The Port of Virginia – Meeting Future Needs Today


      The Virginia Port Authority
The 2040 Master Plan and Intermodal Connectivity




                        May 9, 2005
The Port of Virginia
                  Jamestown 1607
   Godspeed
                      Discovery
  Length = 68’
                   Length = 49’ 6”
                   20 tons (1 TEU)




                     Hapag-Lloyd Columbo Express
Susan Constant      Length = 1,099’    Width = 141’
 Length = 116’              8,750 TEU Ship
The Port of Virginia

 First Ship Sails from Jamestown with Export
  Cargo
   Year is 1607
   No Dredging Required
   No Highway Required
   No Railroad Required
   Small Landside Facilities Required (Wooden
    Pier)
 Low Financial Investment
 By 1630 Tobacco Exports to Europe
   1,500,000 lbs = 750 Tons = 50 TEUs!
Fast Forward 400 Years


 2004 The Port of Virginia Handled 1,810,000 TEUs
 2003 First 8,000 TEU Vessel Sets Sail
 Require Considerable Dredging
 Require Major Interstate Highways
 Require Major Railroads
 Require Considerable Port Infrastructure
Agenda


 The Port of Virginia
 Ports 101
 The VPA 2040 Master Plan
 Summary
The Port of Virginia

 The Virginia Port Authority (VPA)
   An Agency of the Commonwealth
   Fosters and Stimulates the Commerce of the
    Commonwealth
   Engages in Promoting, Developing, Constructing,
    Equipping, Maintaining and Operating the Harbors
    and Seaports Within the Jurisdiction of the
    Commonwealth

 Virginia International Terminals (VIT)
   A Virginia Non-Stock, Non-Profit Operating Affiliate of
    the Virginia Port Authority
   Operates the Terminals Owned by the Commonwealth
Economic Impact of The Port


          1999 Economic Impact Study*
               165,000 Port and Port-Related Jobs
               $762.5 Million in Business Revenues
               $60.7 Million in State and Local Taxes

          2003 Bureau of Economic Statistics Report
               The Port Plays a Part in Over 180,000 Jobs
               Salary and Wages in Excess of $5 Billion



*Source: Martin Associates
Distribution of Ship Calls
                        at The Port of Virginia
        More Than 75 Steamship Lines Serve the Port
        Sailings to Over 250 Ports in 100 Overseas Locations

   The Port of Virginia is within a
    1-day drive of over 2/3 of the
    U.S. population and 301,000
        manufacturing firms


                                                           780
                          The Port
                         of Virginia                       468                    832
                                                                            364
                            780                     208


                                       260      The Port of Virginia is within
                                               750 miles of 60% of the nation’s
                                                 total personal income and
                                                                                        52
                                                   consumer expenditures

*Many services call more than one tradelane.
U.S. National Gateways
  Vancouver, BC

                    90% of Containerized
Seattle/Tacoma
                  Trade Moves Through 10
                    North American Port
                         Gateways



                                                                               New York/
                                                                               New Jersey
  Oakland
                                           The Port of Virginia is the
                                             7th Largest Gateway


  Los Angeles/
  Long Beach
                                                                           Charleston
                                                                         Savannah



                                           Houston                         Miami
U.S. Cargo Trends


 44% of U.S. Import Cargo Comes into the Port of
  Los Angeles/Long Beach
       Transported to Mid-West via Rail and Truck
 West Coast Port Congestion Has Diverted Cargo
  to East Coast Ports via All-Water Route
 VPA Experienced Major Growth in Asia Trade
  Lanes in 2004
       SE Asia         19.6%
       NE Asia         22.8%
VPA Containerized Trade
                                           by Region

       450,000
                                                                                                              Percentage Share of Total
       400,000            30.1%

       350,000                                                        27.3%
TEUs




       300,000

       250,000

       200,000

       150,000                                                                            11.1%
                                                                                                                                        10.0%
       100,000                        6.4%                                        5.8%
        50,000   3.1%                                                                             3.9%

