CRITICAL CHAIN PROJECT MANAGEMENT IN CONSTRUCTION PROJECTS
Mr. A. Vignesh
Assistant Professor, Department of Civil Engineering, AVS College of Technology, Mennampalli, Salem,
Tamilnadu, India
-------------------------------------------------------------------------***------------------------------------------------------------------------
ABSTRACT - Many construction industries have been using Critical Path Method (CPM) scheduling for a very long time.
However, due to the increasingly competitive business environment, tighter time constraints are becoming the norm of the
industry. As a result, more projects are slipping behind schedule. This led some industries to call for more efficient means
to plan and schedule projects. Following to the introduction of the theory of constraints (TOC), a new and innovative project
scheduling paradigm has emerged, that is Critical Chain (CC). Critical Chain Project Management (CCPM) is rapidly
becoming the new standard for project success introduced in 1997 as a new approach to plan and execute projects. A
central driver for adopting CCPM is enabling more predictable and shorter project lead times. The argument being that this
will not only enhance time related order winning criteria but also reduce cost and improve adherence to specification with
appropriate buffer sizing techniques. Typically, CCPM case studies report 95% on-time and on-budget completion when
CCPM is applied correctly.
A detailed literature survey was conducted on “Critical Chain Project Management in scheduling Construction projects”.
Through the literature review, the stability of the Critical chain method in project’s organizational and operational
environment, resource productivity under multi-tasking and overall performance of the project were analyzed and CCPM
projects demonstrates completion with 10% to 50% in cost and duration.
GENERAL:
The Project Management is a process and activity of planning, organizing, motivating and controlling the resources, so as
to achieve specific goal. There are number of approaches available for managing project activities.
Critical chain project management (CCPM) is one such new, popular project management paradigm for planning and
managing projects. CCPM differs from the traditional methods namely Critical Path Method (CPM) and Program Evaluation
Review Technique (PERT) algorithms which emphasizes the task order and rigid scheduling. In critical chain project
management, the uncertainty is aggregated into buffers at the end of the activity path. The project buffers protect the
overall project completion and feeding buffers protect the critical chain from non-critical path merging. Critical chain project
management is adopted to reduce the time duration of the project so that the time delay and cost incurred due to delay can
be reduced and the project can be finished within the due date. Project that uses critical chain project management have a
greatly improved record of schedule, cost and scope performance. Projects experience critical chain project management
demonstrate completionless than three-fourth the time of the project using previous planning and controlling methods.
OBJECT OF THE PROJECT:
The Project proposes the implementation of new and innovative Critical Chain Scheduling method as a solution to the
problems faced in the Traditional Project Management Methods. The study also identifies the benefits and limitations
associated with Critical Chain Project Management Method and its adoptability to the construction scenario.
NEED O FTHE PROJECT:
Despite this relative popularity in some industries worldwide, there was no documentation of applying CC (critical chain)
in the construction industry in India. Admittedly, there have been attempts at applying CC in the international
construction. Industry, yet CC not becoming a well proven industry practice. The study in hand was initiated as an effort to:
1. Gauge the level of awareness of construction industry practitioners about the CC technique.
2. Investigate the applicability of CC in construction projects, from the perspective of those industry
practitioners. Also, investigate the types of construction projects convenient for its application.
3. Point out and possibly tackle an obstacle to itsimplementation.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2656
ADVANTAGES OF CCPM:
The following are the merits of CCPM.
 It accumulates all safety buffers at the end of the project instead of building them into activity estimates, and
protects the critical chain againstinsecurity.
 It focuses on the project constraint (the longest chain of dependent resources or activities).
 Uses average-case estimates (task estimates based on 50% probability of completion.
 Protects project with buffers
 Starts tasks as soon as predecessors are done, finishes tasks as quickly as Possible
 Team ownership of project completion
 Project health is based on days used from the project buffer
 Avoidance of Student’s syndrome, Parkinson’s law, Murphy’s law, and Multitasking
 Relay race Scheduling
 Late start Scheduling of Non-critical activities.
