Scheduling of a five story residential apartment project
1. SCHEDULING OF A FIVE STOREY RESIDENTIAL APARTMENT
PROJECT USING PRIMAVERA P6 PROJECT PLANNER
SOFTWARE
PRESENTED BY
M.SANJEEV 1608-15-732-301
K.AISHWARYA 1608-15-732-
012
M.AKANSH 1608-15-732-026
K.SHASHI PREETHAM 1608-15-732-
041
Under the guidance
of
DR. M. VENU GOPAL
M.E, M.Tech, Ph.D, LMISTE, FIE, FIV
2. TABLE OF CONTENT:
• INTRODUCTION
• OBJECTIVES
• PROJECT SCHEDULING SOFTWARE DO
• ABOUT PRIMAVERA
• METHODOLOGY
• CONCLUSION
• REFERENCES
3. INTRODUCTION:
• THE PROJECT MANAGEMENT INSTITUTE (PMI) DEFINES A PROJECT AS A
TEMPORARY ENDEAVOUR UNDERTAKEN TO CREATE A UNIQUE PRODUCT,
SERVICE, OR RESULT. THE TEMPORARY NATURE OF PROJECTS INDICATES A
DEFINITE BEGINNING AND END. THE END IS REACHED WHEN THE PROJECT’S
OBJECTIVES HAVE BEEN ACHIEVED OR WHEN THE PROJECT IS TERMINATED
BECAUSE ITS OBJECTIVES WILL NOT OR CANNOT BE MET, OR WHEN THE NEED
FOR THE PROJECT NO LONGER EXISTS.
WHAT IS A PROJECT…?
4. WHAT IS PROJECT MANAGEMENT..?
• PROJECT MANAGEMENT IS THE PRACTICE OF INITIATING, PLANNING,
EXECUTING, CONTROLLING, AND CLOSING THE WORK OF A TEAM TO ACHIEVE
SPECIFIC GOALS AND MEET SPECIFIC SUCCESS CRITERIAAT THE SPECIFIED TIME.
• THE PRIMARY CHALLENGE OF PROJECT MANAGEMENT IS TO ACHIEVE ALL OF
THE PROJECT GOALS WITHIN THE GIVEN CONSTRAINTS. THIS INFORMATION IS
USUALLY DESCRIBED IN PROJECT DOCUMENTATION, CREATED AT THE
BEGINNING OF THE DEVELOPMENT PROCESS.
5. THE PROCESS OF PROJECT MANAGEMENT CONSISTS OF
INITIATION
PLANNING
SCHEDULING
EXECUTION
MONITORING AND CONTROLLING
CLOSING
6. INITIATION PHASE :
IT IS THE FIRST PHASE IN A PROJECT MANAGEMENT AS IT INVOLVES
STARTING UP A NEW PROJECT. INITIATION PHASE INCLUDES THE DECIDING POINT
FOR THE STAKEHOLDERS WHETHER OR NOT COMMIT TO A PROJECT.
PLANNING AND DESIGN :
ONCE THE PROJECT RECEIVES THE GREEN LIGHT, IT
NEEDS A SOLID PLAN TO GUIDE THE TEAM, AS WELLAS KEEP THEM ON TIME AND
ON BUDGET. A WELL-WRITTEN PROJECT PLAN GIVES GUIDANCE FOR OBTAINING
RESOURCES, ACQUIRING FINANCING AND PROCURING REQUIRED MATERIALS.
7. SCHEDULING:
SCHEDULING IS THE MECHANICAL PROCESS OF FORMALIZING THE
PLANNED FUNCTIONS, ASSIGNING THE START AND COMPLETION DATES TO EACH
PART OF THE WORK IN SUCH A MANNER THAT THE WHOLE WORK PROCEEDS IN A
LOGICAL SEQUENCE AND IN AN ORDERLY AND SYSTEMATIC MANNER.
IMPLEMENTATION PHASE (OR) EXECUTION :
THIS IS ALSO A CRUCIAL STAGE AS THE PROJECT TAKES SHAPE
DURING THE IMPLEMENTATION PHASE. IT INVOLVES THE CONSTRUCTION OF THE
ACTUAL RESULT OF THE PROJECT. THE PROGRAMMERS ARE WORKING ON
ENCODING, DESIGNERS ARE BUSY WITH GRAPHIC MATERIAL, CONTRACTORS ARE
BUILDING AND SO ON.
