SlideShare una empresa de Scribd logo
1 de 17
Descargar para leer sin conexión
Opportunities and role
of the Quantity
Surveyor in Green
Building Project
Development
By Oyinleye Adebowale. O,
FNIQS ,MRICS, LEED AP BD+C, PMP, ISSP
Introduction
Goals Of
Green
Building
Opportunities
in Green
Building
Roles Of
Quantity
Surveyors
What is green building?
A ‘green’ building is a building that, in its design,
construction or operation, reduces or eliminates
negative impacts, and can create positive impacts,
on our climate and natural environment. Green
buildings preserve precious natural resources and
improve our quality of life.
https://www.worldgbc.org/what-green-building
Who is a Quantity Surveyor?
A quantity surveyor (QS) is a construction industry
professional with expert knowledge on construction
costs and contracts.
https://en.wikipedia.org/wiki/Quantity_surveyor
KEY TERMS
3
ICMS 3?
The international Cost Management
Standard
Global Consistency in Presenting Construction Life Cycle Costs
and Carbon Emissions
https://icms-coalition.org/icms-3/
Some Goals of Green Building
Reduction in Impact categories through:
Siting and structure design efficiency
Energy efficiency
Water efficiency
Materials efficiency
Indoor environmental quality
enhancement
Operations and maintenance
optimization
Waste elimination/reduction
 Sustainability quantity surveyor
UP
DOWN
4
OPPORTUNITIES FOR THE
QUANTITY SURVEYOR
INTEGRATIVE PROCUREMENT MANAGEMENT
BUILDING PERFORMANCE REPORTING
MEASUREMENT OF EMBODIED CARBON AND
FOOTPRINT
LIFE CYCLE COSTING & IMPACT ASSESSMENT
GREEN FINANCING & COSTING
LEED / BIM MANAGER
GREEN BUILDING RATING ASSESSMENT
*TRAINING IS
REQUIRED*
New challenges to QS from sustainable construction
There are peculiar services in green building development and understanding these need will
enlighten the quantity surveyor on the services that can be provided:
INTEGRATIVE PROCUREMENT MANAGEMENT
Procurement of Green Building can sometimes be complex as it requires greater levels of integration between all the
parties concerned. This procurement can be conducted either for the Green Project procurement or Green product
procurement. In either case, the quantity Surveyor can bring his expertise to bear in the drafting of peculiar terms and
conditions of the procurement, development of RFQs and RFPs that suit the peculiar needs of the project owner. The
typical linear procurement process, where the roles and responsibilities of the project team may not overlap does not
lend itself to green building development, in some rating systems, there is a mandatory requirement to conduct a
design charrette which is aimed at bringing all team members up to speed as early as possible in the project
development cycle. Adopting specific construction technologies or processes can create the need for selection of
contractors and suppliers early in the design process, this may require development of special procurement processes,
and the profession’s expertise in procurement lends it an advantage in this regard. Quantity surveyors in Nigeria have
furthermore traditionally been responsible for preparation of construction specifications, and the need to redraft these
to reflect sustainability requirements creates an added opportunity for the profession to expand its role in green
building projects.
7
BUILDING PERFORMANCE REPORTING
The development of green buildings does not end with the construction work but
transcends into the operational phase, the performance of a building needs to be well
documented and reported in a standard format which requires trained personnel to do
so. The emphasis on building efficiency and special requirements of occupants who
demand that buildings meet certain standards or thresholds as defined by different
institutional bodies such as WELL, Living Buildings Challenge, Passive house etc.,
consequently requires building owners to provide performance measurement tools and
report to ensure they meet new standards. The assessment process provides both a gap
analysis and the green building methodologies that can be employed to make the
building meet the required standards.
8
MEASUREMENT OF EMBODIED CARBON & FOOTPRINT
The first step in developing a carbon management strategy for buildings will be to accurately measure the Embodied
carbon which requires a knowledge of all materials, or ingredients within your products; and all activities related to
those materials, such as processing and transport. The carbon footprint on the other hand is the current level of
carbon emissions through activities such as electricity used to power the heating & lighting of a building. The
measurement of both the carbon footprint and embodied carbon is required in the assessment of green buildings.
The ICMS 3 has provided guidelines for measuring embodied carbon in buildings, the quantity surveyor’s expertise in
the production of Bills of quantities will always provide a competitive advantage in quantifying the embodied carbon in
building materials, equipment and components. ICMS requires a cost and/or carbon emissions report to be measured
in accordance with the rules set out in both international and country specific standards.
EN 15978:2011 Sustainability of construction works – Assessment of environmental performance of buildings - Calculation method; PAS 2080: 2016 Carbon Management in Infrastructure; ISO 21930:2017
