SlideShare a Scribd company logo
1 of 10
Primavera Scheduling
Tips and Tricks 02-14
1) P6 issue concerning activity dates and/or
duration failing to translate correctly
into the corresponding resource
assignment.
2) P6 issue concerning resources or
commodities failing to distribute to the
expected time duration reflected in each
activity correctly. It brings the start date
but not the finish date.
2014
Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP®
Revision 0: August 7, 2014
080714-Rufran's Primavera Scheduling Tips & Tricks 02-14 Page 2 of 10 8/9/2014
Author: Rufran C. Frago, P. Eng., PMP, CCP, PMI-RMP
TABLE OF CONTENTS
PAGES
1. SITUATION/PROBLEM................................................................................................................. 3
2. RELATED TOOLS.......................................................................................................................... 3
3. DEFINITION................................................................................................................................... 3
4. PROBLEM ANALYSIS (PA).......................................................................................................... 3
5. EXPLANATION.............................................................................................................................. 7
6. SOLUTION...................................................................................................................................... 8
7. REFERENCES................................................................................................................................. 9
8. ADDITIONAL READING MATERIALS....................................................................................... 9
9. APPENDICES.................................................................................................................................. 9
10. INDEX ....................................................................................................................................... 10
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 3 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
1. SITUATION/PROBLEM
1.1. Finish Date and/or duration of each activity corresponding to the resource
assigned to it does not transfer over to the resource time line when viewed in the
“Assignments” window.
1.2. It is only bringing the start date but not the finish date.
1.3. Progress report and resource analysis are incomplete delaying decision.
2. RELATED TOOLS
2.1. Project Management-Primavera P6.1 SP1, P6.2, P6.7 SP1/SP2 & P6.7SP4
3. DEFINITION
3.1. The term “User” in this document is the person using the Primavera scheduling
tool. He can be the planner, the scheduler, the Project Manager or anyone.
3.2. This is a relatively new issue encountered by some of our planners/schedulers in
major projects.
4. PROBLEM ANALYSIS (PA)
4.1. The schedule is resource-loaded. This is to makes sure that there are actually
active and valid resources in the schedule. Note that there is no error message.
4.2. All activity codes are in place and were in the code structure. A quick check will
help us group our points of concern quickly. This will help in the troubleshooting
process as we can zero in to whatever group of activity is affected.
4.3. All activities have the corresponding calendar assigned to them. Calendar
assignment will determine how resources are apportioned using a given time
period of days, weeks, or month.
4.4. Check the activities corresponding to the resources in question. Note the start and
finish date of each of the activities. Figure A below shows the schedule’s activity
window and some of their attributes.
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 4 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
4.5. Let us focus on just one activity to facilitate understanding. Note the highlighted
Activity MRFM3660 scheduled to start on 08-Feb-2016 and finish on 28-Apr-
2016. Everything looks normal.
Figure A - View showing the Early Start, Early Finish & Late Start, Late
Finish dates of activities
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 5 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
4.6. Let us now click the Assignment tab to check the resource distribution
corresponding to the same activity, MRFM3660 (Figure B).
Figure B - Assignments window showing the ES, EF & the resource distribution
4.7. Looking closer, we have identified the reported issue. The resource assigned to
MRFM3660 did not automatically distribute into the timeline. The entire quantity
of 4263 (see red boundary) remained under the May 2014 month column in the
distribution window. This is the data date month. The start date is correct at 08-
Feb-16 but the activity finish date that we see in Figure A failed to translate.
Instead, it took the start date of 08-Feb-16 resulting in duration of one day. Note
that the correct finish date should be 18-Apr-16.
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 6 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
Figure C – Closer look of Figure B
4.8. Checking the rest of the other activities, we found that they have the same issue.
It means the issue reported is pervasive across the schedule.
4.9. Is there a default setting affecting date translation that needs adjustment/change?
Is there something wrong with the assigned calendars and the attributes of the
resources related to its calendars?
4.10.Upon checking, we found that the Default Units/Time setting of the culprit
resource assigned to Activity MRFM3660 is set to zero (see arrow, Figure D).
Figure D – Resource Window showing the attributes like Max Units/Time,
Resource name, Calendar, Default Units/Time, and others
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 7 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
5. EXPLANATION
5.1. The default units/time is an attribute a planner/scheduler should set for any labor
resource or material resource added to the Primavera resource structure. This
value shall be according to what the project wants to be the number of units per
day.
5.2. If it is labor resource, it will be the number of hours per day. If a labor resource is