                                                0.3%     0.6%                                                  0.2%          1.0%




                                                                                                                                         S AMERICA
                                                                       N EUROPE
                                                          C AMERICA




                                                                                  INDIA



                                                                                           MED




                                                                                                                              OCEANIA
                 AFRICA



                           NE ASIA



                                      SE ASIA



                                                 CARIB




                                                                                                                 N AMERICA
Source: PIERS Trade Data, 2004                                                                     MID EAST
The Intermodal Gateway

 The 1.81 Million TEUs
  Exported/Imported From
  the Port of Virginia in 2004
  Were Transported to
  Inland Markets Using:

    Barges (12% of TEUs)

    Rail     (22% of TEUs)

    Trucks (66% of TEUs)
The Port of Virginia Cargo Origins and Destinations




 Origins and
  Destinations
  Throughout the

  Mid-Atlantic &
  Mid-West

 Over 55% of
  Cargo Enters
                                                                CONTAINER VOLUME
  or Leaves                                                         1 - 1,000
                                                                    1,001 - 2,500

  the State                                                         2,501 - 7,500
                                                                    7,501 - 15,000
                                                                    15,001 - 45,000
Agenda


 The Port of Virginia
 Ports 101
 The VPA 2040 Master Plan
 Summary
Ports 101

        20’
                                      Port Capacity and
                                       Productivity is Often
                                       Measured in TEUs
One 20’ container = 1 TEU             TEU Stands for
                    40’
                                       “Twenty Foot
                                       Equivalent Unit”
                                      Original Containers
                                       Were 20’ Long
One 40’ container = 2 TEU
              53’                     Today, Most Cargo is
                                       Moved in 40’
                                       Containers

Typical over the road truck
On-Dock Operations

 Container Vessel Arrives at VPA Marine Terminals Using Deep
  Water Navigation Channels in the Hampton Roads Harbor
On-Dock Operations

 Containers are Unloaded  New Cranes at NIT South Terminal are
  from the Ship Using       the Largest, Fastest, and Most Efficient
  Specialized Cranes        Container Cranes in the World
Live Gate System
        With Straddle Carrier

 Containers are Picked-Off the Wharf by Specialized
  “Straddle Carrier” Vehicles
Live Gate System
              With Straddle Carrier
 Straddle Carriers Transfer    Transport & Location of Each
  the Box to the Container       Container is Tracked Using Highly
  Yard for Temporary Storage     Sophisticated Electronic Systems
Live Gate System
              With Straddle Carrier
 Straddle Carriers Remove the    A “Live Gate” Operation Allows
  Container from Storage and       Just-In-Time Scheduling of
  Load it onto Trucks              Trucks Picking-Up Containers
Gate Operations

 Trucks are Processed at the Gate Interchange for Cargo
  Validation and a Special Roadability Safety Check
Gate Operations

 Trucks are Processed at the VPA  Increased Security Since 9/11
  Port Police Security Gate before  All Port Police are Sworn Law
  Exiting the Terminal               Enforcement Officers
Agenda


 The Port of Virginia
 Ports 101
 The VPA 2040 Master Plan
 Summary
Container Cargo Forecast

                     3.50


                     3.00                               1.8 Million TEU’s in 2004

                                                         9.2% Increase From 2003
                     2.50
  TEUs in Millions




                     2.00


                     1.50


                     1.00

                                                                              Master Plan Forecast*, 4.1% (2000)
                     0.50
                                                                              Actual Growth

                     0.00
                              98


                                     00


                                            02


                                                   04


                                                           06




                                                                         10


                                                                                12


                                                                                       14


                                                                                                16


                                                                                                       18


                                                                                                              20
                                                                  08
                            19


                                   20


                                          20


                                                 20


                                                         20




                                                                       20


                                                                              20


                                                                                     20


                                                                                              20


                                                                                                     20


                                                                                                            20
                                                                20




                                                                  YEAR

Source: VPA 2040 Master Plan
*Forecast Numbers Prepared in 2000 and Represent Average Increase Over the 40-Year Forecast Period.
Projected Cargo Demand
                                        and Planned Capacity

