Managing and Tracking Configure-to-Order
                              Manufacturing with Oracle Applications

        Jason Bletz
        New Generation Consultants


        Overview

        In a Configured-to-Order (CTO) environment, the requirements to fill customer orders are not known
        until the sales order is booked. While some common components from inventory are used to satisfy
        the requirements of multiple configurations, most of the purchased items and subassemblies are
        either bought or built specifcally for the configured order. Such variations in products can include
        size, color/coatings and other accessories. These variations impact downstream activities including
        special operations, outside processing and whether the product is assembled and shipped or first
        shipped and then assembled onsite or at other satellite locations. Controlling the CTO order as it
        moves from Order Entry into Manufacturing and finally into shipping in a configure-to-order
        environment can be a logistical challenge for any organization. Companies need visibility to
        determine when to release the order, where the subassembly components are in the process, how to
        track job specific purchase orders, report on product variablility, how to control and account for
        changes to the order and how to cost related jobs when the order line is modified or canceled.
        Further complicating the process are complex nested BOMs that generate large numbers of work
        orders and purchase orders related to the assemblies and sub-assemblies that comprise the CTO
        product.

        New Generation Consultants (NewGen) provided several solutions to satisfy the business
        requirements of the CTO manufacturer referenced in this paper, however the scope of this paper is
        to discuss the Oracle tools and strategies implemented to satisfy the management and control of
        CTO orders through the manufacturing process. Additional solutions surrounding shipment and
        delivery of the product, configure to quote, configurator rules, and servicing of installed product can
        be found in other White Papers in the NewGen library.

        Industry Methodologies

        Project Manufacturing provides management tools that measure and control large projects in a
        project oriented environment. Capabilities of Project Manufacturing systems include project level
        task breakdown, project level estimation, project level revenue and cost reporting, planning and
        pegging by project as well as project billing by milestone. While these capabilities support several
        configure-to-order manufacturers, the caveat with project manufacturing systems is the ongoing
        management and support of each project required by the organization. This is especially true for
        organizations that have a high volume of customer orders and configurations.

        Discrete and Flow Manaufacturing do an excellent job for build-to-stock environments. The final
        products are planned and built against forecasts of standard items. Shop floor operations are




Managing and Tracking CTO Manufacturing with Oracle Applications                                          Page 1
centered around products that are manufactured, assembled and released to inventory. The orders
        are completed by picking items, newly created or already in inventory, and shipping them.

        Statement of Problem

        While some ERP systems can manage project level manufacturing (low volume and high
        variability/configurations) and others can manage discrete manufacturing (High Volume and Low
        Variability/configurations), very few can support organizations that deal with high volume and high
        variability. If the organizations employ project manufacturing methodolgies they are required to set-
        up and manage a project for every distinct configuration being ordered. If they employ discrete
        manufacturing methodologies, visibility of sales order/project specific information throughout this
        process is not available as the emphasis of discrete manufacturing is on organizing parts and
        assemblies into efficient discrete batches thereby eliminating project specific tagging and tracking.

        Concerns revolving around work-in-process (WIP) management and work-in-process tracking for
        high volume CTO manufacturers include:

                Difficulty in identifying which work orders, other than the top level assemblies, are associated
                 to what sales order demand.
                Excessive number of transactions in WIP to manage and track the associated work orders.
                Difficulty in identifying which work orders are associated to other work orders (which
                 subassemblies are tied to which final assemblies).
                Excessive number of work orders taxes the ability of staff to efficiently process.
                Inability to generate usable standard reports for Shop Floor paperwork without the need to
                 alter the shop floor flow.
                Uniqueness of each CTO product being ordered may cause a proliferation of part numbers.
                Creating new work orders or updating existing work orders is often required for customer-
                 driven change orders. It is difficult to tie them to the current production schedule and parent
                 demand.
                Identifying when to release final assembly orders once all child assemblies are complete.

        Concerns revolving around changes to orders include:

                Changes to the configured item often requires canceling the order line as identifying and
                 making changes to the associated work orders is difficult.
                Difficulty in tracking down all work orders associated with a change order.
                Difficulty in capturing the associated costs related to the change.
                Overall management of work order changes.

        CTO Company Profile

                Mature manufacturing organization, operating since 1889.
                Configure-to-Order manufacturer.
                High degree of configuration of product
                Multiple configurators and order entry systems needed to be centralized.
                CAD and other design applications required integration to the order entry process.




Managing and Tracking CTO Manufacturing with Oracle Applications                                          Page 2
Solution Requirements

        For its client, New Generation determined that any solution had to conform to specific business and
        technology requirements.

        Business:

                Streamline sales order to WIP flow. Using three distinct Configurator tools to configure the
                 product and generate sales orders, the solution needed to capture multiple inputs of demand
                 and communicate these requirements to the shop floor in one unified format.
                Minimize change to the production floor – Radically changing the floor operations to fit
                 the system was not in the client’s best interest. Any solution needed to be transparent to the
                 floor.
                Maintaining Delivery Commitments – Current commitments to the customers could not be
                 impacted. Meeting promised delivery dates is essential to maintaining customer relations.
                Maintaining flexibility in product configurability - Client’s sales and reputation is partly
                 driven by its ability to offer its customers a highly configurable product. Additionally, flexibility
                 is provided to alter the product design up to shipment of finished product. Reducing this
                 capability to fit the out-of-the-box system functionality was not an option.
                Leveraging current investment – Significant investment had been made in Oracle ERP.
                 Any solution would need to leverage the current ERP without requiring the need for
                 investment in additional software applications.

        System:

                Reduction in WIP tracking needs – Reduce complexity for manufacturing team to plan and
                 manage scheduling.
                Maintaining compliance – Any solution must not void any support for E-Business Suite
                 (EBS) by Oracle.
                Feasibility – Technical and functional capability within a tight budget and timeline. Solution
                 must fit within the framework of Oracle EBS.
                Reduction in manual work arounds – The solution needed to reduce overall complexity
                 and allow users to work within the system to manage the process.
                Usability – The solution must match the order-to-cash process flow and leverage current
                 system design and modules.

