. SREEKANTH JABADE
GM AND PROJECT ENGG
HARTEX RUBBER PVT LTD
CONTENTS
1. Process of Air pre-heater
2. Economizer
3. Boiler basics
4. Heat Exchangers
5. Cross Flow & Compact Heat Exchangers
6. Design Calculation of Economizer
7. Design Calculation of Air pre-heater
8. Boiler Efficiency
9. Heat Balance sheet
10. Conclusion
Process of Air pre-heater
• An air pre-heater (APH) is a general term to describe any device designed to heat air
before another process (for example, combustion in a boiler) with the primary objective of
increasing the thermal efficiency of the process.
• There are two types of air pre-heaters for use in steam generators in thermal power
stations: One is a tubular type built into the boiler flue gas ducting, and the other is a
regenerative air pre-heater.
• Ambient air is forced by a fan through ducting at one end of the pre-heater tubes and at
other end the heated air from inside of the tubes emerges into another set of ducting,
which carries it to the boiler furnace for combustion
• There are two types of regenerative air pre-heaters: the rotating-plate regenerative air pre-
heaters (RAPH) and the stationary-plate regenerative air pre-heaters.
• Rotating-plate regenerative air pre-heater
• The rotating-plate design (RAPH) consists of a central rotating-plate element installed
within a casing that is divided into two (bi-sector type), three (tri-sector type) or four
(quad-sector type) sectors containing seals around the element.
• In stationary-plate regenerative air pre-heaters the heating plate elements are also installed
in a casing, but the heating plate elements are stationary rather than rotating.
Economizer
• Economizers are mechanical devices intended to reduce energy
consumption, or to perform another useful function such as preheating a
fluid.
• Economizer performs a key function in providing high overall boiler
thermal efficiency by recovering low level energy from the flue gas before
it is exhausted to the atmosphere.
• Economizer recovers the energy by heating the boiler feed water.
• It scavenge the waste heat from thermal exhaust flue gases by passing the
exhaust effluent through heat transfer surfaces to transfer some of the
waste heat to a process media.
• It Efficiency is in direct relationship to equipment design and stack gas
velocities.
• Velocity increases through the stack as firing rate increases, which results
in a decrease in contact time with the economizer heating surfaces
BOILER BASICS
• The hot water or steam under pressure is then usable for transferring the heat for the steam
requirements of process industries or for power generation.
• During the combustion process, oxygen reacts with carbon, hydrogen and other elements
in the fuel to produce a flame and hot combustion gases.
• As these gases are drawn through the boiler, they cool as heat is transferred to water
• The main components in a boiler system are boiler feed water heaters, deaerator, feed
pump, economizer, super heater, Attemperators, condenser and condensate pump.
Heat Exchangers
Heat Exchangers are classified according to their function and geometry:
Function:
Recuperative: two fluids separated by a solid wall
Evaporative: enthalpy of evaporation of one fluid is used to heat or cool the other fluid.
Regenerative: use a third material which stores/releases heat
Geometry: 1. Double Tube 2. Shell and Tube
3. Cross-flow Heat Exchangers 4. Compact Heat Exchangers
Heat Exchangers
• The heat transfer rate for most heat exchangers can be calculated using the LMTD-method
(Log Mean Temperature Difference), if the inlet (T1) and outlet (T2) temperatures are
known:
U = Overall heat transfer coefficient [ W/m2-oC ]
A = Effective heat transfer surface area [ m2 ]
F = Geometry correction factor
= Log mean temperature difference
 