                6,000,000
                                                      Containerized Cargo
                                                      Forecast, 4.1% AGR
                5,000,000                             (Source: Global Insight, 2003)
TEUs per year




                4,000,000                 Planned Capacity
                                                                                                                                100%

                3,000,000


                2,000,000                                            33%


                1,000,000
                                                Maersk           Maersk                 CIMT       CIMT       CIMT        CIMT
                                   Existing
                                                Phase I          Phase II              Phase I    Phase II   Phase III   Phase IV
                            2001


                                         2005




                                                          2010



                                                                          2015




                                                                                           2020



                                                                                                     2025




                                                                                                                 2030



                                                                                                                         2035




                                                                                                                                       2040
Development Challenges

 The Port Must Meet Cargo Growth Demands to Promote
  Economic Development in Virginia
 The Volume of Containers is Estimated to More Than
  Double Every 20 Years
 Ship Lines are Moving Toward Larger Ships (10,000+ TEUs),
  Which Require…
      …Larger Cranes
      …More Efficient Marine Terminals
      …Efficient Intermodal Transportation Systems (Rail/Roadway)
 Existing Port Infrastructure Requires Renovation and
  Replacement
 Existing Terminals are Very Near Capacity
Development Challenges

 VPA’s 2040 Master Plan Identifies Major Capital
  Improvements Needed to Keep Pace with Growth
 Near Term (0-15 years)
    $510 Million for NIT (Currently Underway)
    $119 Million for PMT
    $27 Million for NNMT
    $6 Million for VIP

 Long Term (15-30 years)
    $1.76 Billion for New Marine Terminal At Craney Island
Summary of 2040 Master Plan
                        Investments


                       Project                                  Investment1              Time Span

 Norfolk International Terminals2                               $     735.0 M            2001 - 2021

 Portsmouth Marine Terminal2                                    $     187.4 M            2002 - 2015

 Newport News Marine Terminal2                                  $       25.7 M           2004 - 2010

 Virginia Inland Port2                                          $         6.1 M          2005 - 2020

 Craney Island Marine Terminal                                  $ 1,760.3 M              2009 - 2032

 55-Foot Channel Dredging                                       $     169.2 M            2011 - 2013

                      TOTAL INVESTMENT:                         $ 2,883.7 M
Notes: (1) Costs adjusted for inflation. (2) Projects entirely within VPA/VIT control.
Sources of VPA Funds
                      for 2040 Master Plan
Master Equipment            State              CPF Bonds
 Lease Program          Appropriations        $693 M (24%)
   $43 M (2%)            $336 M (11%)




                                            Terminal Revenue
    Pay-As-You-Go                                Bonds
     $1.26 B (44%)                            $551 M (19%)


     Total Funds Required From All Sources = $2.88B
Norfolk International Terminals
       Wharf Renovation
Norfolk International Terminals
          New Cranes
Norfolk International Terminals
    Elevating Girder Crane
Norfolk International Terminals
     Backlands Renovation
Craney Island Marine Terminal
      Terminal Build-Out
Schedule to Meet Forecasted Need




 Feasibility Study (1999 – 2005)
              PED (2005 – 2007)
Dike Construction (2007 – 2009)
        Rapid Fill (2009 – 2011)
           Phase I (2012 – 2016)
          Phase II (2019 – 2022)
         Phase III (2026 – 2028)
         Phase IV (2028 – 2032)
                                             08




                                                            14


                                                                      18




                                                                                     24




                                                                                                    30
                                   04

                                        06



                                                  10

                                                       12


                                                                 16



                                                                           20

                                                                                22



                                                                                          26

                                                                                               28



                                                                                                         32

                                                                                                              34
                             02
                                   20

                                        20

                                             20

                                                  20

                                                       20

                                                            20
                                                                 20

                                                                      20

                                                                           20

                                                                                20

                                                                                     20

                                                                                          20

                                                                                               20

                                                                                                    20

                                                                                                         20

                                                                                                              20
                            20
Regional Economic Impact
              of Craney Island

