An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Advanced Work Packaging (AWP)
Achieving Higher Project
Productivity And Predictability
1
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Today’s talking points
2
• The Construction Industry Productivity Dilemma
• Elements of a Successful Project Delivery
• Advanced Work Packaging (AWP)
² Structure
² Deliverables
² Practice Model
Ø A vision for our Industry
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Note about the webinar
• I hope this webinar provides you with new elements of
discussion that you may use to re-think and re-assess
your organizations project delivery maturity and identify
areas of improvements
• Although the primary research focus is on industrial
construction, many elements of this presentation could
very well be applied to other conventional construction
sectors
3
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Let's get started...
4
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
How productive is our industry?
5
A percentage point increase in productivity is worth $7
billion to the industry as a whole.
The industry is leaving big money on the table!
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
A Labor-Intensive Business...
6
Facing an increasingly challenging global market, the construction industry
has remained a labor-intensive business, struggling to achieve higher
capital effectiveness.
• Increased TechnicalComplexity
• Remote GeographicalLocations
• increasingly congested areas
• More Stringent Regulatory Requirements
• Higher Political Risk; more difficult to insure
• Shortage in skilled labor
• Workforce availability
• Unbalanced supply and demand in terms of engineering,procurement and
project managementservices
• Unstable commodity pricing
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
What are we trying to do to cut costs?
7
Gorgon Project, Australia
(source: Chevron.com)
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
More so than ever, Business and
Projects/Engineering concerns are aligned
• Many of these factors are out of control of
individual companies and project teams. It
is, therefore, more compelling to enhance
one's project delivery effectiveness through
executing projects the "right way"
• That encompasses mastering project and
business risk identification, sharing and
management within a project delivery
system capable of delivering the promised
business value, in a predictable fashion
8
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Doing the right projects...
AND doing projects right!
9
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
10
How to deliver profitable capital projects?
Field	Labor	
Productivity
Engineering	 Quality	&	
Timeliness
Procurement	Quality	
&	Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	
Line	with	Stakeholders	
Capabilities
Strong	Project	
Management	
Capabilities
Reliable	
Constructability	
Strategy	
Cost Schedule Safety Operability
Project’s	
Economic		
Output
Exhibit	1
© www.workpackaging.org,2016
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
11
I - Project Outcomes
Field	Labor	
Productivity
Engineering	 Quality	&	
Timeliness
Procurement	Quality	
&	Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	
Line	with	Stakeholders	
Capabilities
Strong	Project	
Management	
Capabilities
Reliable	
Constructability	
Strategy	
Cost Schedule Safety Operability
Project’s	
Economic		
Output
Exhibit	1.	a
© www.workpackaging.org,2016
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
12
II - Project Critical Conditions
Field	Labor	
Productivity
Engineering	 Quality	&	
Timeliness
Procurement	Quality	
&	Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	
Line	with	Stakeholders	
Capabilities
Strong	Project	
Management	
Capabilities
Reliable	
Constructability	
Strategy	
Cost Schedule Safety Operability
Project’s	
Economic		
Output
Exhibit	1.	b
© www.workpackaging.org,2016
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
13
III - Project Execution Success Indicators
Field	Labor	
Productivity
Engineering	 Quality	&	
Timeliness
Procurement	Quality	
&	Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	
Line	with	Stakeholders	
Capabilities
Strong	Project	
Management	
Capabilities
Reliable	
Constructability	
Strategy	
Cost Schedule Safety Operability
Project’s	
Economic		
Output
Exhibit	1.	c
© www.workpackaging.org,2016
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
14
Delivering profitable capital projects requires thinking with the end in mind
Field	Labor	
Productivity
Engineering	 Quality	&	
Timeliness
Procurement	Quality	
&	Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	
Line	with	Stakeholders	
Capabilities
Strong	Project	
Management	
Capabilities
Reliable	
Constructability	
Strategy	
Cost Schedule Safety Operability
Project’s	