F
TT
TT
T
12
12
/ln 


TAUQ 
T
Cross flow and compact heat exchangers
• Cross-flow and compact heat exchangers are used where space is limited. These aim to
maximize the heat transfer surface area.
• Commonly used in gas (air) heating applications.
• The heat transfer is influenced by whether the fluids are unmixed (i.e. confined in a
channel) or mixed (i.e. not confined, hence free to contact several different heat transfer
surfaces).
• In a cross-flow heat exchanger the direction of fluids are perpendicular to each other.
Compact heat exchangers
• In Compact heat exchangers, the heat transfer rate is directly related to pressure loss
Advantages:
• very small
• Ideal for transferring heat to / from fluids with very low conductivity or where the heat
transfer must be done in very small spaces
Disadvantages:
• high manufacturing costs
• very heavy
• Extremely high pressure losses.
DESIGN OF ECONOMIZER
ASSUMPTION:
• The properties are remains constant under steady state conditions and neglect
surrounding losses. Kinetic and potential energies are neglected.
DESIGN ANALYSIS:
Heat Transfer,
Q = m x c x Δt
• Where m = mass of fluid in kg
C = specific heat of water in kj/kg oc
Δt = temperature difference
• Here m = 1800 kg/h
= 5 kg/sec
• Specific heat of water is 4.18 kj/kg oc
• Temperature difference, Δt = (70oc - 40oc) = 30oc
Q = 5 x 4.18 x 30oc
Q = 627 kW
• Heat loosing fluid
Qc = m x c x Δt
= 16 x 1.005 x (200 – 160)
= 643.2 kw.
• In Counter flow
LMTD = ((Th1 – Tc2) - (Th2– Tc1)) / ln ((Th1 – Tc2 ) - ( Th2 – Tc1 ))
= ((200-70) – (160-40)) / ln ((200-70)/ (160-40))
= (130-120) / ln (130/120)
= 10 / ln (1.083)
= 10 / 0.0797
• LMTD = 125.47oc
• Actually this economizer is a cross flow economizer so, the LMTD equation becomes,
(LMTD)cross = F X (LMTD)counter
Here F = correction factor
• It is calculated by using graphical method by using dimension parameters P, Z from graph,
P= (Tc2-Tc1)/(Th1-Tc2)
P= (70-40)/ (200-70)
P= 0.2307
• Z= (Th1-Th2)/(Tc2-Tc1)
Z= (200-160)/ (70-40)
Z= 1.33
• From this values we get F = 0.98 (from graphically, pgno:31)
• So we have multiplied the counter flow LMTD with correction factor F, then we
get LMTD of cross flow
(LMTD) cross = F X (LMTD) counter
= 0.98 x 125.47
= 122.96oc
• From heat transfer equation we calculate the area of economizer as follows
Q = UAΔTm x F
Here F = Correction factor F = 0.98
A = Area of Economizer
A = (627 x 1000) / (850 x 125.4 x 0.98)
A = 6.01 m2
U = 850 w / m2 oc (from tables)
• From Average velocity in the tube and discharge we Calculate total flow area
m = ρ A u
Here m = mass of water
A = Tube flow area
U = velocity of flow = 0.2 m/sec
A = 5 / (1000 x 0.2)
A = 0.025 m2
• The above area is equal to actual cross – sectional area of tube
0.025 =n x π/4 x d2
0.025 = n x 3.14 x (0.025)2 / 4
n= 50
• From Equation 1 the area is 17.47 m2
• Then the total surface area in 2 tube pass is given below
2nπdL = 6.01
L = 6.01/(2 x 0.025 x 3.14 x 50)
L = 76 mtrs
• Each tube = 2.2 mtrs
No. of passes = 2
No. of tubes = 50
DESIGN OF AIR PRE HEATER
• ASSUMPTIONS: The properties are remains constant under steady state conditions and
neglect surrounding losses. Kinetic and potential energies are neglected.
• DESIGN ANALYSIS:
Heat Transfer,
Q = m x c x Δt
Where m = mass flow rate
C = specific heat of air in kJ/kg oc
C = 1.005
Δt = temperature difference in oc
• Here m = 5 kg/sec
Specific heat of water is 4.18 kJ/kg oc
Temperature difference, Δt = (110 oc - 50 oc) = 60 oc
Q = 5 x 1.005 x 60 oc
Q = 301.5 kw
Heat loosing of fluid Q = m x c x Δt
= 5 x 1.005 x (270-200)
= 351.75 kw
• LMTD = ((Th1 – Tc2 ) - ( Th2 – Tc1 )) / ln((Th1 – Tc2 )- ( Th2 – Tc1 ))
= ((270-110) – (200-50))/ln ((270-110)/(200-50))
= (160-150)/ln (160/150)
LMTD = 156.46 oc
• Actually this Air pre-heater is a cross flow Air pre-heater so the LMTD equation
Becomes,
(LMTD)cross = F X (LMTD)counter
Here F = correction factor
• It is calculated by using graphical method by using dimension parameters P, Z from graph,
P= (Tc2-Tc1)/(Th1-Tc2)
P= (110-50)/(270-110)
P= 60/160
P=0.375
Z = (Th1-Th2)/(Tc2-Tc1)
Z = (270-200)/(110-50)
Z = 70/60
Z = 1.16
• From this values we get F = 0.94 (from graphically)
• So we have multiplied the counter flow LMTD with correction factor F, then we get
LMTD of cross flow
(LMTD)cross = F X (LMTD)counter
= 0.94 x 156.46
= 147.07 oc
• Q = UA ΔTm x F
Where U = overall heat transfer coefficient
A = Area of Air Pre heater
F = correction factor
U = 50 w / m2 oc (As per standard tables)
• From Average velocity in the tube and discharge we Calculate total flow area
Here correction factor F = 0.94
A = q / U ΔTm x F