set to work 10 hour in a day, then the default is 10 hours/day.
5.3. If it is material resource, it will be the number of units per day; e.g. tons, linear
meter, square foot, etc. If a material resource is set to work 5 tons a day, then the
default is 5 tons/day.
5.4. We tested the Default Unit/Time set to zero (0) and found it is the reason why the
resource quantity failed to distribute. It is in fact controlling the distribution
across the timeline.
5.5. The quantity distributes through the timeline accordingly when any number
replaces zero (0). However, it only works on resource-loaded activity added after
the correction of the Default Units/Time.
5.6. We change the zero Default Units/Time setting of the culprit resource assigned to
Activity MRFM3660 to 10 hours/day. The quantity still did not distribute.
Reason: The activity exists before correction to the resource’s Default
Units/Time.
5.7. It means that Users should make sure that this particular setting is accurate,
noting most especially to avoid a zero value. Always remember that anything
divided by zero is undefined and any number multiplied by zero is zero.
5.8. Further inspection of the schedule shows that there were other resources with
default units/time set to zero. All these resources should have their default
units/time value corrected.
5.9. It is unbelievable that many planners & schedulers using P6 are not even aware
that such setting exists or if they know about it, that such setting affects resource
distribution.
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 8 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
6. SOLUTION
6.1. We experimented on manually correcting the proper finish date of each activity
and the quantities spread properly. This is an acceptable workaround if one has
the luxury of time. Imagine changing the finish dates of a relatively large
schedule of hundreds of activities not to mention thousands.
6.2. At this time, we know no automatic quick correction of the issue and Oracle has
not offered anything when asked. Our third party consultant did not come up
with a better solution as they recommended a manual correction of dates in the
resource assignment/distribution window.
6.3. An idea occurred today but we have not tested it yet. How about 1) correcting all
the erroneous Default Units/Time in your schedule. 2) In your activity window,
show all the activities. 3) Select all activities. 4) Cut all activities. 5) Paste all
activities back into the empty space. 6) Click Assignment tab and check if
Primavera considered the pasted activities as newly added activities.
Rationale: The activities will adopt the corrected Default Units/Time.
6.4. Second idea today but that we have not tested yet. How about 1) correcting all
the erroneous Default Units/Time in your schedule. 2) Click the WBS tab. 3)
Select all of the WBS structure. 4) Copy WBS. 5) Paste the copied WBS
structure to make a duplicate structure. 6) Click Assignment tab corresponding to
the newly added WBS and check if Primavera considered the duplicate activities
that came with the WBS as newly added activities. 7) If it did, delete the original
WBS Structure.
Rationale: The activities will adopt the corrected Default Units/Time.
6.5. Make sure to back up your project file before trying Section 6.3 and 6.4. These
are untested ideas only. Let us know if it worked, or any iteration similar to the
procedure. Note that doing so will be at your own risk.
6.6. Additional notes:
6.6.1. Do not forget to add the right curve to each resource. Curves are in place
in this specific case.
6.6.2. Ensure that the Drive Activity Dates button on each resource is checked. .
The drive button of each resource is set in this specific case.
6.6.3. Under Time Distributed Data of the User Preferences in the resource’s
analysis tab there is an option for the interval in which to distribute the
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 9 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
resource data. Set this to what you want; e.g. day, week or month. The
correct time unit is in place in this specific case.
7. REFERENCES
7.1. Frago, R. (31-Jul-14). Log book-Troubleshooting records
7.2. Frago, R. (2014). Primavera P6.7 SP4 Activity dates translation issue needs a
solution.LinkedinPrimaveraGroup collaboration.
7.3. Frago, R. (2014).Oracle Community Forum
8. ADDITIONAL READING MATERIALS
8.1. User’s Manual Primavera P6.1 SP1, P6.2, P6.7 SP1/SP2 & P6.7SP4
8.2. Planning Planet ForumThread, 2012.Default Units / Time.Retrieved from
http://www.planningplanet.com/forums/primavera-version-pm5-
pm6/525280/default-units-time
8.3. Planning Planet ForumThread, 2011.Calculate remaining units per time from
crew sizes.Retrieved from http://www.planningplanet.com/forums/primavera-
version-pm5-pm6/506537/calculate-remaining-units-time-crew-sizes
8.4. Oracle Community Thread, (2008). Default Units/Time Format.Retrieved from
https://community.oracle.com/thread/883506?start=0&tstart=0
9. APPENDICES
9.1. NONE
080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 10 of 10
Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP®
10. INDEX
“User” ................................................... 5
ADDITIONAL READING
MATERIALS.................................. 11
Assignment tab...................................... 7
automatic quick correction.................. 10
back up................................................ 10
Calendar assignment ............................. 5
date translation...................................... 8
Default Unit/Time set to zero ............... 9
default units/time .................................. 9
DEFINITION ........................................ 5
EXPLANATION................................... 9
INDEX ................................................ 12
manually correcting ............................ 10
PROBLEM ANALYSIS........................ 5
REFERENCES.................................... 11
RELATED TOOLS............................... 5
SITUATION/PROBLEM...................... 5
SOLUTION......................................... 10
TABLE OF CONTENTS ................... 2
Time Distributed Data......................... 10