        Solution Components Implemented

        Oracle E-Business Suite

                Oracle Order to Cash (OM, Advanced Pricing, Shipping)
                Oracle Financials (AR, AP, General Ledger, Project Costing)
                Oracle Configurator
                Oracle Purchasing
                Oracle Advanced Supply Chain Planning
                Oracle Data Hubs
                Oracle Discrete Manufacturing (Bills of Material, Production Scheduling, Work in Process,
                 Costing)




Managing and Tracking CTO Manufacturing with Oracle Applications                                               Page 3
Solution

        The focus of this solution was to capture and streamline CTO Order demand from Oracle Order
        Management (OM) and release it directly into WIP regardless from which configurator system the
        demand originated. By utilizing Oracle’s workflow capabilities, a Seiban numbering strategy and a
        custom WIP dispatching form, NewGen was able to create discrete jobs in the WIP module for the
        top level assemblies and any make-to-order components specified at any level in the BOM. All jobs
        were linked to their respective sales order line, CAD drawing ID and parent work orders (where
        applicable). The custom form provided a 360 degree view of all jobs that were associated with a
        sales order or drawing ID. From this form they are able to manage all work orders and their release
        statuses. Finally, custom shop floor documents were used to communicate all work instructions to
        the shop floor. These documents included routing sheets, indented bills of material, as well as a
        document that grouped different items with like operations so the machine operators could batch
        disparate jobs across the same resources. These shop floor documents were designed to match
        legacy format and, therefore, eliminated the need to alter product flow through the shop floor
        workstations.

        Solution Components

        Custom Workflow - Standardization of post-order flow for Configured items


        The Make-to-Order Workflow provides features needed to satisfy the following basic business
        needs:
                Control the approval step so as to prevent orders from being released until configuration and
                 manually/automated BOM adjustments are complete.
                Reference number can be associated to order configuration and subassemblies
                Work Orders can be associated with the sales order.
                All Make-To-Order Items (Configured Top level items, MTO subassemblies) can be released
                 directly to WIP (bypass MRP).
                Work Orders can be associated with each other (Parent Child Relationship).
                Release critical time constrained purchase components to Purchasing.
                                   ------------------------------------
        Activities included in the workflow include:
                Require an Approval prior to the job being released from the sales order to WIP
                Call the lead time rollup concurrent program
                Perform a wait function in the line flow prior to release in WIP (Ship Date – (Lead Time + X
                 days))
                Revert to prior activities (prior to release to WIP)
                Automatic Generation of Work in Process Jobs for make-to-order items (includes Configured
                 items as well as make-to-order items)
                Link the WIP Job to a specific sales order
                Link the WIP Job to a specific File Number (CAD drawing ID)
                Link WIP Jobs to related Jobs (Parent/Child relationship)




Managing and Tracking CTO Manufacturing with Oracle Applications                                        Page 4
Managing and Tracking CTO Manufacturing with Oracle Applications   Page 5
Job Tagging

        One of the key requirements of the solution was to provide visibility of all entities linked to a specific
        sales order line. While the unique numbering of the star assembly can track final assembly level
        work orders to the sales order line, it does not provide any visibility to the components below. Job
        specific entities such as purchase orders and subassembly work orders could not be tied to the
        parent assembly or the sales order line. A Seiban number strategy was implemented to
        automatically generate unique numbers and link all these make-to-order/buy- to-order components
        to the sales order line. Seiban numbers provide project-like tracking capabilities without the
        overhead of opening, maintaining, costing, and closing each distinct project.

        Through the use of Seiban numbering NewGen was able to achieve the following:

                Link all entities associated with a specific CTO order
                Provide real time status tracking of all WIP jobs and purchase orders tied to a specific sales
                 order line
                Track and Manage inventory by Seiban and Sales Order
                Use Advanced Supply Chain Planning to plan at the Seiban level
                Respond to Change Orders through Planning
                Provide, when needed, project level costing

        Custom Dispatch Screen

        – Search Form

        To provide control around retrieving and managing information, an Oracle form was created to
        enable searching of WIP jobs based on specific client search criteria. This form was designed to
        provide flexibility in that it allows for searching using various inputs:

                Sales Order - By Sales Order Number. A value entered here will limit the search to just
                 those jobs associated with a sales order number
                File ID and Fan Group– Unique composite (Seiban Number) identifier that ties the sales
                 order line item with WIP jobs as well as CAD drawings and all other associated documents.
                 A value entered here will limit the search to just those jobs associated with a specific Fan
                 design.
                WIP Status – The status of the WIP jobs (released, unreleased, complete, etc.). For
                 example, display all jobs that are unreleased for a specific sales order.
                Parent Job – The Parent job is a Job that is dependent on the completion of subassembly
                 (lower BOM) jobs.
                Department and Resource – Lists jobs specific to a department or resource. A value
                 entered here will show all the jobs that are scheduled for that specific resource. This can be
                 used in conjunction with other fields to make it sales order specific or not.
                Due Dates - To be used in conjunction with a department search and resource search. This
                 will be used to identify the jobs within the date range (not sales order specific).
                Item Type – This will limit the search to a specific Item Type. This would be used in
                 conjunction with the other fields, for example, show all piece parts for order 100000.
                Job Number – This would be used to list a specific job and view all associated information
                 including parent work order, sales order, Seiban, etc.




Managing and Tracking CTO Manufacturing with Oracle Applications                                             Page 6
– Results of the Query

        The searched information returned is organized in a logical/manageable manner and presented in a
        working form to facilitate greater control over the process.