= (301.5X 1000) / (50 x 0.94 x 156.4)
= 43.015m2
m = ρA u
Here m = mass flow rate kg/sec
A = Tube flow area m2
U = velocity of flow = 0.2 m/sec
ρ = 1.5 kg / m3
• From continuity equation
Q = A1 X V1
5 / 1000 = 3.14 X (0.04)2 X V1
V1 = 3.98 m/sec
m = ρA u
A= m/(ρ x V1)
A=5/(1.5 x 3.98 ) = 0.83 m2
A = 0.83 m2
• The above area is equal to actual cross – sectional area of tube
0.83 m2 = n X π/4 X d2
n = 658 tubes
Length of tube for two passes
nπdL = 43.015m2
L = 43.015 / (658 x 3.14 x 0.04)
L = 0.52m
No. of tubes = 658
No. of passes = 2, Length = 0.52m
BOILER EFFICIENCY
• Now we calculate the boiler efficiency of thermax boiler.
• Capacity of boiler = 6 tons/hour
• Exisisting values
• Water temperature (tw) = 35 oc
• Mass of steam (ms) = 6000kg/hr
• Mass of fuel (mf) = 1250 kg/hr
• Calorific value of husk = 3500 k.cal/kg = 14644.35kj/kg ( 1 joule = 0.239 k.cal )
• Temperature of steam (ts ) = 190 oc
• Boiler efficiency = ms (hs-hw)/mf x c.v
• Enthalpy of water at 35 oc hw =hf +x hfg
(x = 0, i.e., dryness factor, by using steam tables)
hw = 151.5 + 0 x hfg
hw = 151.5 kj/kg
• Enthalpy of steam at 190 oc
hs =hf +x hfg
hs = 8067 + (0.8 X 1977.5)
hs = 2388.7 kj/kg
• Therefore, boiler efficiency = ms (hs-hw) /(mf x c.v) x 100
= 6000(2388.7-151.5)/1250 x 14644.35) x 100
= 0.733 x 100 = 73.3%
8.1 BOILER EFFICIENCY WITH ECONOMIZER
• Now introducing economizer the temperature of water increases from 35 oc TO 50 oc
now water temperature (tw) = 50 oc
And quality of steam increases up to 90 percent
• Economizer with boiler efficiency = ms(hs-hw)/mf x c.vx100
• enthalpy of water at 50 oc (hw) = hf + x hfg
= 213.7 + 0 x hfg
hw = 213.7 kj/kg
• enthalpy of steam at 190 oc (hs) = hf+ x hfg
= 806.7 + (0.9 x 1977.5) (here quality of the steam 90%)
= 806.7 + 1779.5
= 2586.45 kj/kg
• Economizer with boiler effieciency = ms(hs-hw)/mf x c.v x 100
= 6000 (2586.45 - 213.7)/(1250 x 14644.35) x 100
=0.77 x 100
=77%
8.2 BOILER EFFICIENCY WITH AIR PRE-HEATER
• Now we are introducing air preheater the husk consumption reduced to 1250 kg to
1083 kg/hr
• Boiler efficiency with air preheater = MS (HS –HW)/MF X CV X 100
= 6000 (2586.45-213.7)/1083 X 14644.35) X 100
= 14236500/15859831.05 X 100
= 0.89 X 100
• Boiler efficiency with air preheater = 89%
• Water consumption per hour = 4250
• Specific heat of water = 1
ΔT = T2-T1
= 95 OC -85 OC
= 10OC
• MCPΔT = 4250 X 1 X 10 X 24 = 1020000 K.CAL
= 291.42857 KJ/KG
• Therefore 291.42857 KJ/KG Rice husk is saving
Heat Balance Sheet
• Pressure of Steam = 14.2 bar
• Steam produced = 6000 kg/hour
• Coal used = 1250 kg/hour
• Moisture in Fuel = 2% of mass
• Mass of Dry Fuel gas = 9 kg of fuel
• Calorific Value of Fuel = 3500 k.cal
• Temperature of gas = 2000c
• Temperature of Boiler room = 280c
• Feed water Temperature = 500c
• Specific heat of gas = 1.005 kj/kg
• Quality of steam = 0.9%
• Heat supplied for the fuel = mf x c.v
H.S = 1 x 3500
= 3500 k.cal
• Heat supplied = 3500 k.cal
• If moisture is present then heat supplied by 1 kg of fuel = (1- mm) c.v
• Where mm is percentage of moisture
= (1-0.02) x 3500
= 3430 k.cal
= 4913.043 kj
• Heat utilized in producing Steam = ms/mf (hs-hw) →1
Where hs = hf + x hfg
= 806.7 + (0.9 x 977.5)
= 2586.45 kg
• hw = hf
hw = 806.7
= 6000/1250 (2586.45 – 206.7)
= 4.8 x 2379.75
= 11422.8 kj
• Heat carried away by the exert gases = mg cp g (Tg-Ts)
= 9 x 1.005 (2000c – 500c)
= 1356.75 kj
• Heat carried away by the moisture in the fuel = mm (2676 + 2.1 (Tg – 100) – hf)
= 0.02 (2676 + 2.1 (200 – 100) - hf)
= 0.02 (2676 + 2.1 (200 – 100) – 121.4)
= 55.292 kj
1250 1250
1083
950
1000
1050
1100
1150
1200
1250
1300
0
10
20
30
40
50
60
70
80
90
100
1 2 3
fuel consumption ( kg/hr
)
boiler efficiency (%)
Name fuel consumption
( kg/hr )
Boiler efficiency
(%)
without airpreheater and
economizer
1250 73.3
with economizer 1250 77
with airpreheater 1083 89
CONCLUSION
• In this course of project it came to learn about the Design of Air pre-heater and
Economizer in boiler.
• By using the Air pre-heater and Economizer boiler Efficiency can be increased.
• Gas flow distribution or heat transfer into the economizer section is improved through use
of guide vanes at inlet of economizer duct.
• Analysis of economizer module was carried out to predict the economizer feed water
outlet temperature.
• The economizer size optimized by reducing the number of tubes of module by enhancing
the heat transfer across the module.
• By installing the Air pre-heater and Economizer the total husk consumption rate is
reduced and the efficiency of the boiler is also increased to 73% to 89%
DESIGN OF AIR PRE HEATER AND ECONOMIZER