 No rescheduling and thus less work-in-progress
 More chance of finishing on time.
BUFFER SIZING METHODS
SQUARE ROOT OF SUM OF SQUARES METHOD (SSQ)
In this method, the size of the buffer is set to the square root of the sum of the squares of the difference between the low
risk duration and the mean duration for each task along the chain leading to the buffer. If the path branches upstream, the
longest chain or the longest result considering each chain should be used. Specifically, when trying to account for the
variation in task durations, adopting the largest result, considering each chain is probably the preferred approach, even
though it will necessarily involve more computation. In this method, duration is with a probability greater than 90%. The
advantage of this method is that it allows to account for known variation in task duration. The disadvantage is that it may
lead to undersize the buffers for the long chain.
ADAPTIVE PROCEDURE WITH DENSITY (ADP)
In this method, for a given number of tasks the likelihood of a delay increases as the number of precedence relationships
increases. Stated differently, there is a greater level of interdependence between the tasks and, if one task is delayed, all of
its successors will be delayed. The number of precedence relationships as the density of the network. In this method,
density effects through the application of this buffer sizing method are accounted. Again the buffer is set to the standard
deviation of the pathscaled by a factor. This time the factor is based on the network density, and is defined as:
K=1+ TOTPRE / NUM TASK
Where TOTPRE is the total number of precedence relationships on the sub-network under consideration, and NUMTASK is
the number of tasks on that sub-network. The buffer size is then given by:
Buffer size = k x σ feeding path
Where ‘K’ is the standard deviation of the longest path on the sub-network under consideration.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2657
WORK PROGRESS DETAILS OF A PROPOSED VILLA AT KANNANKURICHI, SALEM
The following data represents the activities performed in the construction of a single project (villa) done in a small-scale
construction industry at Salem in the year 2019. The sequence of the work details are as given in the following table.
Sl. No. Activity Description Duration
1. A Earthwork Excavation 2 days
2. B Column Erection, Mat Concrete, Taper
Concrete, Column Concrete up to
plinth level
2 days
3. C Curing for Foundation 14 days
4. D Pit Sand filling for Foundation Trench,
Diggingof Earth, River sand filling and P.C.C
for plinth beam layout
4 days
5. E Shuttering, Centring, laying and Curing of
Plinth beam
11 9days
6. F Brickwork and Curing upto Basement level 9 days
7. G Plastering of Brickwork at Basement level,
curing and Pit sand-filling for
Basement
10 days
8. H Flooring at ground level, Brickwork and
Curing at Ground floor lintel
level
9 days
9. I Shuttering, Centring, Laying of Concrete
and Curing of Brickwork at Ground Floor
Lintel Level
19 days
10. J Shuttering, Centring, Laying of concrete and
Curing of Roof Slab and Beams continuing
with decentring works
18 days
11. K Door, Window frame fixing, Electric pipes,
Plumbing and Wall Plastering works, Curing
of Walls
9 days
12. L Exterior wall Plastering and Curing,
Weathering course
works
6 days
13. M One coat white wash with white cement for
all walls, ceilings
2 days
14. N Floor finish with Tiles 2 days
15. O Finishing (Enamel paintings to Doors and
Windows, E.B Supply, Electrical fittings)
4 days
PROCEDURE IN CRITICAL CHAIN PROJECT MANAGEMENT
1. Build the project schedule without safety time, i.e. use 50th percentile estimates of task durations.
2. Drop the notion of due dates and accept the possibility of delays.
3. Identify and protect critical resources (and don’t worry so much about noncritical resources).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2658
4. Aggregate all the required safety time in a project buffer at the end of the critical path.
5. For the critical resources, identify their lead (i.e., startup) times. This information defines resource
buffers.
6. Fast and slow completion of tasks will tend to cancel out, at least in part, enabling a reduction (possibly
better than 50%) in the project buffer size.
7. For noncritical activities, the only priority occurs where they feed into the critical chain. Protect these
points with feeding buffers.
METHODOLOGY
REFERENCES:
1. Bock, D. and Patterson (2010), J.H. “A comparison of due date setting, resource assignment, and job pre-
emption heuristics for the multi-project scheduling problem”, Decision Sciences, Vol. 21, No. 3, pp.387–402.
2. Casey, R.J (2010), “An innovative approach to schedule management on the F/A-22 Major Defence
Acquisition Program (MDAP): demonstration of critical chain project management”, Doctoral dissertation,
Virginia Polytechnic Institute and State University.
3. Dorota Kuchta (2014), “A new concept of project robust schedule – use of buffers”, Information Technology
and Quantitative Management”, 31 957 – 965.