Economic		
Output
Exhibit	1
© www.workpackaging.org,2016
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Reliable and effective
constructability strategy
Definition:
Constructability Reviews (CR) are “ the optimum use of
construction knowledge in planning, design, procurement, and
field operations to achieve overall project objectives". (CII)
A Constructability Review (CR) constitutes an analysis of the
plant design (usually performed by experienced construction,
maintenance, & operations personnel) intended to reduce costs,
save time, ensure quality and safety, as well as enhance the
management of risk in the construction phase, during plant
operation, and during subsequent maintenance of the facility.
15
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
How effective is your company's
CR process?
q Do you start you CR early in definition? (timing)
q Do you have multiple CR sessions throughout the definition phase?
(frequency)
q Does your primary Construction Manager (CM) participate in the
review? Will you have a new CM at execution? (continuity of strategy
ownership and accountability)
q Do you document your CR? (traceability)
q Do you provide enough information as input to your CR (such as
models, site reviews, technology considerations)? (quality)
q Do you use corporate project knowledge in your CR? (lessons
learned & continuous improvement)
q How involved is your project sponsor in the CR? (alignment with
business)
16
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
17
Field	Labor	ProductivityEngineering	Quality	&	Timeliness
Procurement	Quality	&	
Effectiveness
Doing	the	right	project	
Alignment	of	Business	Case,	Scope	and	Project	Objectives
Contracting	Strategies	In	Line	with	
Stakeholders	Capabilities
Strong	Project	Management	
Capabilities Reliable	Constructability	Strategy	
Cost Schedule Safety Operability
Project’s	Economic		
Output
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
The Mortar Concept©
(MC Concept)
18
© www.workpackaging.org,2016
MC
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Linking Together Project Delivery Components:
" The Mortar Concept© "
• To enable the holistic effectiveness of all
these project delivery components, a project
needs to operate within a framework
capable of ensuring both the right timing and
the optimum quality of information used
• This framework is defined based on two
structural features:
1. It needs to support timeliness of decisions
through a Project Decision Support
System (PDSS©)
2. It needs to ensure accurate project
information flow through a workable
Project Information Flow Protocol (PIFP©)
19
©	Hamdi,	The	Mortar	Concept	 in	Project	Management,	2015
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
20
Linking Project Delivery Components
" The Mortar Concept© "
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
21
Linking Project Delivery Components
" The Mortar Concept© "
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Advanced Work Packaging
(AWP)
22
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Research & Development History
• 4 Year Academia-Industry
Research Collaboration (RT272)
• Industry Implementation
Resource – 3 volumes
• First Academic Publication on
AWP from The University of
Texas at Austin
• Implementation case studies &
Validation
23
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Advanced Work Packaging (AWP) is a
project delivery system that emphasizes
construction as a primary planning driver
24
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
What is Advanced Work Packaging
(AWP)?
“Advanced Work Packaging (AWP) is a work process
framework fundamentally based on the idea of thinking with
the end in mind. It is designed to allow engineering
planning be driven by construction sequencing. Simply put,
this is achieved by breaking down the project scope into
Construction Work Packages that are fed with Engineering
Work Packages.”
25
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
How is that achieved?
1. Extending PEPs to the front-end planning phase; "bringing the field
to the office"
2. A focus on field work packages/installation work packages as
project information units
3. Work packaging structure becomes the skeleton of the project; a
workface planner is dedicated to the management of these
packages
4. The benefit of a common intuitive project language and tools
26
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
A quick look at the boundaries
defining each of the Advanced Work
Packaging (AWP) system
deliverables
Key Deliverables:
CWP- Construction Work Packages
IWP- Installation Work Packages
EWP- Engineering Work Packages
27
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Overall Project
Exhibit	of	CII/COAA	RT.272
28
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Construction Work Package (CWP) Boundary
