Quality/Welding inspection during Offshore
Pipeline and Platform Installation
By Rahman Suwandhi
Personal Data
Name: Rahman Suwandhi
Graduated: Technical of Metallurgy 1997
Residence: Batam
Office: EMAS AMC Pte Ltd – Singapore
Position: Quality/Welding Engineer
Main Business: offshore EPCI oil & gas
company
Contact No: +62 8127041931/+65 94524360
Email: r.suwandhi@emas.com or
suwandhi.rahman@gmail.com
Basic Requirements
Qualification and
certification required to
support on the job scope
of work are:
• Welding i.e. CSWIP 3.1,
CWI-AWS
• NDT Level II i.e. ASNT,
PCN
• Painting/Coating i.e.
BGAS, NACE
Production flow chart
Material Receiving
Cutting & Fit up
weld Joint
Welding process
Visual & NDT
inspection
Painting/Coating
Inspection
Welding inspector role:
To ensure quality of material and
welding meet to the requirement
NDT inspector:
To check weld joint using different
methods i.e. RT, UT, MT/PT complied
to the acceptance criteria
Painting/Coating Inspector:
To control & monitor of quality coating
meet to the requirement
Quality Documents:
- ITP (Inspection Testing Plan)
- PQP (Project Quality Plan)
- TQ (Technical Query)
- NCR (Non Conformance Record)
- Procedures: Welding, NDT, Painting, PWHT,
Hydrotest
- Qualified personnel: QC Inspector, Welder, NDT,
Painting Inspector
- Certificates & Reports: material cert, equipments
& tools cert, material & welding traceability record,
NDT report, painting report, PWHT & Hydrotest
report
- MDR (Manufacturing Data Record)
Code/Standard/Specification
Must understand on the following:
• Variety of code i.e. material, general
requirements, testing procedure
• Product application: structure, pressure vessel,
pipeline, piping process, storage tank etc.
• International published i.e. AS, ASTM, API, AWS,
ASME, BS, DIN, EN, EEMUA, ISO, JIS, KS, SNI
• Client’s Specification: Total, Shell, Chevron, Exxon,
ENI
• Third party/class requirements i.e. ABS, LR, GL,
BV, BKI, DNV
Material Inspection
To check the following:
• Surface condition check i.e. mill scale, material
damage, rusty, coating protection
• Dimension check i.e. length, width, thickness,
diameter
• Purchase/Delivery Order, hard stamp
• Material certificates check
Mill Certificates
Welding Procedure & welder qualification test
PWPS
Prepare test coupon &
Record parameters
NDT
DT
WPS
Result
Acc
Reject
PQR
Propose Welder
Prepare test coupon
NDT
DT
Result
Welder Certificate
Acc
Reject
Welding Inspection
To check the following:
• Before welding: approved
procedures in place,
material, consumables &
equipments/tools certificate
available, joint prep &
preheat within tolerance
• During welding: control
parameters i.e. HI, interpass
temp, PWHT
• After welding: visual check
Welding Inspection
Variables to be control & monitor during
production weld:
• Material group i.e. specification, thickness,
diameter
• Joint design, edge preparation
• Welding position & progression
• Welding parameters: voltage, current, travel
speed, Heat Input
• Preheat & interpass temperature
• Post weld heat treatment
WPS (Welding Procedure Specification)
Visual Inspection
To check the following:
• Weld bead, toe blend,
weld consistency, arc
strike, spatter, grinding
mark, mechanical
damage, surface colour,
misalignment, angular
distortion, longitudinal
distortion
• Refer to the acceptance
criteria as per
code/standard i.e. AWS
D1.1, API 1104, ASME IX,
DNV OS F101 etc.
NDT Inspection
• NDT methods: RT, UT,
MT/PT
• Basic testing
• Procedure
Qualification Test
• Approval NDT
procedure
• Acceptance criteria
Painting/Coating Inspection
• Type: Paints, HSS,
3LPP, Concrete
• Procedure
qualification test
• Painting inspection
i.e. DFT, pull test,
salt test
• Acceptance criteria
Qaulity/Welding Inspection during offshore
pipeline & platform installation
Any question?