More Related Content

What's hot

Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheater
dishti7
 

What's hot (20)

Condenser performance test
Condenser performance testCondenser performance test
Condenser performance test
 
Energy audit of Condenser and CW System
Energy audit of Condenser and CW SystemEnergy audit of Condenser and CW System
Energy audit of Condenser and CW System
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
 
Air heater
Air heaterAir heater
Air heater
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Materials used in boiler & furnace
Materials used in boiler & furnaceMaterials used in boiler & furnace
Materials used in boiler & furnace
 
Steam Condensers
Steam CondensersSteam Condensers
Steam Condensers
 
Rankine cycle
Rankine cycleRankine cycle
Rankine cycle
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
 
Project ppt
Project pptProject ppt
Project ppt
 
Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheater
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Boiler performance (Part 1) - Equivalent evaporation - Notes
Boiler performance (Part 1) - Equivalent evaporation - NotesBoiler performance (Part 1) - Equivalent evaporation - Notes
Boiler performance (Part 1) - Equivalent evaporation - Notes
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Heat Exchangers
Heat ExchangersHeat Exchangers
Heat Exchangers
 
Condenser design
Condenser designCondenser design
Condenser design
 
Boiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of LossesBoiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of Losses
 

Similar to DESIGN OF AIR PRE HEATER AND ECONOMIZER

carnot cycle (a theoretical thermodynamic cycle).ppt
carnot cycle (a theoretical thermodynamic cycle).pptcarnot cycle (a theoretical thermodynamic cycle).ppt
carnot cycle (a theoretical thermodynamic cycle).ppt
HafizMudaserAhmad
 
Thermal transfer Characteristics of TCM
Thermal transfer Characteristics of TCMThermal transfer Characteristics of TCM
Thermal transfer Characteristics of TCM
jlrapter
 
New shell & tube heat exchanger
New shell & tube heat exchangerNew shell & tube heat exchanger
New shell & tube heat exchanger
vatsalpateln
 

Similar to DESIGN OF AIR PRE HEATER AND ECONOMIZER (20)

carnot cycle.ppt
carnot cycle.pptcarnot cycle.ppt
carnot cycle.ppt
 
carnot cycle (a theoretical thermodynamic cycle).ppt
carnot cycle (a theoretical thermodynamic cycle).pptcarnot cycle (a theoretical thermodynamic cycle).ppt
carnot cycle (a theoretical thermodynamic cycle).ppt
 
Process Calculation - simple distillation
Process Calculation - simple distillationProcess Calculation - simple distillation
Process Calculation - simple distillation
 
مبدل های حرارتی
مبدل های حرارتیمبدل های حرارتی
مبدل های حرارتی
 
integrated brayton and rankine cycle
integrated brayton and rankine cycle integrated brayton and rankine cycle
integrated brayton and rankine cycle
 
Chemical engineering department
Chemical engineering departmentChemical engineering department
Chemical engineering department
 
FABRICATION OF EXPERIMENTAL SETUP TO EVALUATE CONVECTIVE HEAT TRANSFER COEFFI...
FABRICATION OF EXPERIMENTAL SETUP TO EVALUATE CONVECTIVE HEAT TRANSFER COEFFI...FABRICATION OF EXPERIMENTAL SETUP TO EVALUATE CONVECTIVE HEAT TRANSFER COEFFI...
FABRICATION OF EXPERIMENTAL SETUP TO EVALUATE CONVECTIVE HEAT TRANSFER COEFFI...
 