8. PROJECT PERFORMANCE (OR) MONITORING AND CONTROL :
IN THIS PHASE, AS THE SCHEDULED WORK IS GOING IN PROGRESS, THE
PROJECT MANAGERS WILL COMPARE PROJECT STATUS AND PROGRESS TO THE
ACTUAL PLAN. TO KEEP THE PROJECT ON TRACK, THE MANAGERS NEED TO ADJUST
THE SCHEDULES. SO, BASICALLY, IT INVOLVES MONITORING THE PROJECT FOR
RISKS AND KEEPING DISTANCE WITH THOSE RISKS.
9. CLOSING PHASE :
FOLLOW-UP PHASE OR THE CLOSURE PHASE REPRESENTS THE
COMPLETED PROJECT. THE CONTRACTORS ARE TERMINATED AT THIS TIME
THOSE WHO ARE HIRED TO WORK SPECIFICALLY ON THE PROJECT. MANAGERS
THANK THOSE WHO PARTICIPATED IN THE PROJECT FOR THEIR EFFORTS AND
VALUABLE MEMBERS ARE RECOGNIZED. AFTER THE COMPLETION OF A PROJECT,
A PROJECT MANAGER WILL OFTEN HOLD A MEETING TO IDENTIFY PROJECT
FAILURES AND WHAT WERE THE POSITIVE POINTS IN A PROJECT.
10. OBJECTIVES:
THE OBJECTIVES OF THIS STUDY ARE:
• FIND THE CONSTRUCTION SEQUENCE FOR A RESIDENTIAL BUILDING
CONSTRUCTION.
• CALCULATE THE PRACTICAL DURATIONS REQUIRED TO CARRY OUT THE
ACTIVITIES.
• DEVELOP SCHEDULING USING PROJECT PLANNER SOFTWARE PRIMAVERA.
11. COMMON TECHNIQUES USED INPROJECT SCHEDULING :
1. GANTT CHART:
GANTT CHARTS ARE ALSO KNOWN AS BAR CHARTS. ACTIVITIES
ARE REPRESENTED AS BARS AND THE LENGTH OF EACH BAR REPRESENTS THE
ACTIVITY DURATION. THE BEGINNING OF THE BAR SHOWS THE START DATE AND
THE END OF THE BAR SHOWS THE END DATE OF THE ACTIVITY. DEPENDING ON THE
PROJECT EXECUTION PLAN AND RESOURCE AVAILABILITY, THESE BARS MAY BE
SEQUENTIAL, OR RUN IN PARALLEL.
12.
13. ADVANTAGE OF BAR CHART:
• BAR CHART ARE SIMPLE TO PREPARE
• BAR CHART ARE EASY TO UNDERSTAND
• BAR CHART ARE ACCEPTABLE FOR PRESENTATION, ESPECIALLY FOR FIELD
PEOPLE AND PEOPLE WHO ARE UNFAMILIAR WITH THE CPM
• BAR CHARTS CAN BE LOADED WITH MORE INFORMATION, SUCH AS CASH-FLOW
DIAGRAMS AND MAN-HOURS.
14. LIMITATION OF BAR CHART:
• THE MAIN LIMITATION OF BAR CHART IS LACK OF LOGICAL REPRESENTATION.
BAR CHARTS DO NOT REVEAL THE ANSWERS OF RELATIONSHIP.
• THE BAR CHART DOES NOT SHOWS THE CRITICAL ACTIVITIES INVOLVED IN THE
PROJECT. THE CRITICAL ACTIVITIES ARE IMPORTANT DURING THE RESCHEDULE
OF THE PROJECT IF ANY PROBLEM COME THROUGH.
• THE BAR CHART CAN NOT USED AS AN EFFECTIVE CONTROL DEVICE BECAUSE IT
DOES NOT SHOWS THE PROGRESS OF THE WORK.
15. 2.CRITICAL PATH METHOD:
• THE CRITICAL PATH METHOD IS AN ADVANCED SCHEDULING METHOD WHICH
WAS DEVELOPED IN THE LATE 1950S. THEN IT HAS BEEN USED FOR THE
SCHEDULING OF ANY TYPE OF PROJECTS INCLUDING CONSTRUCTION,
AEROSPACE AND DEFENSE, SOFTWARE DEVELOPMENT, IT, ETC.