 The Proposed Craney Island Marine Terminal will
  Provide Significant Regional Economic Impacts



        Craney Island Regional Economic
            Impact Forecast (Annually)
   Jobs                                 64,255
   Wages                       $ 1,658,000,000
   Taxes – State/Local         $ 487,000,000
   TOTAL IMPACT                $ 5,277,000,000
Hampton Roads
         Transportation Network
         Newport                        Chesapeake Bay
          News
James
 River




                              Norfolk


                                                   Virginia Beach


            Portsmouth


                                                                    Port Facility
                                                                    CIDMMA
                                                                    Interstate/Highway
                     Chesapeake                                     Proposed Third Crossing
                                                                    50/55 Ft Channel
                                                                    Railroad
                                                                    Proposed Maersk Terminal
                                                                    Proposed Craney Island Railway
                                                                    Proposed Craney Island Terminal
Agenda


 The Port of Virginia
 Ports 101
 The VPA 2040 Master Plan
 Summary
Summary


 The Port of Virginia is Poised to Double the Amount
  of Containerized Cargo Moving Through the Port
  over the Next 20 Years
 The Port has a Master Plan Designed to Handle this
  Growth
    Master Plan Accounts for Marine Terminals only
    Fiscally Responsible
 Doubling Containerized Cargo, will Provide
  Additional Economic Growth – Jobs, Good Wages,
  and Tax Revenues
 Transportation Infrastructure Must Be Developed To
  Accommodate Future Growth
The Port of Virginia's 2040 Master Plan for Future Growth

Más contenido relacionado

Similar a The Port of Virginia's 2040 Master Plan for Future Growth

Similar a The Port of Virginia's 2040 Master Plan for Future Growth (6)

MEDA Summer Conference 2015 - Port of Baltimore
MEDA Summer Conference 2015 - Port of BaltimoreMEDA Summer Conference 2015 - Port of Baltimore
MEDA Summer Conference 2015 - Port of Baltimore
 
Maritime, Logistics, Distribution And Warehousing in Virginia's Hampton Roads
Maritime, Logistics, Distribution And Warehousing in Virginia's Hampton RoadsMaritime, Logistics, Distribution And Warehousing in Virginia's Hampton Roads
Maritime, Logistics, Distribution And Warehousing in Virginia's Hampton Roads
 
Maritime, Logistics, Distribution And Warehousing 1st Quarter 2009
Maritime, Logistics, Distribution And Warehousing 1st Quarter 2009Maritime, Logistics, Distribution And Warehousing 1st Quarter 2009
Maritime, Logistics, Distribution And Warehousing 1st Quarter 2009
 
Ism Magazine Ports 2009
Ism Magazine Ports 2009Ism Magazine Ports 2009
Ism Magazine Ports 2009
 
Eero Mäkinen
Eero MäkinenEero Mäkinen
Eero Mäkinen
 
Bill Ralph, R.K. Johns & Associates
Bill Ralph, R.K. Johns & AssociatesBill Ralph, R.K. Johns & Associates
Bill Ralph, R.K. Johns & Associates
 

Más de Artemus Transportation Solutions (7)

Proactive Customer Service 1 16 04
Proactive Customer Service 1 16 04Proactive Customer Service 1 16 04
Proactive Customer Service 1 16 04
 
Viabc Presentation Feb 2010
Viabc Presentation Feb 2010Viabc Presentation Feb 2010
Viabc Presentation Feb 2010
 
Isf Presentation
Isf PresentationIsf Presentation
Isf Presentation
 
Setting Up Centralized Intermodal Iss Case Study
Setting Up Centralized Intermodal   Iss Case StudySetting Up Centralized Intermodal   Iss Case Study
Setting Up Centralized Intermodal Iss Case Study
 
