DEWATERING TECHNIQUES
What is dewatering on a construction site?
• Dewatering is the term for the control of groundwater by pumping.
• On construction sites it may be known as ‘construction dewatering’.
The method is also used on mine sites – ‘mine dewatering’
• The process of dewatering can be defined as – pumping from wells or
sumps to temporarily lower groundwater levels, to allow excavations to be
made in dry and stable conditions below natural groundwater level
WHY DO WE NEED DEWATERING ON
CONSTRUCTION SITE?
• As we all know that for working at a construction site, it should be completely dry
and the surface should be such that one can easily work .
• For excavation and for making basements of building dewatering the site, is
must, for easy working of the people and for the safety of the people working.
• Dewatering is also necessary during the rainy season, when excavation work is
to be done during the rainy season, for smooth and fast working dewatering of
the site is must.
• As discussed before, even in mines dewatering is must , else the mine will be
prone to accidents.
PURPOSE FOR DEWATERING
• During construction stage:
1. Provide a dry excavation and permit construction to proceed efficiently.
2. Reduce lateral loads on sheeting and bracing in excavations.
3. Improve supporting characteristics of foundation materials.
4. Increase stability of excavation slopes and side-hill fills.
5. Cut off capillary rise and prevent piping and frost heaving in pavements.
6. Reduce air pressure in tunneling operations.
• Post construction stage:
1. Reduce or eliminate uplift pressures on bottom slabs and permit economics
from the reduction of slab thicknesses fro basements, buried structures, canal
linings, spillways, dry docks, etc.
2. Provide for dry basements.
3. Reduce lateral pressures on retaining structures.
4. Control embankment seepage in all dams.
5. Control seepage and pore pressures beneath pavements, side-hill fills, and
cut slopes.
HOW IT IS DONE?
Collection of
water
Pumping
Filtering and
removing silt
and impurities
Discharge at
proper
location
Source of unwanted water on construction site
• Sources of surface water
Rainfall
Construction operations (E.G. Concreting, washing of plant)
Seepage through cut-off walls.
• Other source is groundwater
Methods of surface water control
• Source control
Intercept run-off before it reaches the excavation
Prevent unnecessary generation of water in the excavation
Collect water as soon as it reaches the work area (or before!)
• Water collection
French drains to intercept run off
Collector drains and sumps
Pumping systems (keep it simple!)
Dewatering techniques
• Construction dewatering methods
The design of effective construction dewatering methods should be based on
number of information sources:
-Geotechnical and groundwater site investigations undertaken at the
commencement of any project;
-Information provided by any geotechnical study undertaken during the concept
design stage
-Groundwater information source from relevant authorities
-A site risk assesments
Widely used dewatering techniques
•Sump pumping
•Well points
•Deep wells
•Ejector wells
SUMP PUMPING
• A sump is merely a hole in the ground from which water is being pumped for the
purpose of removing water from the adjoining area as shown in fig.
• They are used with ditches leading to them in large excavations. Up to
maximum of 8m below pump installation level; for greater depths a submersible
pump is required.
• Shallow slopes may be required for unsupported excavations in silts and fine
sands. Gravels and coarse sands are more suitable.
• If there are existing foundations in the vicinity pumping may cause settlement of
these foundations. Subsidence of adjacent ground and sloughing of the lower
part of a slope (sloped pits) may occur.
• The sump should be preferably lined with a filter material which has grain size
gradations in compatible with the filter rules.
• For prolonged pumping the sump should be prepared by first driving sheeting
around the sump area for the full depth of the sump and installing a cage inside
the sump made of wire mesh with internal strutting or a perforating pipe filling
the filter material.
ADVANTAGES AND DISADVANTAGES OF
SUMP PITS METHOD
Groundwat
er lowering
method
Advantages Disadvantages
Sump Pits 1. Widely used method.
2. Most economical method for installation and
maintenance.
3. Can be applied for most soil and rock conditions.
4. Most appropriate method in situation where boulders or
massive obstructions are met within the ground.
Greatest depth to which the water table can be lowered
by this method is about 8 m below the pump.
1. Ground water flows towards the
excavation with high head or a
steep slope and hence there is a
risk of collapse of sides.
2. In open or timbered excavations
there is risk of instability of the
base due to upward.
WELL POINT SYSTEM OF DEWATERING
• The most common practice of dewatering used in ahmedabad is the
implementation of a well system. Wells are systematically drilled around the
construction area and submersible pumps placed into these wells. This practice
appears to work effectively for many projects, especially those building projects
that require excavations for deep basements.
• Setup and Procedure of working:
• A well-point is 5.0-7.5 cm diameter metal or plastic pipe 60 cm – 120 cm long
which is perforated and covered with a screen. The lower end of the pipe has a
driving head with water holes for jetting as shown in fig. Well-points are
connected to 5.0-7.5 cm diameter pipes known as riser pipes and are inserted
into the ground by driving or jetting.
• The upper ends of the riser pipes lead to a header pipe which, in turn,
connected to a pump. The ground water is drawn by the pump into the well-
points through the header pipe and discharged as shown in fig.
• The well-points are usually installed with 0.75m – 3m spacing.
