SlideShare una empresa de Scribd logo
1 de 40
1
Mobile Flash Butt Welding Of Rail
s
Kuldeep Singh
Sr.ADEN/SIR
TABLE OF CONTENT
 Mobile Flash Butt Welding
 Uses of Mobile Flash Butt Welding
 Various Options in Mobile Flash Butt Welding
 Staff Requirement for Mobile Flash Butt welding
 Mobile Flash Butt Welding Procedure
 Pre Welding Checks
 Actual Welding Procedure
 Testing of Welds
 Precautions in Mobile Flash Butt Welding
2
Mobile Flash Butt Welding
 Mobile Flash Butt Welding is a Rail cum Road Machine. M
obile Flash Butt Welding Plant is a four wheeled mobile ve
hicle, which can travel on roads with rubberised wheels an
d on rails with metal wheels in which the following are fitt
ed:
 Welding Equipment
 Welding Parameter Recorder
 Separate units for Grinding & USFD Testing Equipment
3
Various Options in Mobile Flash Butt Welding
 FIXED SITE DEPOTS
 MOBILE DEPOTS
 MOBILE FBW PLANT
4
Actual Welding Procedure at Depot
 Clamping the rail ends: The mobile flash butt welding machine is lowered fro
m the vehicle and the rail ends which are close together are clamped. The The rai
l ends are then brought together so that almost touch each other to create the fla
sh. The longitudinal and vertical alignment of the rail is corrected by suitable adj
ustments of the machine.
5
The rail ends being clamped by the welding machine
The rail ends being clamped by the welding mach
ine at Depot
6
Post straightening & Ultrasonic Testing at Dep
ot
 Post straightening: The rails are post straightened mec
hanically to remove horizontal and vertical kinks so as to gi
ve perfect alignment in both directions.
 Ultrasonic Testing: The welded rails are then ultrasonicall
y tested with normal 70° and 45° probes.
7
Mobile Flash Butt Welding Plant moving on trac
k
8
Unloading the welding Equipment from the vehicle Model
FBW-24 Made in India Thermit Corporation
9
Unloading the welding Equipment from the vehicle Model K-900
Made In India Thermit Corp. Ltd.
10
Uses of Mobile Flash Butt Welding
11
1. The basic use of the Mobile Flash Butt Welding is to use
2. the flash butt welding technique in field which otherwise can
not be done using the static plant. The Mobile Flash Butt Wel
ding is preferable as the welds have much better fatigue stren
gth and performance as compared to the AT welding otherwi
se used.
3. It is basically used for the following purposes:
4. In construction works for converting free rails or 3 rail panels
(which is the maximum possible to be laid in new lines due t
o transportation constraints)to LWR.
5. In open Line for Through Weld renewal to replace welds whi
ch have completed their life
Staff Requirement for Mobile Flash Butt welding
 The Welding team may consist of one Supervisor and two
welders. The educational qualification of the Supervisor sh
ould be minimum Diploma in Mechanical / Electrical Engg
. or B.Sc and that of welder should be minimum Class X or
equivalent pass. Zonal Railways should ensure periodic trai
ning of welders on Mobile Flash Butt Welding Plant. The c
ompetency certificate of welder of Mobile Flash Butt Weldi
ng Plant is issued by the Zonal Railways.
12
The Supervisor and Welder of the Plant should have acquaintan
ce in knowledge of the following.
 Welding parameters and its influence on quality of welding and heat af
fected zone
 Suitability of rails for welding
 Preparation of rails to be welded including pre straightening of rails
 Procedure of welding of rails
 Record of welds
 Post weld straightening of rails
 Finishing of joints
 Marking of joints
 Testing of welds
 Precautions to avoid defects in rail joints
13
Mobile Flash Butt Welding Procedure
 There are three basic mechanisms in the machine:
 CLAMPING MECHANISM
 FORGING MECHANISM
 TRANSFORMER
14
Basic Principle of Flash Butt Welding
 The basic principle is that heat is generated by electric resis
tance method at the ends of two rails to be welded which w
ere firmly clamped into the jaws of the welding machine. B
oth the jaws of the machine are movable and as such, the g
ap between the two rail ends can be adjusted.
15
Straightening & Cleaning of rail ends
 Straightening of rails : The rails ends are required to be st
raightened with the help of hydraulic rams before welding s
o as to get good alignment of the welded rail .
 Cleaning of rail ends: The rail ends shall be cleaned using
grinders to get clean surface.
16
Inspection of Rail ends
 A thorough inspection of rail ends shall be carried out and
the deviation of vertical and horizontal misalignment shou
ld be within the tolerable limits as given below:
 Individual welded ends may have a maximum difference in
height of 1.2 mm as in case of second hand rails.
17
If the rail wear is not equal, the grouping of rails so that maximum dif
ference of height does not exceed 1.2 mm shall be done as shown in
figure
18
Welding of second hand rails
