Agenda


            Troubled Projects Defined
            What’s at Stake
            Root Causes of Troubled Projects
            Top Recovery Actions
            Case Studies
            The Positive Influence of Processes
            The Importance of the Project Manager




slide 2 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Troubled Projects Defined

   It is unrealistic to have one all encompassing definition of a
   troubled project because there are many variables. It is better
   to look for indicators that suggest you are there, such as:
            No one really knows when the project will finish and many have
             stopped guessing
            Management cannot control the project or assess current status
             accurately
            Failure to meet key milestones
            Team is working significant extra hours and team morale is low
            High risk of not delivering anticipated benefits
            Resources are not committed or allocated
            Mounting unresolved technical issues
            Excessive number of risk events and/or change requests

slide 3 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
What’s at Stake

   Dollars at Risk in the Average Organization: $74 million
   (Based on 20,821 projects closed in the last 12 months by 134 organizations)


         Average number of projects closed per firm……………………….155
         Average total cost of closed projects per firm………................$200M
         Average Cost per project………………………………………….$1.3M
         Percentage of projects at risk (recovered 25% or failed 12%) ……….…...37%




   Source: Strategies for Project Recovery, PM Solutions’ Research, 2011

slide 4 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Poll Question


      What do you think is the                                                                    Pick list:
      main cause of troubled                                                                       Planning
      projects in your                                                                             Resources
      organization?
                                                                                                   Requirements
                                                                                                   Risks
                                                                                                   Schedules
                                                                                                   Other




slide 5 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Top 5 Causes of Troubled Projects




   Source: Strategies for Project Recovery, PM Solutions’ Research, 2011

slide 6 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Top 5 Actions Taken to Recover Projects


                                 1          Improve Communication


                                         2          Redefine the Project


                                           3          Add and/or Remove Resources


                                        4           Resolve Problematic Technical Issues


                                 5          Replace the Project Manager



   Source: Strategies for Project Recovery, PM Solutions’ Research, 2011

slide 7 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
1. Improve Communication / Stakeholder Mgmt.


               Identify stakeholders
               Plan communications - stakeholder analysis
               Distribute information - needs and resources
               Manage stakeholder expectations
               Report performance


            Create and support open communication
          as the knowledge begins to transfer creative
          solutions will emerge that help speed recovery



   Source: PMBOK Guide, 4th Edition, PMI, 2008

slide 8 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Case Study

                                                                       Actions Taken:
                                                                       A public engagement process was
                                                                       developed; meetings were held with
                                                                       stakeholders to explain the need, address
                                                                       issues, and build support; realistic cost
                                                                       estimates and schedules were developed.
    VELCO was required
    to provide a
    redundant electrical                                               Result
    feed into the area to                                              The project was completed on time and $6
    meet regional                                                      million under budget. At the same time,
    reliability criteria.                                              customer satisfaction scores increased by
    However, the project                                               20%. The project was granted a board
    faced public and                                                   certificate to proceed six months earlier than
    legislative pressures.                                             previous large transmission projects — an
                                                                       exponential savings of time and money for
                                                                       VELCO.

slide 9 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
2. Redefine the Project

         Ensure that all stakeholders
          understand and follow procedures
         Establish predefined authority and
          approval points
         Involve the appropriate people in
          decisions
         Evaluate scope, cost/resources,
          schedule, and risk
         Define and communicate the
          change to project stakeholders
         Document and track the change


slide 10 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Case Study

                                                                       Actions Taken:
                                                                       An outside team was assembled to apply
   Food and beverage
                                                                       more rigorous program controls relative to
   manufacturer, R&D
                                                                       scheduling, cost estimating, resource
   division
                                                                       projections, vendor management, and
                                                                       progress reporting.
   The company had less
   than two years to
                                                                       Result
   reformulate, test,
   produce, and                                                        The program was completed six months
   distribute over 450 of                                              ahead of schedule and $2 million under
   its products in order to                                            budget. A structured program process was
   meet deadlines for                                                  introduced and implemented, the team was
   regulatory compliance.                                              willing to challenge the status quo to simplify
                                                                       the reformulation process, and clear
                                                                       accountability ensured work was being
                                                                       completed as planned.

