iLab 1 of 7: Basics of Project Scheduling

General Comments about the Microsoft Project Exercises

A project plan and schedule are extremely important for managing projects.
Applications are available as tools to assist defining, managing, controlling, and
reporting on project plans and to evaluate how the project is progressing.
Microsoft Project is one application that is commonly used for this purpose and
will be the application used in this course. It will help you put together a plan of
action, define and organize details, track progress, analyze costs and schedule,
assess the quality of your project, and report numerous details to interested
parties.

Guidelines

iLab Lesson 1A Requirements:

Complete Lesson 1A. Print Project Summary Report.Print Unstarted Tasks
Report.

iLab Lesson 1B Requirements:

Complete Lesson 1B. Print Entry Table and Gantt Chart (show only columns up
to and including the Duration Column.) Printout should be no more than two
pages wide. Print Project Summary Report. Print Unstarted Tasks Report (fit
to one page).

Deliverables

All of the following deliverables are required (in a zip file) in order to receive full
credit:

Completed MyLab1B_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_1_Printouts_XXX.docx

When submitting required printouts, if you are not bringing them to class, from the
Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the report
and paste the screen shot to an MS Word document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.
Save the Word document containing printouts as Week_1_Printouts_XXX.docx
and submit this file to the Week 1 iLabDropbox in a zip file, along with the
MyLab1B_XXX.mpp file and the completed Review Questions at the end of
Lesson 1B. Remember to replace "XXX" in the file names with your initials, and
ensure that all of your files are all clearly labeled and include your initials in the
file name.

iLAB STEPS

STEP 1: Download iLab Instructions



Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson1A.docx(There are no Review Questions for Lesson 1A.) MS
Project Lesson1B.docx(Review Questions to be completed and submitted for
Lesson 1B are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 1 based on the Guidelines section and
Lesson documents above.

STEP 3: Submit iLab Deliverables

  Create a folder called MGMT404_YourLastName_Lab1. Place copies of each
required deliverable into this folder. Right-click on the folder and select Send To
→ Compressed (zipped) Folder. You can also use other tools to compress the
files into a single zip folder, (for example, 7-zip). Upload the zip file to the weekly
iLabDropbox in eCollege.

For instructions on how to use the Dropbox, read theseStep-by-Step
Instructionsor watch thisDropbox Tutorial. See Syllabus "Due Dates for
Assignments & Exams" for due date information.

Once your professor has received and graded the Week 1 iLab assignments,
solutions to the Week 1 iLab will be made available to you in Doc Sharing

iLab 2 of 7: Managing Project Resources

 General Comments about the Microsoft Project Exercises

Once the base schedule has been created, resources can be assigned to
tasks. To complete that this week, we will:
Create a list of resources. Assign resources to tasks. Assign costs to resources.
Use resource information to determine a preliminary cost for the project.

Guidelines

Complete Lesson 2. A printout of your Table: Entry showing all columns, but no
Gantt chart A printout of your Table: Cost showing all columns but no Gantt chart
Print the Summary Report. Print the Budget Report. Print the Who Does What
report. Print the Overallocated Resources report.

Deliverables

All of the following deliverables are required (in a zip file) to receive full credit:

Completed MyLab2_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_2_Printouts_XXX.docx

When submitting required printouts, if you are not bringing them to class, from the
Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the report
and paste the screen shot to a MS Word Document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_2_Printouts_XXX.docx,
and submit this file to the Week 2 iLabDropbox in a zip file along with the
MyLab2_XXX.mpp file and the completed Review Questions at the end of Lesson
2. Remember to replace "XXX" in the file names with your initials, and ensure that
all of your files are all clearly labeled and include your initials in the file name.



iLAB STEPS



STEP 1: Download iLab Instructions



Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson2.docx(Review Questions to be completed and submitted for
Lesson 2 are located at the end of this document.)

STEP 2: Complete the iLab Assignment
Complete the iLab assignment for Week 2 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

 Create a folder called MGMT404_YourLastName_Lab2.

iLab 3 of 7: Scheduling with Resources

General Comments about the Microsoft Project Exercises



In this week's iLab, we will use the different ways MS Project allows you to modify
resource assignments and how this can affect work completion. In doing so we
will:

Change the task type settings to control how resources affect task assignments.
Apply preset resource contours to change work value distribution. Work with task
information forms.

Guidelines

Complete Lesson 3. Print the Project Summary Report. Print the Task Usage
Report. Print the Resource Usage Report.

