OBRA-C 2x660 MW
ASH HANDLING SYSTEM
PRESENTATION ON
Ash Handling System
IM&HCSD Silo
BA Hopper
O/F Tank& Pump
Coase Ash Tank&
Pump
Buffer Tower#2
Vacuum Pump
House#2
Vacuum Pump
House!#1
Buffer Tower#1
Ash Slurry Sump
House
Ash Compressor House
Clarifier & Chemical House
Ash Water Pump
House
Terminal Silo
APR-1
APR-2
APR-3 APR-4 APR-5
APR-6
APR-7
APR-8
APR-9
Ash Water Pump House
BAHP (AWPH to Bottom Ash Hoppe#01&02) Φ450NB
BALP (AWPH to Bottom Ash Hopper#01&02) Φ500NB
FAHP (AWPH to Collector Tank in Buffer Hopper
Tower#01&02) Φ500NB-550NB
HCSD flushing line to HCSD Silo Φ300NB
Flushing Water line (AWPH to Ash Slurry Sump) Φ400NB
TAC (To Air lock tank
Buffer Hopper#01)
Φ300NB
IAC Φ100NB-200NB (To Buffer
Hopper tower, BAH, HCSD silo
& Terminal Silo)
Vacuum line
(Vacuum Pump
to Collector
tank#01)
Φ200NB
Fluidizingair blower pipes (From air blower to ESP#01 fluidizing
pads, Buffer Hoppers#01) Φ100NB
From Bottom Ash Overflow Tank Φ300NB U#01 & 02
Pipe
Rack
(By
Arch
Dept)
F
L
W
P
H
C
S
D
W
P
H
C
S
D
W
P
H
C
S
D
W
P
F
A
H
P
F
A
H
P
B
A
L
P
B
A
L
P
B
A
L
P
B
A
H
P
B
A
H
P
B
A
H
P
APR-02
F
A
H
P
Clarifiers
B
A
Buffer
Hopper
Tower U#01
Pass-A
Buffer
Hopper
Tower U#01
Pass-B
Buffer
Hopper
Tower U#01
Pass-C
Buffer
Hopper
Tower U#01
Pass-D
Buffer
Hopper
Tower U#01
Pass-E
Buffer
Hopper
Tower U#01
Pass-F
E
S
P
-
F
E
S
P
-
F
E
S
P
-
E
E
S
P
-
E
E
S
P
-
D
E
S
P
-
D
E
S
P
-
C
E
S
P
-
C
E
S
P
-
B
E
S
P
-
B
E
S
P
-
A
E
S
P
-
A
BAH Bottom Ash Slurry Lines to
Ash Slurry Pump House
Φ200NB
Bottom Ash Overflow Lines
to Clarifier Φ300NB
Coarse Ash Lines to
ASPH Φ 350NB
TAC (To Air lock tank
Buffer Hopper#02)
Φ300NB
APR-
03
Sludge pit to Ash Slurry Sump Φ100NB
Ash
Slurry
Pump
House
Ash Water Sump
To IM/HCSD Silo & Terminal Silo
Φ400mm
Air Blower
Vacuum
Pumps
#01
TAC
TAC
TAC
TAC
IAC
IAC
TAC
TAC
TAC
TAC
APR-08 Ash Compressor House
APR-09
IAC
Mainten
ance Bay
Eco
Hoppers
APH
Hoppers
SCR
Hoppers
Eco Hoppers to
BAH Φ250NB
APH Hoppers to Coarse
Ash Tank Φ200NB
SCR Hoppers to Coarse
Ash Tank Φ400NB
Sludge
Pit
LP Seal water
pumps
Section 1-1 (Showing only for Unit#01 )
1) 12 lines of Φ200NB (Collector tank discharge to Ash Slurry Pump House)
2) 1 line of Φ550NB (FAHP)
3) 6 lines of Φ200NB (Vacuum Line)
4) 4 lines of Φ300NB (TAC line to ESP & air lock tank in buffer hopper tower)
5) 2 lines of Φ100NB (ESP drainpipes)
6) 4 lines of Φ300NB (FA line discharge)
7) 1 line of Φ500NB (BALP Pipes to BAH)
8) 1 line of Φ450NB (BAHP Pipes to BAH)
9) 2 lines of Φ350NB (Coarse Ash pipes to Ash Slurry Pump house)
10) 1 line of Φ300NB (BA Overflow tank to clarifier)
11) 3 lines of Φ200NB (BA discharge)
12) 1 line of Φ150NB (LP Seal water pipe)
Section 2-2
1) 1 line of Φ300NB (Bottom Ah Overflow pipes)
2) 2 lines of Φ400NB (Recovery water line)
3) 1 line of Φ4000NB (Flushing pipe)
4) 1 line of Φ550NB (FAHP)
5) 1 line of Φ500NB (BALP Pipes to BAH)
6) 1 line of Φ450NB (BAHP)
7) 1 line of Φ300NB (HCSD LP pipe)
8) 1 line of Φ550NB (Recovery water line)
9) 8 lines of Φ300NB (TAC line to air lock tank in buffer hopper tower)
10) 1 line of Φ200NB (IAC line)
11) 1 line of Φ100NB (Sludge pipe to Ash Slurry Sump)
12) 1 line of Φ100NB (Vacuum pump area drain line)
Section 3-3
1) 1 line of Φ550NB (Recovery water line)
2) 2 lines of Φ400NB (Recovery water line)
3) 1 line of Φ50NB (Seal water line)
4) 1 line of Φ100NB (DrainpipeSilo Area)
5) 1 line of Φ300NB (HCSD LP pipe)
6) 6 lines of Φ400NB (Ash disposal lines)
Ash Slurry lines Φ200NB X 12lines (from collector tank to Ash Slurry Sump)
Ash water recovery lines (2 lines of Φ400NB & 1
line of Φ550NB (from ash dyke area)
LP seal water lines to clinker grinder, BAOF pump, coarse ash
pump & vacuum pump sealing Φ150NB
LP seal water lines Φ150NB to BAHP seal water pump
1
1
2 2
3 3
Duct Support Structure
Buffer Hoppers to
IM/TM Silo (4lines
Φ300NB)
1 line of Φ100NB (Vacuum pump area drain line)
ASH HANDLING SYSTEM:
• BOTTOM ASH & ECONOMISER ASH COLLECTED IN BOTTOM ASH HOPPER AND
COARSE ASH COLLECTED IN APH AND SCR HOPPERS SHALL BE DISPOSED IN
SLURRY FORM TO ASH DYKE.
• FLY ASH COLLECTED IN ESP HOPPERS CAN BE DISPOSED IN BOTH IN SLURRY FORM
TO ASH DYKE THROUGH WET SYSTEM OR IN DRY FORM TO FLY ASH SILOS
THROUGH PRESSURE CONVEYING SYSTEM (DRY SYSTEM). THE WET SYSTEM
CONSISTS OF BOTH OPTIONS i.e LEAN SLURRY & HCSD SLURRY STSTEM.
• EQUIPMENT REQUIRED TO BE INSTALLED FOR CONTINUOUS OPERATION OF UNIT-1
IN WET MODE IS EXPLAINED IN FOLLOWING SLIDES
ASH HANDLING SYSTEM CONFIGURATION DIAGRAM
BOTTOM ASH COARSE ASH FLY ASH
BOTTOM ASH AND
ECONOMISER HOPPERS
ASH SLURRY SUMP
ASH DYKE
SCR HOPPERS
COARSE ASH TANK
APH HOPPERS ESP HOPPERS
COLLECTOR TANK BUFFER HOPPER
INTERMEDIATE SILOS
WET SYSTEM
DRY SYSTEM
HCSD SILOS
ASH DYKE TERMINAL SILOS
FLY ASH SYSTEM CONFIGURATION
ASH 191.68 TPH
ASH REMOVAL
CAPACITY -360 TPH
BUFFER
HOPPER
AIR LOCK TANK
COLLECTOR
TANK
ESP HOPPER
DRY SYSTEM
WET SYSTEM