        Using the form, Users can elect to mange the work orders in several ways:

                Review - Review the status of all WIP jobs associated with an order line
                Release –
                    o Release like items in batch mode for ERQ
                    o Release individual work orders or nested (items with like resource requirements)
                        work orders
                Schedule - Schedule work orders by department
                Review and act upon - Review and act upon configuration dependencies, dependent work
                 orders, etc
                Job Linking and De-Linking - Job Linking and De-Linking for manual job additions and job
                 removals for change orders
                Print Documents – Print the associated shop floor documents
                Print Nested Documents – Group items with like resource requirements into a master job
                 sheet




Managing and Tracking CTO Manufacturing with Oracle Applications                                   Page 7
<Sample Screen Shot of all WIP jobs specific to a final assembly>

        – Buttons/Actions:

        Several buttons and activities are available to ease the maintenance activities for the work orders
        and better coordinate downstream activities related work orders associated with a sales order line.

                Button         Action                                      Example

                Select All     Select all items returned by the search     Can be used to select all jobs
                                                                           and perform a batch action

                Release        Release all selected work orders            This will update the job to
                               (Dispatch) to the floor                     “released” and allow for charges

                Cancel         Cancel the selected work order(s)           This will update the job status to
                                                                           “cancel”

                Update         This will open the standard Oracle          Changes can be made to the job
                               Discrete Job form                           via the standard Discrete job
                                                                           form

                Print          Print the Shop floor documents for          Depending on the item, this will
                Documents      associated work stations                    print specific shop floor
                                                                           documents

                Print Nested   This will group all items associated with   Nested documents will be used
                Documents      a configuration and/or resource, and        to decrease the need for one
                               group all the jobs onto one job sheet.      document per work order




Managing and Tracking CTO Manufacturing with Oracle Applications                                              Page 8
Custom Reports

        Print Documents
        Shop floor documents for associated work stations

        To better match the flow of production on the shop floor, Newgen’s client required several types of
        shop floor documents for their Fan Jobs and associated work orders. For make-to- order product a
        shop floor packet is created for the master work order. This packet includes all the jobs required to
        make the end assembly. These include piece part work orders (a routing sheet for each piece part),
        Subassembly work orders (1 for each make to order component on a bill of material), and a Master
        Assembly work order. Because the manufacturing of the individual work orders occurs in tandem,
        the work order packet is dispersed through the shop floor with each job sheet following a specific
        routing. After the completion of each job the individual sheets are reunited with the master assembly
        sheet using the unique Seiban as a reference.



        Print Nested Documents
        Group all items associated with a configuration and resource and group all the jobs onto one job sheet.

        The Nested documents report content is driven by the WIP Dispatcher. The form allows the
        dispatcher to perform searches based on department and resource. The user will identify parts with
        similar resource and routing requirements, select those jobs, and then create a nested document list.
        This nested listing contains all the work order numbers due to run in that department or on a
        resource for a given period of time.


        Summary

        Through a combination of Oracle workflow technology and Oracle forms and reports, NewGen was
        able to leverage the information within the Oracle E-Business Suite and provide a complete tracking
        and dispatching solution that matched the physical process of configuring and releasing work to the
        manufacturing floor. The solution also provided a companywide view of all the tasks and related
        statuses of WIP-related information associated with a CTO order line. Additionally, the flexibility of
        linking new work orders associated with the sales order line for change orders answered the
        challenges of accurately costing all work for each custom/configured to order item.


        Before Solution                                       After Solution

        The client was unable to finally approve BOM          All configured-to-order lines require an
        changes prior to the work being released to           approval step for final BOM modification
        the floor                                             resulting in an accurate snapshot of make-to-
                                                              order jobs.




Managing and Tracking CTO Manufacturing with Oracle Applications                                                  Page 9
Before Solution                                    After Solution

        CTO work orders were interfaced to WIP             Custom workflow contains a “wait activity” to
        immediately after order progression                prevent generation of work order until due date
                                                           minus lead time expires.

        Critical Purchase-Order components would not       Critical purchase components are released
        generate requisitions until scheduled MRP          directly to purchasing as a requisition
        completed                                          providing advanced notice for expediting

        Work orders generated for lower level make-        Work orders are generated directly from the
        to-order components would be generated from        sales order line
        MRP

        No visibility of relationship between work         Lower level work orders generated from the
        orders. Lower level work orders generated via      sales order line are linked to the sales order
        MRP and released to WIP were not linked to         and Seiban
        the sales order line or Seiban

        Visibility of work orders related to the sales     Dispatch screen displays all work orders
        order line and the Seiban was limited              associated with a sale order line or a Seiban.
                                                           This visibility allows for tracking and
                                                           management at an aggregate level (Top level).

        Tracking and managing manually created             Jobs can be linked or de-linked from a sales
        rework jobs for a sales order line was difficult   order line or Seiban. This allows for tracking
        and time consuming                                 and costing of all WIP for a sales order line.

        Client was not able to tie work orders to a        Seiban is passed to every work order allowing
        Seiban and was unable to reference CAD             for quick and easy reference to the CAD
        drawings                                           drawings

        Difficulty with scheduling resources for a         WIP dispatch screen displays all resource
        particular sales order                             requirements for a specific sales order line so
                                                           the jobs can be released to the floor in tandem

        Shop Floor paperwork was printed for               Shop floor paperwork represents the physical
        individual jobs and had limited reference to       flow of work on the shop floor. All documents
        final assemblies and Seiban                        reference the final assembly, sales order line,
                                                           and Seiban. Additionally, nesting capabilities
                                                           allowed scheduling sheets to be deployed to
                                                           individual workstations.




Managing and Tracking CTO Manufacturing with Oracle Applications                                            Page 10
Before Solution                                    After Solution

        No Advanced Supply Chain Planning                  Seiban level planning allows planner to see all
        capabilities available at the Project Level. All   planned activities for purchase orders and
        suggested requirements were not linked             work orders for a specific sales order line.
        together.

        Client was not able to respond to order line       Seiban level planning picks up changes in
        configuration changes in a timely and accurate     sales order line demand and makes
        manner. All related work orders and purchase       appropriate suggestions to create, cancel or
        orders had to be tracked manually                  modify existing entities tagged with same
                                                           Seiban identifier.