Más contenido relacionado

La actualidad más candente

FanXuResume_2016
FanXuResume_2016FanXuResume_2016
FanXuResume_2016Fan Xu
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectseSAT Publishing House
 
Resume final(17.11.16) of Anoop Gupta
Resume  final(17.11.16) of Anoop GuptaResume  final(17.11.16) of Anoop Gupta
Resume final(17.11.16) of Anoop GuptaAnoop Gupta
 
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution Raushan Kumar
 

La actualidad más candente (7)

FanXuResume_2016
FanXuResume_2016FanXuResume_2016
FanXuResume_2016
 
Cv's Nitinai_Ratchawat
Cv's Nitinai_RatchawatCv's Nitinai_Ratchawat
Cv's Nitinai_Ratchawat
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
Resume final(17.11.16) of Anoop Gupta
Resume  final(17.11.16) of Anoop GuptaResume  final(17.11.16) of Anoop Gupta
Resume final(17.11.16) of Anoop Gupta
 
DeStephen Derek RESUME
DeStephen Derek RESUMEDeStephen Derek RESUME
DeStephen Derek RESUME
 
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution
Resume of Raushan Kumar having 9 Yrs of Exp in Power Distribution
 
DeStephen Derek Resume
DeStephen Derek ResumeDeStephen Derek Resume
DeStephen Derek Resume
 

Similar a IRJET- Critical Chain Project Management in Construction Projects

IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot TechnologyIRJET Journal
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
IRJET- Enhancement of Productivity and Minimization of Waste using Lean C...
IRJET-  	  Enhancement of Productivity and Minimization of Waste using Lean C...IRJET-  	  Enhancement of Productivity and Minimization of Waste using Lean C...
IRJET- Enhancement of Productivity and Minimization of Waste using Lean C...IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Project management
Project managementProject management
Project managementsmumbahelp
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectIRJET Journal
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewIRJET Journal
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
IRJET-A Review on Precast Concrete
IRJET-A Review on Precast ConcreteIRJET-A Review on Precast Concrete
IRJET-A Review on Precast ConcreteIRJET Journal
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in ConstructionIRJET Journal
 
General Estimation & Abstract Sheet of Royal City
General Estimation & Abstract Sheet of Royal CityGeneral Estimation & Abstract Sheet of Royal City
General Estimation & Abstract Sheet of Royal CityIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 

Similar a IRJET- Critical Chain Project Management in Construction Projects (20)

IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
IRJET- Enhancement of Productivity and Minimization of Waste using Lean C...
IRJET-  	  Enhancement of Productivity and Minimization of Waste using Lean C...IRJET-  	  Enhancement of Productivity and Minimization of Waste using Lean C...
IRJET- Enhancement of Productivity and Minimization of Waste using Lean C...
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional Construction
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Project management
Project managementProject management
Project management
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
IRJET-A Review on Precast Concrete
IRJET-A Review on Precast ConcreteIRJET-A Review on Precast Concrete
IRJET-A Review on Precast Concrete
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
General Estimation & Abstract Sheet of Royal City
General Estimation & Abstract Sheet of Royal CityGeneral Estimation & Abstract Sheet of Royal City
General Estimation & Abstract Sheet of Royal City
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
B1303020508
B1303020508B1303020508
B1303020508
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 

Más de IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Más de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Último

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 

Último (20)