• In gravels spacing required may be too close and impracticable. In clays it is
also not used because it is too slow. In silts and silt – clay mixtures the use of
well points are aided by upper (0.60m – 0.90m long) compacted clay seals and
sand-filtered boreholes (20cm – 60cm diameter). Upper clay seals help to
maintain higher suction (vacuum) pressures and sand filters increase the
amount of discharge.
ADVANTAGE DISADVANTAGE OF WELL
SYSTEM
Groundwater
lowering
method
Advantages disadvantages
Well systems 1. Effective in sandy soils
2. Provide drawdown up to 5-6 meters in sand and
4 meters in silty soil.
1. Relatively cheap and flexible
2. Installation is very rapid.
3. Water is filtered and carries little or no soil
particles.
4. There is less danger of subsidence of the
surrounding ground than with open-sump
pumping
1. Not effective beyond 4-6
meters of drawdown
2. Might require stages of well
installation.
DEEP WELL
• Deep well systems consist of one or more individual wells, each of which has its
own submersible pump at the bottom of the well shaft. Such systems are
particularly suitable. Where large volumes of water in highly permeable sand
and gravel areas permitting rapid recharging of ground water from surrounding
areas exist. The range of permeability under which the deep well system is
applicable.
SPACING OF DEEP WELL POINT SYSTEM
• Normally, individual wells are spaced at an approximate distance of 15 m (50
feet) apart. However, depending upon soil conditions and the dewatering plan
the spacing may need to be just a few meters apart.
DEWATERING CAPACITY OF DEEP WELL POINT SYSTEM
• Individual well capacities are from 2100 to 3000 gallons per minute and with
total systems the capacities can be as high as 60 000 gallons per minute.
• Deep well pumps can lift water 30 m (100 feet) or more in a single stage and the
variation of the typical deep well system is a pressure within an aquifer.
• Deep well points require no pump as the water is forced to the surface by its
own pressure. To boost the water flow a vacuum pump is frequently used.
ADVANTAGE DISADVANTAGES OF DEEP WELL
SYSTEM
Groundwater
lowering method
advantages Disadvantages
Deep wells 1. No limits on
drawdown
2. Fewer wells
required than well
system
1. Expensive to
install
DITCHES AND TRENCHES
• Ditches and french drains (commonly known as trenches in construction
projects in ahmedabad) are also used on qatar’s construction sites.
• The ditches are formed in a pre-planned manner, allowing groundwater flow to
surface in the deeper level trenches. Perforated pipes are then placed in the
trenches, and groundwater extracted through these pipelines to be filtered.
These trenches were particularly common in infrastructure network projects.
• Graded aggregates and geotextile layer to be used when laying out the
pipelines.
ADVANTAGE AND DISADVANTAGE
Groundwater lowering
method
Advantages Disadvantages
Ditches/French drains 1. Relatively inexpensive
2. Controls shallow groundwater
and over bleed.
3. Effective in controlling
groundwater after casting of
foundations.
1. Possible obstruction
of traffic
2. Groundwater will only
be controlled at
shallow depth
3. Unlikely to be
effective in fine
grained soil.
EDUCTOR SYSTEM
• This system also known as the ‘jet eductor system’ or ‘ejector system’ or
‘eductor wellpoint system’ is similar to the wellpoint system.
• Instead of employing a vacuum to draw water to the well-points, the eductor
system uses high pressure water and riser units, each about 30-40mm in
diameter.
• A high pressure supply main feeds water through a venturi tube immediately
above the perforated well screen, creating a reduction in pressure which draws
water through the large diameter rise pipe. The high pressure main feeds off the
return water.
• The advantage of the eductor system is that in operating many well points from
a single pump station, the water table can be lowered in one stage from depths
of 10-45 m.
WORKING PROCEDURE OF EDUCTOR SYSTEM
• Supply pumps at ground level feed high-pressure water to each eductor well
head via a supply main.
• The supply flow passes down the well and through a nozzle and venturi in the
eductor. The flow of water through the nozzle generates a vacuum in the well
and draws in groundwater.
• The supply flow and extracted ground water mix, return to the surface and feed
back to the pumping station via a return main. The return flow is used to prime
the supply pumps and the excess water extracted is discharged by overflow
from the priming tank.
• A single pumping station can be used to operate up to about 75 eductor wells
installed in an appropriate array around the works.
ADVANTAGES OF EDUCTOR SYSTEM
1. They are flexible in level and layout.
2. Stable in operation.
3. Able to run dry without damage.
4. Not limited by depth. Also effective to greater depths.
5. Best in low-yielding wells.
6. Energy intensive.
7. Venturi in base of well creates vacuum.
THINGS TO BE TAKEN CARE DURING
DEWATERING!!!
• Dewatering activities must be done properly to avoid eroding the soil on the
construction site.
• It is also important to choose the best location for discharge, even when you
might be far away from water bodies or catch basins.
• Water should not be pumped directly into slopes.
• Pay special attention and discontinue dewatering if the area shows signs of
instability or erosion.
• Channels used on dewatering must be stable and better if they have been
protected with grass or vegetation.
• Avoid dewatering under heavy rains because the infiltration rate is at a minimum
and water will move slower or just the dewatering process will not function.
• Never discharge water that has been contaminated with oil, grease, chemical
products directly. In such instances an oil/water separator may be necessary.
• Additional permits and requirements might be needed from state, local or
federal agencies.
REFRENCES
• HTTP://WWW.GRIFFINDEWATERING.COM/DEWATERING/EDUCTOR_SYSTEM.HTM
L#.VBIGKVMSXQU

