Risk Management
for Projects & Programmes
Known knowns
Things that we know that we know
Known unknowns
Things that we know that we don’t know
Unknown unknowns
Things that we do not know we don’t know
?
2 of 22
What is Risk?
We know that plans are unlikely to be a precise
prediction of the future
Plans are a model of interconnected tasks believed
certain to be required to achieve an objective
There are also events which are less than certain,
but if they happen, would impact the plan
A Risk is a significant but uncertain event that, if it occurs, has an effect on the plan
A risk can have detrimental or beneficial effects
Threat A risk with a detrimental effect
Opportunity A risk with a beneficial effect
Patsy, Monty Python and the Holy Grail, 1975
3 of 22
What is Risk Management?
How we act to manage significant uncertainty
Uncertain events will always be part of any
plan for the future
Risk Management is a core PM competence
“There are known knowns; there are things that we know that we know.
There are known unknowns; that is to say, there are things that we know that we don’t know.
But there are also unknown unknowns – there are things that we do not know we don’t know.”
Donald Rumsfeld, US Secretary of Defence, 2002
Project Management
Planning &
Scheduling
Risk
Management
Context & Assumptions
significant insignificant
Uncertain
Events
Certain
Events
4 of 22
Why do Risk Management?
Good Risk Management will
 Lead to more realistic plans
 Help to set expectations appropriate to value, risk and complexity
 Inform bid/no bid decisions
 Help in selecting the most appropriate contract type
 Inform PM selection, matching PM competence to value, risk and complexity
 Help set project level contingencies, rather than task level or a fixed amount
 Enable greater honesty, openness and understanding
 Reduce uncertainty by implementing responses to risk
 Enable simpler, more transparent reporting
 Reduce stress and reliance on a hero culture
 Significantly increase the likelihood of meeting time, cost and quality objectives
Cautions
! Risk Management will not guarantee meeting time, cost and quality objectives
! If undertaken as a tick box exercise, or only at bid time, the full value will not be realised
! The effort invested should be proportional to value, risk and complexity
5 of 22
International Standards Organisation
ISO 31000 [2009] Risk Management Principles & Guidelines 
ISO IEC 31010 [2009] Risk Management Risk Assessment Techniques 
ISO Guide 73 [2009] Risk Management Vocabulary 
British Standards
BS 6079-3 [2000] Guide to the Management of Business Related Project Risk 
Association for Project Management
PRAM: Project Risk Analysis and Management Guide, 2nd Edition [2010] 
Interfacing Risk and Earned Value Management [2008] 
Prioritising Project Risks [2008] 
Project Management Institute
Practice Standard for Project Risk Management [2009] 
The Institute of Risk Management
Publications that primarily deal with enterprise risk management 
UK Government
The Orange Book: Management of Risk, Principles and Concepts [2004] 
Management of Risk, Guidance for Practitioners, 3rd edition [2010, Axelos] 
Ministry of Defence Acquisition System Guidance: Risk Management [v4.2.2]
Risk Management Best Practice Guidance
6 of 22
Risk Management Training
Certification Valid Renewal Acquisition Pre-requisite
Association for
Project
Management
Risk Certificate
Level 1
- - 1 hour multiple choice exam: 60 questions, pass ≥60%
Confirms knowledge sufficient to allow contribution to risk management within a project.
Can be taken as a 2 day course, cost £1,100 (inc. exam fee). Open exam fee £164 (£146 for APM members).
Risk Certificate
Level 2
- -
3.25 hour exam: section A, 100 marks;
section B, 100 marks, 2 from 4 questions, 2 relate to case
study, pass ≥60%
Risk Certificate Level 1
knowledge (not certification)
Confirms knowledge, understanding and capability, sufficient to undertake project risk management.
Can be taken as a 2 day course, cost £1,100 (inc. exam fee). Open exam fee £430 (£310 for APM members).
Combined Risk Levels 1 & 2 Open exam fee £558 (£384 for APM members).
UK Cabinet Office
Axelos
M_o_R
Foundation
- -
1 hour multiple choice exam: 75 questions of which 70 count,
pass ≥50% (35/70)
Confirms sufficient knowledge and understanding to contribute to the identification, assessment and control of risks across any
organization.
M_o_R
Practitioner
5
years
1hr exam,
pass ≥55%
3 hour exam: 4 questions, 20 marks each, open book
(specified M_o_R books only), pass ≥50% (40/80)
M_o_R Foundation
Confirms sufficient understanding of how to apply and tailor M_o_R in a scenario situation.
M_o_R Foundation and Practitioner can be taken together in a 5 day course, cost £2,300.
Project
Management
Institute
PMI-RMP
PMI
Risk
Management
Professional
3
years
30 PDUs
over 3 years
3.5 hour multiple choice exam: 170 questions, 150 scoring,
'Modified Angoff Method' to determine pass
Degree, 2 years’ project risk
management experience and 30
hours formal project risk
management training
Recognises competence in assessing and identifying project risks, mitigating threats and capitalizing on opportunities, while still
possessing a core knowledge and practical application in all areas of project management.
2008 launch, 2,033 credential holders worldwide by 30 April 2013. Certification fee $670 ($520 for PMI members).
Project Risk Management is also covered in general PM certifications
APM: PFQ, PQ, RPP Axelos (OGC): PRINCE2 PMI: PMP
7 of 22
Context is the environment in which an organisation seeks to achieve its objectives.
As the context changes, it may be necessary to adjust the approach to Risk Management.
Risk Management principles are the same at all levels – strategic, change & operational.
At the strategic level Risk Management is a significant part of corporate governance. How risk is to be
managed across an organisation taking into account external factors such as legislation, government
policy, market, domain and internal factors such as the organisation’s size, complexity and culture as
well as the strategic vision, balance of risk across the organization, conflict resolution, risk appetite and
lessons learned, may be described in a Risk Management Strategy. The RMS may be a single document
or a number of documents, e.g. Policy, Process and Guidance.
Operational Risk Management covers day-to-day business functions such as health & safety, people,
information security and business continuity.
Change is what projects and programmes deliver.
Apply Risk Management through all project delivery phases
– in a manner proportional to the value, risk and complexity at each phase.
The nature and degree of freedom for responding to risk will change at different project phases, e.g. in
the concept phase there will be a greater chance to adjust the scope and set budgets to manage risk.
Risk Management Context
8 of 22
Risk Management Process
Iterate to keep the Risk Exposure
(the impact of risk on objective attainment),
within the Risk Appetite
(an agreed, acceptable level of risk),
in a cost-effective manner.
Identify
Assess
Plan
Implement
Identify Risks: Experience, Checklist, SWOT, Interviews
Categorise
Probability & Impact