Deliverables

All of the following deliverables are required (in a zip file) to receive full credit:

Completed MyLab3_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_3_Printouts_XXX.docx

When submitting required printouts, if you are not bringing them to class, from the
Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the
report, and paste the screen shot to a MS Word Document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_3_Printouts_XXX.docx,
and submit this file to the Week 3 iLabDropbox in a zip file along with the
MyLab3_XXX.mpp file and the completed Review Questions at the end of Lesson
3. Remember to replace "XXX" in the file names with your initials, and ensure that
all of your files are all clearly labeled, and include your initials in the file name.



iLAB STEPS
STEP 1: Download iLab Instructions



Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson3.docx(Review Questions to be completed and submitted for
Lesson 3 are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 3 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

 Create a folder called MGMT404_YourLastName_Lab3



iLab 4 of 7: Working with Calendars



General Comments about the Microsoft Project Exercises



Calendars are tools that can be assigned to the project and to individual
resources. The calendars can change the length of the workdays and schedule
individual vacations. To work with the calendars, we will:

Change the working and non-working time on Standard Calendar. Change the
working and non-working time on a Resource Calendar. Create new base
calendars. Assign different base calendars to resources.

Guidelines

Complete Lesson 4. Print the Project Summary Report. Print the Gantt Chart
View. (Include only those columns up to and including the Finish Date column
and the Gantt chart. Print this on two pages wide.) Print the Who Does What
When Report. (Print this on three pages.) Print the TaskUsage Report.
Deliverables

All of the following deliverables are required (in a zip file) in order to receive full
credit:

Completed MyLab4_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_4_Printouts_XXX.docx

When submitting required printouts (if you are not bringing them to class), take a
screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview
page and paste the screenshot to an MS Word document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_4_Printouts_XXX.docx,
and submit this file to the Week 4 iLabDropbox in a zip file along with the
MyLab4_XXX.mpp file and the completed Review Questions at the end of Lesson
4. Remember to replace "XXX" in all the file names with your initials, and ensure
that all of your files are clearly labeled.



iLAB STEPS



STEP 1: Download iLab Instructions



Click the links below to access this week's iLab instructions. You also may
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson4.docx(Review Questions to be completed and submitted for
Lesson 4 are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 4 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

 Create a folder called MGMT404_YourLastName_Lab4
Project Monitoring and Control & Managing Project Teams - iLab



iLab 5 of 7: Resource Workloads

General Comments about the Microsoft Project Exercises



A project schedule cannot be confirmed until all resource variations and
overallocations are managed. To do this we will:

View resource workloads. Locate resource conflicts. Use automatic leveling to
resolve resource overallocations. Manually resolve resource overallocations.

Guidelines

Complete Lesson 5. Print the Gantt Chart View. (Include only those columns up
to and including the Finish Date column and the Gantt chart. Print this item on two
pages wide.) Print the Project Summary Report. Print the TaskUsage Report.

Deliverables

All of the following deliverables are required (in a zip file) to receive full credit:

Completed MyLab5_XXX.mpp Completed Review Questions
Printouts/screenshots contained in Week_5_Printouts_XXX.docx

When submitting required printouts (if you are not bringing them to class), take a
screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview
page and paste the screenshot to an MS Word document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_5_Printouts_XXX.docx,
and submit this file to the Week 5 iLabDropbox in a zip file along with the
MyLab5_XXX.mpp file and the completed Review Questions at the end of Lesson
5. Remember to replace "XXX" in all the file names with your initials, and ensure
that all of your files are clearly labeled.



iLAB STEPS



STEP 1: Download iLab Instructions
Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson5.docx(Review Questions to be completed and submitted for
Lesson 5 are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 5 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

 Create a folder called MGMT404_YourLastName_Lab5.



Project Leadership and Outsourcing & Project Procurement - iLab

iLab 6 of 7: Task Constraints and Baselines



General Comments about the Microsoft Project Exercises



Sometimes certain tasks must be constrained by dates, rather than only by the
predecessors. For example, the Independence Day holiday is not dependent
upon us getting our BBQ ready and buying fireworks (predecessor tasks) but by
the fact that this holiday MUST occur on July 4. Once we have determined what
these constraints are, we can set our project baseline and be ready to complete
work on our project. To finalize our project plan in order to begin work, we will:

Use constraints to set date limitations. Set a project baseline schedule.

Guidelines

Complete Lesson 6. Print the Constraints Table. (Include all columns of the
table.) Print the Project Summary Report.