More Related Content

What's hot

Primavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksPrimavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksMohammad khan
 
02 Creating A Task List
02 Creating A Task List02 Creating A Task List
02 Creating A Task ListSoe Naing Win
 
Agile project tracking - burn up charts
Agile project tracking - burn up chartsAgile project tracking - burn up charts
Agile project tracking - burn up chartsJonny LeRoy
 
07 Fine-tuning Task Details
07 Fine-tuning Task Details07 Fine-tuning Task Details
07 Fine-tuning Task DetailsSoe Naing Win
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortKevin C. McCormack, PMP
 
04 Assigning Resources to Tasks
04 Assigning Resources to Tasks04 Assigning Resources to Tasks
04 Assigning Resources to TasksSoe Naing Win
 
Maintenance Management Process
Maintenance Management ProcessMaintenance Management Process
Maintenance Management ProcessPIPINAZRIN
 
Time tracking in orangescrum
Time tracking in orangescrumTime tracking in orangescrum
Time tracking in orangescrumOrangescrum
 
Project Resource Allocation
Project Resource AllocationProject Resource Allocation
Project Resource Allocationmohsin iqbal
 
Ms project general introduction
Ms project general introductionMs project general introduction
Ms project general introductionKushal Patel
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
MS Project 2010 Quick Reference Card
MS Project 2010  Quick Reference CardMS Project 2010  Quick Reference Card
MS Project 2010 Quick Reference CardSoe Naing Win
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-Kanchana Devi
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013Ong-Art Sanpinit
 
Program Management 2.0: Risk Management
Program Management 2.0: Risk ManagementProgram Management 2.0: Risk Management
Program Management 2.0: Risk ManagementJohn Carter
 

What's hot (20)

Primavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksPrimavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricks
 
02 Creating A Task List
02 Creating A Task List02 Creating A Task List
02 Creating A Task List
 
Agile project tracking - burn up charts
Agile project tracking - burn up chartsAgile project tracking - burn up charts
Agile project tracking - burn up charts
 
07 Fine-tuning Task Details
07 Fine-tuning Task Details07 Fine-tuning Task Details
07 Fine-tuning Task Details
 
Oracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricksOracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricks
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure Effort
 
04 Assigning Resources to Tasks
04 Assigning Resources to Tasks04 Assigning Resources to Tasks
04 Assigning Resources to Tasks
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Maintenance Management Process
Maintenance Management ProcessMaintenance Management Process
Maintenance Management Process
 
Time tracking in orangescrum
Time tracking in orangescrumTime tracking in orangescrum
Time tracking in orangescrum
 
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
091414 Rufran's Acumen Fuse Tips & Tricks 01-14 (Issues on imported durations)
 
Project Resource Allocation
Project Resource AllocationProject Resource Allocation
Project Resource Allocation
 
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
043015 Rufran's Acumen Fuse Tips and Tricks 01-15 (Duration Translation Issue)
 
Ms project general introduction
Ms project general introductionMs project general introduction
Ms project general introduction
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
MS Project 2010 Quick Reference Card
MS Project 2010  Quick Reference CardMS Project 2010  Quick Reference Card
MS Project 2010 Quick Reference Card
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Program Management 2.0: Risk Management
Program Management 2.0: Risk ManagementProgram Management 2.0: Risk Management
Program Management 2.0: Risk Management
 

