APPLICATION OF 4D CAD BIM TECHNOLOGY IN CONSTRUCTION
SCHEDULING
Akash Sonar1, Harshita Ambre2
1Student M.Tech Construction Management, Department of Civil Engineering, Sandip University, Nashik
2Assistant Professor, Department of Civil Engineering, Sandip University, Nashik
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Construction scenario ischangingfrom2Dbased
drawings to 3D models. Building Information Modeling (BIM)
is a model based design concept in which buildings are built
virtually before the actual construction work starts.
Construction projects areinformationintensive. Havingaccess
to accurate information at the correct time and in the precise
place is essential for decision-making and also for ensuring a
project to be delivered within time and budgetedcost. Inorder
to introduce the basic concepts of BIM, researchers presented
how BIM can be utilized by project managers as a good tool to
simulate project condition. Their team stated the various
advantages of BIM, its adoption in India, usage of BIM
software's in India, also the challenges faced in BIM adoption.
BIM is a new and promising approach in India which is
gradually gaining acceptance. The value proposition of BIMis
that it integrates all lifecycle phases of the project and has the
potential to benefit all project stakeholders. The proper
understanding of change in business processes and practices
that come with BIM implementation, along with the project
management aspect of BIM, is still a young area of academic
inquiry. The purpose of this study is also to analyze how BIM
can be utilized by construction managers. The case study was
conducted on the residential bungalow to analyze the use of
BIM. The study revealed that BIM can help construction
manager in the task of delivering successful projects. Afocusis
placed on analyzing 3D and 4D BIM as Well as BIM based
scheduling. The research was conducted through literature
review & case studies. Thus, Building Information Modeling
(BIM) is an emerging technology in AEC industry & it provides
users with more accurate and consistent project information
throughout the lifecycle.
Key Words: Visualization, 3D model, Scheduling, 4D
simulation, Project Management, Benefits of BIM
1. INTRODUCTION
Building Information Modeling is a process consisting of
information about different phasesofanyprojectlikedesign,
construction planning, construction, facility management
and operation. It is onethedocumentationprocessbeneficial
for visualization, and construction application such as
estimating, scheduling and design. Main advantage of
implementing BIM application is the visual coordination of
the building systems such as MEP (Mechanical, Electrical,
and Plumbing) systems and it also identifies the possible
conflicts between the building systems. By detecting the
conflicts, problems can be resolved before actual
construction which in turn saves money and time invested.
BIM is helping with better visualization of design by
minimizing design errors better planning of construction
activities, supportingtheconstructionprocessandproviding
a data-rich platform for facility operation and maintenance.
It is also a strong collaboration tool that helps the project
team to work together and collaborate for delivering better
built environment assets. In India, the BIM application isnot
widely practiced till now has scope to use this technology in
a much wider scale.
1.1 The Building Information Model
The building information model refers to the combined
model where the models from the different disciplines have
been merged. According to the BIM handbook the building
information model is characterized by the following
features: 1-“Building components that are represented with
intelligent digital representations (objects)thatknow‟what
they are, and can be associated withcomputablegraphic and
data attributes and parametric rules. 2- Components that
include data that describe how they behave, as needed for
analyses and work processes, e.g. takeoff, specification, and
energy analysis. 3-Consistent and non-redundant data such
that changes to component data are represented in all views
of that component. 4-Coordinated data such that all viewsof
a model are represented in a coordinated way.
1.2 4D CAD BIM
BIM allows use of a parametric 3D model to autogenerate
traditional building documents such as plans, sections,
elevations, details, and schedules. It is a platform to share
knowledge and communicate between project participants.
In other words, BuildingInformationModelingistheprocess
of developing the Building Information Model. High quality
3D renderings of a building can be generated from Building
Information Models. In recent years, there has been a
significant improvement in the tools available to model a
construction project using 3D and 4D technologies. Current
3D Modeling tools offer predefined objects that facilitatethe
development, routing, and connection of buildingsystemsin