Sustainability in buildings and civil engineering works — Core rules for environmental product declarations of construction products and services and EN 15804: 2012 Sustainability of construction works -
Environmental product declarations - Core rules for the product category of construction products
9
LIFE CYCLE COSTING & IMPACT ASSESSMENT
The concept of Life Cycle Costing (LCC) and Whole Life Costing (WLC) are an integral part of Green
Buildings as it forms a basis for alternatives assessment. Life Cycle Assessment on the other hand only
looks at the environmental impact of a material, product or building. LCC is a technique to establish
the total cost of the building throughout its functional lifespan and the results can be used to assist the
management in the decision-making process to go green. Life-cycle assessment typically involves the
evaluation and comparison of the impact of a given material, resource or product on the sustainability
of a portfolio, project or at component level. LEED particularly requires the evaluation of an LCA under
the Materials and resources credit category. This process may be complex and requires expert skills
set. It is expected that as the importance of this grows in the next few years, the Quantity Surveyor,
who is an expert in cost management and in extension LCC or WLC, will develop skills for LCAs. The QS
is in an excellent position to take advantage of this role as it is an area that lends itself for quick
adoption.
10
GREEN FINANCING & COSTING
There is an increasing request by investors for projects to be sustainable, and some investors
require strict adherence to these requirements for funding. The portfolio of green funds has been
steadily increasing and it has become a substantial pool which developers need to pay attention to.
With the increasing prevalence of green building rating systems such as EDGE, and that being the
only way to confirm the sustainability of a building project, organisations such as the IFC have
specialized funds that are dedicated to projects that have green building certification. The Quantity
Surveyor has to be adept in the special financing models available for buildings and sustainable
cities.
Additionally, value engineering & management; and Cost models have to be designed to cater to
Clients’ needs with regards to the extra costs for achieving the different levels of green building
certification of new and emerging technologies that are being utilized in green buildings and also to
appropriately present data on the payback period of the cost of “greening “a project.
11
LEED / BIM PROJECT MANAGER
Building Information Modelling (BIM) is an integral platform for the management of information
throughout a building project lifespan. As the use of building information modelling (BIM) becomes
more widespread, the link between BIM and Green Building management, especially by the rating
bodies, becomes indispensable. While the BIM model was initially suited for use where visual
presentation is required, it has however evolved to 5D, 6D and 7D involving costing and facilities
management with LCC and WLC integrated, this development is aided by the automatic generation of
bills of quantities from BIM, which is called Quantity Information Model (QIM). The QIM relies on the
information within BIM to extract the relevant data and process this into bills of quantities. This
functionality requires an area of expertise well suited to the Quantity Surveyors who can interpolate the
material specifications, costing, quantities LCC and end of life evaluations through a single point
management of Green Assessment points and real time costing.
12
GREEN BUILDING RATING ASSESSMENT
The Green Building sector of the construction industry is made more viable by the presence of rating
systems which seek to declare the level of conformance to the required standards for green buildings.
The prevalent use of green building rating systems such as LEED, BREEAM, WELL, Living Buildings, Green
globe etc., in international projects has created new inroads for the quantity surveyor to exploit.
However, while it is possible for a QS to be involved with introductory knowledge of Green Building
practices, more value will be gotten through the attainment of accreditation in Green building or
sustainability. Accreditations such as the LEED Accredited Professional, BREEAM Advisory Professional,
WELL Accredited Professional have been created to enhance the understanding of the relevant Green
Building rating system and environmentally sustainable designs. With a greater understanding of the
green building rating systems, the QS would be in a better position to advice the Client both on the cost
and sustainable designs.
13
ROLES ARE DEFINED BY THE RATING SYSTEM
LEED
EDGE
WELL
BREEAM
LIVING
BUILDING
LEED
LEED PROJECT
MANAGER
LEED AP
LEED Green Associate
EDGE
EDGE AUDITOR
EDGE EXPERT
BREEAM
ASSESSOR
ADVISORY
PROFESSIONAL
ASSOCIATE
WELL
WELL AP
LIVING
BUILDING
AMBASSADOR
PROFESSIONAL
MEMBER
 Conclusion
 Market is huge
 Need to learn the principles and processes of green building
development
 Become a sustainability quantity surveyor
 Acquire Specific knowledge and proficiencies
 Get accreditation
 EchoStone plans to build 182,000 affordable, certified green homes
in Lagos, Nigeria, by 2023. By working with local banks, it ensures
that home buyers have access to low interest rates and long
mortgage tenors.
 https://echostonehousing.com/2019/06/04/echostone-breaks-ground-in-green-affordable-housing-with-ifcs-
edge-certification/
16
YOU
THANK