Setting Up Centralized Documentation Iss Case Study
Setting Up Centralized Documentation   Iss Case StudySetting Up Centralized Documentation   Iss Case Study
Setting Up Centralized Documentation Iss Case Study
 
Training And Staffing Examples Hampton Roads Nynj Maritime
Training And Staffing Examples   Hampton Roads   Nynj MaritimeTraining And Staffing Examples   Hampton Roads   Nynj Maritime
Training And Staffing Examples Hampton Roads Nynj Maritime
 
E Commerce Vision Anzdl Aus 1997
E Commerce Vision   Anzdl Aus 1997E Commerce Vision   Anzdl Aus 1997
E Commerce Vision Anzdl Aus 1997
 

The Port of Virginia's 2040 Master Plan for Future Growth

  • 1. The Port of Virginia – Meeting Future Needs Today The Virginia Port Authority The 2040 Master Plan and Intermodal Connectivity May 9, 2005
  • 2. The Port of Virginia Jamestown 1607 Godspeed Discovery Length = 68’ Length = 49’ 6” 20 tons (1 TEU) Hapag-Lloyd Columbo Express Susan Constant Length = 1,099’ Width = 141’ Length = 116’ 8,750 TEU Ship
  • 3. The Port of Virginia  First Ship Sails from Jamestown with Export Cargo  Year is 1607  No Dredging Required  No Highway Required  No Railroad Required  Small Landside Facilities Required (Wooden Pier)  Low Financial Investment  By 1630 Tobacco Exports to Europe  1,500,000 lbs = 750 Tons = 50 TEUs!
  • 4. Fast Forward 400 Years  2004 The Port of Virginia Handled 1,810,000 TEUs  2003 First 8,000 TEU Vessel Sets Sail  Require Considerable Dredging  Require Major Interstate Highways  Require Major Railroads  Require Considerable Port Infrastructure
  • 5. Agenda  The Port of Virginia  Ports 101  The VPA 2040 Master Plan  Summary
  • 6.
  • 7. The Port of Virginia  The Virginia Port Authority (VPA)  An Agency of the Commonwealth  Fosters and Stimulates the Commerce of the Commonwealth  Engages in Promoting, Developing, Constructing, Equipping, Maintaining and Operating the Harbors and Seaports Within the Jurisdiction of the Commonwealth  Virginia International Terminals (VIT)  A Virginia Non-Stock, Non-Profit Operating Affiliate of the Virginia Port Authority  Operates the Terminals Owned by the Commonwealth
  • 8.
  • 9. Economic Impact of The Port  1999 Economic Impact Study* 165,000 Port and Port-Related Jobs $762.5 Million in Business Revenues $60.7 Million in State and Local Taxes  2003 Bureau of Economic Statistics Report The Port Plays a Part in Over 180,000 Jobs Salary and Wages in Excess of $5 Billion *Source: Martin Associates
  • 10. Distribution of Ship Calls at The Port of Virginia  More Than 75 Steamship Lines Serve the Port  Sailings to Over 250 Ports in 100 Overseas Locations The Port of Virginia is within a 1-day drive of over 2/3 of the U.S. population and 301,000 manufacturing firms 780 The Port of Virginia 468 832 364 780 208 260 The Port of Virginia is within 750 miles of 60% of the nation’s total personal income and 52 consumer expenditures *Many services call more than one tradelane.
  • 11. U.S. National Gateways Vancouver, BC 90% of Containerized Seattle/Tacoma Trade Moves Through 10 North American Port Gateways New York/ New Jersey Oakland The Port of Virginia is the 7th Largest Gateway Los Angeles/ Long Beach Charleston Savannah Houston Miami
