MAJOR ITEMS OF WORK
Sr. No Description of items Cost
1 Earth work 18539
2 Concrete work 46.521
3 Data Board (1 No) 0.018
4 Outlets (09 No) 3.065
5 RD Marks (18 No) 0.016
6 Tail Cluster (1 No) 0.074
7 Any other 9.894
Total :- 78.127
(Rs in Million)
Government
of
the
Punjab
BENEFITS
1) Seepage loses would be reduced.
2) Safety of canal bank and reduction breaches.
3) Optimum running of the channel with equitable distribution of water from head to tail.
4) Improvement in farm economic.
5) Improvement in Socio-Economic condition.
6) Improvement in public health problems.
7) Control over water logging.
8) Strengthening National Economy.
9) The concrete lining of this minor is of vital importance. It requires every completion to
cope with crop water requirement and running of channel with optimum discharge. This
will surely increase yield of crops and more area will be brought under cultivation. The
irrigators which are deprived off their due share of water from years will get their due
share.
Government
of
the
Punjab
ANNOTATED REPLY
Sr.
No.
Observations Reply
a The estimated cost of the work is Rs. 73.206 million against
provision of Rs. 40.1 million in umbrella PC-1. The procuring
agency may justify the additional cost over and above the
provision made in umbrella PC-1.
The provision of Rs. 40.1 million in
umbrella PC-1 is tentative cost while
actual cost is Rs. 76.762 million
estimate cost as per site position.
b The length of channel proposed in the instant PC-I is 27365
ft (RD: 0+000 to 27+365) against the provision of 27675 ft
(RD: 0+000 to 27+675) in umbrella PC-1. The procuring
agency may justify decrease in length for concrete lining
with reference to provision made in umbrella PC-1
The length of channel proposed in the
instant PC-I is 27365 is correct while
umbrella PC-1 of 27675 ft is incorrect
and written due to typing mistake.
c As this is a perennial channel the procuring agency is
required to justify .The non provision of diversion channel.
This is non perennial channel. No
necessity of diversion channel work
can early executed be stipulated time
period.
d The Procuring Agency may justify/ amend the detail
provision of 1% plantation because tree plantation is meant
for deposit to Forest Department
Deleted
Government
of
the
Punjab
ANNOTATED REPLY
Sr.
No.
Observations Reply
e As per cross sections, there is road on the left side of the
channel, the procuring Agency is required to justify the
earth work on left side
Earth work on left side of road side
already excluded from PC-I.
f The Procuring Agency & required to provide clear copy
index Plan of The Project
Clear Copy attached.
g The Procuring Agency is required to justify the lining by
providing history of last three years regarding shortage of
tail, cuts and breach if any
Lining is recommended as the said
canal damaged due to flood 2010
causes water losses/dry tail.