 Second hand rails within the following limit of tolerance can
also be welded using Mobile Flash Butt Welding:
19
Rail New Rail Second hand Rail
60Kg 172.00 mm 164 mm
52Kg 156.00 mm 150 mm
90R 142.88 mm 139 mm
Rail New Rail (Lateral ) Second hand Rail (w
ear)
60Kg 72.00 mm 66 mm
52Kg 67.00 mm 61 mm
90R 66.68 mm 61mm
The tolerance on the end bends in the vertical plane should be (+) 0
.7mm and (-) 0.0mm on a straight edge of 1.5 m.
Tolerances for rail in vertical plane
 The tolerance on the end bends in the horizontal plane s
hould be (+) or (-) 0.7mm
20
Tolerances specified for rail ends
 The dimensions of the head width of rail should be check
ed and should be less than 0.5 mm deviation
21
Rail head checking gauge for 60Kg rail
22
Tolerances for rail ends
 The rail ends shall be cut vertically and these shall be as
per tolerances given below:
23
Setting up the flash
 The rails are brought towards each other till the flash starts. Th
e flash will lead to heat generation which will soften the steel.
 The electric energy is switched on and thereby allowing and el
ectric current of about 5 volts and 35,000 Amperes to pass bet
ween interfaces of two rails. Lot of flashing takes place and co
nsiderable heat is generated by the passage of electric current
between the rail ends.
 The rail ends are moved to and fro automatically by the machi
ne till the temperature rises to the fusion limits in the range of
1000° C to 1500° C.
24
Work Starting in track
25
Flashing for welding
26
Applying force
 The rail ends are then hydraulically pressed so that the s
oftened rail ends fuse together to form weld.
 At this juncture, the rail ends are pressed together with
an upset pressure of about 37 T.
 The final flashing takes place joining the two rail ends t
ogether. The welding is so regulated that any steel that
might have been oxidized during the heating process ge
ts completely squeezed out.
27
Applying hydraulic force at Depot
28
Stripping the weld
 As soon the rails are welded, they are made to pass
through a stripping Unit where all the extra metal
called upsets is chipped off. The removal of metal
by stripping is so good that except the head no oth
er portion require any finishing.
29
Weld completed
 The average time taken for welding a joint is about 7 to 8 minutes per j
oint and No. of joints that can be welded is about 40 to 50 joints per 8
hrs shift.
30
Grinding rail ends
 The rail table and gauge face of the joints thus welded, are finally ground t
o correct rail profile, by means of a trolley grinder for the rail table and by
pneumatic grinders for other portions.
31
Weld numbering and identification
 Weld recorder: The machine has a weld recorder which measures and stores the weld
ing parameters. The results are stored in machine and can be retrieved later on also.
Print out can also be obtained of the welding parameters which can be used as perm
anent record. The following parameters are recorded (figures in brackets are standar
d values):
 Testing of Welds
 Pre Flash Time (47 sec)
 Flash Time (95 sec)
 Boost Time (07 sec)
 Up set Time (1.8 sec)
 Forge Time (2 sec)
 Current Set (190 – 280 Amps)
 Forge Force (38 – 65 Tons)
 Up set Rail Use (12.7 mm)
 Welding parameters will depend on section and metallurgy of rail to be welded. The
se are, normally, specified by the manufacturer of the plant. Before adoption, the wel
ding parameters shall be got approved from RDSO. RDSO shall consider parameters
suggested by the manufacturer while fixing the parameters.
32
Each weld shall be given a number so as to identify the weld, welder and correlati
on can be established between the field weld and the weld record.
Testing of Flash Butt Welded Joints
 Hardness Test: Brinnel hardness test shall be conducted on the test
weld sample before conducting transverse load test. The hardness
value in HAZ shall not vary from the hardness of the parent rail by
more than + 20 HB. Results shall be maintained as per proforma gi
ven in Annexure – VI C.
 Extent of heat affected zone (max value in mm)
 Head
 38 mm
 Web
 39 mm
 Foot
 36 mm
 The results of tests shall be maintained.
 VALUES OF MINIMUM BREAKING LOAD AND DEFLECTION IN
TRANSVERSE
33
Testing Frequency of Flash Butt Welded Joints
 “Sample joints for first 1000 Joints welded by a Mobile Flash butt welding p
lant will be tested at a frequency of 1 in 100 joints and subsequently at a fre
quency of 1 in 500 joints.” As Per RDSO Manual
34
Rail section S Span Min. Breakin
g Load (tone
s)
Min. Deflec
tion At cent
re(mm)
Frequency of testing
Stationary &
plant
Mobile FBW
P
60 Kg. (UIC) NHH 1.25m 115 30 1 IN 500 1 in 100
60 Kg (UIC) Cr. Mn. Allo
y steel
1.25m 110 12 1 IN 500 1 in 100
60 Kg (UIC) (90 UTS) 1 m 150 20 1 IN 1000 1 in 100
52 kg. 90 UTS 1 m 100 15 1 IN 1000 1 in 100
60 Kg (UIC) MM (72 UT
S)
1 m 135 30 1 IN 1000 1 in 100
52 Kg MM (72 UTS) 1 m 100 30 1 IN 1000 1 in 100