• THE CRITICAL PATH IS THE LONGEST PATH OF THE NETWORK DIAGRAM. IN THIS
METHOD, ACTIVITIES ARE LISTED, ACTIVITY DURATIONS ARE DETERMINED,
DEPENDENCIES BETWEEN THE ACTIVITIES ARE ESTABLISHED AND THE LONGEST
PATH IS IDENTIFIED BY MAKING FORWARD AND BACKWARD CALCULATIONS.
• IT IS A COMMON METHOD FOR DETERMINING THE COMPLETION DATE OF A
PROJECT
16.
17. ADVANTAGES OF CPM:
• IT MAKES CONTROL EASIER FOR THE MANAGEMENT.
• IT IDENTIFIES THE MOST CRITICAL ELEMENTS IN THE PROJECT. THUS, THE
MANAGEMENT IS KEPT ALERT AND PREPARED TO PAY DUE ATTENTION TO THE
CRITICAL ACTIVITIES OF THE PROJECT.
• IT MAKES BETTER AND DETAILED PLANNING POSSIBLE.
LIMITATION OF CPM:
• CPM OPERATES ON THE ASSUMPTION THAT THERE IS A PRECISE KNOWN TIME
THAT EACH ACTIVITY IN THE PROJECT WILL TAKE. BUT, IT MAY NOT BE TRUE IN
REAL PRACTICE.
• CPM TIME ESTIMATES ARE NOT BASED ON STATISTICALANALYSIS.
18. 3.PERT (PROGRAM EVALUATION REVIEW TECHNIQUE):
• PERT IS SIMILAR TO CPM BUT USED WHEN TIME ESTIMATES OF THE ACTIVITIES
ARE UNCERTAIN, IT IS NOT HIGHLY USED FOR CONSTRUCTION PROJECTS.
• THE THREE ESTIMATE TECHNIQUES ARE;
• MOST LIKELY ESTIMATE
• OPTIMISTIC ESTIMATE
• PESSIMISTIC ESTIMATE
• EXPECTED TIME OF THE TASK IS CALCULATED BY USING THESE THREE
ESTIMATES.
19.
20. ADVANTAGES OF PERT:
• IT COMPELS MANAGERS TO PLAN THEIR PROJECTS CRITICALLY AND ANALYSE
ALL FACTORS AFFECTING THE PROGRESS OF THE PLAN. THE PROCESS OF THE
NETWORK ANALYSIS REQUIRES THAT THE PROJECT PLANNING BE CONDUCTED
ON CONSIDERABLE DETAIL FROM THE START TO THE FINISH.
• THE PERT TIME (TE) IS BASED UPON 3-WAY ESTIMATE AND HENCE IS THE MOST
OBJECTIVE TIME IN THE LIGHT OF UNCERTAINTIES AND RESULTS IN GREATER
DEGREE OF ACCURACY IN TIME FORECASTING.
DISADVANTAGES OF PERT:
• THE COSTS MAY BE HIGHER THAN THE CONVENTIONAL METHODS OF
PLANNING AND CONTROL.
• IT IS NOT SUITABLE FOR RELATIVELY SIMPLE AND REPETITIVE PROCESSES
21. WHAT DOES PROJECT SCHEDULING SOFTWARE DO:
• PROJECT SCHEDULING TOOLS ARE A GREAT WAY TO GET YOURSELF
ORGANIZED, PROVIDING THE WHOLE TEAM WITH A PLATFORM WHERE THEY
CAN COLLABORATE.
• SCHEDULING SOFTWARE HELPS YOU NOT PLAN YOUR PROJECTS, BUT TO ALSO
GET A GRIP ON WHAT’S CURRENTLY HAPPENING AS THE PROJECT UNFOLDS.
• FINALLY PROJECT SCHEDULING TOOLS CREATE TRANSPARENCY, NOT ONLY FOR
STAKEHOLDERS, BUT ALSO FOR TEAM MEMBERS WHO WANT TO KNOW WHAT’S
EXPECTED OF THEM.
