SlideShare una empresa de Scribd logo
1 de 35
Title :
Presented by: Major Adviser:
HARPREET KAUR Dr. Jaspal Singh
L-2015- AE- 187 M -Tech Prof. cum Head
 Management functions of construction comprises of some
following activities
1. Tendering and winning the contract
2. Contract negotiations
3. Mobilizing the financial resources for the work
4. Maintaining proper accounts
5. Work planning
6. Work supervision
7. Project control and monitoring
8. Maintenance of good labour relation
9. Completion of the work
Mainly following two methods are widely used in ‘
PROJECT MANAGEMENT’
1.CPM- (Critical Path Method)
2.PERT-(Project Evaluation And Review Technique)
 This method of const. first developed in
western Europe particularly in France &
Germany during 1950’s.
 Over 70 bridges of this type under const.
during 1971-75 in France.
 In India during 1960-61,@ 250m long Barak
bridge was constructed.
 There are the two basic materials for the construction
of prestressed concrete structures
1. High-strength concrete
2. High-tensile steel
According to Indian standard code IS:1343
1. The minimum grade for post tensioning is M-30.
2. The minimum grade for pretensioning is M-40.
Recent advances in concrete technology include the
development of
1.Rheodynamic concrete
2.High performance concrete
3.Nano concrete
4.Ultra high strength concrete
….are suitable for prestressed concrete structures.
These joints are necessary due to following reasons ….
1. Thermal contraction and expansion in structure
2. Shrinkage of concrete
3. Creep or inelastic deformation of structure
4. Elastic shortening under prestress
5. Displacement of the structure under load or any
other action
Construction techniques includes the following….
1.General aspects
2.Cantilever construction
3.Choice of spans and the method of construction
4.Prestressing cables
5.Epoxy bonding of precast segmental box girders
6.Innovative construction techniques
1. Rapid developments in construction
techniques.
2. Advances in materials of construction.
3. Prestressed concrete is ideally suited for
large spans, its application is much less for
substructures than for superstructures.
This method …
1. Eliminates the use of expensive formwork
2. Scaffolding
Especially for bridges in deep valleys and
rivers with large depth of water.
It is mainly includes following two methods
1. Cast insitu construction.
2. Construction using precast segment.
 In this method bridge is cast in situ with
section 3 to 6 m long, cantilevering on both
sides of pier.
 Formwork is cast by steel frame work
 The operations of this method are as follows
1. Fabrication and shuttering
2. Placing of reinforcement and duct tubes for
high tensile cables
3. Concentering
4. Curing of concrete
1. Threading ,anchoring and grounting of the
cables.
2. Releasing the formwork and moving on to
next section.
Prestress can be applied only after the
concrete developed the desired strength
after one week.
For e.g. the Bessein creek bridge by Gammon
India company at Bombay
 This method is used for the long bridges. It
is economical when there is large no of span.
This method involves the following steps.
 Casting of Precast segments in casting yard.
 Transporting the precast segments at the
site.
 Erection of the precast segment using
launcher or crane.
 External Prestressing.
 Grouting.
 A Segmental Bridge is a bridge built in short
sections (called segments), that is one piece
at a time. And then segments are erected to
make the bridge. The bridge is either cast-in-
place or precast.
 It is economical for large project, due to
investment req. for casting, handling &
erection of precast segments.
 The construction of a flyover in an urban
environment is not always welcomed by the
society because of traffic disturbance &
construction delays, nuisance caused during
concreting & erecting the formwork at site and
noise & visual pollution.
Selection of method of construction is mainly
based on following
1. Size of the bridge
2. Length of the span
3. Precasting facilities available at site
4. Equipments available
 Cantilever method is used in range of 50 to
200 m .
 For small spans of less than 50 m ,precast
segmental method is preferred
 The following points are important for
cantilever construction technique
1. After erection of each modular section
cables should be threaded into the ducts.
2. The voids must be enough large for proper
grouting.
3. The commonly used cables comprise 12
wires of 13 dia. And 12wires of 8mm
diameter cables (Freyssient system).
 Following re the techniques used for the
construction of prestressed concrete bridges
are listed below……
1. The staging method
2. Incremental launching or push out technique
3. Progressive placement construction method
4. Cantilever construction method
 This technique is adopted when
1. Low clearance is required below the deck
2. Supporting formwork does not interface with the traffic
This method facilitates rapid construction by maintaining
correct geometry of the structure with low cost.
This technique has been used in the construction of Rhine river
at Maxau,Japan
1. Segments of the Bridge superstructure are cast
at site in length of 10 to 30 m in stationary
forms located behind the abutment.
2. Each unit is cast directly against the previous
unit.
3. After the concrete attains the desired strength,
the new unit is joined to the previous unit by
post tensioning.
4. The assembly of units is pushed forward in
stepwise for casting and succeeding segments
 In this case construction starts at one end of
the structure and proceeds continuously to
the other end (cantilever end)
1. This method have found to be practicable
and economical in range of 30 to 90 m.
2. This method has been used for ‘Linn cove
viaduct in north Carolina’ USA .
Basic information related to ‘ Linn cove
viaduct in north Carolina’USA.
1. Total length1,243 feet (379 m)
2. Width39.5 feet (12.0 m)
3. Construction begin1979
4. Construction end1987
 During the last decades, construction
techniques developed have shown major
progress towards simplification.
 The collective experience and knowledge
gained through research and practice during
the last fifty years will help in involving
innovative applications in the construction of
prestressed concrete structures
1. N Krishna raju Prestressed concrete
,Tata McGraw –Hill publishing Co.
Ltd, New Delhi,2007,pp 715-729
2. Internet
Construction of prestressed concrete structures
Construction of prestressed concrete structures