Testing of Flash Butt Welded Joints
 Macro Examination test: One test joint for every 1000 joints weld
ed in case of mobile flash butt welding plant shall be subjected to
macro examination. 150 mm length of rail with weld at centre sha
ll be cut and the sample shall be sectioned in vertical, longitudina
l directions through the weld. One of the sections shall be etched
with 5 – 10% Nitric acid and also subjected to magna flux test to
ensure freedom fro cracks, lack of fusion or oxide inclusion. Exte
nt of heat affected zone shall be measured for head, foot and we
b of the rail. These values should not be more than the values ac
hieved during standardization of welding parameters of the partic
ular rail section and chemistry of particular make of FBW Plant.
Results shall be maintained as per performa.
35
36
Tolerance after Final Welds Position
A. Welds with new Rails
(i) Vertical misalignment: +0.3mm at the centre of a 1m - 0 mm strai
ght edge.
(ii) Lateral misalignment: +0.3mm at the centre of a 1m straight edg
e.
(iii) Head Finishing (in width) Side of rail head should be finished to:
+- 0.25 mm on gauge side at the centre of
10 cm straight edge.
(iv) Fishing of top table surfac
e
+ 0.2mm at the centre of 10 cm straight ed
ge -0.0mm
(v) Web zone (underside hea
d, web, top of base ,both f
illet each side)
+-3.0 mm of the parent contour –0 mm
37
Tolerance after Final Welds Position
B. Welds with Old Rails
(i) Vertical misalignment: +-0.5mm at the centre of a 1m straight edg
e.
(ii) Lateral misalignment: +-0.5mm at the centre of a 1m straight edg
e.
(iii) Head Finishing (in sides) +-0.3 mm on the gauge side at the centre o
f a 10 cm straight edge.
(iv) Head finishing ( on top tab
le surface)
+- 0.2mm on the gauge side at the centre o
f 10 cm straight edge
(v) Web zone (underside hea
d, web, top of base ,both f
illet each side)
+ 3.0 mm
- 0.0 mm of parent contour –0 mm
Precautions in Mobile Flash Butt Welding
 End squareness of rail faces must be ensured. Better weld strength with minimum value and m
erely parallel shape of heat affecting zone can be achieved using perfect matching of rail ends.
 Secondary out put of current should be sufficient enough to achieve complete fusion of butting
faces.
 Butting stroke should be sufficient for complete coalescence (not less than 12 mm)
 Throughout Uniform and smooth auto trimming of the squeezed out metal and complete grind
ing using profile grinder.
 Minimum and nearly parallel heat affected zone of the joint should be achieved.
 Facilities for auto recording of weld parameters including final butting pressure shall be availa
ble.
 When weld is carried out in situ, minimum 20 minutes time after trimming is required to pass t
he first train through the weld with proper packing and support below the joint.
 Track should be levelled.
 Excess butting pressure leads to high joints. These are strictly prohibited and shall be closely m
onitored by trained departmental staff.
 To avoid buckling of track, the continuous welding is prohibited in skeleton track and a gap sho
uld be left at every 500 m interval which will be used for destressing. (In new line works)
 Night welding and welding during rainy session to be avoided as far as possible for obtaining be
tter results.
 Target should not be fixed more than 40 joints per working day in order to keep sufficient time
gap before moving allowing the machine over the newly welded joints.(In new line works)
 Computer printout has to be obtained for each weld just after the execution in order to rectify t
he variations in various parameters as recommended before commencement of the next joint..
38
39
The different options have their own advantages & disadvantages:
S.
N.
FIXED SITE DEPOTS MOBILE DEPOTS MOBILE FBW PLAN
T
1 Panels can be made at one
point only. Transportation
has to be done.
At convenient locations, the depots ca
n be setup and the panels will require t
o be transported from this location onl
y
Plant moves and reaches
every point of welding.
2 Time for welding is less. Ti
me for transportation of pa
nels maximum.
Time for welding is min but setting up
of plants takes some time at each locati
on. Transportation of panels takes less
er time.
Time for welding maxim
um as plant to be setup f
or each weld. No transpo
rtation of panels.
3 Suitable for smaller lengths
of track where one set up c
an serve the entire stretch i
n construction as well as o
pen line.
Suitable for construction projects if the
welding work to form panels is to be d
one in parallel with the other works. In
open line, suitable for TWR and the pl
ant can be setup near any level crossin
g or approachable location.
Suitable for construction
projects if the track poss
ession can be given for t
he plant to work. Work
will commence only afte
r the rails are laid on co
mpleted formation.
40