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 

IRJET- Critical Chain Project Management in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2655 CRITICAL CHAIN PROJECT MANAGEMENT IN CONSTRUCTION PROJECTS Mr. A. Vignesh Assistant Professor, Department of Civil Engineering, AVS College of Technology, Mennampalli, Salem, Tamilnadu, India -------------------------------------------------------------------------***------------------------------------------------------------------------ ABSTRACT - Many construction industries have been using Critical Path Method (CPM) scheduling for a very long time. However, due to the increasingly competitive business environment, tighter time constraints are becoming the norm of the industry. As a result, more projects are slipping behind schedule. This led some industries to call for more efficient means to plan and schedule projects. Following to the introduction of the theory of constraints (TOC), a new and innovative project scheduling paradigm has emerged, that is Critical Chain (CC). Critical Chain Project Management (CCPM) is rapidly becoming the new standard for project success introduced in 1997 as a new approach to plan and execute projects. A central driver for adopting CCPM is enabling more predictable and shorter project lead times. The argument being that this will not only enhance time related order winning criteria but also reduce cost and improve adherence to specification with appropriate buffer sizing techniques. Typically, CCPM case studies report 95% on-time and on-budget completion when CCPM is applied correctly. A detailed literature survey was conducted on “Critical Chain Project Management in scheduling Construction projects”. Through the literature review, the stability of the Critical chain method in project’s organizational and operational environment, resource productivity under multi-tasking and overall performance of the project were analyzed and CCPM projects demonstrates completion with 10% to 50% in cost and duration. GENERAL: The Project Management is a process and activity of planning, organizing, motivating and controlling the resources, so as to achieve specific goal. There are number of approaches available for managing project activities. Critical chain project management (CCPM) is one such new, popular project management paradigm for planning and managing projects. CCPM differs from the traditional methods namely Critical Path Method (CPM) and Program Evaluation Review Technique (PERT) algorithms which emphasizes the task order and rigid scheduling. In critical chain project management, the uncertainty is aggregated into buffers at the end of the activity path. The project buffers protect the overall project completion and feeding buffers protect the critical chain from non-critical path merging. Critical chain project management is adopted to reduce the time duration of the project so that the time delay and cost incurred due to delay can be reduced and the project can be finished within the due date. Project that uses critical chain project management have a greatly improved record of schedule, cost and scope performance. Projects experience critical chain project management demonstrate completionless than three-fourth the time of the project using previous planning and controlling methods. OBJECT OF THE PROJECT: The Project proposes the implementation of new and innovative Critical Chain Scheduling method as a solution to the problems faced in the Traditional Project Management Methods. The study also identifies the benefits and limitations associated with Critical Chain Project Management Method and its adoptability to the construction scenario. NEED O FTHE PROJECT: Despite this relative popularity in some industries worldwide, there was no documentation of applying CC (critical chain) in the construction industry in India. Admittedly, there have been attempts at applying CC in the international construction. Industry, yet CC not becoming a well proven industry practice. The study in hand was initiated as an effort to: 1. Gauge the level of awareness of construction industry practitioners about the CC technique. 2. Investigate the applicability of CC in construction projects, from the perspective of those industry practitioners. Also, investigate the types of construction projects convenient for its application. 3. Point out and possibly tackle an obstacle to itsimplementation.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2656 ADVANTAGES OF CCPM: The following are the merits of CCPM.  It accumulates all safety buffers at the end of the project instead of building them into activity estimates, and protects the critical chain againstinsecurity.  It focuses on the project constraint (the longest chain of dependent resources or activities).  Uses average-case estimates (task estimates based on 50% probability of completion.  Protects project with buffers  Starts tasks as soon as predecessors are done, finishes tasks as quickly as Possible  Team ownership of project completion  Project health is based on days used from the project buffer  Avoidance of Student’s syndrome, Parkinson’s law, Murphy’s law, and Multitasking  Relay race Scheduling  Late start Scheduling of Non-critical activities.  