Similar to 080714-Rufran's Primavera Scheduling Tips Tricks 02-14

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
D Prior Scrum In The Waterfall
D Prior Scrum In The WaterfallD Prior Scrum In The Waterfall
D Prior Scrum In The WaterfallBrad91364
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Part 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docxPart 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docxherbertwilson5999
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceThe 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceJames Kovacevic, MMP CMRP CAMA
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Best Practices in Maintenance Planning And Scheduling
Best Practices in Maintenance Planning And Scheduling Best Practices in Maintenance Planning And Scheduling
Best Practices in Maintenance Planning And Scheduling Ricky Smith CMRP, CMRT
 
Novel Scheduling Algorithm in DFS9(1)
Novel Scheduling Algorithm in DFS9(1)Novel Scheduling Algorithm in DFS9(1)
Novel Scheduling Algorithm in DFS9(1)kota Ankita
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docxChantellPantoja184
 
Dobson michael pag 52 106
Dobson michael pag 52 106Dobson michael pag 52 106
Dobson michael pag 52 106alextm76
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxcarolinef5
 

Similar to 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 (20)

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
D Prior Scrum In The Waterfall
D Prior Scrum In The WaterfallD Prior Scrum In The Waterfall
D Prior Scrum In The Waterfall
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Part 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docxPart 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docx
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual ConferenceThe 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
The 5 Levels of Maintenance Scheduling - SMRP 2016 Annual Conference
 
Agile planning
Agile planningAgile planning
Agile planning
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Best Practices in Maintenance Planning And Scheduling
Best Practices in Maintenance Planning And Scheduling Best Practices in Maintenance Planning And Scheduling
Best Practices in Maintenance Planning And Scheduling
 
113015 - Understanding ALAP
113015 - Understanding ALAP113015 - Understanding ALAP
113015 - Understanding ALAP
 
Novel Scheduling Algorithm in DFS9(1)
Novel Scheduling Algorithm in DFS9(1)Novel Scheduling Algorithm in DFS9(1)
Novel Scheduling Algorithm in DFS9(1)
 
Rccp report
Rccp reportRccp report
Rccp report
 
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction  B.docxPrintNetwork Diagrams and Resource UtilizationIntroduction  B.docx
PrintNetwork Diagrams and Resource UtilizationIntroduction B.docx
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Dobson michael pag 52 106
Dobson michael pag 52 106Dobson michael pag 52 106
Dobson michael pag 52 106
 
B012440511
B012440511B012440511
B012440511
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 

More from PM SOLUTION PRO| Risk-based Management and Services Inc.

More from PM SOLUTION PRO| Risk-based Management and Services Inc. (20)

121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired121717 Kindle Issue 2 : Figures become so small than desired
121717 Kindle Issue 2 : Figures become so small than desired
 
121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle121717 Kindle Issue : Table lines were showing in kindle
121717 Kindle Issue : Table lines were showing in kindle
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe063016 Man is the Center of the Risk Universe
063016 Man is the Center of the Risk Universe
 
032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop032815 DBM Schedule Development Workshop
032815 DBM Schedule Development Workshop
 
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique 102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
102614 Root Cause Analysis using Fault Tree Analysis (FTA) Technique
 
091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)
 
082314 Road to Operational Excellence
082314 Road to Operational Excellence082314 Road to Operational Excellence
082314 Road to Operational Excellence
 
072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem072414 Resource Distribution Copy-Paste Problem
072414 Resource Distribution Copy-Paste Problem
 
011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?011614 Scaffolding, what is it? Direct or Indirect?
011614 Scaffolding, what is it? Direct or Indirect?
 
121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)121013 Blackberry Business Audit (BMC 205 @ UofC)
121013 Blackberry Business Audit (BMC 205 @ UofC)
 
103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)103013 Case Study, Potash Corporation (BMC205, UofC)
103013 Case Study, Potash Corporation (BMC205, UofC)
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods072213 Understanding Acumen Fuse Scoring Methods
072213 Understanding Acumen Fuse Scoring Methods
 
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
072213 Rufran's Primavera Scheduling Tips & Tricks 06-13 (P6 error AAVA0-3769-8)
 
071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis071513 How to Prepare for Schedule Quantitative Risk Analysis
071513 How to Prepare for Schedule Quantitative Risk Analysis
 
