SPM-UNIT III
RISK MANAGEMENT
MONITORING & CONTROL
Prof. Kanchana Devi
Introduction
 After scheduling , project will start and then
attention must be focused on progress.
 Progress needs monitoring
 What is happening
 Comparison of actual achievement against the schedule
 Revision of plans and schedules (wherever necessary)
2
Prof. Kanchana Devi
Creating Framework
Prof. Kanchana Devi
3
 Exercising control over a project and ensuring
that targets are met is a matter of regular
monitoring.
 Finding out what is happening and comparing
it with targets
 Re-planning also sometimes required
Project control cycle
Prof. Kanchana Devi
4
Responsibility
Prof. Kanchana Devi
5
 The overall responsibility
 Ensuring satisfactory progress on a project
 It is the role of “Steering Committee”, project
management board or Project Board.
Project Reporting Structure
Prof. Kanchana Devi
6
Reporting
Prof. Kanchana Devi
7
 Reporting may be
 Oral/Written
 Formal/Informal
 Regular/Ad-hoc
Assessing Progress
Prof. Kanchana Devi
8
 Information should be collected routinely
 Information should be objective and tangible
 Whether or not a particular report has been delivered
 Sometimes the assessment depends on
estimates of proportion of current activity that
has been completed
Setting Checkpoints
Prof. Kanchana Devi
9
 Necessary to set a series of check points in
the initial activity plan.
 Checkpoints may be:
 Regular(Monthly)
 Tied to specific events (production of report)
Collecting the Data
Prof. Kanchana Devi
10
 Rule: Manager will breakdown the long
activities into more controllable tasks of one or
two weeks.
 It is necessary to gather information about
partially completed activities, forecasts of how
much work is left to be completed.
Example of partial completion reporting
Prof. Kanchana Devi
11
Risk Reporting
Prof. Kanchana Devi
12
 One way to overcome the objections of partial
completion report is to avoid asking for
completion dates. (instead ask for likelihood of meeting the
target)
 Called “Traffic Light Method”.
Consists of following steps
Prof. Kanchana Devi
13
 Identify the key elements for assessment in a piece of
work
 Break these key elements into constituent element
 Assess each of the second level element on the scale
 Green for target,
 Amber for ‘not on target but recoverable’
 Red for ‘not on target and recoverable only with
difficulty’
 Review second level assessment to arrive at first level
 Review first level assessment to produce an overall
assessment
Example
Prof. Kanchana Devi
14
Visualizing Progress
Prof. Kanchana Devi
15
 Gantt Chart
 Slip Chart
 Ball Chart
 Timeline Chart
Cost Monitoring
Prof. Kanchana Devi
16
 Expenditure monitoring is an important
component of project control
 A project might be on time but only because
more money has been spent on activities than
originally budgeted
Tracking cumulative expenditure
Prof. Kanchana Devi
17
Cumulative Expenditure Chart
Prof. Kanchana Devi
18
Earned Value
Prof. Kanchana Devi
19
 Analysis is based on assigning a ‘value’ to each
task or work package based on expenditure
forecasts.
 The assigned value is the original budgeted cost
for the item and is known as the ‘baseline budget’
or ‘budgeted cost of work scheduled’(BCWS)
 The total value credited to a project at any point is
known as the ‘earned value’ or ‘budgeted cost of
the work performed’(BCWP)
Actual Cost
Prof. Kanchana Devi
20
 By recording the “Earned Value”, the actual
cost of each task can be collected as “Actual
Cost” or ACWP-Actual Cost of Work
Performed.
 There are three types of Variance:
 Schedule Variance(SV)
 Time Variance(TV)
 Cost Variance(CV)
Schedule Variance(SV)
Prof. Kanchana Devi
21
 The Schedule Variance is measured in
cost terms as EV-PV
 It indicates the degree to which the value
of the completed work differs from the
planned work.
Example:
Prof. Kanchana Devi
22
 A work with a PV of $40,000 should have
been completed by now. In fact, some of that
work has not been done so that the EV is only
$35,000. Calculate SV.
 SV=EV-PV
 35000-40000= - 5000
 A negative SV means the project is behind
schedule
Time Variance (TV)
Prof. Kanchana Devi
23
 Difference between the time when the
achievement of the current earned value was
planned to occur and the time now.
 Eg:
 The current EV should have been achieved in the
early part of month 9 and as the time now is end
of month 11, the TV is about -1.75 months from
graph.
Cost Variance (CV)
Prof. Kanchana Devi
24
 This is calculated as EV-AC.
 It indicates the difference between the earned
value or budgeted cost and the actual cost of the
completed work.
 Let Actual Cost for previous example is $ 55,000
 CV=35000-55000
 = -20000
 A negative CV means that the project is over cost
Prioritizing Monitoring
Prof. Kanchana Devi
25
 List of priorities
 Critical Path Activities
 Activities with no free float
 Activities with less than a specified float
 High Risk Activities
 Activities using critical resources