Deliverables

All of the following deliverables are required (in a zip file) to receive full credit:
Completed MyLab6_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_6_Printouts_XXX.docx

When submitting required printouts (if you are not bringing them to class), take a
screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview
page and paste the screenshot to an MS Word Document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_6_Printouts_XXX.docx,
and submit this file to the Week 6 iLabDropbox in a zip file along with the
MyLab6_XXX.mpp file and the completed Review Questions at the end of Lesson
6. Remember to replace "XXX" in all the file names with your initials, and ensure
that all of your files are clearly labeled.



iLAB STEPS

STEP 1: Download iLab Instructions



Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson6.docx(Review Questions to be completed and submitted for
Lesson 6 are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 6 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

  Create a folder called MGMT404_YourLastName_Lab6. Place copies of each
required deliverable into this folder. Right-click on the folder and select Send To
→ Compressed (zipped) Folder. You can also use other tools to compress the
files into a single zip folder (for example, 7-zip). Upload the zip file to the weekly
iLabDropbox in eCollege.

For instructions on how to use the Dropbox, read theseStep-by-Step
Instructionsor watch thisDropbox Tutorial. See Syllabus "Due Dates for
Assignments & Exams" for due date information.
Once your professor has received and graded the Week 6 iLab assignments,
solutions to the Week 6 iLab will be made available to you in Doc Sharing

iLab 7 of 7: Tracking Project Progress


Now that the baseline is set, project work can begin. We can use MS Project to
track our project's progress and compare it to our baseline. Comparing to the
baseline allows us to check our progress against the schedule and budget. When
negative variances occur, we are either behind schedule or over budget, so we
know that corrective actions are necessary. In this week's iLab, we will:

General Comments about the Microsoft Project Exercises

 Compare baseline data to actual and scheduled data. View a network diagram.
Overview the Earned Value calculations in MS Project.

Guidelines

Complete Lesson 7. Print the Project Summary Report. Print the Overbudget
Tasks Report. (Print on one page) Print the Earned Value Report.

Deliverables

All of the following deliverables are required (in a zip file) to receive full credit:

Completed MyLab7_XXX.mpp Completed Review Questions
Printouts/Screenshots contained in Week_7_Printouts_XXX.docx

When submitting required printouts (if you are not bringing them to class), take a
screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview
page and paste the screenshot to an MS Word Document. Make sure to crop the
screen to show only the report. After cropping, resize the image appropriately. If
the printout is on more than one page, paste each page individually.

Save the Word document containing printouts as Week_7_Printouts_XXX.docx,
and submit this file to the Week 7 iLabDropbox in a zip file along with the
MyLab7_XXX.mpp file and the completed Review Questions at the end of Lesson
7. Remember to replace "XXX" in all the file names with your initials, and ensure
that all of your files are clearly labeled.



iLAB STEPS



STEP 1: Download iLab Instructions
Click the links below to access this week's iLab instructions. You may also
download both lessons from the MS Project Exercises category in Doc Sharing.

MS Project Lesson7.docx(Review Questions to be completed and submitted for
Lesson 7 are located at the end of this document.)

STEP 2: Complete the iLab Assignment



Complete the iLab assignment for Week 7 based on the Guidelines section and
Lesson document above.

STEP 3: Submit iLab Deliverables

 Create a folder called MGMT404_YourLastName_Lab7

    MGMT404 Project Management - All 7 Weeks
             iLabsDevry University

                         DOWNLOAD HERE

Más contenido relacionado

Destacado

Moda Otoño- Invierno altereggo collection
Moda Otoño- Invierno altereggo collectionModa Otoño- Invierno altereggo collection
Moda Otoño- Invierno altereggo collectionAltereggo Collection
 
Hook42 zero-to-go-pt1-business-v2
Hook42 zero-to-go-pt1-business-v2Hook42 zero-to-go-pt1-business-v2
Hook42 zero-to-go-pt1-business-v2hook42inc
 
.Net Core, Asp.net Core and Docker
.Net Core, Asp.net Core and Docker .Net Core, Asp.net Core and Docker
.Net Core, Asp.net Core and Docker girish goudar
 
Drupal SEO Basics (BADCamp 2012)
Drupal SEO Basics (BADCamp 2012)Drupal SEO Basics (BADCamp 2012)
Drupal SEO Basics (BADCamp 2012)hook42inc
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universitysacascscasc
 