More Related Content

What's hot

Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
1)methods of exploration
1)methods of exploration1)methods of exploration
1)methods of explorationjagadish108
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipessathyan s
 
Proctor compaction test
Proctor compaction testProctor compaction test
Proctor compaction testFaizan Tanoli
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsNatarajaSaiCharan1
 
Stone column
Stone columnStone column
Stone columnGEOMIND
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibrationAnjana R Menon
 

What's hot (20)

Methods of boring ppt
Methods of boring  pptMethods of boring  ppt
Methods of boring ppt
 
Grouting
GroutingGrouting
Grouting
 
Vertical Drain
Vertical Drain Vertical Drain
Vertical Drain
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Grouting
Grouting Grouting
Grouting
 
1)methods of exploration
1)methods of exploration1)methods of exploration
1)methods of exploration
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipes
 
Wash boring
Wash boringWash boring
Wash boring
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Proctor compaction test
Proctor compaction testProctor compaction test
Proctor compaction test
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
Stone column
Stone columnStone column
Stone column
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 

Viewers also liked

Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projectsUmar Faruk
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPointTerry Aylward
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
Control of ground water in excavation
Control of ground water in excavation Control of ground water in excavation
Control of ground water in excavation Aamir Patni
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qbPreethi Abinaya
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniquesMartin Preene
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniquesAHMED NADIM JILANI
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement TechniquesNilesh Bhosale
 
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMDESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMNamitha M R
 
Drainage presentation
Drainage presentationDrainage presentation
Drainage presentationBilly Wiggins
 
Drainage system
Drainage systemDrainage system
Drainage systemNikhil Jp
 
Dewatering Optimization_Gupta
Dewatering Optimization_GuptaDewatering Optimization_Gupta
Dewatering Optimization_GuptaRashi Gupta
 
Piledrivingequipment
PiledrivingequipmentPiledrivingequipment
PiledrivingequipmentDurgesh Patil
 
Structural Lightweight Concrete
Structural Lightweight ConcreteStructural Lightweight Concrete
Structural Lightweight ConcreteMoe Abadla
 

Viewers also liked (20)

Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPoint
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Dewatering
DewateringDewatering
Dewatering
 
Control of ground water in excavation
Control of ground water in excavation Control of ground water in excavation
Control of ground water in excavation
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qb
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniques
 