Prioritise
Qualitative
Quantitative
Define Risk Response: Exploit/Avoid, Share/Transfer,
Enhance/Mitigate, Realise/Accept
Define Contingencies
Iterative
Implement
Review
Communicate
Manage Stakeholders
Lessons Learned
9 of 22
Identify, Assess, Plan, Implement
Identify: What could happen
Identify & List Risks: Experience, Checklist, SWOT, PESTLE, Interviews, Questionnaires
Categorise: By project phase, system element, or other suitable risk event source breakdown
Assess: Understand consequences
Qualitative assessment: Probability of the risk occurring and the size of the Impact on objectives
Prioritise: Rank the risks – focus on those with highest probability and impact
Timing: Understand when the risk may occur
Quantitative analysis: modelling, confidence levels, sensitivity
Plan: Define appropriate responses
Exploit/Avoid, Share/Transfer, Enhance/Mitigate
Define Contingencies
Ignore, Realise/Accept
Residual Risk: Risk that remains after taking enhancement/mitigation measures
Secondary Risk: Risk that arises as a result of taking enhancement/mitigation measures
Implement: Monitor and control the risks
Review: Risk triggers, responses, add new risks, close dead risks & release risk pot
Communicate: Key risks
Manage Stakeholders
10 of 22
Plan: Define appropriate responses
Allocate ownership to manage risk optimally
Insure (internally by pooling or externally)
Reduce the uncertainty – if cost effective to do so
Fall-back, should the risk occur/not occur despite mitigation/enhancement
Risk or Residual Risk after enhancement/mitigation
May also choose to treat as Risks and define a response etc.
Share/Transfer:
Enhance/Mitigate:
Contingencies:
Realise/Accept:
Secondary Risk:
Planning &
Scheduling
Change Scope
Opportunities Threats
AvoidExploit
AcceptRealise
Log / Monitor
MitigateEnhance TransferShare
Contingency
Impact and/or
Probability
Impact and/or
Probability
Residual
Risk
Ignore
Residual
Risk
 Specification  Partners PBS, WBS  Supplierse.g.  Requirements
Contingency
Secondary
Risk
Secondary
Risk
11 of 22
Qualitative Assessment
Rank Risks by assessing risk probabilities and impacts having first adjusted to suit the project
Probability Impact Diagram
Mapping risks helps to decide where
best to focus risk management effort.
Contingency Setting
A Risk Register can calculate the total
Contingency based on the entered data.
This figure is at best a guide
and must be subject to discussion.
Probability VH VH
Probability
H H
M M
L L
VL VL
VL L M H VH VH H M L VL
Negative Impact Positive Impact
Threats Opportunities
Focus effort on
Key Risks
Very Low Low Medium High Very High
Schedule Impact < 2 weeks 2 weeks to < 1 month 1 to < 2 months 2 to < 4 months > 4 months
Cost Impact < 1% 1% to < 2% 2% to < 4% 4% to < 8% > 8%
Performance
Impact
Minor impact
in a secondary aspect
Multiple impacts
in a secondary aspect
Minor impacts
in one key aspect
Major impact
in one key aspect
Major impact
in multiple key aspects
Probability < 10% 10% to < 25% 25% to < 50% 50% to < 75% > 75%
12 of 22
Bias, Concurrency & Estimation Uncertainty
Optimism Bias can make assumptions too positive, perhaps as a result of making a plan fit fixed targets.
Cognitive Bias is where personal past experience unscientifically skews estimates.
Plan dates and costs are often optimistic if
estimation uncertainty is not considered.
Plans generally feature concurrent tasks with
minimal float. Task effort estimates frequently
use expert judgement, often given as single
point, or deterministic, estimates.
The more concurrent tasks, the greater the
impact on the project when, as is likely, some
tasks finish later than estimated. Deterministic
outcomes often have a very low probability.
Range estimates are more realistic, with
3 points (minimum, most likely, maximum)
advised. Key project dates and costs then also
become ranges along with a probability.
Typical plan analysis: Yellow line is the probability of achieving the Deterministic Cost
13 of 22
Funding Estimation Uncertainty & Selective 4 Point Estimating
‘Most Likely’ means equally probable of being under or over, but estimates often
have a negative bias such that most likely (ML) is not 50% probable.
To avoid this negative bias, 4 points are recommended*, 3 point plus probability
of the ‘most likely’ – just for the tasks that most impact the project, found by
sensitivity analysis, as doing this for all tasks is typically not worthwhile.
Min ML P=50% Max
The business Risk Appetite can inform what probability to use across the business, e.g.:
10% Team Target (likely risks do not occur)
50% Best Estimate (as many risks occur as not)
90% ‘Safe’ Estimate (several unlikely major risks occur)
One strategy is to use the cost difference between the project cost for the probability chosen according
to the business Risk Appetite and the deterministic project cost as the main element of a ‘project risk
pot’ to handle estimation uncertainty. Rewarding using as little of this risk pot as possible, whilst
recognising that a proportion is likely to be required, encourages behaviour that enhances results whilst
recognising uncertainty and setting realistic expectations.
4 Point Estimates
* See separate presentation, “Estimation for Projects & Programmes”
Caution
Don’t confuse uncertainty with a lack of knowledge.
Large ranges generally indicate guessing – experience is required to estimate rather than guess.
14 of 22
Risk Management for Projects & Programmes
Strategy
(Need)
Contingency
Opportunities
Enhancement
Tasks
Secondary
Risks
Product
Breakdown
Structure
Work
Breakdown
Structure
Work Packages
& Tasks
Estimates
Zero Risk
(Deterministic)
Cost
INFORM
Inform / Offset
Threats
Mitigation
Tasks
Programme
& Project
Set-up
INFORM
Project
Delivery
Process,
PDP
Risk Register Tool, RRT
Risk Management Strategy, RMS
Risk Management Plan, RMP
Held at Board level: Project, Programme or Business
Held at Project & Programme level
If cost effective
Contingency
Project
Risk Pot
Estimation
Uncertainty
15 of 22
Risk Management Strategy
How risk is to be managed across an organisation, the corporate strategy & policy.
Generally an in-feed for a programme or project but may also be defined at this level, possibly as a flow-
down from an organisation RMS.
Risk Management Plan
How risk will be managed in a programme or project, tailored to that programme or project,
i.e. how the Risk Management Strategy will be delivered.
Risk Management Documents & Tools
Risk Register Tool
Central repository for Risk Events, i.e. risk data
• Opportunity & Threat Log and Analysis
• Risk Owner
• Risk Response & Cost Estimation
• Probability Impact Diagram, PID
• Risk Triggers & Timing
• Classification marking
• Internal Only option
• Baselines & Risk History graphing
• Contingency Estimation
• Risk Exposure calculation
Quantitative Analysis Tools
Quantitative Analysis (uncertainty and probabilistic modelling – Monte Carlo analysis) is best done using
purpose built tools, e.g. @Risk, or integrated scheduling and risk management tools, e.g. Oracle
Primavera Risk Analysis or Safran Risk.
16 of 22
Keep People Safe
HSE: Health, Safety and Environment
Do a Risk Assessment to expose potential hazards
EN ISO 14121-1 is a useful guide in defining potential hazards