Building Sem 2 (EMT 157)
Building Sem 2 (EMT 157)Building Sem 2 (EMT 157)
Building Sem 2 (EMT 157)Faerina MNasir
 
Introduction to SharePoint 2013
Introduction to SharePoint 2013Introduction to SharePoint 2013
Introduction to SharePoint 2013girish goudar
 

Destacado (8)

Moda Otoño- Invierno altereggo collection
Moda Otoño- Invierno altereggo collectionModa Otoño- Invierno altereggo collection
Moda Otoño- Invierno altereggo collection
 
Hook42 zero-to-go-pt1-business-v2
Hook42 zero-to-go-pt1-business-v2Hook42 zero-to-go-pt1-business-v2
Hook42 zero-to-go-pt1-business-v2
 
.Net Core, Asp.net Core and Docker
.Net Core, Asp.net Core and Docker .Net Core, Asp.net Core and Docker
.Net Core, Asp.net Core and Docker
 
Drupal SEO Basics (BADCamp 2012)
Drupal SEO Basics (BADCamp 2012)Drupal SEO Basics (BADCamp 2012)
Drupal SEO Basics (BADCamp 2012)
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Building Sem 2 (EMT 157)
Building Sem 2 (EMT 157)Building Sem 2 (EMT 157)
Building Sem 2 (EMT 157)
 
My dream home
My dream homeMy dream home
My dream home
 
Introduction to SharePoint 2013
Introduction to SharePoint 2013Introduction to SharePoint 2013
Introduction to SharePoint 2013
 