Exhibit	of	CII/COAA	RT.272
29
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Engineering Work Package (EWP) boundary
Exhibit	of	CII/COAA	RT.272
30
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Installation Work Package (IWP) boundary
Exhibit	of	CII/COAA	RT.272
31
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Inside a CWP
CWP Content
• Scope description and
constructability strategy
• Safety Requirements
• Various EWPs (at least one)
• Schedule Requirements
• Budget (labor
hours/cost/plannedproductivity
rate)
• Quality Requirements
• Special Resource Requirements
(tools, equipments etc.)
CWP Features
• In line with the overall
construction plan
• Typically aligned with a bid
package / multiple CWPs
may form one larger bid
package
• In alignment with project
controls
• Measurable
• As independent as possible
32
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Inside an EWP
EWP Content
• Scope of work with equipment
list
• Drawings (e.g. general
arrangement and equipment
installation)
• Installation and material
specifications
• Vendor data
• Bill of materials
• Additional needed information
such as permitting studies,
geotechnicalstudies etc.
• Connection Points
Considerations
EWP Features
• Release plan should be
aligned with the construction
sequence and priorities
• Content should satisfy various
stakeholders requirements
• Planning of EWPs requires
construction input!!
• EWPs are discipline and area-
driven; connections points
expected
• Interface management should
be accounted for
33
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Inside an IWP
IWP Content
• Scope of Work
• Safety Requirements
• QA/QC Requirements
• Trade Coordination
• Material Take Offs & Locations
• Model Shots, Drawings and All
Other Necessary Engineering
Information
• Scaffold Requirements
• IWP Constraints
• Any Other Information Required to
Install the Work
IWP Features
• Reviewed and approved by the
supervisory team
34
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
AWP Recommended Practice Model
35
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
An Industry Momentum
• Multiple case studies of industrial projects (IR272-2 v3)
reported the achieved benefits of:
– 25% productivity improvement
– 10% decrease in total installed cost
• Documented the following benefits resulting from AWP
implementation:
– Greater schedule & cost predictability
– Improved safety performance
– Reduced engineering rework
– Improved quality & stakeholder alignment
– Improved contractor profitability
– Increased supervision time in the field
• Performance/maturity matrix established
36
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
ENR talking
about AWP
37
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Call for action
Advanced Work Packaging (AWP)
constitutes a major competitive advantage
for companies that go through the process
of assessing and improving the maturity and
effectiveness of their own project delivery
capabilities.
38
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
O.H.'s AWP Implementation Roadmap
- Level 1
39
Update corporate program
Implement AWP
Plan AWP implementation
Obtain AWP capabilities
Establish corporate AWP program
Assess current project delivery system effectiveness
Commit to implementing AWP
©	Olfa	Hamdi,	2015
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
O.H. Vision for AWP
and the construction industry
• AWP is currently a strong experience based model; theoretical
validation pending
• Aiming for an industry-wide protocol; project information mapping is
a first step but it should be executed in parallel to other industry-
wide efforts
• The AWP system requires further design
– Mostly a human-powered decision making system
– Spatial representation of projects needs to be integrated with business
decisions
– More to do in terms of quantification, storage, communication of
information
– Integration and interoperability are key
• We are still far from automation but we are heading in the right direction
– Our industry needs to learn from other sectors and experiences
– We need to capitalize on those successful implementations cases
– We need to bring in the best talents from the IT sector to
revolutionize our industry
40
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
"We do well bricks...
It's high time we tackle
the mortar"
41
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
From Project Management to
Project Leadership
42
An Introduction To A New Framework For Successful Construction Project Delivery
Olfa Hamdi, MSc Eng, MSc Res
Founder, The Advanced Work Packaging Institute
Thank You!
Contact:
Olfa Hamdi
The Advanced Work Packaging Institute
268 Bush Street #2926, San Francisco, CA, 94104
www.workpackaging.org
Email: ohamdi@workpackaging.org
43