Consider the whole lifecycle: hazards may differ from one phase to the next
Plan actions to deal with the hazards identified and reduce to an acceptable level the probability of
harm to the team and other stakeholders
There may be tasks and costs arising from the risk assessment: include these in planning
17 of 22
Risk Assessment provides scientific advice on potential threats, often the basis for making decisions to
address these threats via Risk Management.
Europe separates the roles of Risk Assessor and Risk Manager in law to make clear the distinction
between science and politics.
Risk Assessment is concerned with preventing harm to people
The Health and Safety Executive in the UK defines Risk as the chance, high or low, of somebody being
harmed by a hazard, and how serious the harm could be.
Risk Management is minimising the impact of threats and maximising the benefit of opportunities
Risk Assessment actions are aimed at reducing the potential harm to zero, or at least to acceptable
levels by taking reasonably practicable measures – balancing the level of risk against the measures
needed to control the real risk in terms of money, time or trouble.
Action need not be taken if it would be grossly disproportionate to the level of risk.
Risk Assessment is an excellent, essential and in most countries mandatory method for understanding
and reducing potential harm to people.
However, Risk Assessment is not a substitute for Risk Management, e.g. there is no concept of up-side
risk in Risk Assessment since there is no 'harm' in up-side risk.
Risk Management and Risk Assessment
18 of 22
Risk Management: Test Strategy
Unit Test on a PC Regression Test via a simulator
automated on commit automated on commit
get code coverage
System Test the whole system Continuous Integration
doing real things where possible
probably involves people
Field Trial Interoperability Test
Site / Final
Acceptance Test
System Test
Integration Test
Bring-up Test
Subsystem
Production Test
Subsystem Test
Module Test
Unit Test
Low Level Tests
Integration Level Tests
System Level Tests
Optional System Level Tests
(required in some domains)
Compliance Test
System
Production Test
FPGA On-Board
Test
Design TestProduction Test
19 of 22
Prior to ‘Identify’ describe the project and goals of Risk Management for your project (often described
in the Risk Management Plan). Then the project team can raise specific project risks.
The danger of not doing this is that the risks identified may be generic and that this is carried
throughout Risk Management for the project, significantly devaluing Risk Management.
Risk descriptions need to be understandable outside the project, without further explanation.
Risks should be accurately defined and as specific as possible.
Avoid listing an effect rather than the risk leading to the effect.
It may help to think in terms of cause, then risk arising from this cause, then the effect(s) of the risk.
Probability and impact are often guesses and contain cognitive bias so it can be helpful to consider the
relative risk scores rather than the absolute in deciding which risks to actively manage.
Risk Management is more than just keeping a Risk Register.
The Risk Register is only a tool to note the risks, our responses and to help with decision making.
Completing the actions arising add the real value.
Appropriate review frequency depends on project scale and phase.
At some phases, weekly review may be worthwhile; at other phases, monthly may be sufficient.
Practical Risk Management: Hints & Tips I
20 of 22
Experience is needed to judge the appropriate Risk Management effort, but investing more in managing
risk than the cost if all the risks occur clearly makes no sense.
The Risk Management process can be gone through in a few minutes for many risks, so the effort
required need not be high.
The effort level should not however be limited simply by a lack of competence (i.e. knowledge &
experience) of those undertaking Risk Management.
The number of risks typically identified depends on the project value and complexity; usually more than
10, less than 100. How many of the identified risk are selected for managing is an experienced based
judgement; but very rarely all, except perhaps for a strategic Risk Register.
Risk Assessments commonly involve a reassessment of the impact after the risk responses have been
undertaken, since it is vital that we can see that potential harm to people has indeed been reduced to
an acceptable level by our actions. This is much less common in Risk Management in projects and
programmes where there’s often little value in this sort of reassessment.
It can be difficult for many people to consider threats and opportunities concurrently
– e.g. we don’t talk about the ‘risk’ of a beneficial event occurring in normal life.
So it may help to consider threats and opportunities separately rather than concurrently when
identifying risks.
Practical Risk Management: Hints & Tips II
21 of 22
Summary
Most projects and programmes have to deal with risk, this presentation summarises best practice for
visible, repeatable and consistent risk management. Whilst best practice guidance offers no single
definition, it is broadly aligned.
Some level of risk is not only inevitable, but desirable for success.
Project Risk Management is a core PM competence and should be practiced on all projects and
programmes, in a manner appropriate to the value, complexity and risk.
Projects which do not undertake Risk Management are more likely to fail.
Estimation uncertainty alone can reduce the probability of on-time delivery to less than 10%.
Risk Management has many benefits, not least being a higher likelihood of delivery to time and budget.
22 of 22
Author Profile
In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m
project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP,
the Roke Engineering Process, also managing the engineering tools to support it.
After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer,
I moved into project management for 14 years, at Siemens and Roke Manor Research.
Successfully delivering Roke’s most challenging whole lifecycle product developments
on time and under budget led to a role as Director and board member for 6 years.
In 2013 I returned to hands-on project management as Programme Director at
Cambridge Consultants, founder member of the Cambridge Science Park.
Creator of the APM corporate accredited PM Excellence Programme,
I chaired a quarterly PM forum to share best practice and built a
supportive PM community. I coached seven PMs to RPP, five to PQ,
and all passed APMP.
These investments in PM professionalism led to a turn-around and
annual improvement in project results across a 400 project portfolio
and delivered an above budget performance in five consecutive years
with profits totalling £7.9m above budget.
Passionate advocate of PM professionalism, Fellow of the APM and
the IET and author of articles published in Project and PM Today.
Professional Development
Winning Project Work
Planning
Estimating
Risk Management
Earned Value Management
Change Control
Stakeholder Management
3 Steps to Professional Project Management: Case Study
ProjectManagementTopics