slide 11 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
3. Add or Remove Resources


    Successful recovery projects often hinge on key
    resources
     Resources contribute to the problem as well as
       the recovery
     Plan carefully for any changes in personnel
     Resource staffing requires a close examination
       of key resources
     Establish an effective resource on-boarding and
       off-boarding
     A key external resource can be more efficient to
       rapidly recover the project




slide 12 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Case Study

                                                                       Actions Taken:
    Global manufacturer                                                Skilled resources were added to lead the
    of automotive                                                      project. Client/vendor requirements,
    components                                                         milestones, resource projections, estimates,
                                                                       and delivery targets were all reset.
    A major HR
    Transformation                                                     Result
    Program with 15                                                    All 15 projects within the program were
    discreet projects                                                  completed on schedule and on budget, with
    made little progress                                               no service disruptions. Within seven months
    in 8 months, and had                                               of program completion HR expenses were
    just 4 more months                                                 reduced from US $20 million to $6.8 million
    to right-source key                                                per year, and is targeted for a $5 million per
    HR functions.                                                      year run rate.


slide 13 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
4. Resolve Problematic Technical Issues

       Partner closely with the “owner” of the technical system
       Study the technical issue to understand it’s full range of
        effect. A normal technical solution spans functions,
        geographies, etc.
       In recovery, the goal should be to fail early….
       Vendor resources can add real technical value
       Leverage vendor technical expertise early in
        the assessment and recovery effort
       Understand customer needs in order to frame acceptable
        alternative solutions



slide 14 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
5. Replace the Project Manager


       Successful Recovery Project Managers demonstrate a
        specialized skill set:
                – Knowledge of recovery techniques
                – Capability to be frank and honest about
                  critical issues, urgency, change, etc.
                – Decisive
                – Proactive
                – Political awareness and ability to navigate strong politics
                – An understanding of the organizational culture
       If possible, consider a Project Manager skilled in project
        recovery to partner with the current PM

slide 15 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Case Study


 Manufacturer of                                                       Actions Taken:
 nutritional products                                                  Outside help was brought in to review the
                                                                       program, re-plan all projects, and assume
 A company divestiture                                                 control of program operations.
 called for an unmovable
 deadline to convert                                                   Result
 legacy IT systems                                                     All individual projects within the program
 within sales, marketing,                                              were delivered on time and were ready for
 and manufacturing                                                     integration with the enterprise ERP system.
 systems. Little progress                                              The program turnaround quickly saved an
 was made in the first 4                                               estimated US $2 million in system support
 months and the                                                        fees by moving applications in-house.
 program was in peril.




slide 16 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
The Importance of the Project Manager


                                                                         Indicators of an effective recovery PM
                                                                          Stakeholders fare well informed and
                                                                           satisfied.
                                                                          Stakeholders trust the PM
                                                                          The project team is performing at a high level
                                                                          Project milestones are achieved on time
                                                                          The PM “owns” the project and accept
                                                                           responsibility for its status, results, and
                                                                           delivery




   Source: Strategies for Project Recovery, PM Solutions’ Research, 2011

slide 17 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
The Positive Influence of Process

    The benefit of having a standardized project management
    process cannot be overstated. There is a high correlation
    between lack of a process and project failure. Some key
    data;
     Almost a quarter (22%) of firms surveyed did not have a standard
      methodology for managing projects
     Firms without a methodology saw a higher percentage of project
      failures than those with (21% vs. 9%)
     Firms with a troubled project recovery process (68% of firms
      surveyed) had 3x fewer project failures as those that did not have one




   Source: Strategies for Project Recovery, PM Solutions’ Research, 2011

slide 18 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
Thank You!

                 J. Kent Crawford, PMP
                 kcrawford@pmsolutions.com




slide 19 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)

More Related Content

What's hot

Project governance
Project governanceProject governance
Project governanceGlen Alleman
 
Project management
Project managementProject management
Project managementSimran Kaur
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMOfficers PMOAcademy
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxAmjadAlk
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...Edureka!
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklistBob Prieto
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008ITVAMP, LLC
 
8 Most Effective Requirements Gathering Techniques.
8 Most Effective Requirements Gathering Techniques.8 Most Effective Requirements Gathering Techniques.
8 Most Effective Requirements Gathering Techniques.Xebrio
 
Project Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | EdurekaProject Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | EdurekaEdureka!
 