Más contenido relacionado

La actualidad más candente

Welding Presentation
Welding Presentation Welding Presentation
Welding Presentation arun kumar
 
Rod, wire and tube drawing
Rod, wire and tube drawingRod, wire and tube drawing
Rod, wire and tube drawingNaman Dave
 
Continuous casting
Continuous castingContinuous casting
Continuous castingSaurabh Negi
 
Resistance spot welding
Resistance spot weldingResistance spot welding
Resistance spot weldingLahiru Dilshan
 
Sheet Metal Forming
Sheet Metal FormingSheet Metal Forming
Sheet Metal Formingvins049
 
ASTM E 09(COMPRESSION TEST)
ASTM E 09(COMPRESSION TEST)ASTM E 09(COMPRESSION TEST)
ASTM E 09(COMPRESSION TEST)Manthan Chavda
 
Resistance welding
Resistance weldingResistance welding
Resistance weldingSujit Regmi
 
Geometrical tolerance
Geometrical toleranceGeometrical tolerance
Geometrical toleranceChetan Hiwase
 
Welding Introduction
Welding IntroductionWelding Introduction
Welding IntroductionAnkit Kumar
 
Tool materials and tool wear
Tool materials and tool wearTool materials and tool wear
Tool materials and tool wearVJTI Production
 
Design Consideration For Casting
Design Consideration For CastingDesign Consideration For Casting
Design Consideration For CastingMohit Joon
 

La actualidad más candente (20)

Welding Presentation
Welding Presentation Welding Presentation
Welding Presentation
 
Rod, wire and tube drawing
Rod, wire and tube drawingRod, wire and tube drawing
Rod, wire and tube drawing
 
Welding Processes
Welding ProcessesWelding Processes
Welding Processes
 
Continuous casting
Continuous castingContinuous casting
Continuous casting
 
Weldability
WeldabilityWeldability
Weldability
 
Extrusion defects
Extrusion defectsExtrusion defects
Extrusion defects
 
Welding
WeldingWelding
Welding
 
Thermit welding
Thermit weldingThermit welding
Thermit welding
 
Resistance spot welding
Resistance spot weldingResistance spot welding
Resistance spot welding
 
Sheet Metal Forming
Sheet Metal FormingSheet Metal Forming
Sheet Metal Forming
 
FUSION WELDING PROCESS
FUSION WELDING PROCESSFUSION WELDING PROCESS
FUSION WELDING PROCESS
 
ASTM E 09(COMPRESSION TEST)
ASTM E 09(COMPRESSION TEST)ASTM E 09(COMPRESSION TEST)
ASTM E 09(COMPRESSION TEST)
 
Resistance welding
Resistance weldingResistance welding
Resistance welding
 
Geometrical tolerance
Geometrical toleranceGeometrical tolerance
Geometrical tolerance
 
Welding Introduction
Welding IntroductionWelding Introduction
Welding Introduction
 
Tool materials and tool wear
Tool materials and tool wearTool materials and tool wear
Tool materials and tool wear
 
FORGE WELDING
FORGE WELDINGFORGE WELDING
FORGE WELDING
 
Surface Treatment
Surface TreatmentSurface Treatment
Surface Treatment
 
Welding ppt
Welding pptWelding ppt
Welding ppt
 
Design Consideration For Casting
Design Consideration For CastingDesign Consideration For Casting
Design Consideration For Casting
 

Similar a Flash butt welding

mobile flash butt welding of rails
mobile flash butt welding of railsmobile flash butt welding of rails
mobile flash butt welding of railsSujit Sen
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdfTVijayaGowri
 
Wringer_roll_Position_control_final(edited)
Wringer_roll_Position_control_final(edited)Wringer_roll_Position_control_final(edited)
Wringer_roll_Position_control_final(edited)SHASHANK KUMAR
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptAshish585772
 
Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)Prem Prakash Kumar
 
Spatter Reduction by Prateek Biswas
Spatter Reduction by Prateek BiswasSpatter Reduction by Prateek Biswas
Spatter Reduction by Prateek BiswasPrateek Biswas
 
Design of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction MotorDesign of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction MotorParth Patel
 
traction machine shed knapur
traction machine shed knapurtraction machine shed knapur
traction machine shed knapuraadtya2412
 
Industrial training report
Industrial training report Industrial training report
Industrial training report Pritam Samanta
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELPrabhu Raj
 
Arc welding safety rules
Arc welding safety rulesArc welding safety rules
Arc welding safety rulesmusadoto
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsVijay Raj
 
Engineering plant facilities 15 mechanics welding
Engineering plant facilities 15 mechanics weldingEngineering plant facilities 15 mechanics welding
Engineering plant facilities 15 mechanics weldingLuis Cabrera
 
Bushed pin type flexible coupling
Bushed pin type flexible couplingBushed pin type flexible coupling
Bushed pin type flexible couplingnarendra varma
 
Single phase induction motor Design.pptx
Single phase induction motor Design.pptxSingle phase induction motor Design.pptx
Single phase induction motor Design.pptxFaisalSheraz4
 

Similar a Flash butt welding (20)

mobile flash butt welding of rails
mobile flash butt welding of railsmobile flash butt welding of rails
mobile flash butt welding of rails
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdf
 
Wringer_roll_Position_control_final(edited)
Wringer_roll_Position_control_final(edited)Wringer_roll_Position_control_final(edited)
Wringer_roll_Position_control_final(edited)
 
Dlw training
Dlw trainingDlw training
Dlw training
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
 
Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)
 
9417
94179417
9417
 
Spatter Reduction by Prateek Biswas
Spatter Reduction by Prateek BiswasSpatter Reduction by Prateek Biswas
Spatter Reduction by Prateek Biswas
 
Design of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction MotorDesign of stator & rotor for Wound Induction Motor
Design of stator & rotor for Wound Induction Motor
 
traction machine shed knapur
traction machine shed knapurtraction machine shed knapur
traction machine shed knapur
 
Industrial training report
Industrial training report Industrial training report
Industrial training report
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHEL
 
ijaerv10n68spl_104
ijaerv10n68spl_104ijaerv10n68spl_104
ijaerv10n68spl_104
 
Arc welding safety rules
Arc welding safety rulesArc welding safety rules
Arc welding safety rules
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressureparts
 
Engineering plant facilities 15 mechanics welding
Engineering plant facilities 15 mechanics weldingEngineering plant facilities 15 mechanics welding
Engineering plant facilities 15 mechanics welding
 