Drainage
DrainageDrainage
Drainage
 
07 101+ ground improvement techniques
07 101+ ground improvement techniques07 101+ ground improvement techniques
07 101+ ground improvement techniques
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMDESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
 
Drainage presentation
Drainage presentationDrainage presentation
Drainage presentation
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Search engines
Search enginesSearch engines
Search engines
 
Dewatering Optimization_Gupta
Dewatering Optimization_GuptaDewatering Optimization_Gupta
Dewatering Optimization_Gupta
 
Piledrivingequipment
PiledrivingequipmentPiledrivingequipment
Piledrivingequipment
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniques
 
0708 s6 abs
0708 s6 abs0708 s6 abs
0708 s6 abs
 
Structural Lightweight Concrete
Structural Lightweight ConcreteStructural Lightweight Concrete
Structural Lightweight Concrete
 

Similar to Dewatering techniques

Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundationashishcivil098
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTUVATSAL PATEL
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONShivananda Roy
 
Lec-Groundwater_control-Dr AJK - Copy.ppt
Lec-Groundwater_control-Dr AJK - Copy.pptLec-Groundwater_control-Dr AJK - Copy.ppt
Lec-Groundwater_control-Dr AJK - Copy.ppthassanakhar
 
Dewatering
DewateringDewatering
DewateringJNTUK
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSTejaswiniNarayane
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainageChethan B J
 
Drainage in Excavation.ppt
Drainage in Excavation.pptDrainage in Excavation.ppt
Drainage in Excavation.pptVinayakNaik80
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
Tube-Wells and their Designs
Tube-Wells and their DesignsTube-Wells and their Designs
Tube-Wells and their DesignsAnand Kumar
 

Similar to Dewatering techniques (20)

Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
De watering-ppt
De watering-pptDe watering-ppt
De watering-ppt
 
Dewatering
DewateringDewatering
Dewatering
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
5. Dewatering F1.pdf
5. Dewatering F1.pdf5. Dewatering F1.pdf
5. Dewatering F1.pdf
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
 
Lec-Groundwater_control-Dr AJK - Copy.ppt
Lec-Groundwater_control-Dr AJK - Copy.pptLec-Groundwater_control-Dr AJK - Copy.ppt
Lec-Groundwater_control-Dr AJK - Copy.ppt
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
Dewatering
DewateringDewatering
Dewatering
 
Mine dewatering technology data sheet
Mine dewatering technology data sheetMine dewatering technology data sheet
Mine dewatering technology data sheet
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
 
Drainage in Excavation.ppt
Drainage in Excavation.pptDrainage in Excavation.ppt
Drainage in Excavation.ppt
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Tube-Wells and their Designs
Tube-Wells and their DesignsTube-Wells and their Designs
Tube-Wells and their Designs
 