project ppt
project pptproject ppt
project ppt
 
Radial heat conduction
Radial heat conductionRadial heat conduction
Radial heat conduction
 
Heat exchanger training 02. 25. 15
Heat exchanger training 02. 25. 15 Heat exchanger training 02. 25. 15
Heat exchanger training 02. 25. 15
 
Thermal transfer Characteristics of TCM
Thermal transfer Characteristics of TCMThermal transfer Characteristics of TCM
Thermal transfer Characteristics of TCM
 
New shell & tube heat exchanger
New shell & tube heat exchangerNew shell & tube heat exchanger
New shell & tube heat exchanger
 
Design of Heat Exchanger
Design of Heat ExchangerDesign of Heat Exchanger
Design of Heat Exchanger
 
Design of heat exchanger
Design of heat exchangerDesign of heat exchanger
Design of heat exchanger
 
C1303071722
C1303071722C1303071722
C1303071722
 
Plate Type Heat Exchanger Design
Plate Type Heat Exchanger DesignPlate Type Heat Exchanger Design
Plate Type Heat Exchanger Design
 
Boiler design-calculation 3
Boiler design-calculation 3Boiler design-calculation 3
Boiler design-calculation 3
 
4.4.heat exchanger
4.4.heat exchanger4.4.heat exchanger
4.4.heat exchanger
 
Design and Analysis Of Double Pipe Concentric Tube Heat Exchanger
Design and Analysis Of Double Pipe Concentric Tube Heat ExchangerDesign and Analysis Of Double Pipe Concentric Tube Heat Exchanger
Design and Analysis Of Double Pipe Concentric Tube Heat Exchanger
 
Heat exchanger
Heat exchangerHeat exchanger
Heat exchanger
 

Recently uploaded

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Website
mark11275
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
amitlee9823
 
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
instagramfab782445
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
amitlee9823
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
kumaririma588
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
eeanqy
 
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard ...
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard  ...Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard  ...
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard ...
nirzagarg
 

Recently uploaded (20)

Q4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentationQ4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentation
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Website
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
 
Book Paid In Vashi In 8976425520 Navi Mumbai Call Girls
Book Paid In Vashi In 8976425520 Navi Mumbai Call GirlsBook Paid In Vashi In 8976425520 Navi Mumbai Call Girls
Book Paid In Vashi In 8976425520 Navi Mumbai Call Girls
 
Hire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
Hire 💕 8617697112 Meerut Call Girls Service Call Girls AgencyHire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
Hire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
 
Top Rated Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
 
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
 
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
怎样办理伯明翰大学学院毕业证(Birmingham毕业证书)成绩单留信认证
 
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard ...
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard  ...Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard  ...
Anamika Escorts Service Darbhanga ❣️ 7014168258 ❣️ High Cost Unlimited Hard ...
 