Más contenido relacionado

La actualidad más candente

Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaSteve Lojuntin
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Topic 9b - UBBL.ppt
Topic 9b - UBBL.pptTopic 9b - UBBL.ppt
Topic 9b - UBBL.pptAizuddin9
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Elements of Sustainable Construction and Design Parameters
Elements of Sustainable Construction and Design ParametersElements of Sustainable Construction and Design Parameters
Elements of Sustainable Construction and Design ParametersAjit Sabnis
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentationYong Sy
 
Assignment 1 - Software
Assignment 1 - SoftwareAssignment 1 - Software
Assignment 1 - SoftwareKai Yun Pang
 
Sustainable Building Design.ppt
Sustainable Building Design.pptSustainable Building Design.ppt
Sustainable Building Design.pptTantish QS, UTM
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Bim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari NassiBim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari NassiAri Nassi
 
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and Benefits
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and BenefitsBIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and Benefits
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and BenefitsUnited-BIM
 
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTM
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTMLow Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTM
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTMSteve Lojuntin
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 

La actualidad más candente (20)

Construction contract
Construction contract Construction contract
Construction contract
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in Malaysia
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Topic 9b - UBBL.ppt
Topic 9b - UBBL.pptTopic 9b - UBBL.ppt
Topic 9b - UBBL.ppt
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Elements of Sustainable Construction and Design Parameters
Elements of Sustainable Construction and Design ParametersElements of Sustainable Construction and Design Parameters
Elements of Sustainable Construction and Design Parameters
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
Assignment 1 - Software
Assignment 1 - SoftwareAssignment 1 - Software
Assignment 1 - Software
 
Vm report
Vm reportVm report
Vm report
 
Sustainable Building Design.ppt
Sustainable Building Design.pptSustainable Building Design.ppt
Sustainable Building Design.ppt
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Presentation on Zero Carbon Buildings
Presentation on Zero Carbon Buildings Presentation on Zero Carbon Buildings
Presentation on Zero Carbon Buildings
 
Bim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari NassiBim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
Bim For Construction And Maintenance Singapore 09 Oct30 Ari Nassi
 
What is BIM?
What is BIM?What is BIM?
What is BIM?
 
