SlideShare una empresa de Scribd logo
1 de 32
Descargar para leer sin conexión
SPM-UNIT II
ACTIVITY PLANNING
Prof. Kanchana Devi
Network Planning Models
Prof. Kanchana Devi
2
 Scheduling techniques model the project’s activ ities and
their relationships as a “Network”.
 In network time flows from left to right
 These techniques were developed in 1950’s
 There are two best techniques:
 CPM (Critical Path Method)
 PERT (Program Evaluation Review Technique)
 Both uses an “activity-on-arrow” approach
 Activities are drawn as arrows joining circles, or nodes
 Which show the start and completion time of the activities
Precedence Network
Prof. Kanchana Devi
3
 Recently used , Popular one
 It uses “activity-on-node” networks
 Where activities are represented as nodes
 Links between the nodes are represented as
sequencing requirements.
Formulating a Network Model
Prof. Kanchana Devi
4
 First stage:
 Representing the activities and their
relationships as graph.
 In “Activity-on-node”
 Representing the activities as nodes(boxes) and
the lines between nodes represent the
dependencies.
Rules:Constructing Precedence
Network
Prof. Kanchana Devi
5
 A project network should have only one start
node
 A project network should have only one end
node
 A node has a duration
 Links normally have no duration
 Precedents are the immediate preceding
activities
 Time moves from left to right
 A network may not contain loops
 A network should not contain dangles
Fragment of precedence Network
Prof. Kanchana Devi
6
Install
Program
Test
Data
Take-on
Code
A loop represents an impossible
sequence
Prof. Kanchana Devi
7
Code
Program
Release
Program
Test
Program
Diagnose
Errors
Correct
Errors
A Dangle
Prof. Kanchana Devi
8
Design
Program
Install
Program
Test Program
Code
Program
Write User
Manual
Resolving the Dangle
Prof. Kanchana Devi
9
Design
Program
Install
Program
Test
Program
Code
Program
Write
User
Manual
Sign-Off
Representing Lagged Activities
Prof. Kanchana Devi
10
 Undertake two activities in parallel as there
is a lag between two.
 Activities are lagged because a stage in one
activity must be completed before the other
may proceed.
 Show each stage as separate activity.
Adding Time Dimension
Prof. Kanchana Devi
11
 Each activity have an estimate of its duration.
 Forward pass – Earliest dates at which
activities may commence and project be
completed.
 Backward pass – Latest start dates for
activities and critical path.
Project Specification
Prof. Kanchana Devi
12
Project Activity Network
Prof. Kanchana Devi
13
Project Activity Network
represented as CPM Network
Prof. Kanchana Devi
14
Dummy activities
15
 When two paths within a network have a
common event to occur.
 It is incorrect to require both hardware
specification and data structure design
Using Dummy Activities
Prof. Kanchana Devi
16
…….
Prof. Kanchana Devi
17
 Dummy activities shown as dotted lines have
a zero duration and use no resources.
 Use of dummy activity where two activities
share the same start and end nodes makes it
easier to distinguish activity end points.
Forward Pass
Prof. Kanchana Devi
18
Activity Duration
(Weeks)
Earliest Start
Date (Weeks)
Earliest Finish
Date(Weeks)
A 6 0 6
B 4 0 4
C 3 6 9
D 4 4 8
E 3 4 7
F 10 0 10
G 3 10 13
H 2 9 11
CPM Network
Prof. Kanchana Devi
19
A CPM Network after forward
pass
Prof. Kanchana Devi
20
Activity table for forward pass
Prof. Kanchana Devi
21
Activity Duration
(weeks)
Earliest
Start
Date
Latest
Start
Date
Earliest
Finish
Date
Latest
Finish
Date
Total
Float
A 6 0 6
B 4 0 4
C 3 6 9
D 4 4 8
E 3 4 7
F 10 0 10
G 3 10 13
H 2 9 11
Backward Pass
Prof. Kanchana Devi
22
CPM Network after the backward
pass
Prof. Kanchana Devi
23
Identifying the Critical Path
Prof. Kanchana Devi
24
 Any delay on the critical path will delay the
project.
 Difference between earliest and latest date
for an event is known as slack.
 Event with slack of zero is critical as any
delay in achieving that event will delay the
completion date of the project.
Critical Path
Prof. Kanchana Devi
25
Event
Number
Latest
Date
Earliest
Date
Slack
Activity Float
Prof. Kanchana Devi
26
 As events have slack, activities possess float.
 Total float is the difference between earliest
start and latest start ( or difference between
earliest finish and latest finish)
Activity Schedule showing total
float for each activity
Prof. Kanchana Devi
27
Activity Schedule
Prof. Kanchana Devi
28
Actvity Name Time Actvity Name Time
1-2 A 4 5-6 G 4
1-3 B 1 5-7 H 8
2-4 C 1 6-8 I 1
3-4 D 1 7-8 J 2
3-5 E 6 8-10 K 5
4-9 F 5 9-10 L 7
Activity Network Diagram
Prof. Kanchana Devi
29
1
2
3
5
4
7
6
8
109
Solution
Prof. Kanchana Devi
30
Activity Activity
Name
Normal
Time
E.S E.F L.S L.F Total
Float
1-2 A 4 0 4 5 9 5
1-3 B 1 0 1 0 1 0
2-4 C 1 4 5 9 10 5
3-4 D 1 1 2 9 10 8
3-5 E 6 1 7 1 7 0
4-9 F 5 5 10 10 15 5
5-6 G 4 7 11 12 16 5
5-7 H 8 7 15 7 15 0
6-8 I 1 11 12 16 17 5
7-8 J 2 15 17 15 17 0
8-10 K 5 17 22 17 22 0
9-10 L 7 10 17 15 22 5
Problem 1
Prof. Kanchana Devi
31
 Draw activity network of the project.
 Find total float of each activity.
Activity Time inWeeks
1-2 20
1-3 25
2-3 10
2-4 12
3-4 5
3-5 10
Problem 2
Prof. Kanchana Devi
32
 Find out the critical path and total float.
Activity Immediate
Predecessor
Time
A 3
B 8
C 5
D A 9
E C 2
F B,E 6
H B,E 12
G D 11