Pipelines Welding Handbook ESAB.pdf
Pipelines Welding Handbook ESAB.pdfPipelines Welding Handbook ESAB.pdf
Pipelines Welding Handbook ESAB.pdf
 
Bushed pin type flexible coupling
Bushed pin type flexible couplingBushed pin type flexible coupling
Bushed pin type flexible coupling
 
unit-iv.pptx
unit-iv.pptxunit-iv.pptx
unit-iv.pptx
 
Single phase induction motor Design.pptx
Single phase induction motor Design.pptxSingle phase induction motor Design.pptx
Single phase induction motor Design.pptx
 

Más de sabdou

Analyse_dynamique_de_la_reponse_dune_str.pdf
Analyse_dynamique_de_la_reponse_dune_str.pdfAnalyse_dynamique_de_la_reponse_dune_str.pdf
Analyse_dynamique_de_la_reponse_dune_str.pdfsabdou
 
397185702-2-Projet-Ferroviaire.pdf
397185702-2-Projet-Ferroviaire.pdf397185702-2-Projet-Ferroviaire.pdf
397185702-2-Projet-Ferroviaire.pdfsabdou
 
397185700-1-Systeme-ferroviaire.pdf
397185700-1-Systeme-ferroviaire.pdf397185700-1-Systeme-ferroviaire.pdf
397185700-1-Systeme-ferroviaire.pdfsabdou
 
3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdfsabdou
 
Etude-Dalot-Avec-Robot.pdf
Etude-Dalot-Avec-Robot.pdfEtude-Dalot-Avec-Robot.pdf
Etude-Dalot-Avec-Robot.pdfsabdou
 
200_modeles_de_lettres.pdf
200_modeles_de_lettres.pdf200_modeles_de_lettres.pdf
200_modeles_de_lettres.pdfsabdou
 
Approche_perf_beton.pdf
Approche_perf_beton.pdfApproche_perf_beton.pdf
Approche_perf_beton.pdfsabdou
 
3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdfsabdou
 
Pourquoi_armer_le_beton.pdf
Pourquoi_armer_le_beton.pdfPourquoi_armer_le_beton.pdf
Pourquoi_armer_le_beton.pdfsabdou
 
Chapitre ii-composants-de-la-voie-presentation
Chapitre ii-composants-de-la-voie-presentationChapitre ii-composants-de-la-voie-presentation
Chapitre ii-composants-de-la-voie-presentationsabdou
 
Béton précontraint
Béton précontraintBéton précontraint
Béton précontraintsabdou
 
229957659 technologie-ferroviaire
229957659 technologie-ferroviaire229957659 technologie-ferroviaire
229957659 technologie-ferroviairesabdou
 
Les contreventement 2
Les contreventement 2Les contreventement 2
Les contreventement 2sabdou
 
Analyse dynamique de_la_reponse_dune_str
Analyse dynamique de_la_reponse_dune_strAnalyse dynamique de_la_reponse_dune_str
Analyse dynamique de_la_reponse_dune_strsabdou
 
Escalier cours
Escalier coursEscalier cours
Escalier courssabdou
 
Armatures pour béton armé
Armatures pour béton arméArmatures pour béton armé
Armatures pour béton armésabdou
 
La precontrainte dans_le_batiment_dern_v
La precontrainte dans_le_batiment_dern_vLa precontrainte dans_le_batiment_dern_v
La precontrainte dans_le_batiment_dern_vsabdou
 
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...sabdou
 
Béton précontraint
Béton précontraintBéton précontraint
Béton précontraintsabdou
 
Cours r.d.m btps3
Cours r.d.m btps3Cours r.d.m btps3
Cours r.d.m btps3sabdou
 

Más de sabdou (20)

Analyse_dynamique_de_la_reponse_dune_str.pdf
Analyse_dynamique_de_la_reponse_dune_str.pdfAnalyse_dynamique_de_la_reponse_dune_str.pdf
Analyse_dynamique_de_la_reponse_dune_str.pdf
 
397185702-2-Projet-Ferroviaire.pdf
397185702-2-Projet-Ferroviaire.pdf397185702-2-Projet-Ferroviaire.pdf
397185702-2-Projet-Ferroviaire.pdf
 
397185700-1-Systeme-ferroviaire.pdf
397185700-1-Systeme-ferroviaire.pdf397185700-1-Systeme-ferroviaire.pdf
397185700-1-Systeme-ferroviaire.pdf
 
3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf
 
Etude-Dalot-Avec-Robot.pdf
Etude-Dalot-Avec-Robot.pdfEtude-Dalot-Avec-Robot.pdf
Etude-Dalot-Avec-Robot.pdf
 
200_modeles_de_lettres.pdf
200_modeles_de_lettres.pdf200_modeles_de_lettres.pdf
200_modeles_de_lettres.pdf
 
Approche_perf_beton.pdf
Approche_perf_beton.pdfApproche_perf_beton.pdf
Approche_perf_beton.pdf
 
3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf3_La_Correspondance_Administrative.pdf
3_La_Correspondance_Administrative.pdf
 
Pourquoi_armer_le_beton.pdf
Pourquoi_armer_le_beton.pdfPourquoi_armer_le_beton.pdf
Pourquoi_armer_le_beton.pdf
 