- FLY ASH COLLECTED IN APH AND ESP HOPPERS FOR 8
HOURS SHALL BE REMOVED IN – 4.5 HOURS
- TOTAL FLY ASH COLLECTION IN 8 HOURS = 202.34X8=
1618.72 TONS
- FLY ASH REMOVAL CAPACITY = 1618.72/4.5 = 360.0TPH
- ESP IS DIVIDED INTO 6 STREAMS. HENCE REMOVAL
CAPACITY OF EACH STREAM IS 60 TPH
ASH REMOVAL
CAPACITY -360 TPH
ASH SLURRY PUMP
(1060m3/hr ≡ 𝟑𝟔𝟎TPH @ Fly Ash)
TO ASH DYKE
HCSD SLO
HCSD SLURRY PUMP`
TO ASH DYKE
IM SILO Terminal
SILO
ASH SLURRY SUMP
The design concept for Fly Ash to wet ash preparation
Back-up
For fly ash to wet ash preparation INDURE is using
wetting head and each wetting head having 22 nos.
high pressure nozzles with water flow-95
m.cu/hr.@35 MWC and dry capacity is 63 TPH
(Reference same system is running in LARA project
also)
The design concept for Fly Ash to wet ash preparation
Back-up
Elevation at Buffer hopper / collector tank (DP16004-XA00-90ETK-510077)
Wetting
Head
Collector Tank
20THK.Alloy CI LINER(400BHN)
ASH HANDLING SYSTEM
ASH HANDLING SYSTEM CAN BE BROADLY DIVIDED INTO THE FOLLOWING SUB SYSTEMS:
• BOTTOM ASH HANDLING SYSTEM
• COARSE ASH HANDLING SYSTEM
• FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM
• FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM
• ASH WATER SYSTEM
• ASH SLURRY DISPOSAL SYSTEM
• HCSD SLURRY DISPOSAL SYSTEM
• ASH WATER RECIRCULATION SYSTEM
• INSTRUMENT AIR SYSTEM
BOTTOM ECONOMISER & COARSE ASH HANDLING SYSTEM
(DRG. NO. DP16004-XG08-90ETA-510001, SH 1 OF 2)
ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P
& ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION
IN WET MODE OF UNIT 1
BOTTOM ECONOMISER & COARSE ASH HANDLING SYSTEM
(DRG. NO. DP16004-XG08-90ETA-510001, SH 2 OF 2)
ALL THE EQUIPMENT, PIPING AND
INSTRUMENTATION SHOWN IN THIS P &
ID SHALL BE COMPLETELY INSTALLED
FOR CONTINUOUS OPERATION IN WET
MODE
BOTTOM ASH AND COARSE ASH SYSTEM
• THE BOTTOM ASH AND CORASE ASH SYSTEM IS UNITISED.
• ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN IN PREVIOUS TWO SLIDES
SHALL BE COMPLETELY INSTALLED.
• MAJOR EQUIPMENT TO BE INSTALLED:
• BOTTOM ASH HOPPER COMPLETE WITH EQUIPMENT, WATER PIPING, VALVES AND
INSTRUMENTATION
• BOTTOM ASH SLURRY PIPE LINES WITH VALVES AND INSTRUMENTAION UPTO ASH SLURRY SUMP
• BOTTOM ASH OVERFLOW TANK
• BOTTOM ASH OVERFLOW PUMPS WITH PIPING, VALVES AND INSTRUMENTATION
• DRAIN JET PUMPS, PIPING, VALVES AND INSTRUMENTION
• ECONOMISER HOPPERS: FLUSHING APPARATUS, WATER AND SLURRY PIPING, VALVES AND
INSTRUMENTATION
• APH HOPPERS, SCR HOPPERS: FEEDER EJECTORS, WATER AND SLURRY PIPING, VALVES AND
INSTRUMENTATION
• COARSE ASH TANK
• COARSE ASH SLURRY PUMPS WITH PIPING, VALVES AND INSTRUMENTATION
FLY ASH VACUUM CONVEYING & WET CONVEYING SYSTEM
(DRG. NO. DP16004-XG08-90ETK-510002, SH 1 OF 2)
ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P
& ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION
IN WET MODE
FLY ASH VACUUM CONVEYING & WET CONVEYING SYSTEM
(DRG. NO. DP16004-XG08-90ETK-510002, SH 2 OF 2)
ALL THE EQUIPMENT, PIPING AND
INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE
COMPLETELY INSTALLED FOR CONTINUOUS
OPERATION IN WET MODE
FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM
• THE FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM IS ALSO UNITISED.
• FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO WETTING HEAD INSTALLED AT
COLLECTOR TANK OR BUFFER HOPPER BYMEANS OF VACUUM CONVEYING SYSTEM AND IN WETTING
HEAD FLY ASH MIXES WITH FAHP WATER AND DISPOSED IN SLURRY FORM TO ASH SLURRY SUMP FOR
FURTHER DISPOSAL TO ASH DYKE
• ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN IN PREVIOUS TWO SLIDES SHALL
BE COMPLETELY INSTALLED.
• MAJOR EQUIPMENT TO BE INSTALLED:
• ADOPTER, ISOLATION VALVES, MATERIAL HANDLING VALVES, CI PIPE LINE ALONG WITH ACI FITTINGS,
BRANCH SEGREGATING VALVES ETC FROM ESP AND APH HOPPERS TO COLLECTOR TANK/ BUFFER
HOPPER COLLECTOR TANK AND BUFFER HOPPER TOWER STRUCTURE
• COLLECTOR TANK, WETTING HEAD AND TAIL PIPE AND AIR WASHER
• FAHP WATER PIPE WORK ALONG WITH VALVES AND INSTUMENTATION UP TO WETTING HEAD, AIR WASHER
AND JET NOZZLES.
• INSTRUMENTATION PIPE WORK TO VARIOUS PNEUMATIC OPERATED VALVES ALONG WITH VALVES,
INSTRUMENTATION
• VACUUM PUMPS AND VACUUM AIR PIPE WORK FROM VACUUM PUMPS TO AIR WASHER/ BUFFER HOPPER
ALONG WITH VALVES
• SEAL WATER AND DRAIN WATER PIPING FOR VACUUM PUMPS
• FLY ASH SLURRY PIPE WORK FROM COLLECTOR TANK DISCHARGE TO ASH SLURRY SUMP
• ESP/BH FLUIDISING AIR BLOWERS AND HEATERS, PIPE WORK WITH VALVES FROM BLOWERS TO ESP/ APH
HOPPERS
FLY ASH PRESSURE CONVEYING SYSTEM
(DRG. NO. DP16004-XG08-90ETG-510003, SH 1 OF 2)
VACUUM AIR AND FLY ASH TRANSPORT PIPE WORK AND
VALVES IN THE BLUE BOX SHALL BE INSTALLED FOR
CONTINUOUS OPERATION IN WET MODE
FLY ASH PRESSURE CONVEYING SYSTEM(IM SILO)
(DRG. NO. DP16004-XG08-90ETG-510004, SH 2 OF 2)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION AS SHOWN ARE NOT
