TESTING OF CEMENT
Free Powerpoint Templates
Page 2
 FIELD TESTING
 LABORATORY TESTING
METHODS OF TESTING
Free Powerpoint Templates
Page 3
 Open the bag and take a good look at the cement,
then it should not contain any visible lumps.
 Colour of cement should be greenish grey.
 Should get cool feeling when thrusted.
 When we touch the cement, it should give a smooth
&not a gritty feeling.
 When we throw the cement on a bucket full of water
before it sinks the particles should flow.
 When we make a stiff paste of cement & cut it with
sharp edges & kept on a glass plate under water there
wont be any disturbance to the shape& should get
strength after 24hours.
FIELD TEST
Free Powerpoint Templates
Page 4
LABORATORY TESTS
 Fineness test
 Standard consistency test
 Setting time test
 Strength test
 Soundness test
 Heat of hydration test
 Chemical composition test
Free Powerpoint Templates
Page 5
• The fineness of cement has an important bearing
on the rate of hydration, rate of gain of strength,
evolution of heat.
• Finer cement offers greater surface area.
• Disadvantage of fine grinding is that it is
susceptible to air set & early deterioration.
• Maximum no. of particles in a sample of
cement<100microns.
• The smallest particle should have a size if
1.5microns.
• Large particle should have a size of 10microns.
FINENESS TEST
Free Powerpoint Templates
Page 6
Fineness of cement is tested in two ways.
• By sieving.
• By determination specific surface by air permeability
Free Powerpoint Templates
Page 7
• Take correctly 100grams of cement on a
standard IS sieve No.9
• Break down the air-set lumps & sieve it
&weigh it.
• This weight shall not exceed 10% for
ordinary cement.
• Sieve test is rarely used.
• The weight of the residue
should not exceed 10% for
ordinary cement.
SIEVE TEST
Free Powerpoint Templates
Page 8
 Principle of air permeability method is in observing
the time taken for a fixed quantity of air to flow
through compacted cement bed of specified dimension
and porosity.
PROCEDURE:
 cement required to make a cement bed of porosity
0.475 is calculated.
 pass on the air slowly at constant velocity.
Adjust the rate of air flow until the flowmeter shows
a difference in level of 30-50cm.
Repeat these observation for constant h1/h2.
specified air flow.
STANDARD PERMEABILITY TEST
Free Powerpoint Templates
Page 9
Free Powerpoint Templates
Page 10
The standard consistency of a cement paste is
defined as that consistency which will permit
a Vicat plunger having 10 mm diameter and
50 mm length to penetrate to a depth of 33-
35 mm from the top of the mould.
STATNDARD CONSISTENCY TEST
USE
Used to find out the percentage of water
required to produce a cement paste of
standard consistency.
This is also called normal consistency
(CPNC).
Free Powerpoint Templates
Page 11
•For first trial, take about 500gms of cement &
water of r%.
•Fill it in Vicat’s mould with in 3-5min.
•After filling, shake the mould to expel air.
•A standard plunger, 10 mm diameter, 50 mm long
is attached and brought down to touch the surface of
the paste and quickly released.
•Note the reading according to depth of penetration
of the plunger.
Free Powerpoint Templates
Page 12
•Conduct trials continuously by taking
different water cement ratios till the plunger
penetrates for a depth of 33-35mm from top.
• This particular percentage is known as
percentage of water required to produce
cement paste of standard consistency.
This is usually denoted as ‘P’.
SUITABLE CONDITIONS:
Conducted in a constant temperature of
27º±2ºC.
Constant Humidity 90%.
Free Powerpoint Templates
Page 13
An arbitraty division has been made for the
setting time of cement as
 Initial setting time
 Final setting time.
SETTING TIME TEST
Free Powerpoint Templates
Page 14
 The time elapsed between the moment that the
water is added to the cement, to the time that the
paste starts losing its plasticity.
 Normally a minimum of 30min has maintained
for mixing & handling operations.
 It should not be less than 30min.
INITIAL SETTING TIME
Free Powerpoint Templates
Page 15
FINAL SETTING TIME
 The time elapsed between the moment the
water is added to the cement, and the time
when the paste has completely lost its
plasticity and has attained sufficient firmness
to resist certain definite pressure.
 It should not exceed 10hours.
So that it is avoided from least vulnerable to
damages from external activities.
Free Powerpoint Templates
Page 16
PROCEDURE:
 Vicat apparatus is used for finding the setting time
 Take 500gms of cement and add about 0.85p
 The paste should be filled within 3-5 minutes.
 Initial and final setting time is noted.
Free Powerpoint Templates
Page 17
STRENGTH TEST
 This is the most important of all
properties of hardened cement.
 Due to excessive shrinkage and cracking
the strength tests are not made on neat
cement paste.
 Standard sand is used for finding the
strength of cement.
Free Powerpoint Templates
Page 18
 Take sand and cement (i.e., 1:3 ratio of cement
and sand) Mix them for 1min, then add water of
quantity(P/4)+3.0%.
 Mix three ingredients thoroughly until the
mixture is of uniform colour.
 The time of mixing should not be<3min and
>4min.Then the mortar is filled into a cube mould of
7.06cm. Compact the mortar.
 Keep the compacted cube in the mould at a
temperature of 27°C ± 2°C and at least 90 per cent
relative humidity for 24 hours.
 After 24hours the cubes are removed & immersed
in clean fresh water until taken for testing.
Free Powerpoint Templates
Page 19
SOUNDNESS TEST
 It is very important that the cement after setting
shall not undergo any appreciable change of
volume.
 This test is to ensure that the cement does not
show any subsequent expansions.
 The unsoundness in cement is due to the presence
of excess of lime combined with acidic oxide at the
kiln.
 This is due to high proportion of magnesia &
calcium sulphate.
 Therefore magnesia content in cement is limited
to 6%.
Free Powerpoint Templates
Page 20
Free Powerpoint Templates
Page 21
HEAT OF HYDRATION
 cement with water is an exothermic reaction
 Heat of hydration will be found out using thermos flask
 About 120 calories of heat is generated in the hydration
of 1 gm of cement
 Temperature rise of about 50°C is observed and this
causes serious expansion of the body of dam.
Free Powerpoint Templates
Page 22
To avoid this :
 Lean mix
 puzzolanic cement
 Artificial cooling materials
 incorporation of pipe system in the body of dam and
applying cold brine solutions.
Tests :
 To be carried out only in low heat cement
 vaccum flask method for short duration and
adiabatic calorimeter for longer period
 should not exceed 65 cal/gm at 7 days and should be
less than 75 cal/gm at 28 days
Free Powerpoint Templates
Page 23
CHEMICAL COMPOSITION TEST
Ratio of percentage of lime to percentage of silica,alumina
and iron oxide when calculated by
Cao-0.7So3
—————————————
2.8SiO ₂ +1.2Al ₂ O ₃+0.65Fe ₂ O ₃
Should not be greater than 1.02 and not less than 0.66
This is called LIME SATURATION FACTOR PERCENT