More Related Content

What's hot

495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Latest cswip 3.1 book
Latest cswip 3.1 bookLatest cswip 3.1 book
Latest cswip 3.1 bookRehan khan
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wireImran Jamil
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standardsJithu John
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentationMohamed Gaafar
 
Visual Inspection of Welding Process
Visual Inspection of Welding ProcessVisual Inspection of Welding Process
Visual Inspection of Welding ProcessGaurav Singh Rajput
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webmiguelbravo
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questionsKarthik Banari
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksRajSamy
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsThang Do Minh
 
what is process piping
what is process pipingwhat is process piping
what is process pipingVarun Patel
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overviewAshifuddinAli
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswipguest831c1e
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 sJithu John
 
CSWIP 3.2 New BOOK.pdf
CSWIP 3.2  New BOOK.pdfCSWIP 3.2  New BOOK.pdf
CSWIP 3.2 New BOOK.pdfVENKATESAN S
 
04 wis5 symbol
04 wis5 symbol04 wis5 symbol
04 wis5 symbolTori Tom
 

What's hot (20)

495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Latest cswip 3.1 book
Latest cswip 3.1 bookLatest cswip 3.1 book
Latest cswip 3.1 book
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
Visual Inspection of Welding Process
Visual Inspection of Welding ProcessVisual Inspection of Welding Process
Visual Inspection of Welding Process
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_web
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questions
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswip
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
How to Qualify a Welding Procedure
How to Qualify a Welding ProcedureHow to Qualify a Welding Procedure
How to Qualify a Welding Procedure
 
CSWIP 3.2 New BOOK.pdf
CSWIP 3.2  New BOOK.pdfCSWIP 3.2  New BOOK.pdf
CSWIP 3.2 New BOOK.pdf
 
Asme sec ix
Asme sec ixAsme sec ix
Asme sec ix
 
04 wis5 symbol
04 wis5 symbol04 wis5 symbol
04 wis5 symbol
 
QA QC Inspector.doc 1
QA QC Inspector.doc 1QA QC Inspector.doc 1
QA QC Inspector.doc 1
 

Viewers also liked

WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)Abrianto Akuan
 
Guide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsGuide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsTonni Bruce
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualificationvaasuBandaru
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010Jithu John
 
GTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IXGTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IXAntonius Pompi Bramono
 
Interview questions and answers for welding inspector
Interview questions and answers for welding inspectorInterview questions and answers for welding inspector
Interview questions and answers for welding inspectortonyron13
 
Duplex welding guidelines
Duplex welding guidelinesDuplex welding guidelines
Duplex welding guidelinesLalu Rajendran
 
Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014Dinh Truong Van
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c newJithu John
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineIEI GSC
 

Viewers also liked (18)

WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)
 
Guide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsGuide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wps
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
Welding book
Welding bookWelding book
Welding book
 
Welders qualification
Welders qualificationWelders qualification
Welders qualification
 
Asme wps-demo
Asme wps-demoAsme wps-demo
Asme wps-demo
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Welding Defects
Welding DefectsWelding Defects
Welding Defects
 
Question bank
Question bankQuestion bank
Question bank
 
Welder qualification
Welder qualificationWelder qualification
Welder qualification
 
Welder training
Welder trainingWelder training
Welder training
 
GTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IXGTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IX
 
Interview questions and answers for welding inspector
Interview questions and answers for welding inspectorInterview questions and answers for welding inspector
Interview questions and answers for welding inspector
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Duplex welding guidelines
Duplex welding guidelinesDuplex welding guidelines
Duplex welding guidelines
 
Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 

Similar to Offshore qc welding inspection versi 1

Similar to Offshore qc welding inspection versi 1 (20)

Ananda_Mariyan_DsouzaCV
Ananda_Mariyan_DsouzaCVAnanda_Mariyan_DsouzaCV
Ananda_Mariyan_DsouzaCV
 
Nivin Joseph- resume
Nivin Joseph- resumeNivin Joseph- resume
Nivin Joseph- resume
 
Resume Khurshid
Resume KhurshidResume Khurshid
Resume Khurshid
 
Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1
 
ANANDHARAJAN CV
ANANDHARAJAN CVANANDHARAJAN CV
ANANDHARAJAN CV
 
Nookaraju - CV
Nookaraju - CVNookaraju - CV
Nookaraju - CV
 
QA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceQA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrence
 
Curriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPINGCurriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPING
 
Makbul Cv
Makbul CvMakbul Cv
Makbul Cv
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATED
 
VENKAT
VENKATVENKAT
VENKAT
 
ANAND CV
ANAND CVANAND CV
ANAND CV
 
Rajeshwaran - Resume
Rajeshwaran - ResumeRajeshwaran - Resume
Rajeshwaran - Resume
 
RESUME__ASATH_MATHANI_-1-2 (1)
RESUME__ASATH_MATHANI_-1-2 (1)RESUME__ASATH_MATHANI_-1-2 (1)
RESUME__ASATH_MATHANI_-1-2 (1)
 
CV-QC Engg Mech- piping & welding
CV-QC Engg Mech- piping & weldingCV-QC Engg Mech- piping & welding
CV-QC Engg Mech- piping & welding
 