Recently uploaded

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 

Dewatering techniques

  • 2. What is dewatering on a construction site? • Dewatering is the term for the control of groundwater by pumping. • On construction sites it may be known as ‘construction dewatering’. The method is also used on mine sites – ‘mine dewatering’ • The process of dewatering can be defined as – pumping from wells or sumps to temporarily lower groundwater levels, to allow excavations to be made in dry and stable conditions below natural groundwater level
  • 3.
  • 4. WHY DO WE NEED DEWATERING ON CONSTRUCTION SITE? • As we all know that for working at a construction site, it should be completely dry and the surface should be such that one can easily work . • For excavation and for making basements of building dewatering the site, is must, for easy working of the people and for the safety of the people working. • Dewatering is also necessary during the rainy season, when excavation work is to be done during the rainy season, for smooth and fast working dewatering of the site is must. • As discussed before, even in mines dewatering is must , else the mine will be prone to accidents.
  • 5. PURPOSE FOR DEWATERING • During construction stage: 1. Provide a dry excavation and permit construction to proceed efficiently. 2. Reduce lateral loads on sheeting and bracing in excavations. 3. Improve supporting characteristics of foundation materials. 4. Increase stability of excavation slopes and side-hill fills. 5. Cut off capillary rise and prevent piping and frost heaving in pavements. 6. Reduce air pressure in tunneling operations.
  • 6. • Post construction stage: 1. Reduce or eliminate uplift pressures on bottom slabs and permit economics from the reduction of slab thicknesses fro basements, buried structures, canal linings, spillways, dry docks, etc. 2. Provide for dry basements. 3. Reduce lateral pressures on retaining structures. 4. Control embankment seepage in all dams. 5. Control seepage and pore pressures beneath pavements, side-hill fills, and cut slopes.
  • 7. HOW IT IS DONE? Collection of water Pumping Filtering and removing silt and impurities Discharge at proper location
  • 8. Source of unwanted water on construction site • Sources of surface water Rainfall Construction operations (E.G. Concreting, washing of plant) Seepage through cut-off walls. • Other source is groundwater
  • 9. Methods of surface water control • Source control Intercept run-off before it reaches the excavation Prevent unnecessary generation of water in the excavation Collect water as soon as it reaches the work area (or before!) • Water collection French drains to intercept run off Collector drains and sumps Pumping systems (keep it simple!)
  • 10. Dewatering techniques • Construction dewatering methods The design of effective construction dewatering methods should be based on number of information sources: -Geotechnical and groundwater site investigations undertaken at the commencement of any project; -Information provided by any geotechnical study undertaken during the concept design stage -Groundwater information source from relevant authorities -A site risk assesments
  • 11. Widely used dewatering techniques •Sump pumping •Well points •Deep wells •Ejector wells
  • 12. SUMP PUMPING • A sump is merely a hole in the ground from which water is being pumped for the purpose of removing water from the adjoining area as shown in fig. • They are used with ditches leading to them in large excavations. Up to maximum of 8m below pump installation level; for greater depths a submersible pump is required. • Shallow slopes may be required for unsupported excavations in silts and fine sands. Gravels and coarse sands are more suitable. • If there are existing foundations in the vicinity pumping may cause settlement of these foundations. Subsidence of adjacent ground and sloughing of the lower part of a slope (sloped pits) may occur.
  • 13. • The sump should be preferably lined with a filter material which has grain size gradations in compatible with the filter rules. • For prolonged pumping the sump should be prepared by first driving sheeting around the sump area for the full depth of the sump and installing a cage inside the sump made of wire mesh with internal strutting or a perforating pipe filling the filter material.
  • 14.
  • 15. ADVANTAGES AND DISADVANTAGES OF SUMP PITS METHOD Groundwat er lowering method Advantages Disadvantages Sump Pits 1. Widely used method. 2. Most economical method for installation and maintenance. 3. Can be applied for most soil and rock conditions. 4. Most appropriate method in situation where boulders or massive obstructions are met within the ground. Greatest depth to which the water table can be lowered by this method is about 8 m below the pump. 1. Ground water flows towards the excavation with high head or a steep slope and hence there is a risk of collapse of sides. 2. In open or timbered excavations there is risk of instability of the base due to upward.
  • 16. WELL POINT SYSTEM OF DEWATERING • The most common practice of dewatering used in ahmedabad is the implementation of a well system. Wells are systematically drilled around the construction area and submersible pumps placed into these wells. This practice appears to work effectively for many projects, especially those building projects that require excavations for deep basements. • Setup and Procedure of working: • A well-point is 5.0-7.5 cm diameter metal or plastic pipe 60 cm – 120 cm long which is perforated and covered with a screen. The lower end of the pipe has a driving head with water holes for jetting as shown in fig. Well-points are connected to 5.0-7.5 cm diameter pipes known as riser pipes and are inserted into the ground by driving or jetting.