Más contenido relacionado

La actualidad más candente

Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed ConcreteRavi Savani
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMis_web
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPANfaishalniet
 
Shear in prestress concrete
Shear in prestress concreteShear in prestress concrete
Shear in prestress concreteAliAlmayalee
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concreteParag Pal
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1সাফকাত অরিন
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE524001
 
Optimum design of precast prestressed concrete structural element
Optimum design of precast prestressed concrete structural element Optimum design of precast prestressed concrete structural element
Optimum design of precast prestressed concrete structural element Awinash Tiwari
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteBaruti Balinda Jonathan
 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog bassamnakfour
 
Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structuresPraveenKumar Shanmugam
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
 
Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baruKartina Sazali
 

La actualidad más candente (20)

Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEM
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 
Shear in prestress concrete
Shear in prestress concreteShear in prestress concrete
Shear in prestress concrete
 
Ppt
PptPpt
Ppt
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
A Post Tension Primer
A Post Tension PrimerA Post Tension Primer
A Post Tension Primer
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE
 
Optimum design of precast prestressed concrete structural element
Optimum design of precast prestressed concrete structural element Optimum design of precast prestressed concrete structural element
Optimum design of precast prestressed concrete structural element
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concrete
 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog
 
Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structures
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
 
Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baru
 

Destacado

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concretefroskhan08
 
Tünelmak tunneling and shotcrete technologies
Tünelmak tunneling and shotcrete technologiesTünelmak tunneling and shotcrete technologies
Tünelmak tunneling and shotcrete technologiesMurat Aydın
 
Evolution Shotcrete brochure
Evolution Shotcrete brochureEvolution Shotcrete brochure
Evolution Shotcrete brochureNige Austin
 
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...Francois Lepers
 
Pcs module1&2 Cusat syllabus
Pcs module1&2 Cusat syllabusPcs module1&2 Cusat syllabus
Pcs module1&2 Cusat syllabusCochin University
 
Ce572 introductiontoprestressing1
Ce572 introductiontoprestressing1Ce572 introductiontoprestressing1
Ce572 introductiontoprestressing1Prateek Choudhary
 
PT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSPT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSFrancois Lepers
 
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula MathsConstruction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula MathsDaniel Ross
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemLatif Hyder Wadho
 
Reinforced and prestressed concrete kong & evans
Reinforced and prestressed concrete   kong & evansReinforced and prestressed concrete   kong & evans
Reinforced and prestressed concrete kong & evansbridemcdamian
 
post tension slabs in residential building
post tension slabs in residential buildingpost tension slabs in residential building
post tension slabs in residential buildinggovt.poly kalamassery
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsAMSYSCO Inc.
 