3D, and provide conflict detection mechanisms that help to
automatically identify physical interferences between
components. However, implementing 3D and 4D modeling
on an actual project in a multidisciplinary and multi-
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6467
organizational environment is a complicated process that
requires co-ordinate efforts. Implementation of
constructability ideas in the construction industry has a
potential return on investment concerning time and money.
Scheduling and simulations plays an important role in this
project. A schedule is a listing of a project's milestones,
activities, and deliverables, usually with intended start and
finish dates. Those items are often estimated in terms of
resource allocation, budget and duration, linked by
dependencies and scheduled events. Simulation is the
imitation of the operation of a real-world process or system
over time. The act of simulating somethingfirstrequiresthat
a model be developed. The model represents the system
itself, whereas the simulationrepresentstheoperationof the
system over time.
2. LITERATURE REVIEW
Nam Bui et al., (2016) [1] presented an overview of BIM
research in developing countries and the focus of their
present work was limited to China, India, and Malaysia. Han
Yan and PeterDamian[2] conductedaresearchwhichoutlines
the historical evolution of design tools. Theirpaperdescribes
questionnaire data from a survey of about 70 individuals
from the AEC industry on BIM adoption, perceived benefits,
and perceived barriers. Abdulsame Fazlia et al., (2014) [3]
presented how BuildingInformationModelingcanbeutilized
by project managers as a good tool to simulate project
condition to avoid redundant works and waste of time and
cost. Moiz Tarar (2012) [4] concluded 4D modeling as a
promising tool for construction planning. Sheryl Staub-
French and Atul Khanzod (2007) [5] provided guidelines to
help project teams implement 3D and 4D modeling on
building construction projects. Anil Sawhney & Research
team stated the various advantages of BIM, its adoption in
India, usage of BIM software'sinIndia,thechallengesfacedin
BIMadoptionandthefutureofBIMinIndia.RistoTulenheimo
(2015) [6] analyzed the wide range of obstacles generated by
customers, company’s own organization,socialbehaviorand
immaturetechnologies in constructionengineeringindustry.
As a result of this study, different key challenges were
identified that can alone stop a successful implementation of
a BIM technology.
3. STATEMENT OF PROBLEM
BIM technology has already started to benefit the
designers with model-based design and owners witha more
feasible and accessible project and schedule is a key
parameter for the construction management process. In
some developing cities like Dhule, BIM is not applied yet. So
it is essential to know if the information in BIM model can
help for the time and schedule controls and the
developments that can be made with BIM technology.
4. METHODOLOGY
Chart -1: Flowchart of methodology
The goal of this project is to examine the uses and benefits of
BIM for construction manager and analyze BIM based
scheduling. First, it includes the definitionandtheuseofBIM
and its tools & a case study. The case study, a bungalow
project, examined the 3D and 4D Building Information
Modeling as well as BIM based scheduling. Collection of the
data from the site like AutoCADdrawings,designsetc.the 3D
model of the project is developed for the same. The various
benefits of the model are taken into consideration. The
building simulation model with the help of Navisworks
simulate software is developed. By importing the 3D model
to the Navisworks software from 3Ds max and then the
schedule i.e. time with the help of Microsoft project hasbeen
linked to it to generate the simulated model in 4D. The role
of the construction manager on BIM based project &
traditional project will be defined.
4.1 DATA COLLECTION
The primary focus of this project is the use of Building
information model, 4D simulation and its various
parameters on a G+1 bungalow. In this chapter, the case
study on the effective utilization of BIM for the residential
building will be shown. The 3D modeling of residential
bungalow is shown. The data was collected to fulfill the
requirement of the project. This data include the drawings
and specification of a building. Their SectionsandElevations
are prepared by using the 3D AutoCAD. The aspect of the
company for implementation of the project is studied
thoroughly & all the information of the site like, who is
owner, Structural consultant & site engineer etc.iscollected.
Also its intelligent model is developed by using BIM tool.
The 2D AutoCAD drawing and 3D max file of the project are
then taken from the site. The specificationsoftheall material
of the site are also taken and studied.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6468
Fig -1: Site plan 2D
Fig -2: 3D CAD model
Fig -3: 3D modeling by 3Ds Max
4.2 DATA ANALYSIS