  • 17. • The upper ends of the riser pipes lead to a header pipe which, in turn, connected to a pump. The ground water is drawn by the pump into the well- points through the header pipe and discharged as shown in fig. • The well-points are usually installed with 0.75m – 3m spacing. • In gravels spacing required may be too close and impracticable. In clays it is also not used because it is too slow. In silts and silt – clay mixtures the use of well points are aided by upper (0.60m – 0.90m long) compacted clay seals and sand-filtered boreholes (20cm – 60cm diameter). Upper clay seals help to maintain higher suction (vacuum) pressures and sand filters increase the amount of discharge.
  • 18.
  • 19.
  • 20. ADVANTAGE DISADVANTAGE OF WELL SYSTEM Groundwater lowering method Advantages disadvantages Well systems 1. Effective in sandy soils 2. Provide drawdown up to 5-6 meters in sand and 4 meters in silty soil. 1. Relatively cheap and flexible 2. Installation is very rapid. 3. Water is filtered and carries little or no soil particles. 4. There is less danger of subsidence of the surrounding ground than with open-sump pumping 1. Not effective beyond 4-6 meters of drawdown 2. Might require stages of well installation.
  • 21. DEEP WELL • Deep well systems consist of one or more individual wells, each of which has its own submersible pump at the bottom of the well shaft. Such systems are particularly suitable. Where large volumes of water in highly permeable sand and gravel areas permitting rapid recharging of ground water from surrounding areas exist. The range of permeability under which the deep well system is applicable.
  • 22. SPACING OF DEEP WELL POINT SYSTEM • Normally, individual wells are spaced at an approximate distance of 15 m (50 feet) apart. However, depending upon soil conditions and the dewatering plan the spacing may need to be just a few meters apart. DEWATERING CAPACITY OF DEEP WELL POINT SYSTEM • Individual well capacities are from 2100 to 3000 gallons per minute and with total systems the capacities can be as high as 60 000 gallons per minute. • Deep well pumps can lift water 30 m (100 feet) or more in a single stage and the variation of the typical deep well system is a pressure within an aquifer. • Deep well points require no pump as the water is forced to the surface by its own pressure. To boost the water flow a vacuum pump is frequently used.
  • 23.
  • 24. ADVANTAGE DISADVANTAGES OF DEEP WELL SYSTEM Groundwater lowering method advantages Disadvantages Deep wells 1. No limits on drawdown 2. Fewer wells required than well system 1. Expensive to install
  • 25. DITCHES AND TRENCHES • Ditches and french drains (commonly known as trenches in construction projects in ahmedabad) are also used on qatar’s construction sites. • The ditches are formed in a pre-planned manner, allowing groundwater flow to surface in the deeper level trenches. Perforated pipes are then placed in the trenches, and groundwater extracted through these pipelines to be filtered. These trenches were particularly common in infrastructure network projects. • Graded aggregates and geotextile layer to be used when laying out the pipelines.
  • 26.
  • 27. ADVANTAGE AND DISADVANTAGE Groundwater lowering method Advantages Disadvantages Ditches/French drains 1. Relatively inexpensive 2. Controls shallow groundwater and over bleed. 3. Effective in controlling groundwater after casting of foundations. 1. Possible obstruction of traffic 2. Groundwater will only be controlled at shallow depth 3. Unlikely to be effective in fine grained soil.
  • 28. EDUCTOR SYSTEM • This system also known as the ‘jet eductor system’ or ‘ejector system’ or ‘eductor wellpoint system’ is similar to the wellpoint system. • Instead of employing a vacuum to draw water to the well-points, the eductor system uses high pressure water and riser units, each about 30-40mm in diameter. • A high pressure supply main feeds water through a venturi tube immediately above the perforated well screen, creating a reduction in pressure which draws water through the large diameter rise pipe. The high pressure main feeds off the return water. • The advantage of the eductor system is that in operating many well points from a single pump station, the water table can be lowered in one stage from depths of 10-45 m.
  • 29. WORKING PROCEDURE OF EDUCTOR SYSTEM • Supply pumps at ground level feed high-pressure water to each eductor well head via a supply main. • The supply flow passes down the well and through a nozzle and venturi in the eductor. The flow of water through the nozzle generates a vacuum in the well and draws in groundwater. • The supply flow and extracted ground water mix, return to the surface and feed back to the pumping station via a return main. The return flow is used to prime the supply pumps and the excess water extracted is discharged by overflow from the priming tank. • A single pumping station can be used to operate up to about 75 eductor wells installed in an appropriate array around the works.
  • 30.
  • 31. ADVANTAGES OF EDUCTOR SYSTEM 1. They are flexible in level and layout. 2. Stable in operation. 3. Able to run dry without damage. 4. Not limited by depth. Also effective to greater depths. 5. Best in low-yielding wells. 6. Energy intensive. 7. Venturi in base of well creates vacuum.
  • 32. THINGS TO BE TAKEN CARE DURING DEWATERING!!! • Dewatering activities must be done properly to avoid eroding the soil on the construction site. • It is also important to choose the best location for discharge, even when you might be far away from water bodies or catch basins. • Water should not be pumped directly into slopes. • Pay special attention and discontinue dewatering if the area shows signs of instability or erosion.
  • 33. • Channels used on dewatering must be stable and better if they have been protected with grass or vegetation. • Avoid dewatering under heavy rains because the infiltration rate is at a minimum and water will move slower or just the dewatering process will not function. • Never discharge water that has been contaminated with oil, grease, chemical products directly. In such instances an oil/water separator may be necessary. • Additional permits and requirements might be needed from state, local or federal agencies.