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and Benefits
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and BenefitsBIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and Benefits
BIM Dimensions Explained- 3D, 4D, 5D, 6D and 7D- Definition and Benefits
 
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTM
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTMLow Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTM
Low Carbon Buildings in Malaysia @ Low Carbon Asia Conference by UTM
 
ECA form
ECA formECA form
ECA form
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 

Similar a Opportunities and role of the quantity surveyor in green building project development

IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET Journal
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsIRJET Journal
 
Ska Rating CIBSE-Journal-2014-08
Ska Rating CIBSE-Journal-2014-08Ska Rating CIBSE-Journal-2014-08
Ska Rating CIBSE-Journal-2014-08Dave Cheshire
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Dataconstructingexcellence
 
A Review Paper on Retrofitting of Institutional Building into Green Building ...
A Review Paper on Retrofitting of Institutional Building into Green Building ...A Review Paper on Retrofitting of Institutional Building into Green Building ...
A Review Paper on Retrofitting of Institutional Building into Green Building ...IRJET Journal
 
BIM for substainable design-white paper
BIM for substainable design-white paperBIM for substainable design-white paper
BIM for substainable design-white paperMuhannad AbdulRaouf
 
Integrated project
Integrated projectIntegrated project
Integrated projectSasi Cool
 
Ellenzweig Climate Action Plan 2015
Ellenzweig Climate Action Plan 2015Ellenzweig Climate Action Plan 2015
Ellenzweig Climate Action Plan 2015Carolyn Day
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM Mital Damani
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer Bilal Mohamed
 
Hire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaHire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaAEO Design Consultants
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
Sustainable housing development
Sustainable housing developmentSustainable housing development
Sustainable housing developmentPui Chun Shian
 
17 Concepts for the LEED v4 GA Exam
17 Concepts for the LEED v4 GA Exam17 Concepts for the LEED v4 GA Exam
17 Concepts for the LEED v4 GA ExamChamarra McCrorey
 

Similar a Opportunities and role of the quantity surveyor in green building project development (20)

IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable Construction
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
 
Ska Rating CIBSE-Journal-2014-08
Ska Rating CIBSE-Journal-2014-08Ska Rating CIBSE-Journal-2014-08
Ska Rating CIBSE-Journal-2014-08
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 
A Review Paper on Retrofitting of Institutional Building into Green Building ...
A Review Paper on Retrofitting of Institutional Building into Green Building ...A Review Paper on Retrofitting of Institutional Building into Green Building ...
A Review Paper on Retrofitting of Institutional Building into Green Building ...
 
Leaflet Green Building
Leaflet Green BuildingLeaflet Green Building
Leaflet Green Building
 
IGBC RATING SYSTEM
IGBC RATING SYSTEMIGBC RATING SYSTEM
IGBC RATING SYSTEM
 
BIM for substainable design-white paper
BIM for substainable design-white paperBIM for substainable design-white paper
BIM for substainable design-white paper
 
Integrated project
Integrated projectIntegrated project
Integrated project
 
Ellenzweig Climate Action Plan 2015
Ellenzweig Climate Action Plan 2015Ellenzweig Climate Action Plan 2015
Ellenzweig Climate Action Plan 2015
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
integrated-project-delivery-constru
integrated-project-delivery-construintegrated-project-delivery-constru
integrated-project-delivery-constru
 
Hire best BIM Service Providers in Florida
Hire best BIM Service Providers in FloridaHire best BIM Service Providers in Florida
Hire best BIM Service Providers in Florida
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Sustainable housing development
Sustainable housing developmentSustainable housing development
Sustainable housing development
 
17 Concepts for the LEED v4 GA Exam
17 Concepts for the LEED v4 GA Exam17 Concepts for the LEED v4 GA Exam
17 Concepts for the LEED v4 GA Exam
 

Último

Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Último (20)

Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 

Opportunities and role of the quantity surveyor in green building project development