Más contenido relacionado

Destacado

CE 6002 CONCRETE TECHNOLOGY UNIT II
CE 6002 CONCRETE TECHNOLOGY UNIT IICE 6002 CONCRETE TECHNOLOGY UNIT II
CE 6002 CONCRETE TECHNOLOGY UNIT IIcivilguna
 
Field Tests of Cement
Field Tests of CementField Tests of Cement
Field Tests of CementPradipta Sur
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulationFayaz Ahamed A P
 
Properties of aggregrate
Properties of aggregrateProperties of aggregrate
Properties of aggregrateNIT Warangal
 
Aggregate - Concrete Technology
Aggregate - Concrete TechnologyAggregate - Concrete Technology
Aggregate - Concrete TechnologyDavid Grubba
 
Concrete, Its Ingredients and Properties
Concrete, Its Ingredients and PropertiesConcrete, Its Ingredients and Properties
Concrete, Its Ingredients and PropertiesHananeel Sandhi
 
Concrete technology
Concrete technologyConcrete technology
Concrete technologyJNTU
 

Destacado (10)

CE 6002 CONCRETE TECHNOLOGY UNIT II
CE 6002 CONCRETE TECHNOLOGY UNIT IICE 6002 CONCRETE TECHNOLOGY UNIT II
CE 6002 CONCRETE TECHNOLOGY UNIT II
 
Field Tests of Cement
Field Tests of CementField Tests of Cement
Field Tests of Cement
 
SLUMP TEST AND VEE-BEE TEST
SLUMP TEST AND VEE-BEE TEST SLUMP TEST AND VEE-BEE TEST
SLUMP TEST AND VEE-BEE TEST
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulation
 
Properties of aggregrate
Properties of aggregrateProperties of aggregrate
Properties of aggregrate
 
Aggregate - Concrete Technology
Aggregate - Concrete TechnologyAggregate - Concrete Technology
Aggregate - Concrete Technology
 
Concrete, Its Ingredients and Properties
Concrete, Its Ingredients and PropertiesConcrete, Its Ingredients and Properties
Concrete, Its Ingredients and Properties
 
Aggregates ppt
Aggregates pptAggregates ppt
Aggregates ppt
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 
Cement
CementCement
Cement
 

Último

Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 

Último (20)

Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 

Testing of cements

  • 1. Free Powerpoint Templates Page 1 Free Powerpoint Templates TESTING OF CEMENT
  • 2. Free Powerpoint Templates Page 2  FIELD TESTING  LABORATORY TESTING METHODS OF TESTING
  • 3. Free Powerpoint Templates Page 3  Open the bag and take a good look at the cement, then it should not contain any visible lumps.  Colour of cement should be greenish grey.  Should get cool feeling when thrusted.  When we touch the cement, it should give a smooth &not a gritty feeling.  When we throw the cement on a bucket full of water before it sinks the particles should flow.  When we make a stiff paste of cement & cut it with sharp edges & kept on a glass plate under water there wont be any disturbance to the shape& should get strength after 24hours. FIELD TEST
  • 4. Free Powerpoint Templates Page 4 LABORATORY TESTS  Fineness test  Standard consistency test  Setting time test  Strength test  Soundness test  Heat of hydration test  Chemical composition test
  • 5. Free Powerpoint Templates Page 5 • The fineness of cement has an important bearing on the rate of hydration, rate of gain of strength, evolution of heat. • Finer cement offers greater surface area. • Disadvantage of fine grinding is that it is susceptible to air set & early deterioration. • Maximum no. of particles in a sample of cement<100microns. • The smallest particle should have a size if 1.5microns. • Large particle should have a size of 10microns. FINENESS TEST
  • 6. Free Powerpoint Templates Page 6 Fineness of cement is tested in two ways. • By sieving. • By determination specific surface by air permeability
  • 7. Free Powerpoint Templates Page 7 • Take correctly 100grams of cement on a standard IS sieve No.9 • Break down the air-set lumps & sieve it &weigh it. • This weight shall not exceed 10% for ordinary cement. • Sieve test is rarely used. • The weight of the residue should not exceed 10% for ordinary cement. SIEVE TEST
  • 8. Free Powerpoint Templates Page 8  Principle of air permeability method is in observing the time taken for a fixed quantity of air to flow through compacted cement bed of specified dimension and porosity. PROCEDURE:  cement required to make a cement bed of porosity 0.475 is calculated.  pass on the air slowly at constant velocity. Adjust the rate of air flow until the flowmeter shows a difference in level of 30-50cm. Repeat these observation for constant h1/h2. specified air flow. STANDARD PERMEABILITY TEST
  • 10. Free Powerpoint Templates Page 10 The standard consistency of a cement paste is defined as that consistency which will permit a Vicat plunger having 10 mm diameter and 50 mm length to penetrate to a depth of 33- 35 mm from the top of the mould. STATNDARD CONSISTENCY TEST USE Used to find out the percentage of water required to produce a cement paste of standard consistency. This is also called normal consistency (CPNC).
  • 11. Free Powerpoint Templates Page 11 •For first trial, take about 500gms of cement & water of r%. •Fill it in Vicat’s mould with in 3-5min. •After filling, shake the mould to expel air. •A standard plunger, 10 mm diameter, 50 mm long is attached and brought down to touch the surface of the paste and quickly released. •Note the reading according to depth of penetration of the plunger.
  • 12. Free Powerpoint Templates Page 12 •Conduct trials continuously by taking different water cement ratios till the plunger penetrates for a depth of 33-35mm from top. • This particular percentage is known as percentage of water required to produce cement paste of standard consistency. This is usually denoted as ‘P’. SUITABLE CONDITIONS: Conducted in a constant temperature of 27º±2ºC. Constant Humidity 90%.
  • 13. Free Powerpoint Templates Page 13 An arbitraty division has been made for the setting time of cement as  Initial setting time  Final setting time. SETTING TIME TEST
  • 14. Free Powerpoint Templates Page 14  The time elapsed between the moment that the water is added to the cement, to the time that the paste starts losing its plasticity.  Normally a minimum of 30min has maintained for mixing & handling operations.  It should not be less than 30min. INITIAL SETTING TIME
  • 15. Free Powerpoint Templates Page 15 FINAL SETTING TIME  The time elapsed between the moment the water is added to the cement, and the time when the paste has completely lost its plasticity and has attained sufficient firmness to resist certain definite pressure.  It should not exceed 10hours. So that it is avoided from least vulnerable to damages from external activities.
  • 16. Free Powerpoint Templates Page 16 PROCEDURE:  Vicat apparatus is used for finding the setting time  Take 500gms of cement and add about 0.85p  The paste should be filled within 3-5 minutes.  Initial and final setting time is noted.
  • 17. Free Powerpoint Templates Page 17 STRENGTH TEST  This is the most important of all properties of hardened cement.  Due to excessive shrinkage and cracking the strength tests are not made on neat cement paste.  Standard sand is used for finding the strength of cement.
  • 18. Free Powerpoint Templates Page 18  Take sand and cement (i.e., 1:3 ratio of cement and sand) Mix them for 1min, then add water of quantity(P/4)+3.0%.  Mix three ingredients thoroughly until the mixture is of uniform colour.  The time of mixing should not be<3min and >4min.Then the mortar is filled into a cube mould of 7.06cm. Compact the mortar.  Keep the compacted cube in the mould at a temperature of 27°C ± 2°C and at least 90 per cent relative humidity for 24 hours.  After 24hours the cubes are removed & immersed in clean fresh water until taken for testing.
  • 19. Free Powerpoint Templates Page 19 SOUNDNESS TEST  It is very important that the cement after setting shall not undergo any appreciable change of volume.  This test is to ensure that the cement does not show any subsequent expansions.  The unsoundness in cement is due to the presence of excess of lime combined with acidic oxide at the kiln.  This is due to high proportion of magnesia & calcium sulphate.  Therefore magnesia content in cement is limited to 6%.
  • 21. Free Powerpoint Templates Page 21 HEAT OF HYDRATION  cement with water is an exothermic reaction  Heat of hydration will be found out using thermos flask  About 120 calories of heat is generated in the hydration of 1 gm of cement  Temperature rise of about 50°C is observed and this causes serious expansion of the body of dam.
  • 22. Free Powerpoint Templates Page 22 To avoid this :  Lean mix  puzzolanic cement  Artificial cooling materials  incorporation of pipe system in the body of dam and applying cold brine solutions. Tests :  To be carried out only in low heat cement  vaccum flask method for short duration and adiabatic calorimeter for longer period  should not exceed 65 cal/gm at 7 days and should be less than 75 cal/gm at 28 days
  • 23. Free Powerpoint Templates Page 23 CHEMICAL COMPOSITION TEST Ratio of percentage of lime to percentage of silica,alumina and iron oxide when calculated by Cao-0.7So3 ————————————— 2.8SiO ₂ +1.2Al ₂ O ₃+0.65Fe ₂ O ₃ Should not be greater than 1.02 and not less than 0.66 This is called LIME SATURATION FACTOR PERCENT