What's hot (20)

Project governance
Project governanceProject governance
Project governance
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
 
Project management
Project managementProject management
Project management
 
PMO - Delivering Business Results
PMO - Delivering Business ResultsPMO - Delivering Business Results
PMO - Delivering Business Results
 
Project charter-template
Project charter-templateProject charter-template
Project charter-template
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts OverviewPMO - Strategic Model & Concepts Overview
PMO - Strategic Model & Concepts Overview
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptx
 
Why Agile?
Why Agile?Why Agile?
Why Agile?
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Scrum Product Owner
Scrum Product OwnerScrum Product Owner
Scrum Product Owner
 
Project governance
Project governanceProject governance
Project governance
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008
 
8 Most Effective Requirements Gathering Techniques.
8 Most Effective Requirements Gathering Techniques.8 Most Effective Requirements Gathering Techniques.
8 Most Effective Requirements Gathering Techniques.
 
Project Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | EdurekaProject Management Tutorial | PMP Certification | Edureka
Project Management Tutorial | PMP Certification | Edureka
 
PMP
PMPPMP
PMP
 

Similar to Practical Strategies for Project Recovery Webinar Slides

AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdfJamieDornan2
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1Aconex
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_managementSociety of Women Engineers
 
PM-Partners Group 10 Point Project Checklist
PM-Partners Group 10 Point Project ChecklistPM-Partners Group 10 Point Project Checklist
PM-Partners Group 10 Point Project Checklistihoudane
 
ACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxwrite30
 
ACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxwrite22
 
0. Foundations of project management (2).ppt
0. Foundations of project management (2).ppt0. Foundations of project management (2).ppt
0. Foundations of project management (2).pptAbelMuluqen
 
Project+ updated prsntn 2012
Project+ updated prsntn 2012Project+ updated prsntn 2012
Project+ updated prsntn 2012CAMTIC
 
Meeting the Challenge of Vivek Kundra's 25 Point Plan
Meeting the Challenge of Vivek Kundra's 25 Point PlanMeeting the Challenge of Vivek Kundra's 25 Point Plan
Meeting the Challenge of Vivek Kundra's 25 Point PlanPlanet Technologies
 
Project Management1
Project Management1Project Management1
Project Management1ibsslideshow
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)tehreem fatima
 
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management  - part 2 (Ukrainian PM Community)Vijay Prasad - Project Management  - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)mandrew182
 
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)mandrew182
 
Project Management . The Change Agent
Project Management . The Change AgentProject Management . The Change Agent
Project Management . The Change AgentSoftServe
 

Similar to Practical Strategies for Project Recovery Webinar Slides (20)

AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdf
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
1 ch1
1 ch11 ch1
1 ch1
 
PM-Partners Group 10 Point Project Checklist
PM-Partners Group 10 Point Project ChecklistPM-Partners Group 10 Point Project Checklist
PM-Partners Group 10 Point Project Checklist
 
ACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docx
 
ACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docxACT College Arlington Project Management and Company Performance Paper.docx
ACT College Arlington Project Management and Company Performance Paper.docx
 
0. Foundations of project management (2).ppt
0. Foundations of project management (2).ppt0. Foundations of project management (2).ppt
0. Foundations of project management (2).ppt
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Project+ updated prsntn 2012
Project+ updated prsntn 2012Project+ updated prsntn 2012
Project+ updated prsntn 2012
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Meeting the Challenge of Vivek Kundra's 25 Point Plan
Meeting the Challenge of Vivek Kundra's 25 Point PlanMeeting the Challenge of Vivek Kundra's 25 Point Plan
Meeting the Challenge of Vivek Kundra's 25 Point Plan
 
Project Management1
Project Management1Project Management1
Project Management1
 
Project Management by Results / by Objectives
Project Management by Results / by ObjectivesProject Management by Results / by Objectives
Project Management by Results / by Objectives
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)
 
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management  - part 2 (Ukrainian PM Community)Vijay Prasad - Project Management  - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
 
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
Vijay Prasad - Project Management - part 2 (Ukrainian PM Community)
 