Mgmt404 project management all 7 weeks i labs devry university

  • 1. MGMT404 Project Management - All 7 Weeks iLabsDevry University DOWNLOAD HERE iLab 1 of 7: Basics of Project Scheduling General Comments about the Microsoft Project Exercises A project plan and schedule are extremely important for managing projects. Applications are available as tools to assist defining, managing, controlling, and reporting on project plans and to evaluate how the project is progressing. Microsoft Project is one application that is commonly used for this purpose and will be the application used in this course. It will help you put together a plan of action, define and organize details, track progress, analyze costs and schedule, assess the quality of your project, and report numerous details to interested parties. Guidelines iLab Lesson 1A Requirements: Complete Lesson 1A. Print Project Summary Report.Print Unstarted Tasks Report. iLab Lesson 1B Requirements: Complete Lesson 1B. Print Entry Table and Gantt Chart (show only columns up to and including the Duration Column.) Printout should be no more than two pages wide. Print Project Summary Report. Print Unstarted Tasks Report (fit to one page). Deliverables All of the following deliverables are required (in a zip file) in order to receive full credit: Completed MyLab1B_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_1_Printouts_XXX.docx When submitting required printouts, if you are not bringing them to class, from the Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the report and paste the screen shot to an MS Word document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually.
  • 2. Save the Word document containing printouts as Week_1_Printouts_XXX.docx and submit this file to the Week 1 iLabDropbox in a zip file, along with the MyLab1B_XXX.mpp file and the completed Review Questions at the end of Lesson 1B. Remember to replace "XXX" in the file names with your initials, and ensure that all of your files are all clearly labeled and include your initials in the file name. iLAB STEPS STEP 1: Download iLab Instructions Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson1A.docx(There are no Review Questions for Lesson 1A.) MS Project Lesson1B.docx(Review Questions to be completed and submitted for Lesson 1B are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 1 based on the Guidelines section and Lesson documents above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab1. Place copies of each required deliverable into this folder. Right-click on the folder and select Send To → Compressed (zipped) Folder. You can also use other tools to compress the files into a single zip folder, (for example, 7-zip). Upload the zip file to the weekly iLabDropbox in eCollege. For instructions on how to use the Dropbox, read theseStep-by-Step Instructionsor watch thisDropbox Tutorial. See Syllabus "Due Dates for Assignments & Exams" for due date information. Once your professor has received and graded the Week 1 iLab assignments, solutions to the Week 1 iLab will be made available to you in Doc Sharing iLab 2 of 7: Managing Project Resources General Comments about the Microsoft Project Exercises Once the base schedule has been created, resources can be assigned to tasks. To complete that this week, we will:
  • 3. Create a list of resources. Assign resources to tasks. Assign costs to resources. Use resource information to determine a preliminary cost for the project. Guidelines Complete Lesson 2. A printout of your Table: Entry showing all columns, but no Gantt chart A printout of your Table: Cost showing all columns but no Gantt chart Print the Summary Report. Print the Budget Report. Print the Who Does What report. Print the Overallocated Resources report. Deliverables All of the following deliverables are required (in a zip file) to receive full credit: Completed MyLab2_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_2_Printouts_XXX.docx When submitting required printouts, if you are not bringing them to class, from the Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the report and paste the screen shot to a MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_2_Printouts_XXX.docx, and submit this file to the Week 2 iLabDropbox in a zip file along with the MyLab2_XXX.mpp file and the completed Review Questions at the end of Lesson 2. Remember to replace "XXX" in the file names with your initials, and ensure that all of your files are all clearly labeled and include your initials in the file name. iLAB STEPS STEP 1: Download iLab Instructions Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson2.docx(Review Questions to be completed and submitted for Lesson 2 are located at the end of this document.) STEP 2: Complete the iLab Assignment
  • 4. Complete the iLab assignment for Week 2 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab2. iLab 3 of 7: Scheduling with Resources General Comments about the Microsoft Project Exercises In this week's iLab, we will use the different ways MS Project allows you to modify resource assignments and how this can affect work completion. In doing so we will: Change the task type settings to control how resources affect task assignments. Apply preset resource contours to change work value distribution. Work with task information forms. Guidelines Complete Lesson 3. Print the Project Summary Report. Print the Task Usage Report. Print the Resource Usage Report. Deliverables All of the following deliverables are required (in a zip file) to receive full credit: Completed MyLab3_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_3_Printouts_XXX.docx When submitting required printouts, if you are not bringing them to class, from the Print Preview Page, take a screen shot (in Windows <ALT><PrtScr>) of the report, and paste the screen shot to a MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_3_Printouts_XXX.docx, and submit this file to the Week 3 iLabDropbox in a zip file along with the MyLab3_XXX.mpp file and the completed Review Questions at the end of Lesson 3. Remember to replace "XXX" in the file names with your initials, and ensure that all of your files are all clearly labeled, and include your initials in the file name. iLAB STEPS
  • 5. STEP 1: Download iLab Instructions Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson3.docx(Review Questions to be completed and submitted for Lesson 3 are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 3 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab3 iLab 4 of 7: Working with Calendars General Comments about the Microsoft Project Exercises Calendars are tools that can be assigned to the project and to individual resources. The calendars can change the length of the workdays and schedule individual vacations. To work with the calendars, we will: Change the working and non-working time on Standard Calendar. Change the working and non-working time on a Resource Calendar. Create new base calendars. Assign different base calendars to resources. Guidelines Complete Lesson 4. Print the Project Summary Report. Print the Gantt Chart View. (Include only those columns up to and including the Finish Date column and the Gantt chart. Print this on two pages wide.) Print the Who Does What When Report. (Print this on three pages.) Print the TaskUsage Report.