With time estimation, often also called 4D, the objects in a
building information model are linked to the time plan with
the help of Microsoft project 2013. The linkage to time plan
makes it possible to graphically visualize the projects
schedule. After that simulation is done by linking all the
components of 3D model with time with the help of
navisworks simulation software 2018. This type of
simulation providesconsiderableinsightandallowsforearly
detection of planning errors. Instead of realizing planning
mistakes later on in the construction phase, and having to
resolve problems on site which can be very costly, mistakes
can be eliminated already in the design phase.
Fig -4: Microsoft project schedule
Fig -5: Naviswork activities screenshot
Fig -6: Naviswork simulation
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6469
5. RESULTS
Use Of BIM Benefits
Early and efficient
clash detection in
location and sharing.
Early clash detectionispossible
in case of BIM use & also
scheduling of same is possible
which saves the time & cost.
Early and continual
close
Coordination withall
players.
Results in proper coordination
for entire project.
Allows flexibility in
scheduling and
sequencing.
According to requirements of
clients or any other, the
schedule or cost of the project
can be updated at any point
required. This gives flexibility
to the project.
Better visualization 3D views of the project give the
better visualization of project.
Better
documentation with
less errors.
As BIM is the digital process
very less documentation is
required for the project, this
results in less errors and better
coordination.
Enables increased
offsite
prefabrication.
With the help of 3D & 4D
Simulation prefabrication of
the activities can be done
offsite.
Modifications are
quickly visualized,
shared, estimated
and resolved.
All the project related work can
be viewed at a time by the
various persons involved inthe
project. This results in early
detection & solving of the
problem.
6. CONCLUSION
In our case study we utilized BIM for visualization, 3D
coordination, construction planning, and simulation.
Visualization consisted of rendering of exterior, structural
components of the construction. Overall, visualization
helped to understand the expectancy and needs of the
project before construction. Construction planning was
implemented forthe project.Thiswilleasilyavoidschedule
delays and cost during construction. Lastly, a Simulation of
the model is done. By simulation actual progress vs.
planned progress is visualized by construction manager
easily. BIM based 4Dscheduling helpsunderstandingofthe
construction components and schedule progress that in
turn results better constructionplanning.TheConstruction
Manager’s role will remain the same in BIM projects as in
traditional projects. However, the Construction Manager
might be required to learn some new skills related to
working with BIM. Regarding the Construction Manager’s
relationships to other stakeholders within BIM projects,
there are many barriers keeping project participants from
using the latest technology and BIM. The barriers include
fears of too low success low or big failure, high initial
investment costs, the timetolearn how to usethesoftware.
The obstacle in BIM implementation is the lack of
information aboutthestrictBIMimplementationstandards
and rules for certain project participants, contract
obligations in certain countries or unified documentation
for regions. The use of BIM and its benefits have proven to
be a value to construction projects. These benefits are
achieved by the collaborationof the construction team and
the utilization of BIM tools. However,thesetoolshavesome
setbacks especially with interoperability which require
further attention by the construction industry.
REFRENCES
1. Nam Bui, Christoph Merschbrock, Bjorn Erick
Munkvold (2016) “A review of BIM forconstruction
in developing countries”.
2. Han Yan and Peter Damian (Department of Civil
and Building Engineering, Loughborough
University, UK) “Benefits and Barriers of Building
Information Modeling”.
3. Abdulsame Fazlia, SajadFathia, Mohammad
HadiEnferadi, Mayram Fazlib, Behrooz Fathi,2014,
“Appraising effectiveness of Building Information
Management (BIM) in project management”
ScienceDirect.
4. Moiz Tarar, (2012). “Impact of 4D Modeling on
Construction Planning Process”, Chalmers
University of Technology, Civil and Environmental
Engineering, 2012:27Stephen Fai1,KatieGraham1,
Todd Duckworth, Nevil Wood1, Ramtin Attar
“Building Information Modelling and heritage
Documentation.”
5. Sheryl Staub-French and Atul Khanzode, (July
2007). “3D and 4D Modeling for Design and
Construction Coordination.”
6. Anil Sawhney, May 2014, “State of BIM adoption
and outlook in India”, ARICS.
7. Risto Tulenheimo (2016) “Challenges of
implementing new technologies in the world of
BIM– Case study from construction engineering
industry in Finland.” 8th Nordic Conference on
Construction Economics and Organization.