  • 12. U.S. Cargo Trends  44% of U.S. Import Cargo Comes into the Port of Los Angeles/Long Beach  Transported to Mid-West via Rail and Truck  West Coast Port Congestion Has Diverted Cargo to East Coast Ports via All-Water Route  VPA Experienced Major Growth in Asia Trade Lanes in 2004  SE Asia  19.6%  NE Asia  22.8%
  • 13. VPA Containerized Trade by Region 450,000 Percentage Share of Total 400,000 30.1% 350,000 27.3% TEUs 300,000 250,000 200,000 150,000 11.1% 10.0% 100,000 6.4% 5.8% 50,000 3.1% 3.9% 0.3% 0.6% 0.2% 1.0% S AMERICA N EUROPE C AMERICA INDIA MED OCEANIA AFRICA NE ASIA SE ASIA CARIB N AMERICA Source: PIERS Trade Data, 2004 MID EAST
  • 14. The Intermodal Gateway  The 1.81 Million TEUs Exported/Imported From the Port of Virginia in 2004 Were Transported to Inland Markets Using:  Barges (12% of TEUs)  Rail (22% of TEUs)  Trucks (66% of TEUs)
  • 15. The Port of Virginia Cargo Origins and Destinations  Origins and Destinations Throughout the Mid-Atlantic & Mid-West  Over 55% of Cargo Enters CONTAINER VOLUME or Leaves 1 - 1,000 1,001 - 2,500 the State 2,501 - 7,500 7,501 - 15,000 15,001 - 45,000
  • 16. Agenda  The Port of Virginia  Ports 101  The VPA 2040 Master Plan  Summary
  • 17. Ports 101 20’  Port Capacity and Productivity is Often Measured in TEUs One 20’ container = 1 TEU  TEU Stands for 40’ “Twenty Foot Equivalent Unit”  Original Containers Were 20’ Long One 40’ container = 2 TEU 53’  Today, Most Cargo is Moved in 40’ Containers Typical over the road truck
  • 18.
  • 19.
  • 20. On-Dock Operations  Container Vessel Arrives at VPA Marine Terminals Using Deep Water Navigation Channels in the Hampton Roads Harbor
  • 21. On-Dock Operations  Containers are Unloaded  New Cranes at NIT South Terminal are from the Ship Using the Largest, Fastest, and Most Efficient Specialized Cranes Container Cranes in the World
  • 22. Live Gate System With Straddle Carrier  Containers are Picked-Off the Wharf by Specialized “Straddle Carrier” Vehicles
  • 23. Live Gate System With Straddle Carrier  Straddle Carriers Transfer  Transport & Location of Each the Box to the Container Container is Tracked Using Highly Yard for Temporary Storage Sophisticated Electronic Systems
  • 24. Live Gate System With Straddle Carrier  Straddle Carriers Remove the  A “Live Gate” Operation Allows Container from Storage and Just-In-Time Scheduling of Load it onto Trucks Trucks Picking-Up Containers
  • 25. Gate Operations  Trucks are Processed at the Gate Interchange for Cargo Validation and a Special Roadability Safety Check
  • 26. Gate Operations  Trucks are Processed at the VPA  Increased Security Since 9/11 Port Police Security Gate before  All Port Police are Sworn Law Exiting the Terminal Enforcement Officers
  • 27. Agenda  The Port of Virginia  Ports 101  The VPA 2040 Master Plan  Summary
  • 28. Container Cargo Forecast 3.50 3.00 1.8 Million TEU’s in 2004 9.2% Increase From 2003 2.50 TEUs in Millions 2.00 1.50 1.00 Master Plan Forecast*, 4.1% (2000) 0.50 Actual Growth 0.00 98 00 02 04 06 10 12 14 16 18 20 08 19 20 20 20 20 20 20 20 20 20 20 20 YEAR Source: VPA 2040 Master Plan *Forecast Numbers Prepared in 2000 and Represent Average Increase Over the 40-Year Forecast Period.
  • 29. Projected Cargo Demand and Planned Capacity 6,000,000 Containerized Cargo Forecast, 4.1% AGR 5,000,000 (Source: Global Insight, 2003) TEUs per year 4,000,000 Planned Capacity 100% 3,000,000 2,000,000 33% 1,000,000 Maersk Maersk CIMT CIMT CIMT CIMT Existing Phase I Phase II Phase I Phase II Phase III Phase IV 2001 2005 2010 2015 2020 2025 2030 2035 2040