070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC070613 Managing P6 Database Security Using RMC
070613 Managing P6 Database Security Using RMC
 
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
062913 Rufran's Primavera Scheduling Tips & Tricks 03-13
 
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
062813 Rufran's Primavera Scheduling Tips & Tricks 02-13
 

Recently uploaded

Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsAlberto González Trastoy
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfkalichargn70th171
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplatePresentation.STUDIO
 
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfLearn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfkalichargn70th171
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park masabamasaba
 
10 Trends Likely to Shape Enterprise Technology in 2024
10 Trends Likely to Shape Enterprise Technology in 202410 Trends Likely to Shape Enterprise Technology in 2024
10 Trends Likely to Shape Enterprise Technology in 2024Mind IT Systems
 
Exploring the Best Video Editing App.pdf
Exploring the Best Video Editing App.pdfExploring the Best Video Editing App.pdf
Exploring the Best Video Editing App.pdfproinshot.com
 
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerThousandEyes
 
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionIntroducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionOnePlan Solutions
 
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...Jittipong Loespradit
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsArshad QA
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️Delhi Call girls
 
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park %in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park masabamasaba
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providermohitmore19
 
A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxComplianceQuest1
 
The Top App Development Trends Shaping the Industry in 2024-25 .pdf
The Top App Development Trends Shaping the Industry in 2024-25 .pdfThe Top App Development Trends Shaping the Industry in 2024-25 .pdf
The Top App Development Trends Shaping the Industry in 2024-25 .pdfayushiqss
 
Define the academic and professional writing..pdf
Define the academic and professional writing..pdfDefine the academic and professional writing..pdf
Define the academic and professional writing..pdfPearlKirahMaeRagusta1
 
%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrandmasabamasaba
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVshikhaohhpro
 

Recently uploaded (20)

Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation Template
 
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdfLearn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
Learn the Fundamentals of XCUITest Framework_ A Beginner's Guide.pdf
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
 
10 Trends Likely to Shape Enterprise Technology in 2024
10 Trends Likely to Shape Enterprise Technology in 202410 Trends Likely to Shape Enterprise Technology in 2024
10 Trends Likely to Shape Enterprise Technology in 2024
 
Exploring the Best Video Editing App.pdf
Exploring the Best Video Editing App.pdfExploring the Best Video Editing App.pdf
Exploring the Best Video Editing App.pdf
 
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
 
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionIntroducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
 
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview Questions
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park %in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service provider
 
A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docx
 
The Top App Development Trends Shaping the Industry in 2024-25 .pdf
The Top App Development Trends Shaping the Industry in 2024-25 .pdfThe Top App Development Trends Shaping the Industry in 2024-25 .pdf
The Top App Development Trends Shaping the Industry in 2024-25 .pdf
 
Define the academic and professional writing..pdf
Define the academic and professional writing..pdfDefine the academic and professional writing..pdf
Define the academic and professional writing..pdf
 
Microsoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdfMicrosoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdf
 
%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand
 
Optimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTVOptimizing AI for immediate response in Smart CCTV
Optimizing AI for immediate response in Smart CCTV
 