Managing and Tracking CTO Manufacturing with Oracle Applications                                          Page 11
About the Author:

        Jason Bletz is Practice Director for Oracle Applications at multi-national (USA and India) Platinum
        partner New Generation Consultants, Inc. (www.newgenusa.com) in Chicago, Illinois. He has 15+
        years experience in Manufacturing and Distribution Industries and 13+ years experience in IT. Jason
        has assisted many companies with the implementation of business strategies including lean, agile
        and ETO manufacturing, logistics and supply chain management, change management and process
        engineering. As an accomplished Oracle Implementer and Project Manager, Jason provides expert
        advice enabling clients to get optimal value from their investment in Oracle solutions.

        Jason’s industry experience covers small to medium-sized businesses as well as large multinational
        organizations across many sectors including Manufacturing and Distribution, Services, Healthcare,
        Bio-Tech, Utilities and Public Sector. He has extensive Functional and Solution Design experience
        with several Oracle Tools including eBusiness Suite, Hyperion and Oracle Business Intelligence.

        Jason is responsible for leading growth and development of New Generation Consultants’ clients with
        a key focus on managing strategic ERP initiatives to accelerate these objectives.




Managing and Tracking CTO Manufacturing with Oracle Applications                                    Page 12

More Related Content

What's hot

SAP PLM BOM (Bill of Material) Redlining
SAP PLM BOM (Bill of Material) RedliningSAP PLM BOM (Bill of Material) Redlining
SAP PLM BOM (Bill of Material) RedliningEric Stajda
 
Product Life Cycle Management
Product Life Cycle ManagementProduct Life Cycle Management
Product Life Cycle Managementchaitanya122
 
Product Lifecycle management PowerPoint Presentation Slides
Product Lifecycle management PowerPoint Presentation Slides Product Lifecycle management PowerPoint Presentation Slides
Product Lifecycle management PowerPoint Presentation Slides SlideTeam
 
Plm fundas part 2
Plm fundas part 2Plm fundas part 2
Plm fundas part 2Anand Joshi
 
Product Data Management
Product Data ManagementProduct Data Management
Product Data ManagementArchita Singh
 
Methods To Leverage SAP Workflow
Methods To Leverage SAP WorkflowMethods To Leverage SAP Workflow
Methods To Leverage SAP WorkflowEric Stajda
 
Plural's PLM services presentation
Plural's PLM services presentationPlural's PLM services presentation
Plural's PLM services presentationPlural Technolog
 
Product Lifecycle Management Process and Software Tools
Product Lifecycle Management Process and Software ToolsProduct Lifecycle Management Process and Software Tools
Product Lifecycle Management Process and Software ToolsProductCamp Atlanta
 
Agile PLM implementation and systems integration at sun microsystems
Agile PLM implementation and systems integration at sun microsystemsAgile PLM implementation and systems integration at sun microsystems
Agile PLM implementation and systems integration at sun microsystemsulfkoester
 
Implementation framework for_plm_a_case_study_in_t
Implementation framework for_plm_a_case_study_in_tImplementation framework for_plm_a_case_study_in_t
Implementation framework for_plm_a_case_study_in_t17TUME122MITHUNM
 
PLM Implementing Successful Transformational Change
PLM Implementing Successful Transformational ChangePLM Implementing Successful Transformational Change
PLM Implementing Successful Transformational ChangeDavid G Sherburne
 
plm business benefits of a plm system
plm business benefits of a plm systemplm business benefits of a plm system
plm business benefits of a plm systemAmeer Chann
 
241985748 plm-case-study
241985748 plm-case-study241985748 plm-case-study
241985748 plm-case-studyhomeworkping4
 
Plm specialist-Professor-PLM-0909
Plm specialist-Professor-PLM-0909Plm specialist-Professor-PLM-0909
Plm specialist-Professor-PLM-0909francisdt
 

What's hot (20)

SAP PLM BOM (Bill of Material) Redlining
SAP PLM BOM (Bill of Material) RedliningSAP PLM BOM (Bill of Material) Redlining
SAP PLM BOM (Bill of Material) Redlining
 
Product Life Cycle Management
Product Life Cycle ManagementProduct Life Cycle Management
Product Life Cycle Management
 
Product Lifecycle management PowerPoint Presentation Slides
Product Lifecycle management PowerPoint Presentation Slides Product Lifecycle management PowerPoint Presentation Slides
Product Lifecycle management PowerPoint Presentation Slides
 
DreamApps
DreamAppsDreamApps
DreamApps
 
Design For Rapid Product Realization (DFRPR)
Design For Rapid Product Realization (DFRPR)Design For Rapid Product Realization (DFRPR)
Design For Rapid Product Realization (DFRPR)
 
Plm fundas part 2
Plm fundas part 2Plm fundas part 2
Plm fundas part 2
 
Product Data Management
Product Data ManagementProduct Data Management
Product Data Management
 
Methods To Leverage SAP Workflow
Methods To Leverage SAP WorkflowMethods To Leverage SAP Workflow
Methods To Leverage SAP Workflow
 
SAP PLM
SAP PLMSAP PLM
SAP PLM
 
Plm overview
Plm overviewPlm overview
Plm overview
 
Plural's PLM services presentation
Plural's PLM services presentationPlural's PLM services presentation
Plural's PLM services presentation
 
Product Lifecycle Management Process and Software Tools
Product Lifecycle Management Process and Software ToolsProduct Lifecycle Management Process and Software Tools
Product Lifecycle Management Process and Software Tools
 
Iarjset n core tech 8
Iarjset n core tech 8Iarjset n core tech 8
Iarjset n core tech 8
 
Discus and the TDP
Discus and the TDPDiscus and the TDP
Discus and the TDP
 
Agile PLM implementation and systems integration at sun microsystems
Agile PLM implementation and systems integration at sun microsystemsAgile PLM implementation and systems integration at sun microsystems
Agile PLM implementation and systems integration at sun microsystems
 