Project Management . The Change Agent
Project Management . The Change AgentProject Management . The Change Agent
Project Management . The Change Agent
 

More from PM Solutions

The State of the Project Management Office (PMO) 2014
The State of the Project Management Office (PMO) 2014The State of the Project Management Office (PMO) 2014
The State of the Project Management Office (PMO) 2014PM Solutions
 
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...PM Solutions
 
State of Project Portfolio Management (PPM) 2013 Research Report
State of Project Portfolio Management (PPM) 2013 Research ReportState of Project Portfolio Management (PPM) 2013 Research Report
State of Project Portfolio Management (PPM) 2013 Research ReportPM Solutions
 
PMO of the Year Award 2011 eBook
PMO of the Year Award 2011 eBookPMO of the Year Award 2011 eBook
PMO of the Year Award 2011 eBookPM Solutions
 
Research Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryResearch Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryPM Solutions
 
3 Strategies for Overcoming Resource Management Challenges
3 Strategies for Overcoming Resource Management Challenges3 Strategies for Overcoming Resource Management Challenges
3 Strategies for Overcoming Resource Management ChallengesPM Solutions
 
PMO of the Year Award 2010 eBook
PMO of the Year Award 2010 eBookPMO of the Year Award 2010 eBook
PMO of the Year Award 2010 eBookPM Solutions
 

More from PM Solutions (7)

The State of the Project Management Office (PMO) 2014
The State of the Project Management Office (PMO) 2014The State of the Project Management Office (PMO) 2014
The State of the Project Management Office (PMO) 2014
 
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
 
State of Project Portfolio Management (PPM) 2013 Research Report
State of Project Portfolio Management (PPM) 2013 Research ReportState of Project Portfolio Management (PPM) 2013 Research Report
State of Project Portfolio Management (PPM) 2013 Research Report
 
PMO of the Year Award 2011 eBook
PMO of the Year Award 2011 eBookPMO of the Year Award 2011 eBook
PMO of the Year Award 2011 eBook
 
Research Report: Strategies for Project Recovery
Research Report: Strategies for Project RecoveryResearch Report: Strategies for Project Recovery
Research Report: Strategies for Project Recovery
 
3 Strategies for Overcoming Resource Management Challenges
3 Strategies for Overcoming Resource Management Challenges3 Strategies for Overcoming Resource Management Challenges
3 Strategies for Overcoming Resource Management Challenges
 
PMO of the Year Award 2010 eBook
PMO of the Year Award 2010 eBookPMO of the Year Award 2010 eBook
PMO of the Year Award 2010 eBook
 

Recently uploaded

FEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service LightningFEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service LightningFEXLE
 
Copyright: What Creators and Users of Art Need to Know
Copyright: What Creators and Users of Art Need to KnowCopyright: What Creators and Users of Art Need to Know
Copyright: What Creators and Users of Art Need to KnowMiriam Robeson
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxSymbio Agency Ltd
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfAgusHalim9
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future worldChris Skinner
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...srcw2322l101
 
Aptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfAptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfprchbhandari
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesAlejandro Cremades
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseirhcs
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsSlidesAI
 
Aspire Time & Life Leadership Workshop 2024
Aspire Time & Life Leadership Workshop 2024Aspire Time & Life Leadership Workshop 2024
Aspire Time & Life Leadership Workshop 2024Dr Sam Collins
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product DiscoveryDesmond Leo
 
PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsAlejandro Cremades
 
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptxBlinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptxSaksham Gupta
 
Falcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon investment
 
Making Sense of Tactile Indicators: A User-Friendly Guide
Making Sense of Tactile Indicators: A User-Friendly GuideMaking Sense of Tactile Indicators: A User-Friendly Guide
Making Sense of Tactile Indicators: A User-Friendly GuideEminent Tactiles
 
Your Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptxYour Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptxOs Hillman
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Alejandro Cremades
 
tekAura | Desktop Procedure Template (2016)
tekAura | Desktop Procedure Template (2016)tekAura | Desktop Procedure Template (2016)
tekAura | Desktop Procedure Template (2016)Norah Medlin
 
Series A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by AccionSeries A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by AccionAlejandro Cremades
 

Recently uploaded (20)

FEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service LightningFEXLE- Salesforce Field Service Lightning
FEXLE- Salesforce Field Service Lightning
 
Copyright: What Creators and Users of Art Need to Know
Copyright: What Creators and Users of Art Need to KnowCopyright: What Creators and Users of Art Need to Know
Copyright: What Creators and Users of Art Need to Know
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptx
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (2024).pdf
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future world
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 
Aptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdfAptar Closures segment - Corporate Overview-India.pdf
Aptar Closures segment - Corporate Overview-India.pdf
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE Ventures
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings release
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team Presentations
 
Aspire Time & Life Leadership Workshop 2024
Aspire Time & Life Leadership Workshop 2024Aspire Time & Life Leadership Workshop 2024
Aspire Time & Life Leadership Workshop 2024
 
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
8 Questions B2B Commercial Teams Can Ask To Help Product Discovery
 
PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for Startups
 
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptxBlinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
 
Falcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small Businesses
 
Making Sense of Tactile Indicators: A User-Friendly Guide
Making Sense of Tactile Indicators: A User-Friendly GuideMaking Sense of Tactile Indicators: A User-Friendly Guide
Making Sense of Tactile Indicators: A User-Friendly Guide
 
Your Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptxYour Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptx
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)
 
tekAura | Desktop Procedure Template (2016)
tekAura | Desktop Procedure Template (2016)tekAura | Desktop Procedure Template (2016)
tekAura | Desktop Procedure Template (2016)
 
Series A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by AccionSeries A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by Accion
 