Destacado (19)

7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Tünelmak tunneling and shotcrete technologies
Tünelmak tunneling and shotcrete technologiesTünelmak tunneling and shotcrete technologies
Tünelmak tunneling and shotcrete technologies
 
Evolution Shotcrete brochure
Evolution Shotcrete brochureEvolution Shotcrete brochure
Evolution Shotcrete brochure
 
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...Recent challenges and advances on PRESTRESSED  CONCRETE design and construct...
Recent challenges and advances on PRESTRESSED CONCRETE design and construct...
 
Pcs module1&2 Cusat syllabus
Pcs module1&2 Cusat syllabusPcs module1&2 Cusat syllabus
Pcs module1&2 Cusat syllabus
 
Ce572 introductiontoprestressing1
Ce572 introductiontoprestressing1Ce572 introductiontoprestressing1
Ce572 introductiontoprestressing1
 
PT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSPT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGS
 
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula MathsConstruction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
 
Reinforced and prestressed concrete kong & evans
Reinforced and prestressed concrete   kong & evansReinforced and prestressed concrete   kong & evans
Reinforced and prestressed concrete kong & evans
 
6 shotcrete
6 shotcrete6 shotcrete
6 shotcrete
 
post tension slabs in residential building
post tension slabs in residential buildingpost tension slabs in residential building
post tension slabs in residential building
 
compaction equipment
compaction equipmentcompaction equipment
compaction equipment
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 

Similar a Construction of prestressed concrete structures

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridgesmukul srivastava
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...IRJET Journal
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
 
Invention Catalogue Pictures
Invention Catalogue  PicturesInvention Catalogue  Pictures
Invention Catalogue PicturesMehdi Afshar
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET Journal
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09Hans De Wit
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingIRJET Journal
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated ColumnAnees Khan
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction ajinkyaraj
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 

Similar a Construction of prestressed concrete structures (20)

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Invention Catalogue Pictures
Invention Catalogue  PicturesInvention Catalogue  Pictures
Invention Catalogue Pictures
 
Metro Work
Metro WorkMetro Work
Metro Work
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
NSL General HdW.update nov09
NSL General HdW.update nov09NSL General HdW.update nov09
NSL General HdW.update nov09
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
 
Ijciet 08 02_040
Ijciet 08 02_040Ijciet 08 02_040
Ijciet 08 02_040
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 

Último

UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 

Último (20)

UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 

Construction of prestressed concrete structures

  • 1.
  • 2. Title : Presented by: Major Adviser: HARPREET KAUR Dr. Jaspal Singh L-2015- AE- 187 M -Tech Prof. cum Head
  • 3.
  • 4.  Management functions of construction comprises of some following activities 1. Tendering and winning the contract 2. Contract negotiations 3. Mobilizing the financial resources for the work 4. Maintaining proper accounts 5. Work planning 6. Work supervision 7. Project control and monitoring 8. Maintenance of good labour relation 9. Completion of the work
  • 5. Mainly following two methods are widely used in ‘ PROJECT MANAGEMENT’ 1.CPM- (Critical Path Method) 2.PERT-(Project Evaluation And Review Technique)
  • 6.  This method of const. first developed in western Europe particularly in France & Germany during 1950’s.  Over 70 bridges of this type under const. during 1971-75 in France.  In India during 1960-61,@ 250m long Barak bridge was constructed.
  • 7.  There are the two basic materials for the construction of prestressed concrete structures 1. High-strength concrete 2. High-tensile steel
  • 8. According to Indian standard code IS:1343 1. The minimum grade for post tensioning is M-30. 2. The minimum grade for pretensioning is M-40. Recent advances in concrete technology include the development of 1.Rheodynamic concrete 2.High performance concrete 3.Nano concrete 4.Ultra high strength concrete ….are suitable for prestressed concrete structures.
  • 9. These joints are necessary due to following reasons …. 1. Thermal contraction and expansion in structure 2. Shrinkage of concrete 3. Creep or inelastic deformation of structure 4. Elastic shortening under prestress 5. Displacement of the structure under load or any other action
  • 10.
  • 11. Construction techniques includes the following…. 1.General aspects 2.Cantilever construction 3.Choice of spans and the method of construction 4.Prestressing cables 5.Epoxy bonding of precast segmental box girders 6.Innovative construction techniques
  • 12. 1. Rapid developments in construction techniques. 2. Advances in materials of construction. 3. Prestressed concrete is ideally suited for large spans, its application is much less for substructures than for superstructures.
  • 13. This method … 1. Eliminates the use of expensive formwork 2. Scaffolding Especially for bridges in deep valleys and rivers with large depth of water. It is mainly includes following two methods 1. Cast insitu construction. 2. Construction using precast segment.
  • 14.  In this method bridge is cast in situ with section 3 to 6 m long, cantilevering on both sides of pier.  Formwork is cast by steel frame work  The operations of this method are as follows 1. Fabrication and shuttering 2. Placing of reinforcement and duct tubes for high tensile cables 3. Concentering 4. Curing of concrete
  • 15. 1. Threading ,anchoring and grounting of the cables. 2. Releasing the formwork and moving on to next section. Prestress can be applied only after the concrete developed the desired strength after one week. For e.g. the Bessein creek bridge by Gammon India company at Bombay
  • 16.  This method is used for the long bridges. It is economical when there is large no of span. This method involves the following steps.  Casting of Precast segments in casting yard.  Transporting the precast segments at the site.  Erection of the precast segment using launcher or crane.  External Prestressing.  Grouting.
  • 17.
  • 18.  A Segmental Bridge is a bridge built in short sections (called segments), that is one piece at a time. And then segments are erected to make the bridge. The bridge is either cast-in- place or precast.
  • 19.  It is economical for large project, due to investment req. for casting, handling & erection of precast segments.  The construction of a flyover in an urban environment is not always welcomed by the society because of traffic disturbance & construction delays, nuisance caused during concreting & erecting the formwork at site and noise & visual pollution.
  • 20.
  • 21. Selection of method of construction is mainly based on following 1. Size of the bridge 2. Length of the span 3. Precasting facilities available at site 4. Equipments available  Cantilever method is used in range of 50 to 200 m .  For small spans of less than 50 m ,precast segmental method is preferred
  • 22.  The following points are important for cantilever construction technique 1. After erection of each modular section cables should be threaded into the ducts. 2. The voids must be enough large for proper grouting. 3. The commonly used cables comprise 12 wires of 13 dia. And 12wires of 8mm diameter cables (Freyssient system).
  • 23.
  • 24.  Following re the techniques used for the construction of prestressed concrete bridges are listed below…… 1. The staging method 2. Incremental launching or push out technique 3. Progressive placement construction method 4. Cantilever construction method
  • 25.  This technique is adopted when 1. Low clearance is required below the deck 2. Supporting formwork does not interface with the traffic This method facilitates rapid construction by maintaining correct geometry of the structure with low cost. This technique has been used in the construction of Rhine river at Maxau,Japan
  • 26.
  • 27. 1. Segments of the Bridge superstructure are cast at site in length of 10 to 30 m in stationary forms located behind the abutment. 2. Each unit is cast directly against the previous unit. 3. After the concrete attains the desired strength, the new unit is joined to the previous unit by post tensioning. 4. The assembly of units is pushed forward in stepwise for casting and succeeding segments
  • 28.
  • 29.  In this case construction starts at one end of the structure and proceeds continuously to the other end (cantilever end) 1. This method have found to be practicable and economical in range of 30 to 90 m. 2. This method has been used for ‘Linn cove viaduct in north Carolina’ USA .
  • 30.
  • 31. Basic information related to ‘ Linn cove viaduct in north Carolina’USA. 1. Total length1,243 feet (379 m) 2. Width39.5 feet (12.0 m) 3. Construction begin1979 4. Construction end1987
  • 32.  During the last decades, construction techniques developed have shown major progress towards simplification.  The collective experience and knowledge gained through research and practice during the last fifty years will help in involving innovative applications in the construction of prestressed concrete structures
  • 33. 1. N Krishna raju Prestressed concrete ,Tata McGraw –Hill publishing Co. Ltd, New Delhi,2007,pp 715-729 2. Internet