Implementation framework for_plm_a_case_study_in_t
Implementation framework for_plm_a_case_study_in_tImplementation framework for_plm_a_case_study_in_t
Implementation framework for_plm_a_case_study_in_t
 
PLM Implementing Successful Transformational Change
PLM Implementing Successful Transformational ChangePLM Implementing Successful Transformational Change
PLM Implementing Successful Transformational Change
 
plm business benefits of a plm system
plm business benefits of a plm systemplm business benefits of a plm system
plm business benefits of a plm system
 
241985748 plm-case-study
241985748 plm-case-study241985748 plm-case-study
241985748 plm-case-study
 
Plm specialist-Professor-PLM-0909
Plm specialist-Professor-PLM-0909Plm specialist-Professor-PLM-0909
Plm specialist-Professor-PLM-0909
 

Similar to Managing And Tracking Eto Manufacturing With Oracle Apps

High Tech Manufacturing
High Tech ManufacturingHigh Tech Manufacturing
High Tech ManufacturingGarima Sinha
 
Plm & windchill
Plm & windchillPlm & windchill
Plm & windchillsumanrao33
 
microsoft-dynamics-365-for-operations-whats-new
microsoft-dynamics-365-for-operations-whats-newmicrosoft-dynamics-365-for-operations-whats-new
microsoft-dynamics-365-for-operations-whats-newDeneys Minne
 
Infor CloudSuite Industrial Summary
Infor CloudSuite Industrial SummaryInfor CloudSuite Industrial Summary
Infor CloudSuite Industrial SummaryCalvin Schwartz
 
ERP implementation at steel mill
ERP implementation at steel millERP implementation at steel mill
ERP implementation at steel millAsher Jawad
 
Oracle SCM Cloud ERP Solution
Oracle SCM Cloud ERP SolutionOracle SCM Cloud ERP Solution
Oracle SCM Cloud ERP SolutionTony Sebastian
 
Implementing_jde_manufacturing_whitepaper_Oct2016
Implementing_jde_manufacturing_whitepaper_Oct2016Implementing_jde_manufacturing_whitepaper_Oct2016
Implementing_jde_manufacturing_whitepaper_Oct2016Mathur (Matt) Ravikumar
 
Embrace Modular Technology and Agile Process to Deliver Business Impact
Embrace Modular Technology and Agile Process to Deliver Business ImpactEmbrace Modular Technology and Agile Process to Deliver Business Impact
Embrace Modular Technology and Agile Process to Deliver Business ImpactMark Hewitt
 
Flexible and modular software framework as a solution for operational excelle...
Flexible and modular software framework as a solution for operational excelle...Flexible and modular software framework as a solution for operational excelle...
Flexible and modular software framework as a solution for operational excelle...Thomas Schulz
 
SofTech AU2010
SofTech AU2010SofTech AU2010
SofTech AU2010ekelley26
 
Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State
 
"Erp implementation at Tata Steel" XIMB
"Erp implementation at Tata Steel" XIMB"Erp implementation at Tata Steel" XIMB
"Erp implementation at Tata Steel" XIMBRahul Singh Chauhan
 
A Software Factory Integrating Rational & WebSphere Tools
A Software Factory Integrating Rational & WebSphere ToolsA Software Factory Integrating Rational & WebSphere Tools
A Software Factory Integrating Rational & WebSphere Toolsghodgkinson
 

Similar to Managing And Tracking Eto Manufacturing With Oracle Apps (20)

High Tech Manufacturing
High Tech ManufacturingHigh Tech Manufacturing
High Tech Manufacturing
 
Plm & windchill
Plm & windchillPlm & windchill
Plm & windchill
 
microsoft-dynamics-365-for-operations-whats-new
microsoft-dynamics-365-for-operations-whats-newmicrosoft-dynamics-365-for-operations-whats-new
microsoft-dynamics-365-for-operations-whats-new
 
TVRK_RESUME
TVRK_RESUMETVRK_RESUME
TVRK_RESUME
 
Infor CloudSuite Industrial Summary
Infor CloudSuite Industrial SummaryInfor CloudSuite Industrial Summary
Infor CloudSuite Industrial Summary
 
ERP implementation at steel mill
ERP implementation at steel millERP implementation at steel mill
ERP implementation at steel mill
 
om assignment.docx
om assignment.docxom assignment.docx
om assignment.docx
 
Oracle SCM Cloud ERP Solution
Oracle SCM Cloud ERP SolutionOracle SCM Cloud ERP Solution
Oracle SCM Cloud ERP Solution
 
Implementing_jde_manufacturing_whitepaper_Oct2016
Implementing_jde_manufacturing_whitepaper_Oct2016Implementing_jde_manufacturing_whitepaper_Oct2016
Implementing_jde_manufacturing_whitepaper_Oct2016
 
NetSuite for Manufacturers
NetSuite for ManufacturersNetSuite for Manufacturers
NetSuite for Manufacturers
 
NetSuite for Manufacturers
NetSuite for ManufacturersNetSuite for Manufacturers
NetSuite for Manufacturers
 
Ea As Strategy Ver1 0
Ea As Strategy Ver1 0Ea As Strategy Ver1 0
Ea As Strategy Ver1 0
 
Embrace Modular Technology and Agile Process to Deliver Business Impact
Embrace Modular Technology and Agile Process to Deliver Business ImpactEmbrace Modular Technology and Agile Process to Deliver Business Impact
Embrace Modular Technology and Agile Process to Deliver Business Impact
 
Flexible and modular software framework as a solution for operational excelle...
Flexible and modular software framework as a solution for operational excelle...Flexible and modular software framework as a solution for operational excelle...
Flexible and modular software framework as a solution for operational excelle...
 