22. ABOUT PRIMAVERA :
• PRIMAVERA IS THE PROJECT MANAGEMENT TOOL (SOFTWARE) THAT HELPS IN
PLANNING THE RESOURCES, MONITOR AND CONTROL FOR A PROJECT. PLEASE
NOTE THAT IT IS NOT ONLY USED IN CIVIL ENGINEERING BUT ALSO OTHER
FIELDS SUCH AS IT, HVAC, ELECTRICAL ETC WHEREVER THERE ARE PROJECTS.
• IF YOU MANAGE ONE PROJECT THEN ITS PROJECT MANAGEMENT
• IF YOU MANAGE MULTIPLE PROJECTS THEN ITS PROGRAM MANAGEMENT
• IF YOU MANAGE MULTIPLE PROGRAMS THEN ITS CALLED PORTFOLIO
MANAGEMENT
• ORACLE PRIMAVERA P6 IS A PORTFOLIO MANAGEMENT SOFTWARE WHICH CAN
ALSO MANAGE PROGRAMS AND PROJECTS.
23. • IT IS BASED ON CRITICAL PATH METHOD AND HENCE UNDERSTANDING ITS
BASICS IS ESSENTIAL.
• PRIMAVERA HELPS IN
GENERATING THE CRITICAL PATH QUICKLY
PROVIDING OUTPUT FOR RESOURCES SUCH AS MATERIAL, MACHINERY AND
MANPOWER ON DAILY, WEEKLY AND MONTHLY BASICS.
FORECASTING AS TO WHEN THE PROJECT WILL BE COMPLETING
IT ALLOWS EASY COLLABORATION BETWEEN THE PROJECT USERS
24. EARN VALUE ANALYSIS (EVA) - THAT IS WHETHER THE PROJECT IS ON TIME,
AHEAD OR BEHIND AND AT WHAT COST HOWEVER
IT CAN BE USED TO ORGANIZE PROJECTS UP TO 100,000 ACTIVITIES, AND IT
PROVIDES UNLIMITED RESOURCES AND AN UNLIMITED NUMBER OF TARGET
PLANS.
25. IT IS IMPORTANT TO NOTE THAT PRIMAVERA IS THE SOFTWARE ONLY. NOT
ARTIFICIAL INTELLIGENCE. WHICH MEANS YOU WILL HAVE TO
MANUALLY ENTER THE ACTIVITIES
LINK THE ACTIVITIES
ENTER THE DURATION
ALLOCATE THE RESOURCES SUCH AS MANPOWER, MATERIAL AND MACHINERY
ETC INITIALLY IT WILL BE A HECTIC/TIME CONSUMING BUT LATER YOU WILL
BE THANKFUL WHILE MONITORING THE PROJECT. MOST IMPORTANTLY,
PRACTICE MAKES MAN PERFECT
34. 3.ESTIMATE THE DURATION OF EACH JOB.
NOTE: Estimation of duration of the each activity is based on the quantity obtained from above
table and the standard schedule of rates(SSR) given in B.N Datta book
35.
36.
37. 4. WORK BREAKDOWN STRUCTURE & DEFINE THE ACTIVITIES IN THE
PROJECT:
DIVIDING THE PROJECT INTO SUBPROJECTS, SUBPROJECTS TO ACTIVITIES,
ACTIVITIES TO SUB ACTIVITIES IS DONE, WORK BREAKDOWN SHOULD DONE TO
SUCH AN EXTENT THAT THE PROJECT BECOME MANAGEABLE.
38. 5. DEFINED SEQUENCE OF ACTIVITIES IN THE PROJECT.
6.ESTABLISHED THE RELATIONSHIPS OF EACH ACTIVITIES IN THE PROJECT.
7. CREATED THE ENTERPRISE PROJECT STRUCTURE IN THE PRIMAVERA SOFTWARE.
8.CREATE THE PROJECT IN THE PRIMAVERA SOFTWARE.
9.ASSIGNING THE CALENDAR TO THE CREATED PROJECT IN THE PRIMAVERA
SOFTWARE.
39. 10.CREATE THE WORK BREAKDOWN STRUCTURE AND ACTIVITY OF THE PROJECT
IN THE PRIMAVERA SOFTWARE.
11.CREATE THE RELATIONSHIPS OF THE PROJECT ACTIVITIES IN THE PRIMAVERA
SOFTWARE.