Practical Strategies for Project Recovery Webinar Slides

  • 1. Practical Strategies for Project Recovery J. Kent Crawford, PMP, PMI Fellow Originally Presented via Webinar on March 24, 2011 slide 1 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 2. Agenda  Troubled Projects Defined  What’s at Stake  Root Causes of Troubled Projects  Top Recovery Actions  Case Studies  The Positive Influence of Processes  The Importance of the Project Manager slide 2 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 3. Troubled Projects Defined It is unrealistic to have one all encompassing definition of a troubled project because there are many variables. It is better to look for indicators that suggest you are there, such as:  No one really knows when the project will finish and many have stopped guessing  Management cannot control the project or assess current status accurately  Failure to meet key milestones  Team is working significant extra hours and team morale is low  High risk of not delivering anticipated benefits  Resources are not committed or allocated  Mounting unresolved technical issues  Excessive number of risk events and/or change requests slide 3 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 4. What’s at Stake Dollars at Risk in the Average Organization: $74 million (Based on 20,821 projects closed in the last 12 months by 134 organizations)  Average number of projects closed per firm……………………….155  Average total cost of closed projects per firm………................$200M  Average Cost per project………………………………………….$1.3M  Percentage of projects at risk (recovered 25% or failed 12%) ……….…...37% Source: Strategies for Project Recovery, PM Solutions’ Research, 2011 slide 4 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 5. Poll Question What do you think is the Pick list: main cause of troubled  Planning projects in your  Resources organization?  Requirements  Risks  Schedules  Other slide 5 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 6. Top 5 Causes of Troubled Projects Source: Strategies for Project Recovery, PM Solutions’ Research, 2011 slide 6 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 7. Top 5 Actions Taken to Recover Projects 1 Improve Communication 2 Redefine the Project 3 Add and/or Remove Resources 4 Resolve Problematic Technical Issues 5 Replace the Project Manager Source: Strategies for Project Recovery, PM Solutions’ Research, 2011 slide 7 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 8. 1. Improve Communication / Stakeholder Mgmt.  Identify stakeholders  Plan communications - stakeholder analysis  Distribute information - needs and resources  Manage stakeholder expectations  Report performance Create and support open communication as the knowledge begins to transfer creative solutions will emerge that help speed recovery Source: PMBOK Guide, 4th Edition, PMI, 2008 slide 8 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 9. Case Study Actions Taken: A public engagement process was developed; meetings were held with stakeholders to explain the need, address issues, and build support; realistic cost estimates and schedules were developed. VELCO was required to provide a redundant electrical Result feed into the area to The project was completed on time and $6 meet regional million under budget. At the same time, reliability criteria. customer satisfaction scores increased by However, the project 20%. The project was granted a board faced public and certificate to proceed six months earlier than legislative pressures. previous large transmission projects — an exponential savings of time and money for VELCO. slide 9 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 10. 2. Redefine the Project  Ensure that all stakeholders understand and follow procedures  Establish predefined authority and approval points  Involve the appropriate people in decisions  Evaluate scope, cost/resources, schedule, and risk  Define and communicate the change to project stakeholders  Document and track the change slide 10 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 11. Case Study Actions Taken: An outside team was assembled to apply Food and beverage more rigorous program controls relative to manufacturer, R&D scheduling, cost estimating, resource division projections, vendor management, and progress reporting. The company had less than two years to Result reformulate, test, produce, and The program was completed six months distribute over 450 of ahead of schedule and $2 million under its products in order to budget. A structured program process was meet deadlines for introduced and implemented, the team was regulatory compliance. willing to challenge the status quo to simplify the reformulation process, and clear accountability ensured work was being completed as planned. slide 11 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 12. 3. Add or Remove Resources Successful recovery projects often hinge on key resources  Resources contribute to the problem as well as the recovery  Plan carefully for any changes in personnel  Resource staffing requires a close examination of key resources  Establish an effective resource on-boarding and off-boarding  A key external resource can be more efficient to rapidly recover the project slide 12 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 13. Case Study Actions Taken: Global manufacturer Skilled resources were added to lead the of automotive project. Client/vendor requirements, components milestones, resource projections, estimates, and delivery targets were all reset. A major HR Transformation Result Program with 15 All 15 projects within the program were discreet projects completed on schedule and on budget, with made little progress no service disruptions. Within seven months in 8 months, and had of program completion HR expenses were just 4 more months reduced from US $20 million to $6.8 million to right-source key per year, and is targeted for a $5 million per HR functions. year run rate. slide 13 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 14. 4. Resolve Problematic Technical Issues  Partner closely with the “owner” of the technical system  Study the technical issue to understand it’s full range of effect. A normal technical solution spans functions, geographies, etc.  In recovery, the goal should be to fail early….  Vendor resources can add real technical value  Leverage vendor technical expertise early in the assessment and recovery effort  Understand customer needs in order to frame acceptable alternative solutions slide 14 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 15. 5. Replace the Project Manager  Successful Recovery Project Managers demonstrate a specialized skill set: – Knowledge of recovery techniques – Capability to be frank and honest about critical issues, urgency, change, etc. – Decisive – Proactive – Political awareness and ability to navigate strong politics – An understanding of the organizational culture  If possible, consider a Project Manager skilled in project recovery to partner with the current PM slide 15 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 16. Case Study Manufacturer of Actions Taken: nutritional products Outside help was brought in to review the program, re-plan all projects, and assume A company divestiture control of program operations. called for an unmovable deadline to convert Result legacy IT systems All individual projects within the program within sales, marketing, were delivered on time and were ready for and manufacturing integration with the enterprise ERP system. systems. Little progress The program turnaround quickly saved an was made in the first 4 estimated US $2 million in system support months and the fees by moving applications in-house. program was in peril. slide 16 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 17. The Importance of the Project Manager Indicators of an effective recovery PM  Stakeholders fare well informed and satisfied.  Stakeholders trust the PM  The project team is performing at a high level  Project milestones are achieved on time  The PM “owns” the project and accept responsibility for its status, results, and delivery Source: Strategies for Project Recovery, PM Solutions’ Research, 2011 slide 17 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 18. The Positive Influence of Process The benefit of having a standardized project management process cannot be overstated. There is a high correlation between lack of a process and project failure. Some key data;  Almost a quarter (22%) of firms surveyed did not have a standard methodology for managing projects  Firms without a methodology saw a higher percentage of project failures than those with (21% vs. 9%)  Firms with a troubled project recovery process (68% of firms surveyed) had 3x fewer project failures as those that did not have one Source: Strategies for Project Recovery, PM Solutions’ Research, 2011 slide 18 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)
  • 19. Thank You! J. Kent Crawford, PMP kcrawford@pmsolutions.com slide 19 | confidential and proprietary information | © 2011 Project Management Solutions, Inc. (www.pmsolutions.com)