2. Routing
Routing is the selection of paths or routes over
which each piece is to travel in being transformed
from raw material into finished product
3. Importance of Routing
To determine the best and cheapest sequence of operations and
to ensure that this sequence is followed.
Determination of routes demands deliberation and concentration
of mind.
Routing constitutes a function which can been worked out and
recorded.
Once a good route has been worked out and recorded, it can be
used for further similar jobs.
The degrees of detail in routing varies with the factory and the
product.
The department in which each operation is to be performed and
the machine tool to be used in each case.
To be successful routing, requires that the route clerk should
have a thorough knowledge of the product.
Complete knowledge of the capacity and characteristics of every
machine and process.
4. Routing Procedure
The finished products are analysed from the
manufacturing standpoint in order to decide how
many components can be made in the plant and
how many can be purchased from outside
sources. ( Make or Buy decision)
Parts-list and a bill of materials are prepared
showing name of the part, quantity,material
specifications, amount of materials required etc.,
Machines capacities, their characteristics and the
operations which must be performed at each
stage of manufacture are established and listed.
5. Preparation of route sheet
A route sheet contains a complete description of the
item to be manufactures, the details of each operation
required in manufacturing process, the set up time
and standard operation time etc.,
Route sheet also provides the best sequence for the
desired operations taking into consideration the
resources available. This can be done by the
sequencing, assignment, critical path etc.,
Consideration
The machines are to be operated at full capacity
The product passes through those work centres which
are manned by best possible personnel.
The route is shortest and economical
The in-charge should be well acquainted with operations
6. Factors
Type of Manufacture – type of production
Characteristics of individual machines –age,
speed, capacity, tooling etc.,
Availability of alternative routing – breakdown and
absent alternative
Human factors – visual exactness, physical
limitations, intelligence, emotional stability etc.,
8. Definition
Scheduling is the determination of the time that
should be required to perform each operation and
and also the time necessary to perform the entire
series as routed, making allowance for all factors
concerned.
9. Scheduling Problems
Fluctuating demand
Have a static production programme
Have a fluctuating production programme
Have acombination of two systems
Multi-product scheduling in Batch production
The Assignment Problem
Scheduling orders with Random Arrivals
Product Sequencing
10. objectives
Maximum utilisation of the plant at minimum cost
Ensure the requirement of Manpower is optimum
and evenly distributes
Process up-to-date information regarding
availablity of material, expected date of delivery,
material rejection, shortage, purchase orders
cancelled, etc.,
Update yourself with data on each machine
Have complete information on performance
standards
Obtain quick feedback
11. Forms of schedule
A production flow programme
A production master programme for integrating
work on large objects
A cumulative output progress chart
An outline master programme
A schedule for breakdown of orders
A cycle schedule
A detailed schedule
12. Inputs of scheduling
Performance standards
Unit of measurement
Effective capacity per work centre
Extent of rush orders
Overlapping of operations
Individual job schedules
13. Drawing a job schedule
The constant information is entered first in the
schedule which is followed by batch quantity.
The variable information such as operation
number, operation description, machines and
effective capacity is entered
The time is calculated by using the relation
Time for an operation = Std. time/price * Batch
quantity / 60
The length of operation run will be calculated
Operation run = Time for operation / Effective
capacity / day
Each operation run is shown
14. Load schedule or load chart
The amalgamation of individual job scheduleor
load chart indicates the work to be carried out in
each section or department of the company
during the specific period.
Load chart enable us to know the accumulated
load on each machine at a given time, and enable
us to determine the allocation of the machine for
future orders.
15. Factors influencing scheduling
Degree of centralisation
Relative job priority
Items with fewest remaining operations are
scheduled first
Delivery commitment of critical items
Penalty clause items
Long pending jobs
Certain customers
Jobs which feed more work to work centres
Critical items holding other plants
Jobs currently being by competitiors
Load charts accumulation
16. Procedure for scheduling
Preparation of individual job schedule
Assign start and finish dates to each operation on
the job schedule
Post of each schedule onto the load chart
Setting delivery date for an item
17. Reducing problems
Product simplification
Jon enlargement programme
Sub-contracting
Reallocation of resources to suit work content
Minimation of rush orders
Creating controlled work-in-process blanks
Reducing job split-ups
Simplifying available resources
Improving progress chasing
19. Definition
Despatching is the routine of setting productive
activities in motion through the release of orders
and instructions, in accordance with previously
planned time and sequence, embodied in route
sheets and schedule charts.
20. Functions
Despatches assign work to definite machines or
work places and men in order of priority and in
proper sequence
Issuing the required materials, tools, jigs, fixtures,
dice and gauges for various jobs etc.,
Release of necessary order and production forms
Guiding and controlling materials and operations
in processing
Contacting routing and scheduling sections
21. Forms by dispatcher
Material requisition
Job cards
Labour cards or wage payment cards
Move cards
Inspection cards
Tool and guage tickets
22. Despatching rules
Simple Rules
Earliest due date
First come first served
Combination rules
Minimum slack
Critical ratio
23. Follow up
Follow up or expediting or progressing is that
branch of production control procedure which
regulates the progress of materials and parts
through production process.
24. Qualities of a follow up person
Tenacity
Processed responsibility
Product responsibility
25. Problems of follow up
Obtaining information
Mechanical counting
Operator work record
Use of job card
Use of detachable tickets
Problem of volume
26. Types of follow up
Materials
Work-in-progress
Assembly and erection