Chapitre ii-composants-de-la-voie-presentation
Chapitre ii-composants-de-la-voie-presentationChapitre ii-composants-de-la-voie-presentation
Chapitre ii-composants-de-la-voie-presentation
 
Béton précontraint
Béton précontraintBéton précontraint
Béton précontraint
 
229957659 technologie-ferroviaire
229957659 technologie-ferroviaire229957659 technologie-ferroviaire
229957659 technologie-ferroviaire
 
Les contreventement 2
Les contreventement 2Les contreventement 2
Les contreventement 2
 
Analyse dynamique de_la_reponse_dune_str
Analyse dynamique de_la_reponse_dune_strAnalyse dynamique de_la_reponse_dune_str
Analyse dynamique de_la_reponse_dune_str
 
Escalier cours
Escalier coursEscalier cours
Escalier cours
 
Armatures pour béton armé
Armatures pour béton arméArmatures pour béton armé
Armatures pour béton armé
 
La precontrainte dans_le_batiment_dern_v
La precontrainte dans_le_batiment_dern_vLa precontrainte dans_le_batiment_dern_v
La precontrainte dans_le_batiment_dern_v
 
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...
Dimensionnement géotechnique à l’état limiteultime de pieux sous charge axial...
 
Béton précontraint
Béton précontraintBéton précontraint
Béton précontraint
 
Cours r.d.m btps3
Cours r.d.m btps3Cours r.d.m btps3
Cours r.d.m btps3
 

Último

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 

Último (20)