Vijay konathala Resume
Vijay konathala ResumeVijay konathala Resume
Vijay konathala Resume
 
ars resume
ars resumears resume
ars resume
 
Resume_Chintan_Gohil_
Resume_Chintan_Gohil_Resume_Chintan_Gohil_
Resume_Chintan_Gohil_
 
Praneshkumar QC Supervisor
Praneshkumar QC SupervisorPraneshkumar QC Supervisor
Praneshkumar QC Supervisor
 
RAJU CV
RAJU  CVRAJU  CV
RAJU CV
 

Recently uploaded

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Offshore qc welding inspection versi 1

  • 1. Quality/Welding inspection during Offshore Pipeline and Platform Installation By Rahman Suwandhi
  • 2. Personal Data Name: Rahman Suwandhi Graduated: Technical of Metallurgy 1997 Residence: Batam Office: EMAS AMC Pte Ltd – Singapore Position: Quality/Welding Engineer Main Business: offshore EPCI oil & gas company Contact No: +62 8127041931/+65 94524360 Email: r.suwandhi@emas.com or suwandhi.rahman@gmail.com
  • 3. Basic Requirements Qualification and certification required to support on the job scope of work are: • Welding i.e. CSWIP 3.1, CWI-AWS • NDT Level II i.e. ASNT, PCN • Painting/Coating i.e. BGAS, NACE
  • 4. Production flow chart Material Receiving Cutting & Fit up weld Joint Welding process Visual & NDT inspection Painting/Coating Inspection
  • 5. Welding inspector role: To ensure quality of material and welding meet to the requirement NDT inspector: To check weld joint using different methods i.e. RT, UT, MT/PT complied to the acceptance criteria Painting/Coating Inspector: To control & monitor of quality coating meet to the requirement
  • 6. Quality Documents: - ITP (Inspection Testing Plan) - PQP (Project Quality Plan) - TQ (Technical Query) - NCR (Non Conformance Record) - Procedures: Welding, NDT, Painting, PWHT, Hydrotest - Qualified personnel: QC Inspector, Welder, NDT, Painting Inspector - Certificates & Reports: material cert, equipments & tools cert, material & welding traceability record, NDT report, painting report, PWHT & Hydrotest report - MDR (Manufacturing Data Record)
  • 7. Code/Standard/Specification Must understand on the following: • Variety of code i.e. material, general requirements, testing procedure • Product application: structure, pressure vessel, pipeline, piping process, storage tank etc. • International published i.e. AS, ASTM, API, AWS, ASME, BS, DIN, EN, EEMUA, ISO, JIS, KS, SNI • Client’s Specification: Total, Shell, Chevron, Exxon, ENI • Third party/class requirements i.e. ABS, LR, GL, BV, BKI, DNV
  • 8. Material Inspection To check the following: • Surface condition check i.e. mill scale, material damage, rusty, coating protection • Dimension check i.e. length, width, thickness, diameter • Purchase/Delivery Order, hard stamp • Material certificates check
  • 10. Welding Procedure & welder qualification test PWPS Prepare test coupon & Record parameters NDT DT WPS Result Acc Reject PQR Propose Welder Prepare test coupon NDT DT Result Welder Certificate Acc Reject
  • 11. Welding Inspection To check the following: • Before welding: approved procedures in place, material, consumables & equipments/tools certificate available, joint prep & preheat within tolerance • During welding: control parameters i.e. HI, interpass temp, PWHT • After welding: visual check
  • 12. Welding Inspection Variables to be control & monitor during production weld: • Material group i.e. specification, thickness, diameter • Joint design, edge preparation • Welding position & progression • Welding parameters: voltage, current, travel speed, Heat Input • Preheat & interpass temperature • Post weld heat treatment
  • 13. WPS (Welding Procedure Specification)
  • 14. Visual Inspection To check the following: • Weld bead, toe blend, weld consistency, arc strike, spatter, grinding mark, mechanical damage, surface colour, misalignment, angular distortion, longitudinal distortion • Refer to the acceptance criteria as per code/standard i.e. AWS D1.1, API 1104, ASME IX, DNV OS F101 etc.
  • 15. NDT Inspection • NDT methods: RT, UT, MT/PT • Basic testing • Procedure Qualification Test • Approval NDT procedure • Acceptance criteria
  • 16. Painting/Coating Inspection • Type: Paints, HSS, 3LPP, Concrete • Procedure qualification test • Painting inspection i.e. DFT, pull test, salt test • Acceptance criteria
  • 17. Qaulity/Welding Inspection during offshore pipeline & platform installation Any question?