More Related Content

What's hot

Construction Cost Prediction by Using Building Information Modeling
Construction Cost Prediction by Using Building Information ModelingConstruction Cost Prediction by Using Building Information Modeling
Construction Cost Prediction by Using Building Information Modeling
IJERA Editor
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Michael Cook
 
BIM research report
BIM research reportBIM research report
BIM research report
Chen Zhong
 
s131478 - Master Thesis
s131478 - Master Thesiss131478 - Master Thesis
s131478 - Master Thesis
Tomas Miskinis
 

What's hot (18)

THE IMPACT OF BUILDING INFORMATION MODELLING (BIM) ON THE ARCHITECTURAL D...
THE IMPACT OF   BUILDING INFORMATION MODELLING (BIM)  ON THE ARCHITECTURAL  D...THE IMPACT OF   BUILDING INFORMATION MODELLING (BIM)  ON THE ARCHITECTURAL  D...
THE IMPACT OF BUILDING INFORMATION MODELLING (BIM) ON THE ARCHITECTURAL D...
 
IRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building ProjectIRJET- 4D Simulation of MEP using Bim for Residential Building Project
IRJET- 4D Simulation of MEP using Bim for Residential Building Project
 
Construction Cost Prediction by Using Building Information Modeling
Construction Cost Prediction by Using Building Information ModelingConstruction Cost Prediction by Using Building Information Modeling
Construction Cost Prediction by Using Building Information Modeling
 
BIM For Building Product Manufacturers
BIM For Building Product ManufacturersBIM For Building Product Manufacturers
BIM For Building Product Manufacturers
 
Ijmet 10 02_009
Ijmet 10 02_009Ijmet 10 02_009
Ijmet 10 02_009
 
Ijebea14 244
Ijebea14 244Ijebea14 244
Ijebea14 244
 
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's PerspectiveAdvantages and Challenges of Using BIM: a Cost Consultant's Perspective
Advantages and Challenges of Using BIM: a Cost Consultant's Perspective
 
Bim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari NassiBim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
 
Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...
 
BIM research report
BIM research reportBIM research report
BIM research report
 
Bim challenges and potential
Bim challenges and potentialBim challenges and potential
Bim challenges and potential
 
McGraw-Hill The Business Value of BIM
McGraw-Hill The Business Value of BIMMcGraw-Hill The Business Value of BIM
McGraw-Hill The Business Value of BIM
 
IRJET-3D,4D and 5D Building Information Modeling for Commercial Building Proj...
IRJET-3D,4D and 5D Building Information Modeling for Commercial Building Proj...IRJET-3D,4D and 5D Building Information Modeling for Commercial Building Proj...
IRJET-3D,4D and 5D Building Information Modeling for Commercial Building Proj...
 
s131478 - Master Thesis
s131478 - Master Thesiss131478 - Master Thesis
s131478 - Master Thesis
 
CONSTRUCTION ENABLED BY INTERNET OF THINGS
CONSTRUCTION ENABLED BY INTERNET OF THINGSCONSTRUCTION ENABLED BY INTERNET OF THINGS
CONSTRUCTION ENABLED BY INTERNET OF THINGS
 
World Building Information Modeling (BIM) Market is Expected to Garner $11.7 ...
World Building Information Modeling (BIM) Market is Expected to Garner $11.7 ...World Building Information Modeling (BIM) Market is Expected to Garner $11.7 ...
World Building Information Modeling (BIM) Market is Expected to Garner $11.7 ...
 
F1302033340
F1302033340F1302033340
F1302033340
 
BIM & Safety
BIM & SafetyBIM & Safety
BIM & Safety
 

Similar to IRJET- Application of 4D CAD BIM Technology in Construction Scheduling

CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
Est
 

Similar to IRJET- Application of 4D CAD BIM Technology in Construction Scheduling (20)

Application of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction ProjectApplication of BIM for Scheduling and Costing of Construction Project
Application of BIM for Scheduling and Costing of Construction Project
 
4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdf4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdf
 
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET -  	  Digital Engineering & Project Management for AEC Industry using BIMIRJET -  	  Digital Engineering & Project Management for AEC Industry using BIM
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
 
Building information modelling report
Building information modelling reportBuilding information modelling report
Building information modelling report
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...
STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...
STUDY ON BUILDING INFORMATION MODELING AND IMPLEMENTATION OF CLASH DETECTION ...
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group report
 
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
 
A Statistical Analysis of Building Information Modeling in Project Management
A Statistical Analysis of Building Information Modeling in Project ManagementA Statistical Analysis of Building Information Modeling in Project Management
A Statistical Analysis of Building Information Modeling in Project Management
 
A Statistical Analysis Of Building Information Modeling In Project Management
A Statistical Analysis Of Building Information Modeling In Project ManagementA Statistical Analysis Of Building Information Modeling In Project Management
A Statistical Analysis Of Building Information Modeling In Project Management
 
Bim in Construction Management
Bim in Construction ManagementBim in Construction Management
Bim in Construction Management
 
A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...
 