SofTech AU2010
SofTech AU2010SofTech AU2010
SofTech AU2010
 
Arunkumar Resume
Arunkumar ResumeArunkumar Resume
Arunkumar Resume
 
Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start PresentationZero Wait-State Agile EC MCAD Implementation Quick Start Presentation
Zero Wait-State Agile EC MCAD Implementation Quick Start Presentation
 
"Erp implementation at Tata Steel" XIMB
"Erp implementation at Tata Steel" XIMB"Erp implementation at Tata Steel" XIMB
"Erp implementation at Tata Steel" XIMB
 
PL20876-AU2016
PL20876-AU2016PL20876-AU2016
PL20876-AU2016
 
A Software Factory Integrating Rational & WebSphere Tools
A Software Factory Integrating Rational & WebSphere ToolsA Software Factory Integrating Rational & WebSphere Tools
A Software Factory Integrating Rational & WebSphere Tools
 

Managing And Tracking Eto Manufacturing With Oracle Apps

  • 1. Managing and Tracking Configure-to-Order Manufacturing with Oracle Applications Jason Bletz New Generation Consultants Overview In a Configured-to-Order (CTO) environment, the requirements to fill customer orders are not known until the sales order is booked. While some common components from inventory are used to satisfy the requirements of multiple configurations, most of the purchased items and subassemblies are either bought or built specifcally for the configured order. Such variations in products can include size, color/coatings and other accessories. These variations impact downstream activities including special operations, outside processing and whether the product is assembled and shipped or first shipped and then assembled onsite or at other satellite locations. Controlling the CTO order as it moves from Order Entry into Manufacturing and finally into shipping in a configure-to-order environment can be a logistical challenge for any organization. Companies need visibility to determine when to release the order, where the subassembly components are in the process, how to track job specific purchase orders, report on product variablility, how to control and account for changes to the order and how to cost related jobs when the order line is modified or canceled. Further complicating the process are complex nested BOMs that generate large numbers of work orders and purchase orders related to the assemblies and sub-assemblies that comprise the CTO product. New Generation Consultants (NewGen) provided several solutions to satisfy the business requirements of the CTO manufacturer referenced in this paper, however the scope of this paper is to discuss the Oracle tools and strategies implemented to satisfy the management and control of CTO orders through the manufacturing process. Additional solutions surrounding shipment and delivery of the product, configure to quote, configurator rules, and servicing of installed product can be found in other White Papers in the NewGen library. Industry Methodologies Project Manufacturing provides management tools that measure and control large projects in a project oriented environment. Capabilities of Project Manufacturing systems include project level task breakdown, project level estimation, project level revenue and cost reporting, planning and pegging by project as well as project billing by milestone. While these capabilities support several configure-to-order manufacturers, the caveat with project manufacturing systems is the ongoing management and support of each project required by the organization. This is especially true for organizations that have a high volume of customer orders and configurations. Discrete and Flow Manaufacturing do an excellent job for build-to-stock environments. The final products are planned and built against forecasts of standard items. Shop floor operations are Managing and Tracking CTO Manufacturing with Oracle Applications Page 1
  • 2. centered around products that are manufactured, assembled and released to inventory. The orders are completed by picking items, newly created or already in inventory, and shipping them. Statement of Problem While some ERP systems can manage project level manufacturing (low volume and high variability/configurations) and others can manage discrete manufacturing (High Volume and Low Variability/configurations), very few can support organizations that deal with high volume and high variability. If the organizations employ project manufacturing methodolgies they are required to set- up and manage a project for every distinct configuration being ordered. If they employ discrete manufacturing methodologies, visibility of sales order/project specific information throughout this process is not available as the emphasis of discrete manufacturing is on organizing parts and assemblies into efficient discrete batches thereby eliminating project specific tagging and tracking. Concerns revolving around work-in-process (WIP) management and work-in-process tracking for high volume CTO manufacturers include:  Difficulty in identifying which work orders, other than the top level assemblies, are associated to what sales order demand.  Excessive number of transactions in WIP to manage and track the associated work orders.  Difficulty in identifying which work orders are associated to other work orders (which subassemblies are tied to which final assemblies).  Excessive number of work orders taxes the ability of staff to efficiently process.  Inability to generate usable standard reports for Shop Floor paperwork without the need to alter the shop floor flow.  Uniqueness of each CTO product being ordered may cause a proliferation of part numbers.  Creating new work orders or updating existing work orders is often required for customer- driven change orders. It is difficult to tie them to the current production schedule and parent demand.  Identifying when to release final assembly orders once all child assemblies are complete. Concerns revolving around changes to orders include:  Changes to the configured item often requires canceling the order line as identifying and making changes to the associated work orders is difficult.  Difficulty in tracking down all work orders associated with a change order.  Difficulty in capturing the associated costs related to the change.  Overall management of work order changes. CTO Company Profile  Mature manufacturing organization, operating since 1889.  Configure-to-Order manufacturer.  High degree of configuration of product  Multiple configurators and order entry systems needed to be centralized.  CAD and other design applications required integration to the order entry process. Managing and Tracking CTO Manufacturing with Oracle Applications Page 2
  • 3. Solution Requirements For its client, New Generation determined that any solution had to conform to specific business and technology requirements. Business:  Streamline sales order to WIP flow. Using three distinct Configurator tools to configure the product and generate sales orders, the solution needed to capture multiple inputs of demand and communicate these requirements to the shop floor in one unified format.  Minimize change to the production floor – Radically changing the floor operations to fit the system was not in the client’s best interest. Any solution needed to be transparent to the floor.  Maintaining Delivery Commitments – Current commitments to the customers could not be impacted. Meeting promised delivery dates is essential to maintaining customer relations.  Maintaining flexibility in product configurability - Client’s sales and reputation is partly driven by its ability to offer its customers a highly configurable product. Additionally, flexibility is provided to alter the product design up to shipment of finished product. Reducing this capability to fit the out-of-the-box system functionality was not an option.  Leveraging current investment – Significant investment had been made in Oracle ERP. Any solution would need to leverage the current ERP without requiring the need for investment in additional software applications. System:  Reduction in WIP tracking needs – Reduce complexity for manufacturing team to plan and manage scheduling.  Maintaining compliance – Any solution must not void any support for E-Business Suite (EBS) by Oracle.  Feasibility – Technical and functional capability within a tight budget and timeline. Solution must fit within the framework of Oracle EBS.  Reduction in manual work arounds – The solution needed to reduce overall complexity and allow users to work within the system to manage the process.  Usability – The solution must match the order-to-cash process flow and leverage current system design and modules. Solution Components Implemented Oracle E-Business Suite  Oracle Order to Cash (OM, Advanced Pricing, Shipping)  Oracle Financials (AR, AP, General Ledger, Project Costing)  Oracle Configurator  Oracle Purchasing  Oracle Advanced Supply Chain Planning  Oracle Data Hubs  Oracle Discrete Manufacturing (Bills of Material, Production Scheduling, Work in Process, Costing) Managing and Tracking CTO Manufacturing with Oracle Applications Page 3