  • 6. Deliverables All of the following deliverables are required (in a zip file) in order to receive full credit: Completed MyLab4_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_4_Printouts_XXX.docx When submitting required printouts (if you are not bringing them to class), take a screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview page and paste the screenshot to an MS Word document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_4_Printouts_XXX.docx, and submit this file to the Week 4 iLabDropbox in a zip file along with the MyLab4_XXX.mpp file and the completed Review Questions at the end of Lesson 4. Remember to replace "XXX" in all the file names with your initials, and ensure that all of your files are clearly labeled. iLAB STEPS STEP 1: Download iLab Instructions Click the links below to access this week's iLab instructions. You also may download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson4.docx(Review Questions to be completed and submitted for Lesson 4 are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 4 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab4
  • 7. Project Monitoring and Control & Managing Project Teams - iLab iLab 5 of 7: Resource Workloads General Comments about the Microsoft Project Exercises A project schedule cannot be confirmed until all resource variations and overallocations are managed. To do this we will: View resource workloads. Locate resource conflicts. Use automatic leveling to resolve resource overallocations. Manually resolve resource overallocations. Guidelines Complete Lesson 5. Print the Gantt Chart View. (Include only those columns up to and including the Finish Date column and the Gantt chart. Print this item on two pages wide.) Print the Project Summary Report. Print the TaskUsage Report. Deliverables All of the following deliverables are required (in a zip file) to receive full credit: Completed MyLab5_XXX.mpp Completed Review Questions Printouts/screenshots contained in Week_5_Printouts_XXX.docx When submitting required printouts (if you are not bringing them to class), take a screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview page and paste the screenshot to an MS Word document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_5_Printouts_XXX.docx, and submit this file to the Week 5 iLabDropbox in a zip file along with the MyLab5_XXX.mpp file and the completed Review Questions at the end of Lesson 5. Remember to replace "XXX" in all the file names with your initials, and ensure that all of your files are clearly labeled. iLAB STEPS STEP 1: Download iLab Instructions
  • 8. Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson5.docx(Review Questions to be completed and submitted for Lesson 5 are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 5 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab5. Project Leadership and Outsourcing & Project Procurement - iLab iLab 6 of 7: Task Constraints and Baselines General Comments about the Microsoft Project Exercises Sometimes certain tasks must be constrained by dates, rather than only by the predecessors. For example, the Independence Day holiday is not dependent upon us getting our BBQ ready and buying fireworks (predecessor tasks) but by the fact that this holiday MUST occur on July 4. Once we have determined what these constraints are, we can set our project baseline and be ready to complete work on our project. To finalize our project plan in order to begin work, we will: Use constraints to set date limitations. Set a project baseline schedule. Guidelines Complete Lesson 6. Print the Constraints Table. (Include all columns of the table.) Print the Project Summary Report. Deliverables All of the following deliverables are required (in a zip file) to receive full credit:
  • 9. Completed MyLab6_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_6_Printouts_XXX.docx When submitting required printouts (if you are not bringing them to class), take a screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview page and paste the screenshot to an MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_6_Printouts_XXX.docx, and submit this file to the Week 6 iLabDropbox in a zip file along with the MyLab6_XXX.mpp file and the completed Review Questions at the end of Lesson 6. Remember to replace "XXX" in all the file names with your initials, and ensure that all of your files are clearly labeled. iLAB STEPS STEP 1: Download iLab Instructions Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson6.docx(Review Questions to be completed and submitted for Lesson 6 are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 6 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab6. Place copies of each required deliverable into this folder. Right-click on the folder and select Send To → Compressed (zipped) Folder. You can also use other tools to compress the files into a single zip folder (for example, 7-zip). Upload the zip file to the weekly iLabDropbox in eCollege. For instructions on how to use the Dropbox, read theseStep-by-Step Instructionsor watch thisDropbox Tutorial. See Syllabus "Due Dates for Assignments & Exams" for due date information.
  • 10. Once your professor has received and graded the Week 6 iLab assignments, solutions to the Week 6 iLab will be made available to you in Doc Sharing iLab 7 of 7: Tracking Project Progress Now that the baseline is set, project work can begin. We can use MS Project to track our project's progress and compare it to our baseline. Comparing to the baseline allows us to check our progress against the schedule and budget. When negative variances occur, we are either behind schedule or over budget, so we know that corrective actions are necessary. In this week's iLab, we will: General Comments about the Microsoft Project Exercises Compare baseline data to actual and scheduled data. View a network diagram. Overview the Earned Value calculations in MS Project. Guidelines Complete Lesson 7. Print the Project Summary Report. Print the Overbudget Tasks Report. (Print on one page) Print the Earned Value Report. Deliverables All of the following deliverables are required (in a zip file) to receive full credit: Completed MyLab7_XXX.mpp Completed Review Questions Printouts/Screenshots contained in Week_7_Printouts_XXX.docx When submitting required printouts (if you are not bringing them to class), take a screenshot (in Windows <ALT><PrtScr>) of the report from the Print Preview page and paste the screenshot to an MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than one page, paste each page individually. Save the Word document containing printouts as Week_7_Printouts_XXX.docx, and submit this file to the Week 7 iLabDropbox in a zip file along with the MyLab7_XXX.mpp file and the completed Review Questions at the end of Lesson 7. Remember to replace "XXX" in all the file names with your initials, and ensure that all of your files are clearly labeled. iLAB STEPS STEP 1: Download iLab Instructions
  • 11. Click the links below to access this week's iLab instructions. You may also download both lessons from the MS Project Exercises category in Doc Sharing. MS Project Lesson7.docx(Review Questions to be completed and submitted for Lesson 7 are located at the end of this document.) STEP 2: Complete the iLab Assignment Complete the iLab assignment for Week 7 based on the Guidelines section and Lesson document above. STEP 3: Submit iLab Deliverables Create a folder called MGMT404_YourLastName_Lab7 MGMT404 Project Management - All 7 Weeks iLabsDevry University DOWNLOAD HERE