  • 1. Opportunities and role of the Quantity Surveyor in Green Building Project Development By Oyinleye Adebowale. O, FNIQS ,MRICS, LEED AP BD+C, PMP, ISSP
  • 3. What is green building? A ‘green’ building is a building that, in its design, construction or operation, reduces or eliminates negative impacts, and can create positive impacts, on our climate and natural environment. Green buildings preserve precious natural resources and improve our quality of life. https://www.worldgbc.org/what-green-building Who is a Quantity Surveyor? A quantity surveyor (QS) is a construction industry professional with expert knowledge on construction costs and contracts. https://en.wikipedia.org/wiki/Quantity_surveyor KEY TERMS 3 ICMS 3? The international Cost Management Standard Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions https://icms-coalition.org/icms-3/
  • 4. Some Goals of Green Building Reduction in Impact categories through: Siting and structure design efficiency Energy efficiency Water efficiency Materials efficiency Indoor environmental quality enhancement Operations and maintenance optimization Waste elimination/reduction  Sustainability quantity surveyor UP DOWN 4
  • 6. INTEGRATIVE PROCUREMENT MANAGEMENT BUILDING PERFORMANCE REPORTING MEASUREMENT OF EMBODIED CARBON AND FOOTPRINT LIFE CYCLE COSTING & IMPACT ASSESSMENT GREEN FINANCING & COSTING LEED / BIM MANAGER GREEN BUILDING RATING ASSESSMENT *TRAINING IS REQUIRED* New challenges to QS from sustainable construction There are peculiar services in green building development and understanding these need will enlighten the quantity surveyor on the services that can be provided:
  • 7. INTEGRATIVE PROCUREMENT MANAGEMENT Procurement of Green Building can sometimes be complex as it requires greater levels of integration between all the parties concerned. This procurement can be conducted either for the Green Project procurement or Green product procurement. In either case, the quantity Surveyor can bring his expertise to bear in the drafting of peculiar terms and conditions of the procurement, development of RFQs and RFPs that suit the peculiar needs of the project owner. The typical linear procurement process, where the roles and responsibilities of the project team may not overlap does not lend itself to green building development, in some rating systems, there is a mandatory requirement to conduct a design charrette which is aimed at bringing all team members up to speed as early as possible in the project development cycle. Adopting specific construction technologies or processes can create the need for selection of contractors and suppliers early in the design process, this may require development of special procurement processes, and the profession’s expertise in procurement lends it an advantage in this regard. Quantity surveyors in Nigeria have furthermore traditionally been responsible for preparation of construction specifications, and the need to redraft these to reflect sustainability requirements creates an added opportunity for the profession to expand its role in green building projects. 7
  • 8. BUILDING PERFORMANCE REPORTING The development of green buildings does not end with the construction work but transcends into the operational phase, the performance of a building needs to be well documented and reported in a standard format which requires trained personnel to do so. The emphasis on building efficiency and special requirements of occupants who demand that buildings meet certain standards or thresholds as defined by different institutional bodies such as WELL, Living Buildings Challenge, Passive house etc., consequently requires building owners to provide performance measurement tools and report to ensure they meet new standards. The assessment process provides both a gap analysis and the green building methodologies that can be employed to make the building meet the required standards. 8
  • 9. MEASUREMENT OF EMBODIED CARBON & FOOTPRINT The first step in developing a carbon management strategy for buildings will be to accurately measure the Embodied carbon which requires a knowledge of all materials, or ingredients within your products; and all activities related to those materials, such as processing and transport. The carbon footprint on the other hand is the current level of carbon emissions through activities such as electricity used to power the heating & lighting of a building. The measurement of both the carbon footprint and embodied carbon is required in the assessment of green buildings. The ICMS 3 has provided guidelines for measuring embodied carbon in buildings, the quantity surveyor’s expertise in the production of Bills of quantities will always provide a competitive advantage in quantifying the embodied carbon in building materials, equipment and components. ICMS requires a cost and/or carbon emissions report to be measured in accordance with the rules set out in both international and country specific standards. EN 15978:2011 Sustainability of construction works – Assessment of environmental performance of buildings - Calculation method; PAS 2080: 2016 Carbon Management in Infrastructure; ISO 21930:2017 Sustainability in buildings and civil engineering works — Core rules for environmental product declarations of construction products and services and EN 15804: 2012 Sustainability of construction works - Environmental product declarations - Core rules for the product category of construction products 9