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 

Flash butt welding

  • 1. 1 Mobile Flash Butt Welding Of Rail s Kuldeep Singh Sr.ADEN/SIR
  • 2. TABLE OF CONTENT  Mobile Flash Butt Welding  Uses of Mobile Flash Butt Welding  Various Options in Mobile Flash Butt Welding  Staff Requirement for Mobile Flash Butt welding  Mobile Flash Butt Welding Procedure  Pre Welding Checks  Actual Welding Procedure  Testing of Welds  Precautions in Mobile Flash Butt Welding 2
  • 3. Mobile Flash Butt Welding  Mobile Flash Butt Welding is a Rail cum Road Machine. M obile Flash Butt Welding Plant is a four wheeled mobile ve hicle, which can travel on roads with rubberised wheels an d on rails with metal wheels in which the following are fitt ed:  Welding Equipment  Welding Parameter Recorder  Separate units for Grinding & USFD Testing Equipment 3
  • 4. Various Options in Mobile Flash Butt Welding  FIXED SITE DEPOTS  MOBILE DEPOTS  MOBILE FBW PLANT 4
  • 5. Actual Welding Procedure at Depot  Clamping the rail ends: The mobile flash butt welding machine is lowered fro m the vehicle and the rail ends which are close together are clamped. The The rai l ends are then brought together so that almost touch each other to create the fla sh. The longitudinal and vertical alignment of the rail is corrected by suitable adj ustments of the machine. 5 The rail ends being clamped by the welding machine
  • 6. The rail ends being clamped by the welding mach ine at Depot 6
  • 7. Post straightening & Ultrasonic Testing at Dep ot  Post straightening: The rails are post straightened mec hanically to remove horizontal and vertical kinks so as to gi ve perfect alignment in both directions.  Ultrasonic Testing: The welded rails are then ultrasonicall y tested with normal 70° and 45° probes. 7
  • 8. Mobile Flash Butt Welding Plant moving on trac k 8
  • 9. Unloading the welding Equipment from the vehicle Model FBW-24 Made in India Thermit Corporation 9
  • 10. Unloading the welding Equipment from the vehicle Model K-900 Made In India Thermit Corp. Ltd. 10
  • 11. Uses of Mobile Flash Butt Welding 11 1. The basic use of the Mobile Flash Butt Welding is to use 2. the flash butt welding technique in field which otherwise can not be done using the static plant. The Mobile Flash Butt Wel ding is preferable as the welds have much better fatigue stren gth and performance as compared to the AT welding otherwi se used. 3. It is basically used for the following purposes: 4. In construction works for converting free rails or 3 rail panels (which is the maximum possible to be laid in new lines due t o transportation constraints)to LWR. 5. In open Line for Through Weld renewal to replace welds whi ch have completed their life
  • 12. Staff Requirement for Mobile Flash Butt welding  The Welding team may consist of one Supervisor and two welders. The educational qualification of the Supervisor sh ould be minimum Diploma in Mechanical / Electrical Engg . or B.Sc and that of welder should be minimum Class X or equivalent pass. Zonal Railways should ensure periodic trai ning of welders on Mobile Flash Butt Welding Plant. The c ompetency certificate of welder of Mobile Flash Butt Weldi ng Plant is issued by the Zonal Railways. 12
  • 13. The Supervisor and Welder of the Plant should have acquaintan ce in knowledge of the following.  Welding parameters and its influence on quality of welding and heat af fected zone  Suitability of rails for welding  Preparation of rails to be welded including pre straightening of rails  Procedure of welding of rails  Record of welds  Post weld straightening of rails  Finishing of joints  Marking of joints  Testing of welds  Precautions to avoid defects in rail joints 13
  • 14. Mobile Flash Butt Welding Procedure  There are three basic mechanisms in the machine:  CLAMPING MECHANISM  FORGING MECHANISM  TRANSFORMER 14
  • 15. Basic Principle of Flash Butt Welding  The basic principle is that heat is generated by electric resis tance method at the ends of two rails to be welded which w ere firmly clamped into the jaws of the welding machine. B oth the jaws of the machine are movable and as such, the g ap between the two rail ends can be adjusted. 15
  • 16. Straightening & Cleaning of rail ends  Straightening of rails : The rails ends are required to be st raightened with the help of hydraulic rams before welding s o as to get good alignment of the welded rail .  Cleaning of rail ends: The rail ends shall be cleaned using grinders to get clean surface. 16
  • 17. Inspection of Rail ends  A thorough inspection of rail ends shall be carried out and the deviation of vertical and horizontal misalignment shou ld be within the tolerable limits as given below:  Individual welded ends may have a maximum difference in height of 1.2 mm as in case of second hand rails. 17
  • 18. If the rail wear is not equal, the grouping of rails so that maximum dif ference of height does not exceed 1.2 mm shall be done as shown in figure 18
  • 19. Welding of second hand rails  Second hand rails within the following limit of tolerance can also be welded using Mobile Flash Butt Welding: 19 Rail New Rail Second hand Rail 60Kg 172.00 mm 164 mm 52Kg 156.00 mm 150 mm 90R 142.88 mm 139 mm Rail New Rail (Lateral ) Second hand Rail (w ear) 60Kg 72.00 mm 66 mm 52Kg 67.00 mm 61 mm 90R 66.68 mm 61mm The tolerance on the end bends in the vertical plane should be (+) 0 .7mm and (-) 0.0mm on a straight edge of 1.5 m.
  • 20. Tolerances for rail in vertical plane  The tolerance on the end bends in the horizontal plane s hould be (+) or (-) 0.7mm 20
  • 21. Tolerances specified for rail ends  The dimensions of the head width of rail should be check ed and should be less than 0.5 mm deviation 21
  • 22. Rail head checking gauge for 60Kg rail 22
  • 23. Tolerances for rail ends  The rail ends shall be cut vertically and these shall be as per tolerances given below: 23
  • 24. Setting up the flash  The rails are brought towards each other till the flash starts. Th e flash will lead to heat generation which will soften the steel.  The electric energy is switched on and thereby allowing and el ectric current of about 5 volts and 35,000 Amperes to pass bet ween interfaces of two rails. Lot of flashing takes place and co nsiderable heat is generated by the passage of electric current between the rail ends.  The rail ends are moved to and fro automatically by the machi ne till the temperature rises to the fusion limits in the range of 1000° C to 1500° C. 24
  • 25. Work Starting in track 25
  • 27. Applying force  The rail ends are then hydraulically pressed so that the s oftened rail ends fuse together to form weld.  At this juncture, the rail ends are pressed together with an upset pressure of about 37 T.  The final flashing takes place joining the two rail ends t ogether. The welding is so regulated that any steel that might have been oxidized during the heating process ge ts completely squeezed out. 27
  • 29. Stripping the weld  As soon the rails are welded, they are made to pass through a stripping Unit where all the extra metal called upsets is chipped off. The removal of metal by stripping is so good that except the head no oth er portion require any finishing. 29
  • 30. Weld completed  The average time taken for welding a joint is about 7 to 8 minutes per j oint and No. of joints that can be welded is about 40 to 50 joints per 8 hrs shift. 30