More Related Content

What's hot

Risk management
Risk managementRisk management
Risk managementMECandPMV
 
Risk Management
Risk ManagementRisk Management
Risk Managementcgeorgeo
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management OverviewJIGNESH PADIA
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
Risk Analysis PowerPoint Presentation Slides
Risk Analysis PowerPoint Presentation Slides Risk Analysis PowerPoint Presentation Slides
Risk Analysis PowerPoint Presentation Slides SlideTeam
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Risk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationRisk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationUsama Saeed
 
Advanced program management risk mitigation and management
Advanced program management   risk mitigation and managementAdvanced program management   risk mitigation and management
Advanced program management risk mitigation and managementMarcus Vannini
 

What's hot (20)

Risk management
Risk managementRisk management
Risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Risk Management in Project Management
Risk Management in Project ManagementRisk Management in Project Management
Risk Management in Project Management
 
Risk management
Risk managementRisk management
Risk management
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management Overview
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Risk Analysis PowerPoint Presentation Slides
Risk Analysis PowerPoint Presentation Slides Risk Analysis PowerPoint Presentation Slides
Risk Analysis PowerPoint Presentation Slides
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Risk management
Risk managementRisk management
Risk management
 
Risk management
Risk managementRisk management
Risk management
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Risk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationRisk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix Presentation
 
Advanced program management risk mitigation and management
Advanced program management   risk mitigation and managementAdvanced program management   risk mitigation and management
Advanced program management risk mitigation and management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 

Viewers also liked

APMP Foundation Certification Training - Qualifying the right opportunity
APMP Foundation Certification Training - Qualifying the right opportunityAPMP Foundation Certification Training - Qualifying the right opportunity
APMP Foundation Certification Training - Qualifying the right opportunityAbhijit Majumdar CP.APMP
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementBid to Win Ltd
 
Steps in resolving ethical dilemmas
Steps in resolving ethical dilemmasSteps in resolving ethical dilemmas
Steps in resolving ethical dilemmasPeter Columa
 
Ethical Dilemma
Ethical DilemmaEthical Dilemma
Ethical Dilemmapurval
 
control techniques
control techniquescontrol techniques
control techniquesRakesh Kumar
 
Information system presentation assignment 1 (management information system) ...
Information system presentation assignment 1 (management information system) ...Information system presentation assignment 1 (management information system) ...
Information system presentation assignment 1 (management information system) ...vibrant6000
 
ISRO Presentation
ISRO Presentation  ISRO Presentation
ISRO Presentation ashu chauhan
 
Ethical dilemmas presentation
Ethical dilemmas presentationEthical dilemmas presentation
Ethical dilemmas presentationmansine
 
Ethical Dilemmas in Business
Ethical Dilemmas in BusinessEthical Dilemmas in Business
Ethical Dilemmas in BusinessShahzad Khan
 

Viewers also liked (12)

APMP Foundation Certification Training - Qualifying the right opportunity
APMP Foundation Certification Training - Qualifying the right opportunityAPMP Foundation Certification Training - Qualifying the right opportunity
APMP Foundation Certification Training - Qualifying the right opportunity
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process Management
 
Steps in resolving ethical dilemmas
Steps in resolving ethical dilemmasSteps in resolving ethical dilemmas
Steps in resolving ethical dilemmas
 
Ethical Dilemma
Ethical DilemmaEthical Dilemma
Ethical Dilemma
 
Ethical dilemma powerpoint
Ethical dilemma powerpointEthical dilemma powerpoint
Ethical dilemma powerpoint
 
APM Risk SIG Uncertainty or risk - is there any difference?
APM Risk SIG Uncertainty or risk - is there any difference?APM Risk SIG Uncertainty or risk - is there any difference?
APM Risk SIG Uncertainty or risk - is there any difference?
 
control techniques
control techniquescontrol techniques
control techniques
 
Information system presentation assignment 1 (management information system) ...
Information system presentation assignment 1 (management information system) ...Information system presentation assignment 1 (management information system) ...
Information system presentation assignment 1 (management information system) ...
 