NECESSARY TO BE INSTALLED FOR WET
MODE OPERATION.
FLY ASH PRESSURE CONVEYING SYSTEM(TERMINAL SILO)
(DRG. NO. DP16004-XG08-90ETG-510004, SH 1 OF 2)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION AS SHOWN ARE NOT
NECESSARY TO BE INSTALLED FOR WET
MODE OPERATION.
FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM
• THE FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM IS UNITISED UP TO HSCD,
INTERMEDIATE & TERMINAL SILOS.
• FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO WETTING HEAD
INSTALLED AT COLLECTOR TANK OR BUFFER HOPPER BYMEANS OF VACUUM CONVEYING
SYSTEM AND FROM BUFFER HOPPER, FLY ASH IS TRANSPORTED TO FLY ASH SILOS BYMEANS
OF COMPRESSED AIR SUPPLIED BY TRANSPORT AIR COMPRESSORS.
• VACUUM CONVEYING SYSTEM FOR EXTRACTION AND TRANSPORTATION OF FLY ASH TO
BUFFER HOPPER AND COLLECTOR TANK IS COMMON
• VACUUM AIR AND FLY ASH TRANSPORT PIPE WORK AND VALVES HIGHLIGHTED IN THE BLUE
BOX SHALL BE INSTALLED FOR CONTINUOUS OPERATION OF FLY ASH SYSTEM IN WET MODE.
• INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED ISOLATION VALVES ON VACUUM AIR
AND FLY ASH TRANSPORT PIPE LINES `
FLY ASH PRESSURE CONVEYING SYSTEM(HCSD SILO)
(DRG. NO. DP16004-XG08-90ETA-510007)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION AS SHOWN ARE NOT
NECESSARY TO BE INSTALLED FOR WET
MODE OPERATION
HCSD SYSTEM
• THE FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM IS UNITISED
UP TO HSCD SILOS.
• FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO
WETTING HEAD INSTALLED AT COLLECTOR TANK OR BUFFER HOPPER
BYMEANS OF VACUUM CONVEYING SYSTEM AND FROM BUFFER HOPPER, FLY
ASH IS TRANSPORTED TO HCSD SILOS BYMEANS OF COMPRESSED AIR
SUPPLIED BY TRANSPORT AIR COMPRESSORS.
• EACH HCSD SILO CONSISTS OF HYDROMIX DUST CONDITIONER, MIXING TANK,
ETC
• THE FLYASH IS DISPOSED OFF IN WET MODE BY BOOSTER/ CHARGE PUMP AND
HCSD PUMP. UPTO ASH DYKE.
ASH SLURRY & ASH WATER SYSTEM
(DRG. NO. DP16004-XG08-90ETN-510006, SH 1 OF 2)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION IN THE BLUE BOX
SHALL BE INSTALLED FOR CONTINUOUS
OPERATION IN WET MODE OF UNIT 1
ASH WATER SYSTEM
• ASH WATER SYSTEM IS COMMON FOR BOTH UNITS.
• FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING
EQUIPEMNT AND PIPE WORK, HIGHLIGHTED IN THE BLUE BOXES SHALL BE
INSTALLED.
• BALP WATER PUMPS – 2 NOS (1W+1S)
• BAHP WATER PUMPS – 2 NOS (1W+1S)
• BAHP SEAL WATER PUMPS – 2 NOS (1W+1S)
• FAHP WATER PUMPS – 2 NOS (1W+1S)
• FLUSHING WATER PUMP – 1 NO
• COMPLETE PIPE WORK FROM THE ABOVE PUMPS TO RESPECTIVE
CONSUMERS ALONG WITH VALVES.
• INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED VALVES
• ASH WATER SUMP MAKEUP LINES FROM VARIOUS SOURCES
ASH SLURRY & SSH WATER SYSTEM
(DRG. NO. DP16004-XG08-90ETN-510006, SH 2 OF 2)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION IN THE RED BOXES ARE
NOT NECESSARY TO BE INSTALLED FOR
CONTINUOUS OPERATION IN WET MODE OF
UNIT 1.
ASH SLURRY DISPOSAL SYSTEM
• ASH SLURRY DISPOSAL SYSTEM IS COMMON FOR BOTH UNITS.
• FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING
EQUIPEMNT AND PIPE WORK SHALL BE INSTALLED.
• ASH SLURRY PUMPS – 4 NOS I.E 2 SERIES (1SERIES W + 1 SERIES S)
• DRAIN PUMPS – 2 NOS (1W+1S)
• ASH SLURRY DISPOSAL PIPE WORK FROM THE ABOVE PUMPS TO ASH DYKE
ALONG WITH VALVES.
• SEAL WATER AND COOLING WATER LINES ALONG WITH VALVES AND
INSTUMENTATION
• INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED VALVES
• ASH SLURRY SUMP FLUSHING/ MAKEUP WATER LINES FROM VARIOUS SOURCES
INSTRUMENT AIR SYSTEM
(DRG. NO. DP16004-XG08-90ETY-510009)
ALL THE EQUIPMENT, PIPING WORK AND
INSTRUMENTATION IN THE RED BOXES ARE
NOT NECESSARY TO BE INSTALLED FOR
CONTINUOUS OPERATION IN WET MODE OF
UNIT 1.
INSTRUMENT AIR SYSTEM
• INSTRUMENT AIR SYSTEM IS COMMON FOR BOTH UNITS.
• FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING EQUIPEMNT AND
PIPE WORK, HIGHLIGHTED IN RED COLOUR ARE NOT NECESSARY TO BE INSTALLED.
• INSTRUMENT AIR COMPRESSORS – 2 NOS (1W+1S)
• INSTRUMENT AIR DRYER - 2 NOS (1W+1S)
• AIR RECEIVERS – 2 NOS (1W+1S)
• INSTRUMENR AIR PIPE WORK VARIOUS PNEUMATIC OPERATED VALVES WITH VALVES
AND FITTINGS
• COOLING WATER LINES WITH VALVES AND INSTUMENTATION
ASH WATER CLARIFIER SYSTEM
(DRG. NO. DP16004-XG08-90ETN-510008)
ALL THE EQUIPMENT, PIPING AND
INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE
COMPLETELY INSTALLED FOR CONTINUOUS
OPERATION IN WET MODE
ASH WATER RECIRCULATION SYSTEM
• ASH WATER RECIRCULATION SYSTEM IS COMMON FOR BOTH UNITS.
• ALUM AND LIME DOSING TANKS, PUMPS, PIPE WORK WITH VALVES AND INSTRUMENTATION IS
REQUIRED TO BE INSTALLED TO TREAT BOTTOM ASH OVERFLOW AND DRAIN WATER COLLECTED IN
CLARIFIER.
• COMPLETE STILLING CHAMBER, CLARIFIER, BRIDGE MECHANSM, SLUDGE PUMPS, PIPE WORK WITH
VALVES AND INSTRUMENTAION IS REQUIRED TO BE INSTALLED
BOTTOM ASH HOPPER
EQUIPMENT
Obra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptx

More Related Content

What's hot

Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing systemAshvani Shukla
 
Condensate system
Condensate systemCondensate system
Condensate systemRAVI PAL SINGH
 
Control valves for thermal power plants
Control valves for thermal power plantsControl valves for thermal power plants
Control valves for thermal power plantsSHIVAJI CHOUDHURY
 
BoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationBoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationHashim Hasnain Hadi
 
Boi_5_ST-2 Ball and Tube Mill .ppt
Boi_5_ST-2 Ball and Tube Mill  .pptBoi_5_ST-2 Ball and Tube Mill  .ppt
Boi_5_ST-2 Ball and Tube Mill .pptTravelTechnology1
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump Vundavilli Gautham
 
coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser Rhitesh Gupta
 
Heat recovery steam generator
Heat recovery steam generatorHeat recovery steam generator
Heat recovery steam generatorumar farooq
 
Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheaterdishti7
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and FillShad Edwards
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Compressor
CompressorCompressor
CompressorARUN VISHNU
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
condensate system
condensate systemcondensate system
condensate systemvikrantdesh
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANTAditya Anand
 
Steam turbine
Steam turbineSteam turbine
Steam turbineAbdul Rahim
 

What's hot (20)

Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Control valves for thermal power plants
Control valves for thermal power plantsControl valves for thermal power plants
Control valves for thermal power plants
 
BoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationBoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & Classification
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 
Boi_5_ST-2 Ball and Tube Mill .ppt
Boi_5_ST-2 Ball and Tube Mill  .pptBoi_5_ST-2 Ball and Tube Mill  .ppt
Boi_5_ST-2 Ball and Tube Mill .ppt
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser
 
200 mw FSSS
200 mw FSSS200 mw FSSS
200 mw FSSS
 
Heat recovery steam generator
Heat recovery steam generatorHeat recovery steam generator
Heat recovery steam generator
 
Economiser & air preheater
Economiser & air preheaterEconomiser & air preheater
Economiser & air preheater
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and Fill
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Compressor
CompressorCompressor
Compressor
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
condensate system
condensate systemcondensate system
condensate system
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANT
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 

Similar to Obra Presentaton Ash Handling Sysytem 28032023.pptx

ASH HANDLING PRESENTATION ON POWER PLANT
ASH HANDLING PRESENTATION ON POWER PLANTASH HANDLING PRESENTATION ON POWER PLANT
ASH HANDLING PRESENTATION ON POWER PLANTneerajshopping
 
Coal & RHA overview-on-ash-handling-system.ppt
Coal & RHA overview-on-ash-handling-system.pptCoal & RHA overview-on-ash-handling-system.ppt
Coal & RHA overview-on-ash-handling-system.pptMadan Karki
 
ESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxKhemantOd
 
Water-Powered Water Pumping Systems for Livestock Watering
Water-Powered Water Pumping Systems for Livestock WateringWater-Powered Water Pumping Systems for Livestock Watering
Water-Powered Water Pumping Systems for Livestock WateringFifi62z
 
Steam blowing stages before turbine rolling
Steam blowing stages before turbine rollingSteam blowing stages before turbine rolling
Steam blowing stages before turbine rollingabhinav kumar
 
Turbo generator & its auxiliaries
Turbo generator & its auxiliariesTurbo generator & its auxiliaries
Turbo generator & its auxiliariesarvind singh rathore
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewVladimir Popovic
 
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIHIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIwina kauzi
 
Turbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptTurbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptNarhari1
 
500 mw utility boiler ppt
500 mw utility boiler ppt500 mw utility boiler ppt
500 mw utility boiler pptandyappan1
 
Pompa.pptx
Pompa.pptxPompa.pptx
Pompa.pptxgaluh311517
 
Home Built Hydraulic Ram Pumps - NW Independent Power Resources
Home Built Hydraulic Ram Pumps - NW Independent Power ResourcesHome Built Hydraulic Ram Pumps - NW Independent Power Resources
Home Built Hydraulic Ram Pumps - NW Independent Power ResourcesFatin62c
 