Más contenido relacionado

La actualidad más candente

Software estimation
Software estimationSoftware estimation
Software estimationMd Shakir
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning IntroductionKanchana Devi
 
Software project management
Software project managementSoftware project management
Software project managementR A Akerkar
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approachtumetr1
 
Software project estimation
Software project estimationSoftware project estimation
Software project estimationinayat khan
 
rules of formulating network planning model .
rules of formulating network planning model .rules of formulating network planning model .
rules of formulating network planning model .ritambharaaatre
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementkarthikeyanC40
 
Project Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProject Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProf Ansari
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introductionKanchana Devi
 
Software process and project metrics
Software process and project metricsSoftware process and project metrics
Software process and project metricsIndu Sharma Bhardwaj
 
Cocomo model
Cocomo modelCocomo model
Cocomo modelMZ5512
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 

La actualidad más candente (20)

Software estimation
Software estimationSoftware estimation
Software estimation
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning Introduction
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Software project management
Software project managementSoftware project management
Software project management
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approach
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Function Point Analysis
Function Point AnalysisFunction Point Analysis
Function Point Analysis
 
SPM Evaluation
SPM EvaluationSPM Evaluation
SPM Evaluation
 
Scheduling algorithms
Scheduling algorithmsScheduling algorithms
Scheduling algorithms
 
Software project estimation
Software project estimationSoftware project estimation
Software project estimation
 
rules of formulating network planning model .
rules of formulating network planning model .rules of formulating network planning model .
rules of formulating network planning model .
 
Software quality
Software qualitySoftware quality
Software quality
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Project Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProject Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software Development
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introduction
 
Software process and project metrics
Software process and project metricsSoftware process and project metrics
Software process and project metrics
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 

Destacado

5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 
1.7 project management
1.7 project management1.7 project management
1.7 project managementexemplar2401
 
Project management glossary_of_terms
Project management glossary_of_termsProject management glossary_of_terms
Project management glossary_of_termsnagham ali hasan
 
2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn
2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn
2016 Integrated Activity Planning (IAP) Project Overview - LinkedInAmiruddin Talib
 
Daily planning plan template
Daily planning plan templateDaily planning plan template
Daily planning plan templatePaul Doherty
 
Dispersed and cross border projects
Dispersed and cross border projectsDispersed and cross border projects
Dispersed and cross border projectstumetr1
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
Managing contracts
Managing contractsManaging contracts
Managing contractstumetr1
 
Resource allocation
Resource allocationResource allocation
Resource allocationtumetr1
 
Software and Hardware Tools for Microprocessors
Software and Hardware Tools for MicroprocessorsSoftware and Hardware Tools for Microprocessors
Software and Hardware Tools for MicroprocessorsDeepak Tathe
 
Unit II Software Testing and Quality Assurance
Unit II Software Testing and Quality AssuranceUnit II Software Testing and Quality Assurance
Unit II Software Testing and Quality AssuranceVinothkumaR Ramu
 