ISRO Presentation
ISRO Presentation  ISRO Presentation
ISRO Presentation
 
Ethical dilemmas presentation
Ethical dilemmas presentationEthical dilemmas presentation
Ethical dilemmas presentation
 
Ethical Dilemmas in Business
Ethical Dilemmas in BusinessEthical Dilemmas in Business
Ethical Dilemmas in Business
 

Similar to Project Risk Management

ToTCOOP+i O3 o4 unit-9_final_version_en
ToTCOOP+i O3 o4 unit-9_final_version_enToTCOOP+i O3 o4 unit-9_final_version_en
ToTCOOP+i O3 o4 unit-9_final_version_enToTCOOPiTech
 
Project Management by Mostafa Ewees
Project Management  by Mostafa EweesProject Management  by Mostafa Ewees
Project Management by Mostafa EweesMostafa Ewees
 
Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)rafeeqameen
 
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects Mark Ritchie
 
Risk Management Toolkit
Risk Management ToolkitRisk Management Toolkit
Risk Management ToolkitPeterFranz6
 
Fundamentals Of Risk Management
Fundamentals Of Risk ManagementFundamentals Of Risk Management
Fundamentals Of Risk ManagementDr David Hancock
 
You will construct a manual for your company that defines the Risk M.pdf
You will construct a manual for your company that defines the Risk M.pdfYou will construct a manual for your company that defines the Risk M.pdf
You will construct a manual for your company that defines the Risk M.pdfthangarajarivukadal
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinsteinRamaica Ona
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinsteinAahil Malik
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinsteinSukumar Reddy
 
Pm0016 project risk management
Pm0016  project risk managementPm0016  project risk management
Pm0016 project risk managementsmumbahelp
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategiesDebashishDas49
 
Pm0016 set-1
Pm0016 set-1Pm0016 set-1
Pm0016 set-1Paul Hunt
 
An introduction to finance
An introduction to financeAn introduction to finance
An introduction to financeRobert Reed
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...PECB
 

Similar to Project Risk Management (20)

Project/Program Risk management
Project/Program Risk managementProject/Program Risk management
Project/Program Risk management
 
ToTCOOP+i O3 o4 unit-9_final_version_en
ToTCOOP+i O3 o4 unit-9_final_version_enToTCOOP+i O3 o4 unit-9_final_version_en
ToTCOOP+i O3 o4 unit-9_final_version_en
 
Project Management by Mostafa Ewees
Project Management  by Mostafa EweesProject Management  by Mostafa Ewees
Project Management by Mostafa Ewees
 
Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)
 
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
 
Risk Management Toolkit
Risk Management ToolkitRisk Management Toolkit
Risk Management Toolkit
 
Fundamentals Of Risk Management
Fundamentals Of Risk ManagementFundamentals Of Risk Management
Fundamentals Of Risk Management
 
You will construct a manual for your company that defines the Risk M.pdf
You will construct a manual for your company that defines the Risk M.pdfYou will construct a manual for your company that defines the Risk M.pdf
You will construct a manual for your company that defines the Risk M.pdf
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinstein
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinstein
 
1 -corinne_berinstein
1  -corinne_berinstein1  -corinne_berinstein
1 -corinne_berinstein
 
Pm0016 project risk management
Pm0016  project risk managementPm0016  project risk management
Pm0016 project risk management
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategies
 
Risk Management Assignment
Risk Management AssignmentRisk Management Assignment
Risk Management Assignment
 
Pm0016 set-1
Pm0016 set-1Pm0016 set-1
Pm0016 set-1
 
An introduction to finance
An introduction to financeAn introduction to finance
An introduction to finance
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...
Implementation of Enterprise Risk Management with ISO 31000 Risk Management S...
 
Risk Management 1 (2)
Risk Management 1 (2)Risk Management 1 (2)
Risk Management 1 (2)
 

More from Russell Taylor BEng CEng FAPM FIET (7)

Change Control
Change ControlChange Control
Change Control
 
Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
Stakeholder Management
Stakeholder ManagementStakeholder Management
Stakeholder Management
 
Planning
PlanningPlanning
Planning
 
Estimating
EstimatingEstimating
Estimating
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PM Professional Development
PM Professional DevelopmentPM Professional Development
PM Professional Development
 

Recently uploaded

Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 

Recently uploaded (20)

Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 

Project Risk Management

  • 1. 1 of 22 Risk Management for Projects & Programmes Known knowns Things that we know that we know Known unknowns Things that we know that we don’t know Unknown unknowns Things that we do not know we don’t know ?
  • 2. 2 of 22 What is Risk? We know that plans are unlikely to be a precise prediction of the future Plans are a model of interconnected tasks believed certain to be required to achieve an objective There are also events which are less than certain, but if they happen, would impact the plan A Risk is a significant but uncertain event that, if it occurs, has an effect on the plan A risk can have detrimental or beneficial effects Threat A risk with a detrimental effect Opportunity A risk with a beneficial effect Patsy, Monty Python and the Holy Grail, 1975
  • 3. 3 of 22 What is Risk Management? How we act to manage significant uncertainty Uncertain events will always be part of any plan for the future Risk Management is a core PM competence “There are known knowns; there are things that we know that we know. There are known unknowns; that is to say, there are things that we know that we don’t know. But there are also unknown unknowns – there are things that we do not know we don’t know.” Donald Rumsfeld, US Secretary of Defence, 2002 Project Management Planning & Scheduling Risk Management Context & Assumptions significant insignificant Uncertain Events Certain Events
  • 4. 4 of 22 Why do Risk Management? Good Risk Management will  Lead to more realistic plans  Help to set expectations appropriate to value, risk and complexity  Inform bid/no bid decisions  Help in selecting the most appropriate contract type  Inform PM selection, matching PM competence to value, risk and complexity  Help set project level contingencies, rather than task level or a fixed amount  Enable greater honesty, openness and understanding  Reduce uncertainty by implementing responses to risk  Enable simpler, more transparent reporting  Reduce stress and reliance on a hero culture  Significantly increase the likelihood of meeting time, cost and quality objectives Cautions ! Risk Management will not guarantee meeting time, cost and quality objectives ! If undertaken as a tick box exercise, or only at bid time, the full value will not be realised ! The effort invested should be proportional to value, risk and complexity
  • 5. 5 of 22 International Standards Organisation ISO 31000 [2009] Risk Management Principles & Guidelines  ISO IEC 31010 [2009] Risk Management Risk Assessment Techniques  ISO Guide 73 [2009] Risk Management Vocabulary  British Standards BS 6079-3 [2000] Guide to the Management of Business Related Project Risk  Association for Project Management PRAM: Project Risk Analysis and Management Guide, 2nd Edition [2010]  Interfacing Risk and Earned Value Management [2008]  Prioritising Project Risks [2008]  Project Management Institute Practice Standard for Project Risk Management [2009]  The Institute of Risk Management Publications that primarily deal with enterprise risk management  UK Government The Orange Book: Management of Risk, Principles and Concepts [2004]  Management of Risk, Guidance for Practitioners, 3rd edition [2010, Axelos]  Ministry of Defence Acquisition System Guidance: Risk Management [v4.2.2] Risk Management Best Practice Guidance
  • 6. 6 of 22 Risk Management Training Certification Valid Renewal Acquisition Pre-requisite Association for Project Management Risk Certificate Level 1 - - 1 hour multiple choice exam: 60 questions, pass ≥60% Confirms knowledge sufficient to allow contribution to risk management within a project. Can be taken as a 2 day course, cost £1,100 (inc. exam fee). Open exam fee £164 (£146 for APM members). Risk Certificate Level 2 - - 3.25 hour exam: section A, 100 marks; section B, 100 marks, 2 from 4 questions, 2 relate to case study, pass ≥60% Risk Certificate Level 1 knowledge (not certification) Confirms knowledge, understanding and capability, sufficient to undertake project risk management. Can be taken as a 2 day course, cost £1,100 (inc. exam fee). Open exam fee £430 (£310 for APM members). Combined Risk Levels 1 & 2 Open exam fee £558 (£384 for APM members). UK Cabinet Office Axelos M_o_R Foundation - - 1 hour multiple choice exam: 75 questions of which 70 count, pass ≥50% (35/70) Confirms sufficient knowledge and understanding to contribute to the identification, assessment and control of risks across any organization. M_o_R Practitioner 5 years 1hr exam, pass ≥55% 3 hour exam: 4 questions, 20 marks each, open book (specified M_o_R books only), pass ≥50% (40/80) M_o_R Foundation Confirms sufficient understanding of how to apply and tailor M_o_R in a scenario situation. M_o_R Foundation and Practitioner can be taken together in a 5 day course, cost £2,300. Project Management Institute PMI-RMP PMI Risk Management Professional 3 years 30 PDUs over 3 years 3.5 hour multiple choice exam: 170 questions, 150 scoring, 'Modified Angoff Method' to determine pass Degree, 2 years’ project risk management experience and 30 hours formal project risk management training Recognises competence in assessing and identifying project risks, mitigating threats and capitalizing on opportunities, while still possessing a core knowledge and practical application in all areas of project management. 2008 launch, 2,033 credential holders worldwide by 30 April 2013. Certification fee $670 ($520 for PMI members). Project Risk Management is also covered in general PM certifications APM: PFQ, PQ, RPP Axelos (OGC): PRINCE2 PMI: PMP
  • 7. 7 of 22 Context is the environment in which an organisation seeks to achieve its objectives. As the context changes, it may be necessary to adjust the approach to Risk Management. Risk Management principles are the same at all levels – strategic, change & operational. At the strategic level Risk Management is a significant part of corporate governance. How risk is to be managed across an organisation taking into account external factors such as legislation, government policy, market, domain and internal factors such as the organisation’s size, complexity and culture as well as the strategic vision, balance of risk across the organization, conflict resolution, risk appetite and lessons learned, may be described in a Risk Management Strategy. The RMS may be a single document or a number of documents, e.g. Policy, Process and Guidance. Operational Risk Management covers day-to-day business functions such as health & safety, people, information security and business continuity. Change is what projects and programmes deliver. Apply Risk Management through all project delivery phases – in a manner proportional to the value, risk and complexity at each phase. The nature and degree of freedom for responding to risk will change at different project phases, e.g. in the concept phase there will be a greater chance to adjust the scope and set budgets to manage risk. Risk Management Context
