31. Timelines for the Development of proposed projects Phase I Approx. 7 – 10 mths Phase 1 Zoo Jamaican Paradise and Naturale Approx. 6 mths Animal Hospital Year 1 Start Ornamental Gardens Approx. 6 mths Nursery Development Approx. 3 mths Jogging Trail Approx. 4 mths Orchid House Approx. 8 mths Phase 1 Gardens (including fencing & lighting)
32. Timelines for the Development of proposed projects Phase II Start Roads and car parks Start Theme Park (formerly Coconut Park) Phase 2 Gardens Start to completion Phase 2 Zoo African Outpost Start JCDT Building Year 2 –3 Continuation Ornamental Gardens 1 year Botanical Museum
33. Timelines for the Development of proposed projects Phase III Phase 3 Gardens Start to completion Phase 3 Zoo: The Americas Completion JCDT Building Start Conservation & Research Facilities Continuation Ornamental Gardens Yr 3 –5