DESIGN OF AIR PRE HEATER AND ECONOMIZER

  • 1. DESIGN OF AIR PRE HEATER AND ECONOMIZER Submitted by J.SHANMUKA VENKATA GOPICHAND (101FA08133) L.SURYA TEJA (101FA08141) Under the guidance of(Internal) N.B.PRAKASH TIRUVEEDULA ASSISTANT PROFESSOR VIGNAN UNIVERSITY Under the guidance of(External) Mr. SREEKANTH JABADE GM AND PROJECT ENGG HARTEX RUBBER PVT LTD
  • 2. CONTENTS 1. Process of Air pre-heater 2. Economizer 3. Boiler basics 4. Heat Exchangers 5. Cross Flow & Compact Heat Exchangers 6. Design Calculation of Economizer 7. Design Calculation of Air pre-heater 8. Boiler Efficiency 9. Heat Balance sheet 10. Conclusion
  • 3. Process of Air pre-heater • An air pre-heater (APH) is a general term to describe any device designed to heat air before another process (for example, combustion in a boiler) with the primary objective of increasing the thermal efficiency of the process. • There are two types of air pre-heaters for use in steam generators in thermal power stations: One is a tubular type built into the boiler flue gas ducting, and the other is a regenerative air pre-heater. • Ambient air is forced by a fan through ducting at one end of the pre-heater tubes and at other end the heated air from inside of the tubes emerges into another set of ducting, which carries it to the boiler furnace for combustion
  • 4. • There are two types of regenerative air pre-heaters: the rotating-plate regenerative air pre- heaters (RAPH) and the stationary-plate regenerative air pre-heaters. • Rotating-plate regenerative air pre-heater
  • 5. • The rotating-plate design (RAPH) consists of a central rotating-plate element installed within a casing that is divided into two (bi-sector type), three (tri-sector type) or four (quad-sector type) sectors containing seals around the element. • In stationary-plate regenerative air pre-heaters the heating plate elements are also installed in a casing, but the heating plate elements are stationary rather than rotating.
  • 6. Economizer • Economizers are mechanical devices intended to reduce energy consumption, or to perform another useful function such as preheating a fluid. • Economizer performs a key function in providing high overall boiler thermal efficiency by recovering low level energy from the flue gas before it is exhausted to the atmosphere. • Economizer recovers the energy by heating the boiler feed water.
  • 7. • It scavenge the waste heat from thermal exhaust flue gases by passing the exhaust effluent through heat transfer surfaces to transfer some of the waste heat to a process media. • It Efficiency is in direct relationship to equipment design and stack gas velocities. • Velocity increases through the stack as firing rate increases, which results in a decrease in contact time with the economizer heating surfaces
  • 8. BOILER BASICS • The hot water or steam under pressure is then usable for transferring the heat for the steam requirements of process industries or for power generation. • During the combustion process, oxygen reacts with carbon, hydrogen and other elements in the fuel to produce a flame and hot combustion gases. • As these gases are drawn through the boiler, they cool as heat is transferred to water • The main components in a boiler system are boiler feed water heaters, deaerator, feed pump, economizer, super heater, Attemperators, condenser and condensate pump.
  • 9. Heat Exchangers Heat Exchangers are classified according to their function and geometry: Function: Recuperative: two fluids separated by a solid wall Evaporative: enthalpy of evaporation of one fluid is used to heat or cool the other fluid. Regenerative: use a third material which stores/releases heat Geometry: 1. Double Tube 2. Shell and Tube 3. Cross-flow Heat Exchangers 4. Compact Heat Exchangers
  • 10. Heat Exchangers • The heat transfer rate for most heat exchangers can be calculated using the LMTD-method (Log Mean Temperature Difference), if the inlet (T1) and outlet (T2) temperatures are known: U = Overall heat transfer coefficient [ W/m2-oC ] A = Effective heat transfer surface area [ m2 ] F = Geometry correction factor = Log mean temperature difference   F TT TT T 12 12 /ln    TAUQ  T
  • 11. Cross flow and compact heat exchangers • Cross-flow and compact heat exchangers are used where space is limited. These aim to maximize the heat transfer surface area. • Commonly used in gas (air) heating applications. • The heat transfer is influenced by whether the fluids are unmixed (i.e. confined in a channel) or mixed (i.e. not confined, hence free to contact several different heat transfer surfaces). • In a cross-flow heat exchanger the direction of fluids are perpendicular to each other.