  • 8. 8 of 22 Risk Management Process Iterate to keep the Risk Exposure (the impact of risk on objective attainment), within the Risk Appetite (an agreed, acceptable level of risk), in a cost-effective manner. Identify Assess Plan Implement Identify Risks: Experience, Checklist, SWOT, Interviews Categorise Probability & Impact Prioritise Qualitative Quantitative Define Risk Response: Exploit/Avoid, Share/Transfer, Enhance/Mitigate, Realise/Accept Define Contingencies Iterative Implement Review Communicate Manage Stakeholders Lessons Learned
  • 9. 9 of 22 Identify, Assess, Plan, Implement Identify: What could happen Identify & List Risks: Experience, Checklist, SWOT, PESTLE, Interviews, Questionnaires Categorise: By project phase, system element, or other suitable risk event source breakdown Assess: Understand consequences Qualitative assessment: Probability of the risk occurring and the size of the Impact on objectives Prioritise: Rank the risks – focus on those with highest probability and impact Timing: Understand when the risk may occur Quantitative analysis: modelling, confidence levels, sensitivity Plan: Define appropriate responses Exploit/Avoid, Share/Transfer, Enhance/Mitigate Define Contingencies Ignore, Realise/Accept Residual Risk: Risk that remains after taking enhancement/mitigation measures Secondary Risk: Risk that arises as a result of taking enhancement/mitigation measures Implement: Monitor and control the risks Review: Risk triggers, responses, add new risks, close dead risks & release risk pot Communicate: Key risks Manage Stakeholders
  • 10. 10 of 22 Plan: Define appropriate responses Allocate ownership to manage risk optimally Insure (internally by pooling or externally) Reduce the uncertainty – if cost effective to do so Fall-back, should the risk occur/not occur despite mitigation/enhancement Risk or Residual Risk after enhancement/mitigation May also choose to treat as Risks and define a response etc. Share/Transfer: Enhance/Mitigate: Contingencies: Realise/Accept: Secondary Risk: Planning & Scheduling Change Scope Opportunities Threats AvoidExploit AcceptRealise Log / Monitor MitigateEnhance TransferShare Contingency Impact and/or Probability Impact and/or Probability Residual Risk Ignore Residual Risk  Specification  Partners PBS, WBS  Supplierse.g.  Requirements Contingency Secondary Risk Secondary Risk
  • 11. 11 of 22 Qualitative Assessment Rank Risks by assessing risk probabilities and impacts having first adjusted to suit the project Probability Impact Diagram Mapping risks helps to decide where best to focus risk management effort. Contingency Setting A Risk Register can calculate the total Contingency based on the entered data. This figure is at best a guide and must be subject to discussion. Probability VH VH Probability H H M M L L VL VL VL L M H VH VH H M L VL Negative Impact Positive Impact Threats Opportunities Focus effort on Key Risks Very Low Low Medium High Very High Schedule Impact < 2 weeks 2 weeks to < 1 month 1 to < 2 months 2 to < 4 months > 4 months Cost Impact < 1% 1% to < 2% 2% to < 4% 4% to < 8% > 8% Performance Impact Minor impact in a secondary aspect Multiple impacts in a secondary aspect Minor impacts in one key aspect Major impact in one key aspect Major impact in multiple key aspects Probability < 10% 10% to < 25% 25% to < 50% 50% to < 75% > 75%
  • 12. 12 of 22 Bias, Concurrency & Estimation Uncertainty Optimism Bias can make assumptions too positive, perhaps as a result of making a plan fit fixed targets. Cognitive Bias is where personal past experience unscientifically skews estimates. Plan dates and costs are often optimistic if estimation uncertainty is not considered. Plans generally feature concurrent tasks with minimal float. Task effort estimates frequently use expert judgement, often given as single point, or deterministic, estimates. The more concurrent tasks, the greater the impact on the project when, as is likely, some tasks finish later than estimated. Deterministic outcomes often have a very low probability. Range estimates are more realistic, with 3 points (minimum, most likely, maximum) advised. Key project dates and costs then also become ranges along with a probability. Typical plan analysis: Yellow line is the probability of achieving the Deterministic Cost
  • 13. 13 of 22 Funding Estimation Uncertainty & Selective 4 Point Estimating ‘Most Likely’ means equally probable of being under or over, but estimates often have a negative bias such that most likely (ML) is not 50% probable. To avoid this negative bias, 4 points are recommended*, 3 point plus probability of the ‘most likely’ – just for the tasks that most impact the project, found by sensitivity analysis, as doing this for all tasks is typically not worthwhile. Min ML P=50% Max The business Risk Appetite can inform what probability to use across the business, e.g.: 10% Team Target (likely risks do not occur) 50% Best Estimate (as many risks occur as not) 90% ‘Safe’ Estimate (several unlikely major risks occur) One strategy is to use the cost difference between the project cost for the probability chosen according to the business Risk Appetite and the deterministic project cost as the main element of a ‘project risk pot’ to handle estimation uncertainty. Rewarding using as little of this risk pot as possible, whilst recognising that a proportion is likely to be required, encourages behaviour that enhances results whilst recognising uncertainty and setting realistic expectations. 4 Point Estimates * See separate presentation, “Estimation for Projects & Programmes” Caution Don’t confuse uncertainty with a lack of knowledge. Large ranges generally indicate guessing – experience is required to estimate rather than guess.
  • 14. 14 of 22 Risk Management for Projects & Programmes Strategy (Need) Contingency Opportunities Enhancement Tasks Secondary Risks Product Breakdown Structure Work Breakdown Structure Work Packages & Tasks Estimates Zero Risk (Deterministic) Cost INFORM Inform / Offset Threats Mitigation Tasks Programme & Project Set-up INFORM Project Delivery Process, PDP Risk Register Tool, RRT Risk Management Strategy, RMS Risk Management Plan, RMP Held at Board level: Project, Programme or Business Held at Project & Programme level If cost effective Contingency Project Risk Pot Estimation Uncertainty
  • 15. 15 of 22 Risk Management Strategy How risk is to be managed across an organisation, the corporate strategy & policy. Generally an in-feed for a programme or project but may also be defined at this level, possibly as a flow- down from an organisation RMS. Risk Management Plan How risk will be managed in a programme or project, tailored to that programme or project, i.e. how the Risk Management Strategy will be delivered. Risk Management Documents & Tools Risk Register Tool Central repository for Risk Events, i.e. risk data • Opportunity & Threat Log and Analysis • Risk Owner • Risk Response & Cost Estimation • Probability Impact Diagram, PID • Risk Triggers & Timing • Classification marking • Internal Only option • Baselines & Risk History graphing • Contingency Estimation • Risk Exposure calculation Quantitative Analysis Tools Quantitative Analysis (uncertainty and probabilistic modelling – Monte Carlo analysis) is best done using purpose built tools, e.g. @Risk, or integrated scheduling and risk management tools, e.g. Oracle Primavera Risk Analysis or Safran Risk.