080714-Rufran's Primavera Scheduling Tips Tricks 02-14

  • 1. Primavera Scheduling Tips and Tricks 02-14 1) P6 issue concerning activity dates and/or duration failing to translate correctly into the corresponding resource assignment. 2) P6 issue concerning resources or commodities failing to distribute to the expected time duration reflected in each activity correctly. It brings the start date but not the finish date. 2014 Rufran C. Frago, P. Eng., PMP®, CCP, PMI-RMP® Revision 0: August 7, 2014
  • 2. 080714-Rufran's Primavera Scheduling Tips & Tricks 02-14 Page 2 of 10 8/9/2014 Author: Rufran C. Frago, P. Eng., PMP, CCP, PMI-RMP TABLE OF CONTENTS PAGES 1. SITUATION/PROBLEM................................................................................................................. 3 2. RELATED TOOLS.......................................................................................................................... 3 3. DEFINITION................................................................................................................................... 3 4. PROBLEM ANALYSIS (PA).......................................................................................................... 3 5. EXPLANATION.............................................................................................................................. 7 6. SOLUTION...................................................................................................................................... 8 7. REFERENCES................................................................................................................................. 9 8. ADDITIONAL READING MATERIALS....................................................................................... 9 9. APPENDICES.................................................................................................................................. 9 10. INDEX ....................................................................................................................................... 10
  • 3. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 3 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 1. SITUATION/PROBLEM 1.1. Finish Date and/or duration of each activity corresponding to the resource assigned to it does not transfer over to the resource time line when viewed in the “Assignments” window. 1.2. It is only bringing the start date but not the finish date. 1.3. Progress report and resource analysis are incomplete delaying decision. 2. RELATED TOOLS 2.1. Project Management-Primavera P6.1 SP1, P6.2, P6.7 SP1/SP2 & P6.7SP4 3. DEFINITION 3.1. The term “User” in this document is the person using the Primavera scheduling tool. He can be the planner, the scheduler, the Project Manager or anyone. 3.2. This is a relatively new issue encountered by some of our planners/schedulers in major projects. 4. PROBLEM ANALYSIS (PA) 4.1. The schedule is resource-loaded. This is to makes sure that there are actually active and valid resources in the schedule. Note that there is no error message. 4.2. All activity codes are in place and were in the code structure. A quick check will help us group our points of concern quickly. This will help in the troubleshooting process as we can zero in to whatever group of activity is affected. 4.3. All activities have the corresponding calendar assigned to them. Calendar assignment will determine how resources are apportioned using a given time period of days, weeks, or month. 4.4. Check the activities corresponding to the resources in question. Note the start and finish date of each of the activities. Figure A below shows the schedule’s activity window and some of their attributes.
  • 4. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 4 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 4.5. Let us focus on just one activity to facilitate understanding. Note the highlighted Activity MRFM3660 scheduled to start on 08-Feb-2016 and finish on 28-Apr- 2016. Everything looks normal. Figure A - View showing the Early Start, Early Finish & Late Start, Late Finish dates of activities
  • 5. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 5 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 4.6. Let us now click the Assignment tab to check the resource distribution corresponding to the same activity, MRFM3660 (Figure B). Figure B - Assignments window showing the ES, EF & the resource distribution 4.7. Looking closer, we have identified the reported issue. The resource assigned to MRFM3660 did not automatically distribute into the timeline. The entire quantity of 4263 (see red boundary) remained under the May 2014 month column in the distribution window. This is the data date month. The start date is correct at 08- Feb-16 but the activity finish date that we see in Figure A failed to translate. Instead, it took the start date of 08-Feb-16 resulting in duration of one day. Note that the correct finish date should be 18-Apr-16.
  • 6. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 6 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® Figure C – Closer look of Figure B 4.8. Checking the rest of the other activities, we found that they have the same issue. It means the issue reported is pervasive across the schedule. 4.9. Is there a default setting affecting date translation that needs adjustment/change? Is there something wrong with the assigned calendars and the attributes of the resources related to its calendars? 4.10.Upon checking, we found that the Default Units/Time setting of the culprit resource assigned to Activity MRFM3660 is set to zero (see arrow, Figure D). Figure D – Resource Window showing the attributes like Max Units/Time, Resource name, Calendar, Default Units/Time, and others