Boiler feed and pump sizing c-b and grundfos july 2016(1)
Boiler feed and pump sizing   c-b and grundfos july 2016(1)Boiler feed and pump sizing   c-b and grundfos july 2016(1)
Boiler feed and pump sizing c-b and grundfos july 2016(1)lorenzo Monasca
 

Similar to Obra Presentaton Ash Handling Sysytem 28032023.pptx (20)

ASH HANDLING PRESENTATION ON POWER PLANT
ASH HANDLING PRESENTATION ON POWER PLANTASH HANDLING PRESENTATION ON POWER PLANT
ASH HANDLING PRESENTATION ON POWER PLANT
 
Coal & RHA overview-on-ash-handling-system.ppt
Coal & RHA overview-on-ash-handling-system.pptCoal & RHA overview-on-ash-handling-system.ppt
Coal & RHA overview-on-ash-handling-system.ppt
 
ESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptx
 
Water-Powered Water Pumping Systems for Livestock Watering
Water-Powered Water Pumping Systems for Livestock WateringWater-Powered Water Pumping Systems for Livestock Watering
Water-Powered Water Pumping Systems for Livestock Watering
 
Steam blowing stages before turbine rolling
Steam blowing stages before turbine rollingSteam blowing stages before turbine rolling
Steam blowing stages before turbine rolling
 
Turbo generator & its auxiliaries
Turbo generator & its auxiliariesTurbo generator & its auxiliaries
Turbo generator & its auxiliaries
 
HVAC Pumps and End Suction Pumps
HVAC Pumps and End Suction PumpsHVAC Pumps and End Suction Pumps
HVAC Pumps and End Suction Pumps
 
Piping system
Piping systemPiping system
Piping system
 
steam_blowing.pdf
steam_blowing.pdfsteam_blowing.pdf
steam_blowing.pdf
 
Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12
 
Plumbing training
Plumbing training Plumbing training
Plumbing training
 
Lanchkhuti WS Project Overview
Lanchkhuti WS Project OverviewLanchkhuti WS Project Overview
Lanchkhuti WS Project Overview
 
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIHIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
 
Turbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptTurbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.ppt
 
Steam boiler
Steam boilerSteam boiler
Steam boiler
 
500 mw utility boiler ppt
500 mw utility boiler ppt500 mw utility boiler ppt
500 mw utility boiler ppt
 
MBBR PRESENTATION
MBBR PRESENTATIONMBBR PRESENTATION
MBBR PRESENTATION
 
Pompa.pptx
Pompa.pptxPompa.pptx
Pompa.pptx
 
Home Built Hydraulic Ram Pumps - NW Independent Power Resources
Home Built Hydraulic Ram Pumps - NW Independent Power ResourcesHome Built Hydraulic Ram Pumps - NW Independent Power Resources
Home Built Hydraulic Ram Pumps - NW Independent Power Resources
 
Boiler feed and pump sizing c-b and grundfos july 2016(1)
Boiler feed and pump sizing   c-b and grundfos july 2016(1)Boiler feed and pump sizing   c-b and grundfos july 2016(1)
Boiler feed and pump sizing c-b and grundfos july 2016(1)
 

More from mrujjavalsinghvarana

welding procedure-P F number And WPS.ppt
welding procedure-P  F number And WPS.pptwelding procedure-P  F number And WPS.ppt
welding procedure-P F number And WPS.pptmrujjavalsinghvarana
 
Switch Yard PPT By Deepak raipptx
Switch Yard PPT By Deepak raipptxSwitch Yard PPT By Deepak raipptx
Switch Yard PPT By Deepak raipptxmrujjavalsinghvarana
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxmrujjavalsinghvarana
 

More from mrujjavalsinghvarana (6)

GEN PPT.pptx
GEN PPT.pptxGEN PPT.pptx
GEN PPT.pptx
 
welding procedure-P F number And WPS.ppt
welding procedure-P  F number And WPS.pptwelding procedure-P  F number And WPS.ppt
welding procedure-P F number And WPS.ppt
 
Switch Yard PPT By Deepak raipptx
Switch Yard PPT By Deepak raipptxSwitch Yard PPT By Deepak raipptx
Switch Yard PPT By Deepak raipptx
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
 
WQT.pptx
WQT.pptxWQT.pptx
WQT.pptx
 
ROAD WORK ppt RCC.pptx
ROAD WORK ppt RCC.pptxROAD WORK ppt RCC.pptx
ROAD WORK ppt RCC.pptx
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 