No rescheduling and thus less work-in-progress  More chance of finishing on time. BUFFER SIZING METHODS SQUARE ROOT OF SUM OF SQUARES METHOD (SSQ) In this method, the size of the buffer is set to the square root of the sum of the squares of the difference between the low risk duration and the mean duration for each task along the chain leading to the buffer. If the path branches upstream, the longest chain or the longest result considering each chain should be used. Specifically, when trying to account for the variation in task durations, adopting the largest result, considering each chain is probably the preferred approach, even though it will necessarily involve more computation. In this method, duration is with a probability greater than 90%. The advantage of this method is that it allows to account for known variation in task duration. The disadvantage is that it may lead to undersize the buffers for the long chain. ADAPTIVE PROCEDURE WITH DENSITY (ADP) In this method, for a given number of tasks the likelihood of a delay increases as the number of precedence relationships increases. Stated differently, there is a greater level of interdependence between the tasks and, if one task is delayed, all of its successors will be delayed. The number of precedence relationships as the density of the network. In this method, density effects through the application of this buffer sizing method are accounted. Again the buffer is set to the standard deviation of the pathscaled by a factor. This time the factor is based on the network density, and is defined as: K=1+ TOTPRE / NUM TASK Where TOTPRE is the total number of precedence relationships on the sub-network under consideration, and NUMTASK is the number of tasks on that sub-network. The buffer size is then given by: Buffer size = k x σ feeding path Where ‘K’ is the standard deviation of the longest path on the sub-network under consideration.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2657 WORK PROGRESS DETAILS OF A PROPOSED VILLA AT KANNANKURICHI, SALEM The following data represents the activities performed in the construction of a single project (villa) done in a small-scale construction industry at Salem in the year 2019. The sequence of the work details are as given in the following table. Sl. No. Activity Description Duration 1. A Earthwork Excavation 2 days 2. B Column Erection, Mat Concrete, Taper Concrete, Column Concrete up to plinth level 2 days 3. C Curing for Foundation 14 days 4. D Pit Sand filling for Foundation Trench, Diggingof Earth, River sand filling and P.C.C for plinth beam layout 4 days 5. E Shuttering, Centring, laying and Curing of Plinth beam 11 9days 6. F Brickwork and Curing upto Basement level 9 days 7. G Plastering of Brickwork at Basement level, curing and Pit sand-filling for Basement 10 days 8. H Flooring at ground level, Brickwork and Curing at Ground floor lintel level 9 days 9. I Shuttering, Centring, Laying of Concrete and Curing of Brickwork at Ground Floor Lintel Level 19 days 10. J Shuttering, Centring, Laying of concrete and Curing of Roof Slab and Beams continuing with decentring works 18 days 11. K Door, Window frame fixing, Electric pipes, Plumbing and Wall Plastering works, Curing of Walls 9 days 12. L Exterior wall Plastering and Curing, Weathering course works 6 days 13. M One coat white wash with white cement for all walls, ceilings 2 days 14. N Floor finish with Tiles 2 days 15. O Finishing (Enamel paintings to Doors and Windows, E.B Supply, Electrical fittings) 4 days PROCEDURE IN CRITICAL CHAIN PROJECT MANAGEMENT 1. Build the project schedule without safety time, i.e. use 50th percentile estimates of task durations. 2. Drop the notion of due dates and accept the possibility of delays. 3. Identify and protect critical resources (and don’t worry so much about noncritical resources).
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2658 4. Aggregate all the required safety time in a project buffer at the end of the critical path. 5. For the critical resources, identify their lead (i.e., startup) times. This information defines resource buffers. 6. Fast and slow completion of tasks will tend to cancel out, at least in part, enabling a reduction (possibly better than 50%) in the project buffer size. 7. For noncritical activities, the only priority occurs where they feed into the critical chain. Protect these points with feeding buffers. METHODOLOGY REFERENCES: 1. Bock, D. and Patterson (2010), J.H. “A comparison of due date setting, resource assignment, and job pre- emption heuristics for the multi-project scheduling problem”, Decision Sciences, Vol. 21, No. 3, pp.387–402. 2. Casey, R.J (2010), “An innovative approach to schedule management on the F/A-22 Major Defence Acquisition Program (MDAP): demonstration of critical chain project management”, Doctoral dissertation, Virginia Polytechnic Institute and State University. 3. Dorota Kuchta (2014), “A new concept of project robust schedule – use of buffers”, Information Technology and Quantitative Management”, 31 957 – 965.