The document describes the application of critical chain project management and portfolio management approaches to the construction of a 670km gas pipeline project in Brazil. Key points:
1) The project faced serious schedule delays due to weather issues and unforeseen problems, so advanced project management methods were applied to try to recover schedule.
2) Methods used included Success Driven Project Management (SDPM), a Russian approach similar to critical chain principles, and project portfolio management to optimize resource allocation across smaller sub-projects.
3) SDPM involved planning for risks/uncertainties, tracking success probabilities, and managing contingency reserves to aid schedule recovery.