  • 31. Grinding rail ends  The rail table and gauge face of the joints thus welded, are finally ground t o correct rail profile, by means of a trolley grinder for the rail table and by pneumatic grinders for other portions. 31
  • 32. Weld numbering and identification  Weld recorder: The machine has a weld recorder which measures and stores the weld ing parameters. The results are stored in machine and can be retrieved later on also. Print out can also be obtained of the welding parameters which can be used as perm anent record. The following parameters are recorded (figures in brackets are standar d values):  Testing of Welds  Pre Flash Time (47 sec)  Flash Time (95 sec)  Boost Time (07 sec)  Up set Time (1.8 sec)  Forge Time (2 sec)  Current Set (190 – 280 Amps)  Forge Force (38 – 65 Tons)  Up set Rail Use (12.7 mm)  Welding parameters will depend on section and metallurgy of rail to be welded. The se are, normally, specified by the manufacturer of the plant. Before adoption, the wel ding parameters shall be got approved from RDSO. RDSO shall consider parameters suggested by the manufacturer while fixing the parameters. 32 Each weld shall be given a number so as to identify the weld, welder and correlati on can be established between the field weld and the weld record.
  • 33. Testing of Flash Butt Welded Joints  Hardness Test: Brinnel hardness test shall be conducted on the test weld sample before conducting transverse load test. The hardness value in HAZ shall not vary from the hardness of the parent rail by more than + 20 HB. Results shall be maintained as per proforma gi ven in Annexure – VI C.  Extent of heat affected zone (max value in mm)  Head  38 mm  Web  39 mm  Foot  36 mm  The results of tests shall be maintained.  VALUES OF MINIMUM BREAKING LOAD AND DEFLECTION IN TRANSVERSE 33
  • 34. Testing Frequency of Flash Butt Welded Joints  “Sample joints for first 1000 Joints welded by a Mobile Flash butt welding p lant will be tested at a frequency of 1 in 100 joints and subsequently at a fre quency of 1 in 500 joints.” As Per RDSO Manual 34 Rail section S Span Min. Breakin g Load (tone s) Min. Deflec tion At cent re(mm) Frequency of testing Stationary & plant Mobile FBW P 60 Kg. (UIC) NHH 1.25m 115 30 1 IN 500 1 in 100 60 Kg (UIC) Cr. Mn. Allo y steel 1.25m 110 12 1 IN 500 1 in 100 60 Kg (UIC) (90 UTS) 1 m 150 20 1 IN 1000 1 in 100 52 kg. 90 UTS 1 m 100 15 1 IN 1000 1 in 100 60 Kg (UIC) MM (72 UT S) 1 m 135 30 1 IN 1000 1 in 100 52 Kg MM (72 UTS) 1 m 100 30 1 IN 1000 1 in 100
  • 35. Testing of Flash Butt Welded Joints  Macro Examination test: One test joint for every 1000 joints weld ed in case of mobile flash butt welding plant shall be subjected to macro examination. 150 mm length of rail with weld at centre sha ll be cut and the sample shall be sectioned in vertical, longitudina l directions through the weld. One of the sections shall be etched with 5 – 10% Nitric acid and also subjected to magna flux test to ensure freedom fro cracks, lack of fusion or oxide inclusion. Exte nt of heat affected zone shall be measured for head, foot and we b of the rail. These values should not be more than the values ac hieved during standardization of welding parameters of the partic ular rail section and chemistry of particular make of FBW Plant. Results shall be maintained as per performa. 35
  • 36. 36 Tolerance after Final Welds Position A. Welds with new Rails (i) Vertical misalignment: +0.3mm at the centre of a 1m - 0 mm strai ght edge. (ii) Lateral misalignment: +0.3mm at the centre of a 1m straight edg e. (iii) Head Finishing (in width) Side of rail head should be finished to: +- 0.25 mm on gauge side at the centre of 10 cm straight edge. (iv) Fishing of top table surfac e + 0.2mm at the centre of 10 cm straight ed ge -0.0mm (v) Web zone (underside hea d, web, top of base ,both f illet each side) +-3.0 mm of the parent contour –0 mm
  • 37. 37 Tolerance after Final Welds Position B. Welds with Old Rails (i) Vertical misalignment: +-0.5mm at the centre of a 1m straight edg e. (ii) Lateral misalignment: +-0.5mm at the centre of a 1m straight edg e. (iii) Head Finishing (in sides) +-0.3 mm on the gauge side at the centre o f a 10 cm straight edge. (iv) Head finishing ( on top tab le surface) +- 0.2mm on the gauge side at the centre o f 10 cm straight edge (v) Web zone (underside hea d, web, top of base ,both f illet each side) + 3.0 mm - 0.0 mm of parent contour –0 mm
  • 38. Precautions in Mobile Flash Butt Welding  End squareness of rail faces must be ensured. Better weld strength with minimum value and m erely parallel shape of heat affecting zone can be achieved using perfect matching of rail ends.  Secondary out put of current should be sufficient enough to achieve complete fusion of butting faces.  Butting stroke should be sufficient for complete coalescence (not less than 12 mm)  Throughout Uniform and smooth auto trimming of the squeezed out metal and complete grind ing using profile grinder.  Minimum and nearly parallel heat affected zone of the joint should be achieved.  Facilities for auto recording of weld parameters including final butting pressure shall be availa ble.  When weld is carried out in situ, minimum 20 minutes time after trimming is required to pass t he first train through the weld with proper packing and support below the joint.  Track should be levelled.  Excess butting pressure leads to high joints. These are strictly prohibited and shall be closely m onitored by trained departmental staff.  To avoid buckling of track, the continuous welding is prohibited in skeleton track and a gap sho uld be left at every 500 m interval which will be used for destressing. (In new line works)  Night welding and welding during rainy session to be avoided as far as possible for obtaining be tter results.  Target should not be fixed more than 40 joints per working day in order to keep sufficient time gap before moving allowing the machine over the newly welded joints.(In new line works)  Computer printout has to be obtained for each weld just after the execution in order to rectify t he variations in various parameters as recommended before commencement of the next joint.. 38
  • 39. 39 The different options have their own advantages & disadvantages: S. N. FIXED SITE DEPOTS MOBILE DEPOTS MOBILE FBW PLAN T 1 Panels can be made at one point only. Transportation has to be done. At convenient locations, the depots ca n be setup and the panels will require t o be transported from this location onl y Plant moves and reaches every point of welding. 2 Time for welding is less. Ti me for transportation of pa nels maximum. Time for welding is min but setting up of plants takes some time at each locati on. Transportation of panels takes less er time. Time for welding maxim um as plant to be setup f or each weld. No transpo rtation of panels. 3 Suitable for smaller lengths of track where one set up c an serve the entire stretch i n construction as well as o pen line. Suitable for construction projects if the welding work to form panels is to be d one in parallel with the other works. In open line, suitable for TWR and the pl ant can be setup near any level crossin g or approachable location. Suitable for construction projects if the track poss ession can be given for t he plant to work. Work will commence only afte r the rails are laid on co mpleted formation.
  • 40. 40