More Related Content

What's hot

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-introKanchana Devi
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementAhsan Rahim
 
Lecture6
Lecture6Lecture6
Lecture6soloeng
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimationtumetr1
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Kimmy Chen
 
Project communication management
Project communication  managementProject communication  management
Project communication managementyouness jabbar
 
Project Integration Management.pptx
Project Integration Management.pptxProject Integration Management.pptx
Project Integration Management.pptxMUST
 
Project communications management
Project communications managementProject communications management
Project communications managementSanket Gandhi
 

What's hot (20)

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-intro
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project Management
 
Lecture6
Lecture6Lecture6
Lecture6
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Project Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk ManagementProject Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk Management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimation
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project quality management.ppt msm
Project quality management.ppt msmProject quality management.ppt msm
Project quality management.ppt msm
 
Project communication management
Project communication  managementProject communication  management
Project communication management
 
Project Integration Management.pptx
Project Integration Management.pptxProject Integration Management.pptx
Project Integration Management.pptx
 
Unit 2 spm
Unit 2 spmUnit 2 spm
Unit 2 spm
 
Project communications management
Project communications managementProject communications management
Project communications management
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 

Viewers also liked

Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationKanchana Devi
 
Risk Management
Risk ManagementRisk Management
Risk Managementcgeorgeo
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pertKanchana Devi
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsKanchana Devi
 
List of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsList of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsTriCorps Technologies
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 
How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progressAsif A. Kabani
 
Bank risk management
Bank risk managementBank risk management
Bank risk managementAshima Thakur
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
Risk management in banks
Risk management in banksRisk management in banks
Risk management in bankseduCBA
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Managementguest484a666
 

Viewers also liked (20)

Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocation
 
Risk management
Risk managementRisk management
Risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pert
 
Spm chapter 8
Spm chapter 8Spm chapter 8
Spm chapter 8
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teams
 
List of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsList of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) Vendors
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progress
 
Bank risk management
Bank risk managementBank risk management
Bank risk management
 
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
Effective Risk Mgmt Kylucas (C) 2009 All Rights ReservedEffective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Risk management in banks
Risk management in banksRisk management in banks
Risk management in banks
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Management
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 

Similar to Spm unit iii-risk-monitoring & control1

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptadabotor7
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning IntroductionKanchana Devi
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..EngrMuhammadJavidNaw
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 

Similar to Spm unit iii-risk-monitoring & control1 (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning Introduction
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 

More from Kanchana Devi

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-Kanchana Devi
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-introKanchana Devi
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesKanchana Devi
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introKanchana Devi
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-Kanchana Devi
 
Spm software effort estimation
Spm software effort estimationSpm software effort estimation
Spm software effort estimationKanchana Devi
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm toolsKanchana Devi
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introductionKanchana Devi
 

More from Kanchana Devi (9)

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-intro
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilities
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-intro
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
Spm software effort estimation
Spm software effort estimationSpm software effort estimation
Spm software effort estimation
 
SPM Evaluation
SPM EvaluationSPM Evaluation
SPM Evaluation
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm tools
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introduction
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Spm unit iii-risk-monitoring & control1