More Related Content

What's hot

Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeCCT International
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...Ibrahim Al-Hudhaif
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
RAB resume 09 01 2016
RAB resume    09 01 2016RAB resume    09 01 2016
RAB resume 09 01 2016Rich Bellino
 
Resume_Bernard Estrada Buenaventura._Updated as of 2017
Resume_Bernard Estrada Buenaventura._Updated as of 2017Resume_Bernard Estrada Buenaventura._Updated as of 2017
Resume_Bernard Estrada Buenaventura._Updated as of 2017Bernie Buenavent
 
Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...AVEVA Group plc
 
AVEVA World Conference NA - Alan Smith, WorleyParsons
AVEVA World Conference NA - Alan Smith, WorleyParsonsAVEVA World Conference NA - Alan Smith, WorleyParsons
AVEVA World Conference NA - Alan Smith, WorleyParsonsAVEVA-Americas
 
Global EPC Project Management Summit 2021
Global EPC Project Management Summit 2021Global EPC Project Management Summit 2021
Global EPC Project Management Summit 2021EPCConferenceAmsterd
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without IsometricCCT International
 
The Completions Group Overview
The Completions Group OverviewThe Completions Group Overview
The Completions Group OverviewSterling McLeod
 
Jason E Stephens’ 2020 Resume/CV
Jason E Stephens’ 2020 Resume/CVJason E Stephens’ 2020 Resume/CV
Jason E Stephens’ 2020 Resume/CVjasonstephens
 
AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsVanessa Erickson
 
Total contract control for rail projects mounir boemond
Total contract control for rail projects   mounir boemondTotal contract control for rail projects   mounir boemond
Total contract control for rail projects mounir boemondIbrahim Al-Hudhaif
 

What's hot (19)

Advanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An IntroductionAdvanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An Introduction
 
Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to Practice
 
TC-CV-2015
TC-CV-2015TC-CV-2015
TC-CV-2015
 
Advanced Work Packaging: The Path of Construction
Advanced Work Packaging: The Path of ConstructionAdvanced Work Packaging: The Path of Construction
Advanced Work Packaging: The Path of Construction
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
RAB resume 09 01 2016
RAB resume    09 01 2016RAB resume    09 01 2016
RAB resume 09 01 2016
 
Resume_Bernard Estrada Buenaventura._Updated as of 2017
Resume_Bernard Estrada Buenaventura._Updated as of 2017Resume_Bernard Estrada Buenaventura._Updated as of 2017
Resume_Bernard Estrada Buenaventura._Updated as of 2017
 
Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...
 
AVEVA World Conference NA - Alan Smith, WorleyParsons
AVEVA World Conference NA - Alan Smith, WorleyParsonsAVEVA World Conference NA - Alan Smith, WorleyParsons
AVEVA World Conference NA - Alan Smith, WorleyParsons
 
Global EPC Project Management Summit 2021
Global EPC Project Management Summit 2021Global EPC Project Management Summit 2021
Global EPC Project Management Summit 2021
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
 
The Completions Group Overview
The Completions Group OverviewThe Completions Group Overview
The Completions Group Overview
 
Jason E Stephens’ 2020 Resume/CV
Jason E Stephens’ 2020 Resume/CVJason E Stephens’ 2020 Resume/CV
Jason E Stephens’ 2020 Resume/CV
 
L_Bacha_Project_Summary
L_Bacha_Project_SummaryL_Bacha_Project_Summary
L_Bacha_Project_Summary
 
Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203
 
Portfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce todayPortfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce today
 
AVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker SolutionsAVEVA World Conference NA - Tom Singer, Aker Solutions
AVEVA World Conference NA - Tom Singer, Aker Solutions
 
Total contract control for rail projects mounir boemond
Total contract control for rail projects   mounir boemondTotal contract control for rail projects   mounir boemond
Total contract control for rail projects mounir boemond
 

Viewers also liked

Viewers also liked (8)

Monitoring And Evaluation Of Knowledge Management Elb
Monitoring And Evaluation Of Knowledge Management   ElbMonitoring And Evaluation Of Knowledge Management   Elb
Monitoring And Evaluation Of Knowledge Management Elb
 
Leading & Inspiring Employees In the Collaborative Economy
Leading & Inspiring Employees In the Collaborative EconomyLeading & Inspiring Employees In the Collaborative Economy
Leading & Inspiring Employees In the Collaborative Economy
 
The Joy of Data Driven Storytelling
The Joy of Data Driven StorytellingThe Joy of Data Driven Storytelling
The Joy of Data Driven Storytelling
 
Pecha Kucha
Pecha KuchaPecha Kucha
Pecha Kucha
 
Web metrics final
Web metrics finalWeb metrics final
Web metrics final
 
Capital Projects blog
Capital Projects blogCapital Projects blog
Capital Projects blog
 
Advanced Work Packaging
Advanced Work Packaging Advanced Work Packaging
Advanced Work Packaging
 
5 Ways Companies Mismanage Capital Projects Risk
5 Ways Companies Mismanage Capital Projects Risk5 Ways Companies Mismanage Capital Projects Risk
5 Ways Companies Mismanage Capital Projects Risk
 