  • 16. 16 of 22 Keep People Safe HSE: Health, Safety and Environment Do a Risk Assessment to expose potential hazards EN ISO 14121-1 is a useful guide in defining potential hazards Consider the whole lifecycle: hazards may differ from one phase to the next Plan actions to deal with the hazards identified and reduce to an acceptable level the probability of harm to the team and other stakeholders There may be tasks and costs arising from the risk assessment: include these in planning
  • 17. 17 of 22 Risk Assessment provides scientific advice on potential threats, often the basis for making decisions to address these threats via Risk Management. Europe separates the roles of Risk Assessor and Risk Manager in law to make clear the distinction between science and politics. Risk Assessment is concerned with preventing harm to people The Health and Safety Executive in the UK defines Risk as the chance, high or low, of somebody being harmed by a hazard, and how serious the harm could be. Risk Management is minimising the impact of threats and maximising the benefit of opportunities Risk Assessment actions are aimed at reducing the potential harm to zero, or at least to acceptable levels by taking reasonably practicable measures – balancing the level of risk against the measures needed to control the real risk in terms of money, time or trouble. Action need not be taken if it would be grossly disproportionate to the level of risk. Risk Assessment is an excellent, essential and in most countries mandatory method for understanding and reducing potential harm to people. However, Risk Assessment is not a substitute for Risk Management, e.g. there is no concept of up-side risk in Risk Assessment since there is no 'harm' in up-side risk. Risk Management and Risk Assessment
  • 18. 18 of 22 Risk Management: Test Strategy Unit Test on a PC Regression Test via a simulator automated on commit automated on commit get code coverage System Test the whole system Continuous Integration doing real things where possible probably involves people Field Trial Interoperability Test Site / Final Acceptance Test System Test Integration Test Bring-up Test Subsystem Production Test Subsystem Test Module Test Unit Test Low Level Tests Integration Level Tests System Level Tests Optional System Level Tests (required in some domains) Compliance Test System Production Test FPGA On-Board Test Design TestProduction Test
  • 19. 19 of 22 Prior to ‘Identify’ describe the project and goals of Risk Management for your project (often described in the Risk Management Plan). Then the project team can raise specific project risks. The danger of not doing this is that the risks identified may be generic and that this is carried throughout Risk Management for the project, significantly devaluing Risk Management. Risk descriptions need to be understandable outside the project, without further explanation. Risks should be accurately defined and as specific as possible. Avoid listing an effect rather than the risk leading to the effect. It may help to think in terms of cause, then risk arising from this cause, then the effect(s) of the risk. Probability and impact are often guesses and contain cognitive bias so it can be helpful to consider the relative risk scores rather than the absolute in deciding which risks to actively manage. Risk Management is more than just keeping a Risk Register. The Risk Register is only a tool to note the risks, our responses and to help with decision making. Completing the actions arising add the real value. Appropriate review frequency depends on project scale and phase. At some phases, weekly review may be worthwhile; at other phases, monthly may be sufficient. Practical Risk Management: Hints & Tips I
  • 20. 20 of 22 Experience is needed to judge the appropriate Risk Management effort, but investing more in managing risk than the cost if all the risks occur clearly makes no sense. The Risk Management process can be gone through in a few minutes for many risks, so the effort required need not be high. The effort level should not however be limited simply by a lack of competence (i.e. knowledge & experience) of those undertaking Risk Management. The number of risks typically identified depends on the project value and complexity; usually more than 10, less than 100. How many of the identified risk are selected for managing is an experienced based judgement; but very rarely all, except perhaps for a strategic Risk Register. Risk Assessments commonly involve a reassessment of the impact after the risk responses have been undertaken, since it is vital that we can see that potential harm to people has indeed been reduced to an acceptable level by our actions. This is much less common in Risk Management in projects and programmes where there’s often little value in this sort of reassessment. It can be difficult for many people to consider threats and opportunities concurrently – e.g. we don’t talk about the ‘risk’ of a beneficial event occurring in normal life. So it may help to consider threats and opportunities separately rather than concurrently when identifying risks. Practical Risk Management: Hints & Tips II
  • 21. 21 of 22 Summary Most projects and programmes have to deal with risk, this presentation summarises best practice for visible, repeatable and consistent risk management. Whilst best practice guidance offers no single definition, it is broadly aligned. Some level of risk is not only inevitable, but desirable for success. Project Risk Management is a core PM competence and should be practiced on all projects and programmes, in a manner appropriate to the value, complexity and risk. Projects which do not undertake Risk Management are more likely to fail. Estimation uncertainty alone can reduce the probability of on-time delivery to less than 10%. Risk Management has many benefits, not least being a higher likelihood of delivery to time and budget.
  • 22. 22 of 22 Author Profile In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP, the Roke Engineering Process, also managing the engineering tools to support it. After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer, I moved into project management for 14 years, at Siemens and Roke Manor Research. Successfully delivering Roke’s most challenging whole lifecycle product developments on time and under budget led to a role as Director and board member for 6 years. In 2013 I returned to hands-on project management as Programme Director at Cambridge Consultants, founder member of the Cambridge Science Park. Creator of the APM corporate accredited PM Excellence Programme, I chaired a quarterly PM forum to share best practice and built a supportive PM community. I coached seven PMs to RPP, five to PQ, and all passed APMP. These investments in PM professionalism led to a turn-around and annual improvement in project results across a 400 project portfolio and delivered an above budget performance in five consecutive years with profits totalling £7.9m above budget. Passionate advocate of PM professionalism, Fellow of the APM and the IET and author of articles published in Project and PM Today. Professional Development Winning Project Work Planning Estimating Risk Management Earned Value Management Change Control Stakeholder Management 3 Steps to Professional Project Management: Case Study ProjectManagementTopics