  • 1. SPM-UNIT III RISK MANAGEMENT MONITORING & CONTROL Prof. Kanchana Devi
  • 2. Introduction  After scheduling , project will start and then attention must be focused on progress.  Progress needs monitoring  What is happening  Comparison of actual achievement against the schedule  Revision of plans and schedules (wherever necessary) 2 Prof. Kanchana Devi
  • 3. Creating Framework Prof. Kanchana Devi 3  Exercising control over a project and ensuring that targets are met is a matter of regular monitoring.  Finding out what is happening and comparing it with targets  Re-planning also sometimes required
  • 4. Project control cycle Prof. Kanchana Devi 4
  • 5. Responsibility Prof. Kanchana Devi 5  The overall responsibility  Ensuring satisfactory progress on a project  It is the role of “Steering Committee”, project management board or Project Board.
  • 7. Reporting Prof. Kanchana Devi 7  Reporting may be  Oral/Written  Formal/Informal  Regular/Ad-hoc
  • 8. Assessing Progress Prof. Kanchana Devi 8  Information should be collected routinely  Information should be objective and tangible  Whether or not a particular report has been delivered  Sometimes the assessment depends on estimates of proportion of current activity that has been completed
  • 9. Setting Checkpoints Prof. Kanchana Devi 9  Necessary to set a series of check points in the initial activity plan.  Checkpoints may be:  Regular(Monthly)  Tied to specific events (production of report)
  • 10. Collecting the Data Prof. Kanchana Devi 10  Rule: Manager will breakdown the long activities into more controllable tasks of one or two weeks.  It is necessary to gather information about partially completed activities, forecasts of how much work is left to be completed.
  • 11. Example of partial completion reporting Prof. Kanchana Devi 11
  • 12. Risk Reporting Prof. Kanchana Devi 12  One way to overcome the objections of partial completion report is to avoid asking for completion dates. (instead ask for likelihood of meeting the target)  Called “Traffic Light Method”.
  • 13. Consists of following steps Prof. Kanchana Devi 13  Identify the key elements for assessment in a piece of work  Break these key elements into constituent element  Assess each of the second level element on the scale  Green for target,  Amber for ‘not on target but recoverable’  Red for ‘not on target and recoverable only with difficulty’  Review second level assessment to arrive at first level  Review first level assessment to produce an overall assessment
  • 15. Visualizing Progress Prof. Kanchana Devi 15  Gantt Chart  Slip Chart  Ball Chart  Timeline Chart
  • 16. Cost Monitoring Prof. Kanchana Devi 16  Expenditure monitoring is an important component of project control  A project might be on time but only because more money has been spent on activities than originally budgeted
  • 19. Earned Value Prof. Kanchana Devi 19  Analysis is based on assigning a ‘value’ to each task or work package based on expenditure forecasts.  The assigned value is the original budgeted cost for the item and is known as the ‘baseline budget’ or ‘budgeted cost of work scheduled’(BCWS)  The total value credited to a project at any point is known as the ‘earned value’ or ‘budgeted cost of the work performed’(BCWP)
  • 20. Actual Cost Prof. Kanchana Devi 20  By recording the “Earned Value”, the actual cost of each task can be collected as “Actual Cost” or ACWP-Actual Cost of Work Performed.  There are three types of Variance:  Schedule Variance(SV)  Time Variance(TV)  Cost Variance(CV)
  • 21. Schedule Variance(SV) Prof. Kanchana Devi 21  The Schedule Variance is measured in cost terms as EV-PV  It indicates the degree to which the value of the completed work differs from the planned work.
  • 22. Example: Prof. Kanchana Devi 22  A work with a PV of $40,000 should have been completed by now. In fact, some of that work has not been done so that the EV is only $35,000. Calculate SV.  SV=EV-PV  35000-40000= - 5000  A negative SV means the project is behind schedule
  • 23. Time Variance (TV) Prof. Kanchana Devi 23  Difference between the time when the achievement of the current earned value was planned to occur and the time now.  Eg:  The current EV should have been achieved in the early part of month 9 and as the time now is end of month 11, the TV is about -1.75 months from graph.
  • 24. Cost Variance (CV) Prof. Kanchana Devi 24  This is calculated as EV-AC.  It indicates the difference between the earned value or budgeted cost and the actual cost of the completed work.  Let Actual Cost for previous example is $ 55,000  CV=35000-55000  = -20000  A negative CV means that the project is over cost
  • 25. Prioritizing Monitoring Prof. Kanchana Devi 25  List of priorities  Critical Path Activities  Activities with no free float  Activities with less than a specified float  High Risk Activities  Activities using critical resources