IRJET - To Extract GFC’s from Clash Free and Well Coordinated Revit Model
IRJET - To Extract GFC’s from Clash Free and Well Coordinated Revit ModelIRJET - To Extract GFC’s from Clash Free and Well Coordinated Revit Model
IRJET - To Extract GFC’s from Clash Free and Well Coordinated Revit Model
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
Sc bim
Sc bimSc bim
Sc bim
 
Building Information Model
Building Information ModelBuilding Information Model
Building Information Model
 
An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...
 
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsApplication Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
 
Bim its applications
Bim   its applicationsBim   its applications
Bim its applications
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...
 

More from IRJET Journal

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 

IRJET- Application of 4D CAD BIM Technology in Construction Scheduling

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6466 APPLICATION OF 4D CAD BIM TECHNOLOGY IN CONSTRUCTION SCHEDULING Akash Sonar1, Harshita Ambre2 1Student M.Tech Construction Management, Department of Civil Engineering, Sandip University, Nashik 2Assistant Professor, Department of Civil Engineering, Sandip University, Nashik ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Construction scenario ischangingfrom2Dbased drawings to 3D models. Building Information Modeling (BIM) is a model based design concept in which buildings are built virtually before the actual construction work starts. Construction projects areinformationintensive. Havingaccess to accurate information at the correct time and in the precise place is essential for decision-making and also for ensuring a project to be delivered within time and budgetedcost. Inorder to introduce the basic concepts of BIM, researchers presented how BIM can be utilized by project managers as a good tool to simulate project condition. Their team stated the various advantages of BIM, its adoption in India, usage of BIM software's in India, also the challenges faced in BIM adoption. BIM is a new and promising approach in India which is gradually gaining acceptance. The value proposition of BIMis that it integrates all lifecycle phases of the project and has the potential to benefit all project stakeholders. The proper understanding of change in business processes and practices that come with BIM implementation, along with the project management aspect of BIM, is still a young area of academic inquiry. The purpose of this study is also to analyze how BIM can be utilized by construction managers. The case study was conducted on the residential bungalow to analyze the use of BIM. The study revealed that BIM can help construction manager in the task of delivering successful projects. Afocusis placed on analyzing 3D and 4D BIM as Well as BIM based scheduling. The research was conducted through literature review & case studies. Thus, Building Information Modeling (BIM) is an emerging technology in AEC industry & it provides users with more accurate and consistent project information throughout the lifecycle. Key Words: Visualization, 3D model, Scheduling, 4D simulation, Project Management, Benefits of BIM 1. INTRODUCTION Building Information Modeling is a process consisting of information about different phasesofanyprojectlikedesign, construction planning, construction, facility management and operation. It is onethedocumentationprocessbeneficial for visualization, and construction application such as estimating, scheduling and design. Main advantage of implementing BIM application is the visual coordination of the building systems such as MEP (Mechanical, Electrical, and Plumbing) systems and it also identifies the possible conflicts between the building systems. By detecting the conflicts, problems can be resolved before actual construction which in turn saves money and time invested. BIM is helping with better visualization of design by minimizing design errors better planning of construction activities, supportingtheconstructionprocessandproviding a data-rich platform for facility operation and maintenance. It is also a strong collaboration tool that helps the project team to work together and collaborate for delivering better built environment assets. In India, the BIM application isnot widely practiced till now has scope to use this technology in a much wider scale. 1.1 The Building Information Model The building information model refers to the combined model where the models from the different disciplines have been merged. According to the BIM handbook the building information model is characterized by the following features: 1-“Building components that are represented with intelligent digital representations (objects)thatknow‟what they are, and can be associated withcomputablegraphic and data attributes and parametric rules. 2- Components that include data that describe how they behave, as needed for analyses and work processes, e.g. takeoff, specification, and energy analysis. 3-Consistent and non-redundant data such that changes to component data are represented in all views of that component. 