Obra Presentaton Ash Handling Sysytem 28032023.pptx

  • 1. OBRA-C 2x660 MW ASH HANDLING SYSTEM PRESENTATION ON Ash Handling System
  • 2. IM&HCSD Silo BA Hopper O/F Tank& Pump Coase Ash Tank& Pump Buffer Tower#2 Vacuum Pump House#2 Vacuum Pump House!#1 Buffer Tower#1 Ash Slurry Sump House Ash Compressor House Clarifier & Chemical House Ash Water Pump House Terminal Silo APR-1 APR-2 APR-3 APR-4 APR-5 APR-6 APR-7 APR-8 APR-9
  • 3. Ash Water Pump House BAHP (AWPH to Bottom Ash Hoppe#01&02) Φ450NB BALP (AWPH to Bottom Ash Hopper#01&02) Φ500NB FAHP (AWPH to Collector Tank in Buffer Hopper Tower#01&02) Φ500NB-550NB HCSD flushing line to HCSD Silo Φ300NB Flushing Water line (AWPH to Ash Slurry Sump) Φ400NB TAC (To Air lock tank Buffer Hopper#01) Φ300NB IAC Φ100NB-200NB (To Buffer Hopper tower, BAH, HCSD silo & Terminal Silo) Vacuum line (Vacuum Pump to Collector tank#01) Φ200NB Fluidizingair blower pipes (From air blower to ESP#01 fluidizing pads, Buffer Hoppers#01) Φ100NB From Bottom Ash Overflow Tank Φ300NB U#01 & 02 Pipe Rack (By Arch Dept) F L W P H C S D W P H C S D W P H C S D W P F A H P F A H P B A L P B A L P B A L P B A H P B A H P B A H P APR-02 F A H P Clarifiers B A Buffer Hopper Tower U#01 Pass-A Buffer Hopper Tower U#01 Pass-B Buffer Hopper Tower U#01 Pass-C Buffer Hopper Tower U#01 Pass-D Buffer Hopper Tower U#01 Pass-E Buffer Hopper Tower U#01 Pass-F E S P - F E S P - F E S P - E E S P - E E S P - D E S P - D E S P - C E S P - C E S P - B E S P - B E S P - A E S P - A BAH Bottom Ash Slurry Lines to Ash Slurry Pump House Φ200NB Bottom Ash Overflow Lines to Clarifier Φ300NB Coarse Ash Lines to ASPH Φ 350NB TAC (To Air lock tank Buffer Hopper#02) Φ300NB APR- 03 Sludge pit to Ash Slurry Sump Φ100NB Ash Slurry Pump House Ash Water Sump To IM/HCSD Silo & Terminal Silo Φ400mm Air Blower Vacuum Pumps #01 TAC TAC TAC TAC IAC IAC TAC TAC TAC TAC APR-08 Ash Compressor House APR-09 IAC Mainten ance Bay Eco Hoppers APH Hoppers SCR Hoppers Eco Hoppers to BAH Φ250NB APH Hoppers to Coarse Ash Tank Φ200NB SCR Hoppers to Coarse Ash Tank Φ400NB Sludge Pit LP Seal water pumps Section 1-1 (Showing only for Unit#01 ) 1) 12 lines of Φ200NB (Collector tank discharge to Ash Slurry Pump House) 2) 1 line of Φ550NB (FAHP) 3) 6 lines of Φ200NB (Vacuum Line) 4) 4 lines of Φ300NB (TAC line to ESP & air lock tank in buffer hopper tower) 5) 2 lines of Φ100NB (ESP drainpipes) 6) 4 lines of Φ300NB (FA line discharge) 7) 1 line of Φ500NB (BALP Pipes to BAH) 8) 1 line of Φ450NB (BAHP Pipes to BAH) 9) 2 lines of Φ350NB (Coarse Ash pipes to Ash Slurry Pump house) 10) 1 line of Φ300NB (BA Overflow tank to clarifier) 11) 3 lines of Φ200NB (BA discharge) 12) 1 line of Φ150NB (LP Seal water pipe) Section 2-2 1) 1 line of Φ300NB (Bottom Ah Overflow pipes) 2) 2 lines of Φ400NB (Recovery water line) 3) 1 line of Φ4000NB (Flushing pipe) 4) 1 line of Φ550NB (FAHP) 5) 1 line of Φ500NB (BALP Pipes to BAH) 6) 1 line of Φ450NB (BAHP) 7) 1 line of Φ300NB (HCSD LP pipe) 8) 1 line of Φ550NB (Recovery water line) 9) 8 lines of Φ300NB (TAC line to air lock tank in buffer hopper tower) 10) 1 line of Φ200NB (IAC line) 11) 1 line of Φ100NB (Sludge pipe to Ash Slurry Sump) 12) 1 line of Φ100NB (Vacuum pump area drain line) Section 3-3 1) 1 line of Φ550NB (Recovery water line) 2) 2 lines of Φ400NB (Recovery water line) 3) 1 line of Φ50NB (Seal water line) 4) 1 line of Φ100NB (DrainpipeSilo Area) 5) 1 line of Φ300NB (HCSD LP pipe) 6) 6 lines of Φ400NB (Ash disposal lines) Ash Slurry lines Φ200NB X 12lines (from collector tank to Ash Slurry Sump) Ash water recovery lines (2 lines of Φ400NB & 1 line of Φ550NB (from ash dyke area) LP seal water lines to clinker grinder, BAOF pump, coarse ash pump & vacuum pump sealing Φ150NB LP seal water lines Φ150NB to BAHP seal water pump 1 1 2 2 3 3 Duct Support Structure Buffer Hoppers to IM/TM Silo (4lines Φ300NB) 1 line of Φ100NB (Vacuum pump area drain line)
  • 4. ASH HANDLING SYSTEM: • BOTTOM ASH & ECONOMISER ASH COLLECTED IN BOTTOM ASH HOPPER AND COARSE ASH COLLECTED IN APH AND SCR HOPPERS SHALL BE DISPOSED IN SLURRY FORM TO ASH DYKE. • FLY ASH COLLECTED IN ESP HOPPERS CAN BE DISPOSED IN BOTH IN SLURRY FORM TO ASH DYKE THROUGH WET SYSTEM OR IN DRY FORM TO FLY ASH SILOS THROUGH PRESSURE CONVEYING SYSTEM (DRY SYSTEM). THE WET SYSTEM CONSISTS OF BOTH OPTIONS i.e LEAN SLURRY & HCSD SLURRY STSTEM. • EQUIPMENT REQUIRED TO BE INSTALLED FOR CONTINUOUS OPERATION OF UNIT-1 IN WET MODE IS EXPLAINED IN FOLLOWING SLIDES
  • 5. ASH HANDLING SYSTEM CONFIGURATION DIAGRAM BOTTOM ASH COARSE ASH FLY ASH BOTTOM ASH AND ECONOMISER HOPPERS ASH SLURRY SUMP ASH DYKE SCR HOPPERS COARSE ASH TANK APH HOPPERS ESP HOPPERS COLLECTOR TANK BUFFER HOPPER INTERMEDIATE SILOS WET SYSTEM DRY SYSTEM HCSD SILOS ASH DYKE TERMINAL SILOS