  • 30. Development Challenges  The Port Must Meet Cargo Growth Demands to Promote Economic Development in Virginia  The Volume of Containers is Estimated to More Than Double Every 20 Years  Ship Lines are Moving Toward Larger Ships (10,000+ TEUs), Which Require… …Larger Cranes …More Efficient Marine Terminals …Efficient Intermodal Transportation Systems (Rail/Roadway)  Existing Port Infrastructure Requires Renovation and Replacement  Existing Terminals are Very Near Capacity
  • 31. Development Challenges  VPA’s 2040 Master Plan Identifies Major Capital Improvements Needed to Keep Pace with Growth  Near Term (0-15 years)  $510 Million for NIT (Currently Underway)  $119 Million for PMT  $27 Million for NNMT  $6 Million for VIP  Long Term (15-30 years)  $1.76 Billion for New Marine Terminal At Craney Island
  • 32. Summary of 2040 Master Plan Investments Project Investment1 Time Span Norfolk International Terminals2 $ 735.0 M 2001 - 2021 Portsmouth Marine Terminal2 $ 187.4 M 2002 - 2015 Newport News Marine Terminal2 $ 25.7 M 2004 - 2010 Virginia Inland Port2 $ 6.1 M 2005 - 2020 Craney Island Marine Terminal $ 1,760.3 M 2009 - 2032 55-Foot Channel Dredging $ 169.2 M 2011 - 2013 TOTAL INVESTMENT: $ 2,883.7 M Notes: (1) Costs adjusted for inflation. (2) Projects entirely within VPA/VIT control.
  • 33. Sources of VPA Funds for 2040 Master Plan Master Equipment State CPF Bonds Lease Program Appropriations $693 M (24%) $43 M (2%) $336 M (11%) Terminal Revenue Pay-As-You-Go Bonds $1.26 B (44%) $551 M (19%) Total Funds Required From All Sources = $2.88B
  • 34.
  • 35.
  • 38. Norfolk International Terminals Elevating Girder Crane
  • 39. Norfolk International Terminals Backlands Renovation
  • 40.
  • 41. Craney Island Marine Terminal Terminal Build-Out
  • 42. Schedule to Meet Forecasted Need Feasibility Study (1999 – 2005) PED (2005 – 2007) Dike Construction (2007 – 2009) Rapid Fill (2009 – 2011) Phase I (2012 – 2016) Phase II (2019 – 2022) Phase III (2026 – 2028) Phase IV (2028 – 2032) 08 14 18 24 30 04 06 10 12 16 20 22 26 28 32 34 02 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
  • 43. Regional Economic Impact of Craney Island  The Proposed Craney Island Marine Terminal will Provide Significant Regional Economic Impacts Craney Island Regional Economic Impact Forecast (Annually) Jobs 64,255 Wages $ 1,658,000,000 Taxes – State/Local $ 487,000,000 TOTAL IMPACT $ 5,277,000,000
  • 44. Hampton Roads Transportation Network Newport Chesapeake Bay News James River Norfolk Virginia Beach Portsmouth Port Facility CIDMMA Interstate/Highway Chesapeake Proposed Third Crossing 50/55 Ft Channel Railroad Proposed Maersk Terminal Proposed Craney Island Railway Proposed Craney Island Terminal
  • 45. Agenda  The Port of Virginia  Ports 101  The VPA 2040 Master Plan  Summary
  • 46. Summary  The Port of Virginia is Poised to Double the Amount of Containerized Cargo Moving Through the Port over the Next 20 Years  The Port has a Master Plan Designed to Handle this Growth  Master Plan Accounts for Marine Terminals only  Fiscally Responsible  Doubling Containerized Cargo, will Provide Additional Economic Growth – Jobs, Good Wages, and Tax Revenues  Transportation Infrastructure Must Be Developed To Accommodate Future Growth