Activity planning
Activity planningActivity planning
Activity planningtumetr1
 
SDPM - Lecture 4 - Activity planning and resource allocation
SDPM - Lecture 4 - Activity planning and resource allocationSDPM - Lecture 4 - Activity planning and resource allocation
SDPM - Lecture 4 - Activity planning and resource allocationOpenLearningLab
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimationtumetr1
 
The project schedule and budget
The project schedule and budgetThe project schedule and budget
The project schedule and budgettumetr1
 
Software product quality
Software product qualitySoftware product quality
Software product qualitytumetr1
 

Destacado (20)

5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
24593648 levels-of-planning
24593648 levels-of-planning24593648 levels-of-planning
24593648 levels-of-planning
 
Project management glossary_of_terms
Project management glossary_of_termsProject management glossary_of_terms
Project management glossary_of_terms
 
2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn
2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn
2016 Integrated Activity Planning (IAP) Project Overview - LinkedIn
 
Daily planning plan template
Daily planning plan templateDaily planning plan template
Daily planning plan template
 
Dispersed and cross border projects
Dispersed and cross border projectsDispersed and cross border projects
Dispersed and cross border projects
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
Softwaretesting
SoftwaretestingSoftwaretesting
Softwaretesting
 
Managing contracts
Managing contractsManaging contracts
Managing contracts
 
Daily planning system
Daily planning systemDaily planning system
Daily planning system
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Software and Hardware Tools for Microprocessors
Software and Hardware Tools for MicroprocessorsSoftware and Hardware Tools for Microprocessors
Software and Hardware Tools for Microprocessors
 
Unit II Software Testing and Quality Assurance
Unit II Software Testing and Quality AssuranceUnit II Software Testing and Quality Assurance
Unit II Software Testing and Quality Assurance
 
Activity planning
Activity planningActivity planning
Activity planning
 
SDPM - Lecture 4 - Activity planning and resource allocation
SDPM - Lecture 4 - Activity planning and resource allocationSDPM - Lecture 4 - Activity planning and resource allocation
SDPM - Lecture 4 - Activity planning and resource allocation
 
boilers
boilersboilers
boilers
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimation
 
The project schedule and budget
The project schedule and budgetThe project schedule and budget
The project schedule and budget
 
Software product quality
Software product qualitySoftware product quality
Software product quality
 

Similar a Spm ap-network model-

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLSiddanna Balapgol
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrixdmdk12
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Chapter 14Managing Projects1Chapter Objectives
Chapter 14Managing Projects1Chapter ObjectivesChapter 14Managing Projects1Chapter Objectives
Chapter 14Managing Projects1Chapter ObjectivesEstelaJeffery653
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertDagnaygebawGoshme
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxMuhammadAbubakar114879
 

Similar a Spm ap-network model- (20)

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrix
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Spm
SpmSpm
Spm
 
Chapter 14Managing Projects1Chapter Objectives
Chapter 14Managing Projects1Chapter ObjectivesChapter 14Managing Projects1Chapter Objectives
Chapter 14Managing Projects1Chapter Objectives
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
project network
project networkproject network
project network
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 

Más de Kanchana Devi

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-Kanchana Devi
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-introKanchana Devi
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesKanchana Devi
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introKanchana Devi
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsKanchana Devi
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationKanchana Devi
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pertKanchana Devi
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Kanchana Devi
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-introKanchana Devi
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm toolsKanchana Devi
 

Más de Kanchana Devi (11)

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-intro
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilities
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-intro
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teams
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocation
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pert
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-intro
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm tools
 

Último

Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 

Último (20)

Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 

Spm ap-network model-

  • 2. Network Planning Models Prof. Kanchana Devi 2  Scheduling techniques model the project’s activ ities and their relationships as a “Network”.  In network time flows from left to right  These techniques were developed in 1950’s  There are two best techniques:  CPM (Critical Path Method)  PERT (Program Evaluation Review Technique)  Both uses an “activity-on-arrow” approach  Activities are drawn as arrows joining circles, or nodes  Which show the start and completion time of the activities
  • 3. Precedence Network Prof. Kanchana Devi 3  Recently used , Popular one  It uses “activity-on-node” networks  Where activities are represented as nodes  Links between the nodes are represented as sequencing requirements.
  • 4. Formulating a Network Model Prof. Kanchana Devi 4  First stage:  Representing the activities and their relationships as graph.  In “Activity-on-node”  Representing the activities as nodes(boxes) and the lines between nodes represent the dependencies.
  • 5. Rules:Constructing Precedence Network Prof. Kanchana Devi 5  A project network should have only one start node  A project network should have only one end node  A node has a duration  Links normally have no duration  Precedents are the immediate preceding activities  Time moves from left to right  A network may not contain loops  A network should not contain dangles
  • 6. Fragment of precedence Network Prof. Kanchana Devi 6 Install Program Test Data Take-on Code
  • 7. A loop represents an impossible sequence Prof. Kanchana Devi 7 Code Program Release Program Test Program Diagnose Errors Correct Errors
  • 8. A Dangle Prof. Kanchana Devi 8 Design Program Install Program Test Program Code Program Write User Manual
  • 9. Resolving the Dangle Prof. Kanchana Devi 9 Design Program Install Program Test Program Code Program Write User Manual Sign-Off
  • 10. Representing Lagged Activities Prof. Kanchana Devi 10  Undertake two activities in parallel as there is a lag between two.  Activities are lagged because a stage in one activity must be completed before the other may proceed.  Show each stage as separate activity.
  • 11. Adding Time Dimension Prof. Kanchana Devi 11  Each activity have an estimate of its duration.  Forward pass – Earliest dates at which activities may commence and project be completed.  Backward pass – Latest start dates for activities and critical path.
  • 13. Project Activity Network Prof. Kanchana Devi 13
  • 14. Project Activity Network represented as CPM Network Prof. Kanchana Devi 14
  • 15. Dummy activities 15  When two paths within a network have a common event to occur.  It is incorrect to require both hardware specification and data structure design
  • 16. Using Dummy Activities Prof. Kanchana Devi 16
  • 17. ……. Prof. Kanchana Devi 17  Dummy activities shown as dotted lines have a zero duration and use no resources.  Use of dummy activity where two activities share the same start and end nodes makes it easier to distinguish activity end points.
  • 18. Forward Pass Prof. Kanchana Devi 18 Activity Duration (Weeks) Earliest Start Date (Weeks) Earliest Finish Date(Weeks) A 6 0 6 B 4 0 4 C 3 6 9 D 4 4 8 E 3 4 7 F 10 0 10 G 3 10 13 H 2 9 11
  • 20. A CPM Network after forward pass Prof. Kanchana Devi 20
  • 21. Activity table for forward pass Prof. Kanchana Devi 21 Activity Duration (weeks) Earliest Start Date Latest Start Date Earliest Finish Date Latest Finish Date Total Float A 6 0 6 B 4 0 4 C 3 6 9 D 4 4 8 E 3 4 7 F 10 0 10 G 3 10 13 H 2 9 11
  • 23. CPM Network after the backward pass Prof. Kanchana Devi 23
  • 24. Identifying the Critical Path Prof. Kanchana Devi 24  Any delay on the critical path will delay the project.  Difference between earliest and latest date for an event is known as slack.  Event with slack of zero is critical as any delay in achieving that event will delay the completion date of the project.
  • 25. Critical Path Prof. Kanchana Devi 25 Event Number Latest Date Earliest Date Slack
  • 26. Activity Float Prof. Kanchana Devi 26  As events have slack, activities possess float.  Total float is the difference between earliest start and latest start ( or difference between earliest finish and latest finish)
  • 27. Activity Schedule showing total float for each activity Prof. Kanchana Devi 27
  • 28. Activity Schedule Prof. Kanchana Devi 28 Actvity Name Time Actvity Name Time 1-2 A 4 5-6 G 4 1-3 B 1 5-7 H 8 2-4 C 1 6-8 I 1 3-4 D 1 7-8 J 2 3-5 E 6 8-10 K 5 4-9 F 5 9-10 L 7
  • 29. Activity Network Diagram Prof. Kanchana Devi 29 1 2 3 5 4 7 6 8 109
  • 30. Solution Prof. Kanchana Devi 30 Activity Activity Name Normal Time E.S E.F L.S L.F Total Float 1-2 A 4 0 4 5 9 5 1-3 B 1 0 1 0 1 0 2-4 C 1 4 5 9 10 5 3-4 D 1 1 2 9 10 8 3-5 E 6 1 7 1 7 0 4-9 F 5 5 10 10 15 5 5-6 G 4 7 11 12 16 5 5-7 H 8 7 15 7 15 0 6-8 I 1 11 12 16 17 5 7-8 J 2 15 17 15 17 0 8-10 K 5 17 22 17 22 0 9-10 L 7 10 17 15 22 5
  • 31. Problem 1 Prof. Kanchana Devi 31  Draw activity network of the project.  Find total float of each activity. Activity Time inWeeks 1-2 20 1-3 25 2-3 10 2-4 12 3-4 5 3-5 10
  • 32. Problem 2 Prof. Kanchana Devi 32  Find out the critical path and total float. Activity Immediate Predecessor Time A 3 B 8 C 5 D A 9 E C 2 F B,E 6 H B,E 12 G D 11