  • 12. Compact heat exchangers • In Compact heat exchangers, the heat transfer rate is directly related to pressure loss Advantages: • very small • Ideal for transferring heat to / from fluids with very low conductivity or where the heat transfer must be done in very small spaces Disadvantages: • high manufacturing costs • very heavy • Extremely high pressure losses.
  • 13. DESIGN OF ECONOMIZER ASSUMPTION: • The properties are remains constant under steady state conditions and neglect surrounding losses. Kinetic and potential energies are neglected. DESIGN ANALYSIS: Heat Transfer, Q = m x c x Δt • Where m = mass of fluid in kg C = specific heat of water in kj/kg oc Δt = temperature difference
  • 14. • Here m = 1800 kg/h = 5 kg/sec • Specific heat of water is 4.18 kj/kg oc • Temperature difference, Δt = (70oc - 40oc) = 30oc Q = 5 x 4.18 x 30oc Q = 627 kW • Heat loosing fluid Qc = m x c x Δt = 16 x 1.005 x (200 – 160) = 643.2 kw.
  • 15. • In Counter flow LMTD = ((Th1 – Tc2) - (Th2– Tc1)) / ln ((Th1 – Tc2 ) - ( Th2 – Tc1 )) = ((200-70) – (160-40)) / ln ((200-70)/ (160-40)) = (130-120) / ln (130/120) = 10 / ln (1.083) = 10 / 0.0797 • LMTD = 125.47oc
  • 16. • Actually this economizer is a cross flow economizer so, the LMTD equation becomes, (LMTD)cross = F X (LMTD)counter Here F = correction factor • It is calculated by using graphical method by using dimension parameters P, Z from graph, P= (Tc2-Tc1)/(Th1-Tc2) P= (70-40)/ (200-70) P= 0.2307
  • 17. • Z= (Th1-Th2)/(Tc2-Tc1) Z= (200-160)/ (70-40) Z= 1.33 • From this values we get F = 0.98 (from graphically, pgno:31) • So we have multiplied the counter flow LMTD with correction factor F, then we get LMTD of cross flow (LMTD) cross = F X (LMTD) counter = 0.98 x 125.47 = 122.96oc
  • 18. • From heat transfer equation we calculate the area of economizer as follows Q = UAΔTm x F Here F = Correction factor F = 0.98 A = Area of Economizer A = (627 x 1000) / (850 x 125.4 x 0.98) A = 6.01 m2 U = 850 w / m2 oc (from tables)
  • 19. • From Average velocity in the tube and discharge we Calculate total flow area m = ρ A u Here m = mass of water A = Tube flow area U = velocity of flow = 0.2 m/sec A = 5 / (1000 x 0.2) A = 0.025 m2
  • 20. • The above area is equal to actual cross – sectional area of tube 0.025 =n x π/4 x d2 0.025 = n x 3.14 x (0.025)2 / 4 n= 50 • From Equation 1 the area is 17.47 m2 • Then the total surface area in 2 tube pass is given below 2nπdL = 6.01 L = 6.01/(2 x 0.025 x 3.14 x 50) L = 76 mtrs
  • 21. • Each tube = 2.2 mtrs No. of passes = 2 No. of tubes = 50
  • 22. DESIGN OF AIR PRE HEATER • ASSUMPTIONS: The properties are remains constant under steady state conditions and neglect surrounding losses. Kinetic and potential energies are neglected. • DESIGN ANALYSIS: Heat Transfer, Q = m x c x Δt Where m = mass flow rate C = specific heat of air in kJ/kg oc C = 1.005 Δt = temperature difference in oc
  • 23. • Here m = 5 kg/sec Specific heat of water is 4.18 kJ/kg oc Temperature difference, Δt = (110 oc - 50 oc) = 60 oc Q = 5 x 1.005 x 60 oc Q = 301.5 kw Heat loosing of fluid Q = m x c x Δt = 5 x 1.005 x (270-200) = 351.75 kw
  • 24. • LMTD = ((Th1 – Tc2 ) - ( Th2 – Tc1 )) / ln((Th1 – Tc2 )- ( Th2 – Tc1 )) = ((270-110) – (200-50))/ln ((270-110)/(200-50)) = (160-150)/ln (160/150) LMTD = 156.46 oc • Actually this Air pre-heater is a cross flow Air pre-heater so the LMTD equation Becomes, (LMTD)cross = F X (LMTD)counter Here F = correction factor
  • 25. • It is calculated by using graphical method by using dimension parameters P, Z from graph, P= (Tc2-Tc1)/(Th1-Tc2) P= (110-50)/(270-110) P= 60/160 P=0.375 Z = (Th1-Th2)/(Tc2-Tc1) Z = (270-200)/(110-50) Z = 70/60 Z = 1.16 • From this values we get F = 0.94 (from graphically)
  • 26. • So we have multiplied the counter flow LMTD with correction factor F, then we get LMTD of cross flow (LMTD)cross = F X (LMTD)counter = 0.94 x 156.46 = 147.07 oc • Q = UA ΔTm x F Where U = overall heat transfer coefficient A = Area of Air Pre heater F = correction factor U = 50 w / m2 oc (As per standard tables)
  • 27. • From Average velocity in the tube and discharge we Calculate total flow area Here correction factor F = 0.94 A = q / U ΔTm x F = (301.5X 1000) / (50 x 0.94 x 156.4) = 43.015m2 m = ρA u Here m = mass flow rate kg/sec A = Tube flow area m2 U = velocity of flow = 0.2 m/sec ρ = 1.5 kg / m3