Similar to Advanced Work Packaging (AWP): An Illustration of the Mortar Concept(c)

R. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderR. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderJay Gann
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessIRJET Journal
 
Enaam Alum cv (2019)
Enaam Alum cv (2019)Enaam Alum cv (2019)
Enaam Alum cv (2019)EnaamAlum
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryDavid Pires
 
Eugene Eybers - CURRICULUM VITAE Rev 4 oman
Eugene Eybers - CURRICULUM VITAE Rev 4 oman Eugene Eybers - CURRICULUM VITAE Rev 4 oman
Eugene Eybers - CURRICULUM VITAE Rev 4 oman Eugene Eybers
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road ConstructionHeidi Owens
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Aconex
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Austin_C _Mattson_II_resume_Sep_2015
Austin_C _Mattson_II_resume_Sep_2015Austin_C _Mattson_II_resume_Sep_2015
Austin_C _Mattson_II_resume_Sep_2015Austin C. Mattson II
 

Similar to Advanced Work Packaging (AWP): An Illustration of the Mortar Concept(c) (20)

Amit_Kumar
Amit_KumarAmit_Kumar
Amit_Kumar
 
Mission Bo Kv3
Mission Bo Kv3Mission Bo Kv3
Mission Bo Kv3
 
Dawn Thompson
Dawn ThompsonDawn Thompson
Dawn Thompson
 
R. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderR. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management Leader
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
LNABrochureEN
LNABrochureENLNABrochureEN
LNABrochureEN
 
Kannan PEM
Kannan PEMKannan PEM
Kannan PEM
 
Enaam Alum cv (2019)
Enaam Alum cv (2019)Enaam Alum cv (2019)
Enaam Alum cv (2019)
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 
Eugene Eybers - CURRICULUM VITAE Rev 4 oman
Eugene Eybers - CURRICULUM VITAE Rev 4 oman Eugene Eybers - CURRICULUM VITAE Rev 4 oman
Eugene Eybers - CURRICULUM VITAE Rev 4 oman
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road Construction
 
10_PFCRoundup
10_PFCRoundup10_PFCRoundup
10_PFCRoundup
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
Creative Overview
Creative OverviewCreative Overview
Creative Overview
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Resume ng ji xian jason
Resume ng ji xian jasonResume ng ji xian jason
Resume ng ji xian jason
 
India capability web
India capability webIndia capability web
India capability web
 
Austin_C _Mattson_II_resume_Sep_2015
Austin_C _Mattson_II_resume_Sep_2015Austin_C _Mattson_II_resume_Sep_2015
Austin_C _Mattson_II_resume_Sep_2015
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 

Advanced Work Packaging (AWP): An Illustration of the Mortar Concept(c)

