2. Samsung SDI Energy Storage System | Younicos Case Study
Copyright ยฉ 2013 Samsung SDI. All rights reserved
Description
Schwerinโs green power utility WEMAG has ordered Europeโs first battery park
for the commercial balancing of grid fluctuations. The battery park will hold up
to 5MWh of energy and will be commissioned in mid-2014. The battery power
plant will be connected to the 100-KV substation at Schwerin-Lankow, ensuring
its integration into the regional distribution grid as well as connection to the
next-level 380-KV high voltage grid.
SAMSUNG SDI
+
Younicos
=
Battery park for commercial
balancing of grid fluctuations
Younicos Technology Center
Lithium ion test lab
Lithium ion battery
demonstration installation
3. Samsung SDI Energy Storage System | Younicos Case Study
Project Overview
Project
Schwerin Project
5MW/5MWh
Location
Schwerin-Lankow, Germany
Copyright ยฉ 2013 Samsung SDI. All rights reserved
4. Samsung SDI Energy Storage System | Younicos Case Study
Copyright ยฉ 2013 Samsung SDI. All rights reserved
Location
Mecklenburg
Vorpommern
in
Schwerin
Lankow
Samsung SDI + Younicos BESS
Schwerin Project
5. Samsung SDI Energy Storage System | Younicos Case Study
Copyright ยฉ 2013 Samsung SDI. All rights reserved
Related Parties
Battery Energy Storage System : Samsung SDI + Younicos
โข Samsung SDI : Lithium Manganese Oxide (LMO) battery
โข Younicos : Automated Grid integration system
โข Power Utility : WEMAG
Younicos
WEMAG
6. Samsung SDI Energy Storage System | Younicos Case Study
Copyright ยฉ 2013 Samsung SDI. All rights reserved
Purpose
1. Combining utility scale energy storage with wind and solar generation
2. Mitigating intermittent fluctuations of wind turbines and PV panels
3. Voltage control
4. Primary/secondary frequency response
5. Power frequency control
1
2
ESS
3
volt
45
0
ESS
7. Samsung SDI Energy Storage System | Younicos Case Study
Status
The battery park will be commissioned in mid-2014. With this project
WEMAG hope to level short-term fluctuations as well as regulate the
supply frequency on the transmission network level. This will aid the
safe integration of wind and solar power into the existing network.
Younicos has started working on the park from June this year.
Copyright ยฉ 2013 Samsung SDI. All rights reserved
8. Copyright ยฉ 2013 Samsung SDI. All rights reserved
Stay Tuned!
We will post another slide about how we help YOUINCOSโs project
when we have accumulated meaningful data
9. Copyright ยฉ 2013 Samsung SDI. All rights reserved
Check out more about
our business on :
DISCLAIMER: You are more than welcome to spread this content. Also, we would like to notify that all the copyright and technical information belongs to Samsung SDI.