12.ENTER THE ESTIMATED DURATION OF EACH JOB IN THE PRIMAVERA SOFTWARE.
12.DEVELOPED THE SCHEDULE IN THE PRIMAVERA SOFTWARE.
OUTCOMES: Obtained a project network , critical path , critical
activities , float of non critical activities and critical duration of 328 days.
40.
41.
42.
43.
44.
45. CONCLUSION:
PRIMAVERA SERVES AS AN EFFECTIVE TOOL FOR GENERATING GANTT CHART FOR THE
SCHEDULE OF A HIGH RISE CONSTRUCTION. WITH THE HELP OF PRIMAVERA A
SCHEDULER CAN:
• EFFECTIVELY LINK ALL THE ACTIVITIES INVOLVED IN THE CONSTRUCTION OF THE
PROJECT.
• DETERMINE THE TOTAL DURATION REQUIRED FOR THE CONSTRUCTION OF THE
DIFFERENT PHASES INVOLVED.
• KEEP A TRACK OF THE SCHEDULED AND THE ON-SITE CONSTRUCTION.
• ASSIGN THE RESOURCES IN A MANNER THAT EXPENSES AND TIME DURATION AND
SHORTENED AND THE PROJECT PROVES ECONOMICAL.
46. • REFERENCES
[1] DEVI KAMALAM.J.JANE HELENA. 2013 “RESOURCE SCHEDULING OF
CONSTRUCTION PROJECTS USING GENETIC ALGORITHM” INTERNATIONAL JOURNAL
OF ADVANCED ENGINEERING TECHNOLOGY
[2] AHAMED E. HAROUN, ADIL H.A. LOGHMAN, AND SALAM Y. M. MAHMOUD..ETC
(2012) “SCHEDULING PROBLEM UNDER CONSTRAINED RESOURCE: A HISTORICAL
REVIEW OF SOLUTION METHODS AND COMPUTER APPLICATION” JOURNAL OF
SCIENCE AND TECHNOLOGY
[3] MILOS SEDA (2008) “A CONSTRUCTION TO SHIFT ALGORITHMS FOR RESOURCE-
CONSTRAINED SCHEDULING WITH DYNAMIC CHANGES” INTERNATIONAL JOURNAL
OF ADVANCED ENGINEERING TECHNOLOGY
[4] KASTOR AND K. SRIAKOULIS (2010) “EFFECTIVENESS OF RESOURCE LEVELING
TOOLS FOR RESOURCE CONSTRAINT PROJECT SCHEDULING PROBLEM”
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT
47. [5] FRANCOIS BERTHAUT..ETC (2011) “OPTIMAL RESOURCE CONSTRAIN PROJECT
SCHEDULING WITH OVERLAPPING MODES” INTERNATIONAL JOURNAL OF
ADVANCED ENGINEERING TECHNOLOGY
[6]T. SUBRAMANI, K. CHINNADURAI (2015) “CONSTRUCTION MANAGEMENT AND
SCHEDULING OF RESIDENTIAL BUILDING USING PRIMAVERA” INTERNATIONAL
JOURNAL OF APPLICATION OR INNOVATION IN ENGINEERING & MANAGEMENT
[7]RHUTA JOSHIL, PROS. V. Z. PATIL (2013) “RESOURCE SCHEDULING OF
CONSTRUCTION PROJECT: CASE STUDY” INTERNATIONAL JOURNAL OF SCIENCE
AND RESEARCH
[8] B. S. K. REDDY, S K.NAGARAJU, M D SALMAN (2015) “A STUDY ON OPTIMIZATION
OF RESOURCES FOR MULTIPLE PROJECTS BY USING PRIMAVERA” JOURNAL OF
ENGINEERING SCIENCE AND TECHNOLOGY
48. [9] JIN- LEE KIM AND RALPH D. ELLIS JR.(2008) “PERMUTATION-BASED ELITIST
GENETIC ALGORITHM FOR OPTIMIZATION OF LARGE- SIZED RESOURCE PROJECT
SCHEDULING”, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT
[10] ANDREW FERNANS TOM, SACHIN PAUL (2013) “PROJECT MONITORING AND
CONTROL USING PRIMAVERA” INTERNATIONAL JOURNAL OF INNOVATIVE
RESEARCH IN SCIENCE, ENGINEERING AND TECHNOLOGY