4-Coordinated data such that all viewsof a model are represented in a coordinated way. 1.2 4D CAD BIM BIM allows use of a parametric 3D model to autogenerate traditional building documents such as plans, sections, elevations, details, and schedules. It is a platform to share knowledge and communicate between project participants. In other words, BuildingInformationModelingistheprocess of developing the Building Information Model. High quality 3D renderings of a building can be generated from Building Information Models. In recent years, there has been a significant improvement in the tools available to model a construction project using 3D and 4D technologies. Current 3D Modeling tools offer predefined objects that facilitatethe development, routing, and connection of buildingsystemsin 3D, and provide conflict detection mechanisms that help to automatically identify physical interferences between components. However, implementing 3D and 4D modeling on an actual project in a multidisciplinary and multi-
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6467 organizational environment is a complicated process that requires co-ordinate efforts. Implementation of constructability ideas in the construction industry has a potential return on investment concerning time and money. Scheduling and simulations plays an important role in this project. A schedule is a listing of a project's milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. Simulation is the imitation of the operation of a real-world process or system over time. The act of simulating somethingfirstrequiresthat a model be developed. The model represents the system itself, whereas the simulationrepresentstheoperationof the system over time. 2. LITERATURE REVIEW Nam Bui et al., (2016) [1] presented an overview of BIM research in developing countries and the focus of their present work was limited to China, India, and Malaysia. Han Yan and PeterDamian[2] conductedaresearchwhichoutlines the historical evolution of design tools. Theirpaperdescribes questionnaire data from a survey of about 70 individuals from the AEC industry on BIM adoption, perceived benefits, and perceived barriers. Abdulsame Fazlia et al., (2014) [3] presented how BuildingInformationModelingcanbeutilized by project managers as a good tool to simulate project condition to avoid redundant works and waste of time and cost. Moiz Tarar (2012) [4] concluded 4D modeling as a promising tool for construction planning. Sheryl Staub- French and Atul Khanzod (2007) [5] provided guidelines to help project teams implement 3D and 4D modeling on building construction projects. Anil Sawhney & Research team stated the various advantages of BIM, its adoption in India, usage of BIM software'sinIndia,thechallengesfacedin BIMadoptionandthefutureofBIMinIndia.RistoTulenheimo (2015) [6] analyzed the wide range of obstacles generated by customers, company’s own organization,socialbehaviorand immaturetechnologies in constructionengineeringindustry. As a result of this study, different key challenges were identified that can alone stop a successful implementation of a BIM technology. 3. STATEMENT OF PROBLEM BIM technology has already started to benefit the designers with model-based design and owners witha more feasible and accessible project and schedule is a key parameter for the construction management process. In some developing cities like Dhule, BIM is not applied yet. So it is essential to know if the information in BIM model can help for the time and schedule controls and the developments that can be made with BIM technology. 4. METHODOLOGY Chart -1: Flowchart of methodology The goal of this project is to examine the uses and benefits of BIM for construction manager and analyze BIM based scheduling. First, it includes the definitionandtheuseofBIM and its tools & a case study. The case study, a bungalow project, examined the 3D and 4D Building Information Modeling as well as BIM based scheduling. Collection of the data from the site like AutoCADdrawings,designsetc.the 3D model of the project is developed for the same. The various benefits of the model are taken into consideration. The building simulation model with the help of Navisworks simulate software is developed. By importing the 3D model to the Navisworks software from 3Ds max and then the schedule i.e. time with the help of Microsoft project hasbeen linked to it to generate the simulated model in 4D. The role of the construction manager on BIM based project & traditional project will be defined. 4.1 DATA COLLECTION The primary focus of this project is the use of Building information model, 4D simulation and its various parameters on a G+1 bungalow. In this chapter, the case study on the effective utilization of BIM for the residential building will be shown. The 3D modeling of residential bungalow is shown. The data was collected to fulfill the requirement of the project. This data include the drawings and specification of a building. Their SectionsandElevations are prepared by using the 3D AutoCAD. The aspect of the company for implementation of the project is studied thoroughly & all the information of the site like, who is owner, Structural consultant & site engineer etc.iscollected. Also its intelligent model is developed by using BIM tool. The 2D AutoCAD drawing and 3D max file of the project are then taken from the site. The specificationsoftheall material of the site are also taken and studied.