  • 10. LIFE CYCLE COSTING & IMPACT ASSESSMENT The concept of Life Cycle Costing (LCC) and Whole Life Costing (WLC) are an integral part of Green Buildings as it forms a basis for alternatives assessment. Life Cycle Assessment on the other hand only looks at the environmental impact of a material, product or building. LCC is a technique to establish the total cost of the building throughout its functional lifespan and the results can be used to assist the management in the decision-making process to go green. Life-cycle assessment typically involves the evaluation and comparison of the impact of a given material, resource or product on the sustainability of a portfolio, project or at component level. LEED particularly requires the evaluation of an LCA under the Materials and resources credit category. This process may be complex and requires expert skills set. It is expected that as the importance of this grows in the next few years, the Quantity Surveyor, who is an expert in cost management and in extension LCC or WLC, will develop skills for LCAs. The QS is in an excellent position to take advantage of this role as it is an area that lends itself for quick adoption. 10
  • 11. GREEN FINANCING & COSTING There is an increasing request by investors for projects to be sustainable, and some investors require strict adherence to these requirements for funding. The portfolio of green funds has been steadily increasing and it has become a substantial pool which developers need to pay attention to. With the increasing prevalence of green building rating systems such as EDGE, and that being the only way to confirm the sustainability of a building project, organisations such as the IFC have specialized funds that are dedicated to projects that have green building certification. The Quantity Surveyor has to be adept in the special financing models available for buildings and sustainable cities. Additionally, value engineering & management; and Cost models have to be designed to cater to Clients’ needs with regards to the extra costs for achieving the different levels of green building certification of new and emerging technologies that are being utilized in green buildings and also to appropriately present data on the payback period of the cost of “greening “a project. 11
  • 12. LEED / BIM PROJECT MANAGER Building Information Modelling (BIM) is an integral platform for the management of information throughout a building project lifespan. As the use of building information modelling (BIM) becomes more widespread, the link between BIM and Green Building management, especially by the rating bodies, becomes indispensable. While the BIM model was initially suited for use where visual presentation is required, it has however evolved to 5D, 6D and 7D involving costing and facilities management with LCC and WLC integrated, this development is aided by the automatic generation of bills of quantities from BIM, which is called Quantity Information Model (QIM). The QIM relies on the information within BIM to extract the relevant data and process this into bills of quantities. This functionality requires an area of expertise well suited to the Quantity Surveyors who can interpolate the material specifications, costing, quantities LCC and end of life evaluations through a single point management of Green Assessment points and real time costing. 12
  • 13. GREEN BUILDING RATING ASSESSMENT The Green Building sector of the construction industry is made more viable by the presence of rating systems which seek to declare the level of conformance to the required standards for green buildings. The prevalent use of green building rating systems such as LEED, BREEAM, WELL, Living Buildings, Green globe etc., in international projects has created new inroads for the quantity surveyor to exploit. However, while it is possible for a QS to be involved with introductory knowledge of Green Building practices, more value will be gotten through the attainment of accreditation in Green building or sustainability. Accreditations such as the LEED Accredited Professional, BREEAM Advisory Professional, WELL Accredited Professional have been created to enhance the understanding of the relevant Green Building rating system and environmentally sustainable designs. With a greater understanding of the green building rating systems, the QS would be in a better position to advice the Client both on the cost and sustainable designs. 13
  • 14. ROLES ARE DEFINED BY THE RATING SYSTEM LEED EDGE WELL BREEAM LIVING BUILDING
  • 15. LEED LEED PROJECT MANAGER LEED AP LEED Green Associate EDGE EDGE AUDITOR EDGE EXPERT BREEAM ASSESSOR ADVISORY PROFESSIONAL ASSOCIATE WELL WELL AP LIVING BUILDING AMBASSADOR PROFESSIONAL MEMBER
  • 16.  Conclusion  Market is huge  Need to learn the principles and processes of green building development  Become a sustainability quantity surveyor  Acquire Specific knowledge and proficiencies  Get accreditation  EchoStone plans to build 182,000 affordable, certified green homes in Lagos, Nigeria, by 2023. By working with local banks, it ensures that home buyers have access to low interest rates and long mortgage tenors.  https://echostonehousing.com/2019/06/04/echostone-breaks-ground-in-green-affordable-housing-with-ifcs- edge-certification/ 16