  • 6. FLY ASH SYSTEM CONFIGURATION ASH 191.68 TPH ASH REMOVAL CAPACITY -360 TPH BUFFER HOPPER AIR LOCK TANK COLLECTOR TANK ESP HOPPER DRY SYSTEM WET SYSTEM - FLY ASH COLLECTED IN APH AND ESP HOPPERS FOR 8 HOURS SHALL BE REMOVED IN – 4.5 HOURS - TOTAL FLY ASH COLLECTION IN 8 HOURS = 202.34X8= 1618.72 TONS - FLY ASH REMOVAL CAPACITY = 1618.72/4.5 = 360.0TPH - ESP IS DIVIDED INTO 6 STREAMS. HENCE REMOVAL CAPACITY OF EACH STREAM IS 60 TPH ASH REMOVAL CAPACITY -360 TPH ASH SLURRY PUMP (1060m3/hr ≡ 𝟑𝟔𝟎TPH @ Fly Ash) TO ASH DYKE HCSD SLO HCSD SLURRY PUMP` TO ASH DYKE IM SILO Terminal SILO ASH SLURRY SUMP
  • 7. The design concept for Fly Ash to wet ash preparation Back-up For fly ash to wet ash preparation INDURE is using wetting head and each wetting head having 22 nos. high pressure nozzles with water flow-95 m.cu/hr.@35 MWC and dry capacity is 63 TPH (Reference same system is running in LARA project also)
  • 8. The design concept for Fly Ash to wet ash preparation Back-up Elevation at Buffer hopper / collector tank (DP16004-XA00-90ETK-510077) Wetting Head Collector Tank 20THK.Alloy CI LINER(400BHN)
  • 9. ASH HANDLING SYSTEM ASH HANDLING SYSTEM CAN BE BROADLY DIVIDED INTO THE FOLLOWING SUB SYSTEMS: • BOTTOM ASH HANDLING SYSTEM • COARSE ASH HANDLING SYSTEM • FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM • FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM • ASH WATER SYSTEM • ASH SLURRY DISPOSAL SYSTEM • HCSD SLURRY DISPOSAL SYSTEM • ASH WATER RECIRCULATION SYSTEM • INSTRUMENT AIR SYSTEM
  • 10. BOTTOM ECONOMISER & COARSE ASH HANDLING SYSTEM (DRG. NO. DP16004-XG08-90ETA-510001, SH 1 OF 2) ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION IN WET MODE OF UNIT 1
  • 11. BOTTOM ECONOMISER & COARSE ASH HANDLING SYSTEM (DRG. NO. DP16004-XG08-90ETA-510001, SH 2 OF 2) ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION IN WET MODE
  • 12. BOTTOM ASH AND COARSE ASH SYSTEM • THE BOTTOM ASH AND CORASE ASH SYSTEM IS UNITISED. • ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN IN PREVIOUS TWO SLIDES SHALL BE COMPLETELY INSTALLED. • MAJOR EQUIPMENT TO BE INSTALLED: • BOTTOM ASH HOPPER COMPLETE WITH EQUIPMENT, WATER PIPING, VALVES AND INSTRUMENTATION • BOTTOM ASH SLURRY PIPE LINES WITH VALVES AND INSTRUMENTAION UPTO ASH SLURRY SUMP • BOTTOM ASH OVERFLOW TANK • BOTTOM ASH OVERFLOW PUMPS WITH PIPING, VALVES AND INSTRUMENTATION • DRAIN JET PUMPS, PIPING, VALVES AND INSTRUMENTION • ECONOMISER HOPPERS: FLUSHING APPARATUS, WATER AND SLURRY PIPING, VALVES AND INSTRUMENTATION • APH HOPPERS, SCR HOPPERS: FEEDER EJECTORS, WATER AND SLURRY PIPING, VALVES AND INSTRUMENTATION • COARSE ASH TANK • COARSE ASH SLURRY PUMPS WITH PIPING, VALVES AND INSTRUMENTATION
  • 13. FLY ASH VACUUM CONVEYING & WET CONVEYING SYSTEM (DRG. NO. DP16004-XG08-90ETK-510002, SH 1 OF 2) ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION IN WET MODE
  • 14. FLY ASH VACUUM CONVEYING & WET CONVEYING SYSTEM (DRG. NO. DP16004-XG08-90ETK-510002, SH 2 OF 2) ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION IN WET MODE
  • 15. FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM • THE FLY ASH HANDLING SYSTEM – VACUUM CONVEYING SYSTEM IS ALSO UNITISED. • FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO WETTING HEAD INSTALLED AT COLLECTOR TANK OR BUFFER HOPPER BYMEANS OF VACUUM CONVEYING SYSTEM AND IN WETTING HEAD FLY ASH MIXES WITH FAHP WATER AND DISPOSED IN SLURRY FORM TO ASH SLURRY SUMP FOR FURTHER DISPOSAL TO ASH DYKE • ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN IN PREVIOUS TWO SLIDES SHALL BE COMPLETELY INSTALLED. • MAJOR EQUIPMENT TO BE INSTALLED: • ADOPTER, ISOLATION VALVES, MATERIAL HANDLING VALVES, CI PIPE LINE ALONG WITH ACI FITTINGS, BRANCH SEGREGATING VALVES ETC FROM ESP AND APH HOPPERS TO COLLECTOR TANK/ BUFFER HOPPER COLLECTOR TANK AND BUFFER HOPPER TOWER STRUCTURE • COLLECTOR TANK, WETTING HEAD AND TAIL PIPE AND AIR WASHER • FAHP WATER PIPE WORK ALONG WITH VALVES AND INSTUMENTATION UP TO WETTING HEAD, AIR WASHER AND JET NOZZLES. • INSTRUMENTATION PIPE WORK TO VARIOUS PNEUMATIC OPERATED VALVES ALONG WITH VALVES, INSTRUMENTATION • VACUUM PUMPS AND VACUUM AIR PIPE WORK FROM VACUUM PUMPS TO AIR WASHER/ BUFFER HOPPER ALONG WITH VALVES • SEAL WATER AND DRAIN WATER PIPING FOR VACUUM PUMPS • FLY ASH SLURRY PIPE WORK FROM COLLECTOR TANK DISCHARGE TO ASH SLURRY SUMP • ESP/BH FLUIDISING AIR BLOWERS AND HEATERS, PIPE WORK WITH VALVES FROM BLOWERS TO ESP/ APH HOPPERS
  • 16. FLY ASH PRESSURE CONVEYING SYSTEM (DRG. NO. DP16004-XG08-90ETG-510003, SH 1 OF 2) VACUUM AIR AND FLY ASH TRANSPORT PIPE WORK AND VALVES IN THE BLUE BOX SHALL BE INSTALLED FOR CONTINUOUS OPERATION IN WET MODE
  • 17. FLY ASH PRESSURE CONVEYING SYSTEM(IM SILO) (DRG. NO. DP16004-XG08-90ETG-510004, SH 2 OF 2) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN ARE NOT NECESSARY TO BE INSTALLED FOR WET MODE OPERATION.