  • 28. • From continuity equation Q = A1 X V1 5 / 1000 = 3.14 X (0.04)2 X V1 V1 = 3.98 m/sec m = ρA u A= m/(ρ x V1) A=5/(1.5 x 3.98 ) = 0.83 m2 A = 0.83 m2
  • 29. • The above area is equal to actual cross – sectional area of tube 0.83 m2 = n X π/4 X d2 n = 658 tubes Length of tube for two passes nπdL = 43.015m2 L = 43.015 / (658 x 3.14 x 0.04) L = 0.52m No. of tubes = 658 No. of passes = 2, Length = 0.52m
  • 30. BOILER EFFICIENCY • Now we calculate the boiler efficiency of thermax boiler. • Capacity of boiler = 6 tons/hour • Exisisting values • Water temperature (tw) = 35 oc • Mass of steam (ms) = 6000kg/hr • Mass of fuel (mf) = 1250 kg/hr • Calorific value of husk = 3500 k.cal/kg = 14644.35kj/kg ( 1 joule = 0.239 k.cal ) • Temperature of steam (ts ) = 190 oc • Boiler efficiency = ms (hs-hw)/mf x c.v
  • 31. • Enthalpy of water at 35 oc hw =hf +x hfg (x = 0, i.e., dryness factor, by using steam tables) hw = 151.5 + 0 x hfg hw = 151.5 kj/kg • Enthalpy of steam at 190 oc hs =hf +x hfg hs = 8067 + (0.8 X 1977.5) hs = 2388.7 kj/kg • Therefore, boiler efficiency = ms (hs-hw) /(mf x c.v) x 100 = 6000(2388.7-151.5)/1250 x 14644.35) x 100 = 0.733 x 100 = 73.3%
  • 32. 8.1 BOILER EFFICIENCY WITH ECONOMIZER • Now introducing economizer the temperature of water increases from 35 oc TO 50 oc now water temperature (tw) = 50 oc And quality of steam increases up to 90 percent • Economizer with boiler efficiency = ms(hs-hw)/mf x c.vx100 • enthalpy of water at 50 oc (hw) = hf + x hfg = 213.7 + 0 x hfg hw = 213.7 kj/kg
  • 33. • enthalpy of steam at 190 oc (hs) = hf+ x hfg = 806.7 + (0.9 x 1977.5) (here quality of the steam 90%) = 806.7 + 1779.5 = 2586.45 kj/kg • Economizer with boiler effieciency = ms(hs-hw)/mf x c.v x 100 = 6000 (2586.45 - 213.7)/(1250 x 14644.35) x 100 =0.77 x 100 =77%
  • 34. 8.2 BOILER EFFICIENCY WITH AIR PRE-HEATER • Now we are introducing air preheater the husk consumption reduced to 1250 kg to 1083 kg/hr • Boiler efficiency with air preheater = MS (HS –HW)/MF X CV X 100 = 6000 (2586.45-213.7)/1083 X 14644.35) X 100 = 14236500/15859831.05 X 100 = 0.89 X 100 • Boiler efficiency with air preheater = 89%
  • 35. • Water consumption per hour = 4250 • Specific heat of water = 1 ΔT = T2-T1 = 95 OC -85 OC = 10OC • MCPΔT = 4250 X 1 X 10 X 24 = 1020000 K.CAL = 291.42857 KJ/KG • Therefore 291.42857 KJ/KG Rice husk is saving
  • 36. Heat Balance Sheet • Pressure of Steam = 14.2 bar • Steam produced = 6000 kg/hour • Coal used = 1250 kg/hour • Moisture in Fuel = 2% of mass • Mass of Dry Fuel gas = 9 kg of fuel • Calorific Value of Fuel = 3500 k.cal • Temperature of gas = 2000c • Temperature of Boiler room = 280c • Feed water Temperature = 500c • Specific heat of gas = 1.005 kj/kg • Quality of steam = 0.9%
  • 37. • Heat supplied for the fuel = mf x c.v H.S = 1 x 3500 = 3500 k.cal • Heat supplied = 3500 k.cal • If moisture is present then heat supplied by 1 kg of fuel = (1- mm) c.v • Where mm is percentage of moisture = (1-0.02) x 3500 = 3430 k.cal = 4913.043 kj • Heat utilized in producing Steam = ms/mf (hs-hw) →1 Where hs = hf + x hfg = 806.7 + (0.9 x 977.5) = 2586.45 kg
  • 38. • hw = hf hw = 806.7 = 6000/1250 (2586.45 – 206.7) = 4.8 x 2379.75 = 11422.8 kj
  • 39. • Heat carried away by the exert gases = mg cp g (Tg-Ts) = 9 x 1.005 (2000c – 500c) = 1356.75 kj • Heat carried away by the moisture in the fuel = mm (2676 + 2.1 (Tg – 100) – hf) = 0.02 (2676 + 2.1 (200 – 100) - hf) = 0.02 (2676 + 2.1 (200 – 100) – 121.4) = 55.292 kj
  • 40. 1250 1250 1083 950 1000 1050 1100 1150 1200 1250 1300 0 10 20 30 40 50 60 70 80 90 100 1 2 3 fuel consumption ( kg/hr ) boiler efficiency (%) Name fuel consumption ( kg/hr ) Boiler efficiency (%) without airpreheater and economizer 1250 73.3 with economizer 1250 77 with airpreheater 1083 89
  • 41. CONCLUSION • In this course of project it came to learn about the Design of Air pre-heater and Economizer in boiler. • By using the Air pre-heater and Economizer boiler Efficiency can be increased. • Gas flow distribution or heat transfer into the economizer section is improved through use of guide vanes at inlet of economizer duct. • Analysis of economizer module was carried out to predict the economizer feed water outlet temperature. • The economizer size optimized by reducing the number of tubes of module by enhancing the heat transfer across the module. • By installing the Air pre-heater and Economizer the total husk consumption rate is reduced and the efficiency of the boiler is also increased to 73% to 89%