  • 1. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Advanced Work Packaging (AWP) Achieving Higher Project Productivity And Predictability 1
  • 2. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Today’s talking points 2 • The Construction Industry Productivity Dilemma • Elements of a Successful Project Delivery • Advanced Work Packaging (AWP) ² Structure ² Deliverables ² Practice Model Ø A vision for our Industry
  • 3. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Note about the webinar • I hope this webinar provides you with new elements of discussion that you may use to re-think and re-assess your organizations project delivery maturity and identify areas of improvements • Although the primary research focus is on industrial construction, many elements of this presentation could very well be applied to other conventional construction sectors 3
  • 4. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Let's get started... 4
  • 5. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute How productive is our industry? 5 A percentage point increase in productivity is worth $7 billion to the industry as a whole. The industry is leaving big money on the table!
  • 6. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute A Labor-Intensive Business... 6 Facing an increasingly challenging global market, the construction industry has remained a labor-intensive business, struggling to achieve higher capital effectiveness. • Increased TechnicalComplexity • Remote GeographicalLocations • increasingly congested areas • More Stringent Regulatory Requirements • Higher Political Risk; more difficult to insure • Shortage in skilled labor • Workforce availability • Unbalanced supply and demand in terms of engineering,procurement and project managementservices • Unstable commodity pricing
  • 7. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute What are we trying to do to cut costs? 7 Gorgon Project, Australia (source: Chevron.com)
  • 8. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute More so than ever, Business and Projects/Engineering concerns are aligned • Many of these factors are out of control of individual companies and project teams. It is, therefore, more compelling to enhance one's project delivery effectiveness through executing projects the "right way" • That encompasses mastering project and business risk identification, sharing and management within a project delivery system capable of delivering the promised business value, in a predictable fashion 8
  • 9. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Doing the right projects... AND doing projects right! 9
  • 10. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 10 How to deliver profitable capital projects? Field Labor Productivity Engineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output Exhibit 1 © www.workpackaging.org,2016
  • 11. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 11 I - Project Outcomes Field Labor Productivity Engineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output Exhibit 1. a © www.workpackaging.org,2016
  • 12. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 12 II - Project Critical Conditions Field Labor Productivity Engineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output Exhibit 1. b © www.workpackaging.org,2016
  • 13. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 13 III - Project Execution Success Indicators Field Labor Productivity Engineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output Exhibit 1. c © www.workpackaging.org,2016
  • 14. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 14 Delivering profitable capital projects requires thinking with the end in mind Field Labor Productivity Engineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output Exhibit 1 © www.workpackaging.org,2016
  • 15. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Reliable and effective constructability strategy Definition: Constructability Reviews (CR) are “ the optimum use of construction knowledge in planning, design, procurement, and field operations to achieve overall project objectives". (CII) A Constructability Review (CR) constitutes an analysis of the plant design (usually performed by experienced construction, maintenance, & operations personnel) intended to reduce costs, save time, ensure quality and safety, as well as enhance the management of risk in the construction phase, during plant operation, and during subsequent maintenance of the facility. 15
  • 16. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute How effective is your company's CR process? q Do you start you CR early in definition? (timing) q Do you have multiple CR sessions throughout the definition phase? (frequency) q Does your primary Construction Manager (CM) participate in the review? Will you have a new CM at execution? (continuity of strategy ownership and accountability) q Do you document your CR? (traceability) q Do you provide enough information as input to your CR (such as models, site reviews, technology considerations)? (quality) q Do you use corporate project knowledge in your CR? (lessons learned & continuous improvement) q How involved is your project sponsor in the CR? (alignment with business) 16
  • 17. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 17 Field Labor ProductivityEngineering Quality & Timeliness Procurement Quality & Effectiveness Doing the right project Alignment of Business Case, Scope and Project Objectives Contracting Strategies In Line with Stakeholders Capabilities Strong Project Management Capabilities Reliable Constructability Strategy Cost Schedule Safety Operability Project’s Economic Output
  • 18. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute The Mortar Concept© (MC Concept) 18 © www.workpackaging.org,2016 MC
  • 19. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Linking Together Project Delivery Components: " The Mortar Concept© " • To enable the holistic effectiveness of all these project delivery components, a project needs to operate within a framework capable of ensuring both the right timing and the optimum quality of information used • This framework is defined based on two structural features: 1. It needs to support timeliness of decisions through a Project Decision Support System (PDSS©) 2. It needs to ensure accurate project information flow through a workable Project Information Flow Protocol (PIFP©) 19 © Hamdi, The Mortar Concept in Project Management, 2015
  • 20. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 20 Linking Project Delivery Components " The Mortar Concept© "
  • 21. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute 21 Linking Project Delivery Components " The Mortar Concept© "
  • 22. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Advanced Work Packaging (AWP) 22