  • 4. Solution The focus of this solution was to capture and streamline CTO Order demand from Oracle Order Management (OM) and release it directly into WIP regardless from which configurator system the demand originated. By utilizing Oracle’s workflow capabilities, a Seiban numbering strategy and a custom WIP dispatching form, NewGen was able to create discrete jobs in the WIP module for the top level assemblies and any make-to-order components specified at any level in the BOM. All jobs were linked to their respective sales order line, CAD drawing ID and parent work orders (where applicable). The custom form provided a 360 degree view of all jobs that were associated with a sales order or drawing ID. From this form they are able to manage all work orders and their release statuses. Finally, custom shop floor documents were used to communicate all work instructions to the shop floor. These documents included routing sheets, indented bills of material, as well as a document that grouped different items with like operations so the machine operators could batch disparate jobs across the same resources. These shop floor documents were designed to match legacy format and, therefore, eliminated the need to alter product flow through the shop floor workstations. Solution Components Custom Workflow - Standardization of post-order flow for Configured items The Make-to-Order Workflow provides features needed to satisfy the following basic business needs:  Control the approval step so as to prevent orders from being released until configuration and manually/automated BOM adjustments are complete.  Reference number can be associated to order configuration and subassemblies  Work Orders can be associated with the sales order.  All Make-To-Order Items (Configured Top level items, MTO subassemblies) can be released directly to WIP (bypass MRP).  Work Orders can be associated with each other (Parent Child Relationship).  Release critical time constrained purchase components to Purchasing. ------------------------------------ Activities included in the workflow include:  Require an Approval prior to the job being released from the sales order to WIP  Call the lead time rollup concurrent program  Perform a wait function in the line flow prior to release in WIP (Ship Date – (Lead Time + X days))  Revert to prior activities (prior to release to WIP)  Automatic Generation of Work in Process Jobs for make-to-order items (includes Configured items as well as make-to-order items)  Link the WIP Job to a specific sales order  Link the WIP Job to a specific File Number (CAD drawing ID)  Link WIP Jobs to related Jobs (Parent/Child relationship) Managing and Tracking CTO Manufacturing with Oracle Applications Page 4
  • 5. Managing and Tracking CTO Manufacturing with Oracle Applications Page 5
  • 6. Job Tagging One of the key requirements of the solution was to provide visibility of all entities linked to a specific sales order line. While the unique numbering of the star assembly can track final assembly level work orders to the sales order line, it does not provide any visibility to the components below. Job specific entities such as purchase orders and subassembly work orders could not be tied to the parent assembly or the sales order line. A Seiban number strategy was implemented to automatically generate unique numbers and link all these make-to-order/buy- to-order components to the sales order line. Seiban numbers provide project-like tracking capabilities without the overhead of opening, maintaining, costing, and closing each distinct project. Through the use of Seiban numbering NewGen was able to achieve the following:  Link all entities associated with a specific CTO order  Provide real time status tracking of all WIP jobs and purchase orders tied to a specific sales order line  Track and Manage inventory by Seiban and Sales Order  Use Advanced Supply Chain Planning to plan at the Seiban level  Respond to Change Orders through Planning  Provide, when needed, project level costing Custom Dispatch Screen – Search Form To provide control around retrieving and managing information, an Oracle form was created to enable searching of WIP jobs based on specific client search criteria. This form was designed to provide flexibility in that it allows for searching using various inputs:  Sales Order - By Sales Order Number. A value entered here will limit the search to just those jobs associated with a sales order number  File ID and Fan Group– Unique composite (Seiban Number) identifier that ties the sales order line item with WIP jobs as well as CAD drawings and all other associated documents. A value entered here will limit the search to just those jobs associated with a specific Fan design.  WIP Status – The status of the WIP jobs (released, unreleased, complete, etc.). For example, display all jobs that are unreleased for a specific sales order.  Parent Job – The Parent job is a Job that is dependent on the completion of subassembly (lower BOM) jobs.  Department and Resource – Lists jobs specific to a department or resource. A value entered here will show all the jobs that are scheduled for that specific resource. This can be used in conjunction with other fields to make it sales order specific or not.  Due Dates - To be used in conjunction with a department search and resource search. This will be used to identify the jobs within the date range (not sales order specific).  Item Type – This will limit the search to a specific Item Type. This would be used in conjunction with the other fields, for example, show all piece parts for order 100000.  Job Number – This would be used to list a specific job and view all associated information including parent work order, sales order, Seiban, etc. Managing and Tracking CTO Manufacturing with Oracle Applications Page 6
  • 7. – Results of the Query The searched information returned is organized in a logical/manageable manner and presented in a working form to facilitate greater control over the process. Using the form, Users can elect to mange the work orders in several ways:  Review - Review the status of all WIP jobs associated with an order line  Release – o Release like items in batch mode for ERQ o Release individual work orders or nested (items with like resource requirements) work orders  Schedule - Schedule work orders by department  Review and act upon - Review and act upon configuration dependencies, dependent work orders, etc  Job Linking and De-Linking - Job Linking and De-Linking for manual job additions and job removals for change orders  Print Documents – Print the associated shop floor documents  Print Nested Documents – Group items with like resource requirements into a master job sheet Managing and Tracking CTO Manufacturing with Oracle Applications Page 7