  • 18. FLY ASH PRESSURE CONVEYING SYSTEM(TERMINAL SILO) (DRG. NO. DP16004-XG08-90ETG-510004, SH 1 OF 2) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN ARE NOT NECESSARY TO BE INSTALLED FOR WET MODE OPERATION.
  • 19. FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM • THE FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM IS UNITISED UP TO HSCD, INTERMEDIATE & TERMINAL SILOS. • FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO WETTING HEAD INSTALLED AT COLLECTOR TANK OR BUFFER HOPPER BYMEANS OF VACUUM CONVEYING SYSTEM AND FROM BUFFER HOPPER, FLY ASH IS TRANSPORTED TO FLY ASH SILOS BYMEANS OF COMPRESSED AIR SUPPLIED BY TRANSPORT AIR COMPRESSORS. • VACUUM CONVEYING SYSTEM FOR EXTRACTION AND TRANSPORTATION OF FLY ASH TO BUFFER HOPPER AND COLLECTOR TANK IS COMMON • VACUUM AIR AND FLY ASH TRANSPORT PIPE WORK AND VALVES HIGHLIGHTED IN THE BLUE BOX SHALL BE INSTALLED FOR CONTINUOUS OPERATION OF FLY ASH SYSTEM IN WET MODE. • INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED ISOLATION VALVES ON VACUUM AIR AND FLY ASH TRANSPORT PIPE LINES `
  • 20. FLY ASH PRESSURE CONVEYING SYSTEM(HCSD SILO) (DRG. NO. DP16004-XG08-90ETA-510007) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION AS SHOWN ARE NOT NECESSARY TO BE INSTALLED FOR WET MODE OPERATION
  • 21. HCSD SYSTEM • THE FLY ASH HANDLING SYSTEM – PRESSURE CONVEYING SYSTEM IS UNITISED UP TO HSCD SILOS. • FLY ASH COLLECTED IN ESP HOPPER IS EXTRACTED AND TRANSPORTED TO WETTING HEAD INSTALLED AT COLLECTOR TANK OR BUFFER HOPPER BYMEANS OF VACUUM CONVEYING SYSTEM AND FROM BUFFER HOPPER, FLY ASH IS TRANSPORTED TO HCSD SILOS BYMEANS OF COMPRESSED AIR SUPPLIED BY TRANSPORT AIR COMPRESSORS. • EACH HCSD SILO CONSISTS OF HYDROMIX DUST CONDITIONER, MIXING TANK, ETC • THE FLYASH IS DISPOSED OFF IN WET MODE BY BOOSTER/ CHARGE PUMP AND HCSD PUMP. UPTO ASH DYKE.
  • 22. ASH SLURRY & ASH WATER SYSTEM (DRG. NO. DP16004-XG08-90ETN-510006, SH 1 OF 2) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION IN THE BLUE BOX SHALL BE INSTALLED FOR CONTINUOUS OPERATION IN WET MODE OF UNIT 1
  • 23. ASH WATER SYSTEM • ASH WATER SYSTEM IS COMMON FOR BOTH UNITS. • FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING EQUIPEMNT AND PIPE WORK, HIGHLIGHTED IN THE BLUE BOXES SHALL BE INSTALLED. • BALP WATER PUMPS – 2 NOS (1W+1S) • BAHP WATER PUMPS – 2 NOS (1W+1S) • BAHP SEAL WATER PUMPS – 2 NOS (1W+1S) • FAHP WATER PUMPS – 2 NOS (1W+1S) • FLUSHING WATER PUMP – 1 NO • COMPLETE PIPE WORK FROM THE ABOVE PUMPS TO RESPECTIVE CONSUMERS ALONG WITH VALVES. • INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED VALVES • ASH WATER SUMP MAKEUP LINES FROM VARIOUS SOURCES
  • 24. ASH SLURRY & SSH WATER SYSTEM (DRG. NO. DP16004-XG08-90ETN-510006, SH 2 OF 2) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION IN THE RED BOXES ARE NOT NECESSARY TO BE INSTALLED FOR CONTINUOUS OPERATION IN WET MODE OF UNIT 1.
  • 25. ASH SLURRY DISPOSAL SYSTEM • ASH SLURRY DISPOSAL SYSTEM IS COMMON FOR BOTH UNITS. • FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING EQUIPEMNT AND PIPE WORK SHALL BE INSTALLED. • ASH SLURRY PUMPS – 4 NOS I.E 2 SERIES (1SERIES W + 1 SERIES S) • DRAIN PUMPS – 2 NOS (1W+1S) • ASH SLURRY DISPOSAL PIPE WORK FROM THE ABOVE PUMPS TO ASH DYKE ALONG WITH VALVES. • SEAL WATER AND COOLING WATER LINES ALONG WITH VALVES AND INSTUMENTATION • INSTRUMENT AIR PIPE LINE TO PNEUMATIC OPERATED VALVES • ASH SLURRY SUMP FLUSHING/ MAKEUP WATER LINES FROM VARIOUS SOURCES
  • 26. INSTRUMENT AIR SYSTEM (DRG. NO. DP16004-XG08-90ETY-510009) ALL THE EQUIPMENT, PIPING WORK AND INSTRUMENTATION IN THE RED BOXES ARE NOT NECESSARY TO BE INSTALLED FOR CONTINUOUS OPERATION IN WET MODE OF UNIT 1.
  • 27. INSTRUMENT AIR SYSTEM • INSTRUMENT AIR SYSTEM IS COMMON FOR BOTH UNITS. • FOR CONTINUOS OPERATION OF UNIT-1 IN WET MODE, THE FOLLOWING EQUIPEMNT AND PIPE WORK, HIGHLIGHTED IN RED COLOUR ARE NOT NECESSARY TO BE INSTALLED. • INSTRUMENT AIR COMPRESSORS – 2 NOS (1W+1S) • INSTRUMENT AIR DRYER - 2 NOS (1W+1S) • AIR RECEIVERS – 2 NOS (1W+1S) • INSTRUMENR AIR PIPE WORK VARIOUS PNEUMATIC OPERATED VALVES WITH VALVES AND FITTINGS • COOLING WATER LINES WITH VALVES AND INSTUMENTATION
  • 28. ASH WATER CLARIFIER SYSTEM (DRG. NO. DP16004-XG08-90ETN-510008) ALL THE EQUIPMENT, PIPING AND INSTRUMENTATION SHOWN IN THIS P & ID SHALL BE COMPLETELY INSTALLED FOR CONTINUOUS OPERATION IN WET MODE
  • 29. ASH WATER RECIRCULATION SYSTEM • ASH WATER RECIRCULATION SYSTEM IS COMMON FOR BOTH UNITS. • ALUM AND LIME DOSING TANKS, PUMPS, PIPE WORK WITH VALVES AND INSTRUMENTATION IS REQUIRED TO BE INSTALLED TO TREAT BOTTOM ASH OVERFLOW AND DRAIN WATER COLLECTED IN CLARIFIER. • COMPLETE STILLING CHAMBER, CLARIFIER, BRIDGE MECHANSM, SLUDGE PUMPS, PIPE WORK WITH VALVES AND INSTRUMENTAION IS REQUIRED TO BE INSTALLED