  • 23. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Research & Development History • 4 Year Academia-Industry Research Collaboration (RT272) • Industry Implementation Resource – 3 volumes • First Academic Publication on AWP from The University of Texas at Austin • Implementation case studies & Validation 23
  • 24. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Advanced Work Packaging (AWP) is a project delivery system that emphasizes construction as a primary planning driver 24
  • 25. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute What is Advanced Work Packaging (AWP)? “Advanced Work Packaging (AWP) is a work process framework fundamentally based on the idea of thinking with the end in mind. It is designed to allow engineering planning be driven by construction sequencing. Simply put, this is achieved by breaking down the project scope into Construction Work Packages that are fed with Engineering Work Packages.” 25
  • 26. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute How is that achieved? 1. Extending PEPs to the front-end planning phase; "bringing the field to the office" 2. A focus on field work packages/installation work packages as project information units 3. Work packaging structure becomes the skeleton of the project; a workface planner is dedicated to the management of these packages 4. The benefit of a common intuitive project language and tools 26
  • 27. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute A quick look at the boundaries defining each of the Advanced Work Packaging (AWP) system deliverables Key Deliverables: CWP- Construction Work Packages IWP- Installation Work Packages EWP- Engineering Work Packages 27
  • 28. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Overall Project Exhibit of CII/COAA RT.272 28
  • 29. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Construction Work Package (CWP) Boundary Exhibit of CII/COAA RT.272 29
  • 30. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Engineering Work Package (EWP) boundary Exhibit of CII/COAA RT.272 30
  • 31. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Installation Work Package (IWP) boundary Exhibit of CII/COAA RT.272 31
  • 32. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Inside a CWP CWP Content • Scope description and constructability strategy • Safety Requirements • Various EWPs (at least one) • Schedule Requirements • Budget (labor hours/cost/plannedproductivity rate) • Quality Requirements • Special Resource Requirements (tools, equipments etc.) CWP Features • In line with the overall construction plan • Typically aligned with a bid package / multiple CWPs may form one larger bid package • In alignment with project controls • Measurable • As independent as possible 32
  • 33. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Inside an EWP EWP Content • Scope of work with equipment list • Drawings (e.g. general arrangement and equipment installation) • Installation and material specifications • Vendor data • Bill of materials • Additional needed information such as permitting studies, geotechnicalstudies etc. • Connection Points Considerations EWP Features • Release plan should be aligned with the construction sequence and priorities • Content should satisfy various stakeholders requirements • Planning of EWPs requires construction input!! • EWPs are discipline and area- driven; connections points expected • Interface management should be accounted for 33
  • 34. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Inside an IWP IWP Content • Scope of Work • Safety Requirements • QA/QC Requirements • Trade Coordination • Material Take Offs & Locations • Model Shots, Drawings and All Other Necessary Engineering Information • Scaffold Requirements • IWP Constraints • Any Other Information Required to Install the Work IWP Features • Reviewed and approved by the supervisory team 34
  • 35. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute AWP Recommended Practice Model 35
  • 36. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute An Industry Momentum • Multiple case studies of industrial projects (IR272-2 v3) reported the achieved benefits of: – 25% productivity improvement – 10% decrease in total installed cost • Documented the following benefits resulting from AWP implementation: – Greater schedule & cost predictability – Improved safety performance – Reduced engineering rework – Improved quality & stakeholder alignment – Improved contractor profitability – Increased supervision time in the field • Performance/maturity matrix established 36
  • 37. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute ENR talking about AWP 37
  • 38. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Call for action Advanced Work Packaging (AWP) constitutes a major competitive advantage for companies that go through the process of assessing and improving the maturity and effectiveness of their own project delivery capabilities. 38
  • 39. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute O.H.'s AWP Implementation Roadmap - Level 1 39 Update corporate program Implement AWP Plan AWP implementation Obtain AWP capabilities Establish corporate AWP program Assess current project delivery system effectiveness Commit to implementing AWP © Olfa Hamdi, 2015
  • 40. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute O.H. Vision for AWP and the construction industry • AWP is currently a strong experience based model; theoretical validation pending • Aiming for an industry-wide protocol; project information mapping is a first step but it should be executed in parallel to other industry- wide efforts • The AWP system requires further design – Mostly a human-powered decision making system – Spatial representation of projects needs to be integrated with business decisions – More to do in terms of quantification, storage, communication of information – Integration and interoperability are key • We are still far from automation but we are heading in the right direction – Our industry needs to learn from other sectors and experiences – We need to capitalize on those successful implementations cases – We need to bring in the best talents from the IT sector to revolutionize our industry 40
  • 41. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute "We do well bricks... It's high time we tackle the mortar" 41
  • 42. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute From Project Management to Project Leadership 42
  • 43. An Introduction To A New Framework For Successful Construction Project Delivery Olfa Hamdi, MSc Eng, MSc Res Founder, The Advanced Work Packaging Institute Thank You! Contact: Olfa Hamdi The Advanced Work Packaging Institute 268 Bush Street #2926, San Francisco, CA, 94104 www.workpackaging.org Email: ohamdi@workpackaging.org 43