  • 8. <Sample Screen Shot of all WIP jobs specific to a final assembly> – Buttons/Actions: Several buttons and activities are available to ease the maintenance activities for the work orders and better coordinate downstream activities related work orders associated with a sales order line. Button Action Example Select All Select all items returned by the search Can be used to select all jobs and perform a batch action Release Release all selected work orders This will update the job to (Dispatch) to the floor “released” and allow for charges Cancel Cancel the selected work order(s) This will update the job status to “cancel” Update This will open the standard Oracle Changes can be made to the job Discrete Job form via the standard Discrete job form Print Print the Shop floor documents for Depending on the item, this will Documents associated work stations print specific shop floor documents Print Nested This will group all items associated with Nested documents will be used Documents a configuration and/or resource, and to decrease the need for one group all the jobs onto one job sheet. document per work order Managing and Tracking CTO Manufacturing with Oracle Applications Page 8
  • 9. Custom Reports Print Documents Shop floor documents for associated work stations To better match the flow of production on the shop floor, Newgen’s client required several types of shop floor documents for their Fan Jobs and associated work orders. For make-to- order product a shop floor packet is created for the master work order. This packet includes all the jobs required to make the end assembly. These include piece part work orders (a routing sheet for each piece part), Subassembly work orders (1 for each make to order component on a bill of material), and a Master Assembly work order. Because the manufacturing of the individual work orders occurs in tandem, the work order packet is dispersed through the shop floor with each job sheet following a specific routing. After the completion of each job the individual sheets are reunited with the master assembly sheet using the unique Seiban as a reference. Print Nested Documents Group all items associated with a configuration and resource and group all the jobs onto one job sheet. The Nested documents report content is driven by the WIP Dispatcher. The form allows the dispatcher to perform searches based on department and resource. The user will identify parts with similar resource and routing requirements, select those jobs, and then create a nested document list. This nested listing contains all the work order numbers due to run in that department or on a resource for a given period of time. Summary Through a combination of Oracle workflow technology and Oracle forms and reports, NewGen was able to leverage the information within the Oracle E-Business Suite and provide a complete tracking and dispatching solution that matched the physical process of configuring and releasing work to the manufacturing floor. The solution also provided a companywide view of all the tasks and related statuses of WIP-related information associated with a CTO order line. Additionally, the flexibility of linking new work orders associated with the sales order line for change orders answered the challenges of accurately costing all work for each custom/configured to order item. Before Solution After Solution The client was unable to finally approve BOM All configured-to-order lines require an changes prior to the work being released to approval step for final BOM modification the floor resulting in an accurate snapshot of make-to- order jobs. Managing and Tracking CTO Manufacturing with Oracle Applications Page 9
  • 10. Before Solution After Solution CTO work orders were interfaced to WIP Custom workflow contains a “wait activity” to immediately after order progression prevent generation of work order until due date minus lead time expires. Critical Purchase-Order components would not Critical purchase components are released generate requisitions until scheduled MRP directly to purchasing as a requisition completed providing advanced notice for expediting Work orders generated for lower level make- Work orders are generated directly from the to-order components would be generated from sales order line MRP No visibility of relationship between work Lower level work orders generated from the orders. Lower level work orders generated via sales order line are linked to the sales order MRP and released to WIP were not linked to and Seiban the sales order line or Seiban Visibility of work orders related to the sales Dispatch screen displays all work orders order line and the Seiban was limited associated with a sale order line or a Seiban. This visibility allows for tracking and management at an aggregate level (Top level). Tracking and managing manually created Jobs can be linked or de-linked from a sales rework jobs for a sales order line was difficult order line or Seiban. This allows for tracking and time consuming and costing of all WIP for a sales order line. Client was not able to tie work orders to a Seiban is passed to every work order allowing Seiban and was unable to reference CAD for quick and easy reference to the CAD drawings drawings Difficulty with scheduling resources for a WIP dispatch screen displays all resource particular sales order requirements for a specific sales order line so the jobs can be released to the floor in tandem Shop Floor paperwork was printed for Shop floor paperwork represents the physical individual jobs and had limited reference to flow of work on the shop floor. All documents final assemblies and Seiban reference the final assembly, sales order line, and Seiban. Additionally, nesting capabilities allowed scheduling sheets to be deployed to individual workstations. Managing and Tracking CTO Manufacturing with Oracle Applications Page 10
  • 11. Before Solution After Solution No Advanced Supply Chain Planning Seiban level planning allows planner to see all capabilities available at the Project Level. All planned activities for purchase orders and suggested requirements were not linked work orders for a specific sales order line. together. Client was not able to respond to order line Seiban level planning picks up changes in configuration changes in a timely and accurate sales order line demand and makes manner. All related work orders and purchase appropriate suggestions to create, cancel or orders had to be tracked manually modify existing entities tagged with same Seiban identifier. Managing and Tracking CTO Manufacturing with Oracle Applications Page 11
  • 12. About the Author: Jason Bletz is Practice Director for Oracle Applications at multi-national (USA and India) Platinum partner New Generation Consultants, Inc. (www.newgenusa.com) in Chicago, Illinois. He has 15+ years experience in Manufacturing and Distribution Industries and 13+ years experience in IT. Jason has assisted many companies with the implementation of business strategies including lean, agile and ETO manufacturing, logistics and supply chain management, change management and process engineering. As an accomplished Oracle Implementer and Project Manager, Jason provides expert advice enabling clients to get optimal value from their investment in Oracle solutions. Jason’s industry experience covers small to medium-sized businesses as well as large multinational organizations across many sectors including Manufacturing and Distribution, Services, Healthcare, Bio-Tech, Utilities and Public Sector. He has extensive Functional and Solution Design experience with several Oracle Tools including eBusiness Suite, Hyperion and Oracle Business Intelligence. Jason is responsible for leading growth and development of New Generation Consultants’ clients with a key focus on managing strategic ERP initiatives to accelerate these objectives. Managing and Tracking CTO Manufacturing with Oracle Applications Page 12