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6468 Fig -1: Site plan 2D Fig -2: 3D CAD model Fig -3: 3D modeling by 3Ds Max 4.2 DATA ANALYSIS With time estimation, often also called 4D, the objects in a building information model are linked to the time plan with the help of Microsoft project 2013. The linkage to time plan makes it possible to graphically visualize the projects schedule. After that simulation is done by linking all the components of 3D model with time with the help of navisworks simulation software 2018. This type of simulation providesconsiderableinsightandallowsforearly detection of planning errors. Instead of realizing planning mistakes later on in the construction phase, and having to resolve problems on site which can be very costly, mistakes can be eliminated already in the design phase. Fig -4: Microsoft project schedule Fig -5: Naviswork activities screenshot Fig -6: Naviswork simulation
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6469 5. RESULTS Use Of BIM Benefits Early and efficient clash detection in location and sharing. Early clash detectionispossible in case of BIM use & also scheduling of same is possible which saves the time & cost. Early and continual close Coordination withall players. Results in proper coordination for entire project. Allows flexibility in scheduling and sequencing. According to requirements of clients or any other, the schedule or cost of the project can be updated at any point required. This gives flexibility to the project. Better visualization 3D views of the project give the better visualization of project. Better documentation with less errors. As BIM is the digital process very less documentation is required for the project, this results in less errors and better coordination. Enables increased offsite prefabrication. With the help of 3D & 4D Simulation prefabrication of the activities can be done offsite. Modifications are quickly visualized, shared, estimated and resolved. All the project related work can be viewed at a time by the various persons involved inthe project. This results in early detection & solving of the problem. 6. CONCLUSION In our case study we utilized BIM for visualization, 3D coordination, construction planning, and simulation. Visualization consisted of rendering of exterior, structural components of the construction. Overall, visualization helped to understand the expectancy and needs of the project before construction. Construction planning was implemented forthe project.Thiswilleasilyavoidschedule delays and cost during construction. Lastly, a Simulation of the model is done. By simulation actual progress vs. planned progress is visualized by construction manager easily. BIM based 4Dscheduling helpsunderstandingofthe construction components and schedule progress that in turn results better constructionplanning.TheConstruction Manager’s role will remain the same in BIM projects as in traditional projects. However, the Construction Manager might be required to learn some new skills related to working with BIM. Regarding the Construction Manager’s relationships to other stakeholders within BIM projects, there are many barriers keeping project participants from using the latest technology and BIM. The barriers include fears of too low success low or big failure, high initial investment costs, the timetolearn how to usethesoftware. The obstacle in BIM implementation is the lack of information aboutthestrictBIMimplementationstandards and rules for certain project participants, contract obligations in certain countries or unified documentation for regions. The use of BIM and its benefits have proven to be a value to construction projects. These benefits are achieved by the collaborationof the construction team and the utilization of BIM tools. However,thesetoolshavesome setbacks especially with interoperability which require further attention by the construction industry. REFRENCES 1. Nam Bui, Christoph Merschbrock, Bjorn Erick Munkvold (2016) “A review of BIM forconstruction in developing countries”. 2. Han Yan and Peter Damian (Department of Civil and Building Engineering, Loughborough University, UK) “Benefits and Barriers of Building Information Modeling”. 3. Abdulsame Fazlia, SajadFathia, Mohammad HadiEnferadi, Mayram Fazlib, Behrooz Fathi,2014, “Appraising effectiveness of Building Information Management (BIM) in project management” ScienceDirect. 4. Moiz Tarar, (2012). “Impact of 4D Modeling on Construction Planning Process”, Chalmers University of Technology, Civil and Environmental Engineering, 2012:27Stephen Fai1,KatieGraham1, Todd Duckworth, Nevil Wood1, Ramtin Attar “Building Information Modelling and heritage Documentation.” 5. Sheryl Staub-French and Atul Khanzode, (July 2007). “3D and 4D Modeling for Design and Construction Coordination.” 6. Anil Sawhney, May 2014, “State of BIM adoption and outlook in India”, ARICS. 7. Risto Tulenheimo (2016) “Challenges of implementing new technologies in the world of BIM– Case study from construction engineering industry in Finland.” 8th Nordic Conference on Construction Economics and Organization.