  • 7. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 7 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 5. EXPLANATION 5.1. The default units/time is an attribute a planner/scheduler should set for any labor resource or material resource added to the Primavera resource structure. This value shall be according to what the project wants to be the number of units per day. 5.2. If it is labor resource, it will be the number of hours per day. If a labor resource is set to work 10 hour in a day, then the default is 10 hours/day. 5.3. If it is material resource, it will be the number of units per day; e.g. tons, linear meter, square foot, etc. If a material resource is set to work 5 tons a day, then the default is 5 tons/day. 5.4. We tested the Default Unit/Time set to zero (0) and found it is the reason why the resource quantity failed to distribute. It is in fact controlling the distribution across the timeline. 5.5. The quantity distributes through the timeline accordingly when any number replaces zero (0). However, it only works on resource-loaded activity added after the correction of the Default Units/Time. 5.6. We change the zero Default Units/Time setting of the culprit resource assigned to Activity MRFM3660 to 10 hours/day. The quantity still did not distribute. Reason: The activity exists before correction to the resource’s Default Units/Time. 5.7. It means that Users should make sure that this particular setting is accurate, noting most especially to avoid a zero value. Always remember that anything divided by zero is undefined and any number multiplied by zero is zero. 5.8. Further inspection of the schedule shows that there were other resources with default units/time set to zero. All these resources should have their default units/time value corrected. 5.9. It is unbelievable that many planners & schedulers using P6 are not even aware that such setting exists or if they know about it, that such setting affects resource distribution.
  • 8. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 8 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 6. SOLUTION 6.1. We experimented on manually correcting the proper finish date of each activity and the quantities spread properly. This is an acceptable workaround if one has the luxury of time. Imagine changing the finish dates of a relatively large schedule of hundreds of activities not to mention thousands. 6.2. At this time, we know no automatic quick correction of the issue and Oracle has not offered anything when asked. Our third party consultant did not come up with a better solution as they recommended a manual correction of dates in the resource assignment/distribution window. 6.3. An idea occurred today but we have not tested it yet. How about 1) correcting all the erroneous Default Units/Time in your schedule. 2) In your activity window, show all the activities. 3) Select all activities. 4) Cut all activities. 5) Paste all activities back into the empty space. 6) Click Assignment tab and check if Primavera considered the pasted activities as newly added activities. Rationale: The activities will adopt the corrected Default Units/Time. 6.4. Second idea today but that we have not tested yet. How about 1) correcting all the erroneous Default Units/Time in your schedule. 2) Click the WBS tab. 3) Select all of the WBS structure. 4) Copy WBS. 5) Paste the copied WBS structure to make a duplicate structure. 6) Click Assignment tab corresponding to the newly added WBS and check if Primavera considered the duplicate activities that came with the WBS as newly added activities. 7) If it did, delete the original WBS Structure. Rationale: The activities will adopt the corrected Default Units/Time. 6.5. Make sure to back up your project file before trying Section 6.3 and 6.4. These are untested ideas only. Let us know if it worked, or any iteration similar to the procedure. Note that doing so will be at your own risk. 6.6. Additional notes: 6.6.1. Do not forget to add the right curve to each resource. Curves are in place in this specific case. 6.6.2. Ensure that the Drive Activity Dates button on each resource is checked. . The drive button of each resource is set in this specific case. 6.6.3. Under Time Distributed Data of the User Preferences in the resource’s analysis tab there is an option for the interval in which to distribute the
  • 9. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 9 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® resource data. Set this to what you want; e.g. day, week or month. The correct time unit is in place in this specific case. 7. REFERENCES 7.1. Frago, R. (31-Jul-14). Log book-Troubleshooting records 7.2. Frago, R. (2014). Primavera P6.7 SP4 Activity dates translation issue needs a solution.LinkedinPrimaveraGroup collaboration. 7.3. Frago, R. (2014).Oracle Community Forum 8. ADDITIONAL READING MATERIALS 8.1. User’s Manual Primavera P6.1 SP1, P6.2, P6.7 SP1/SP2 & P6.7SP4 8.2. Planning Planet ForumThread, 2012.Default Units / Time.Retrieved from http://www.planningplanet.com/forums/primavera-version-pm5- pm6/525280/default-units-time 8.3. Planning Planet ForumThread, 2011.Calculate remaining units per time from crew sizes.Retrieved from http://www.planningplanet.com/forums/primavera- version-pm5-pm6/506537/calculate-remaining-units-time-crew-sizes 8.4. Oracle Community Thread, (2008). Default Units/Time Format.Retrieved from https://community.oracle.com/thread/883506?start=0&tstart=0 9. APPENDICES 9.1. NONE
  • 10. 080714-Rufran's Primavera Scheduling Tips Tricks 02-14 Page 10 of 10 Author: RUFRAN C. FRAGO, P.Eng, PMP®, CCP, PMI-RMP® 10. INDEX “User” ................................................... 5 ADDITIONAL READING MATERIALS.................................. 11 Assignment tab...................................... 7 automatic quick correction.................. 10 back up................................................ 10 Calendar assignment ............................. 5 date translation...................................... 8 Default Unit/Time set to zero ............... 9 default units/time .................................. 9 DEFINITION ........................................ 5 EXPLANATION................................... 9 INDEX ................................................ 12 manually correcting ............................ 10 PROBLEM ANALYSIS........................ 5 REFERENCES.................................... 11 RELATED TOOLS............................... 5 SITUATION/PROBLEM...................... 5 SOLUTION......................................... 10 TABLE OF CONTENTS ................... 2 Time Distributed Data......................... 10