Project Team:
Madeleine Brannon, Srija,
Alexander Brill, Maithili Gaddam
Agenda
1. Background
2. Scope Plan
Stakeholders
Work Breakdown Structure
Top Level Requirements
3. Schedule Plan
Schedule Performance
Baseline
Milestone List
PERT Chart
4. Cost Plan
Cost Performance Baseline
5. Quality Plan
Audit Plan
Process Improvement Plan
6. Human Resources Plan
Resource Staffing Plan
Project Organization Chart
7. Communication Plan
Stakeholder Analysis Matrix
8. Risk Plan
Risk Matrix
9. Procurement Plan
Make or Buy Decisions
Supplier Management Plan
10. Configuration Management
Plan
11. Change Control Plan
12. Conclusion
Background
• Create a Wind Farm in
Simoda, West Virginia
• 100 1.5 MW wind
turbines
• Clean energy is
produced from wind
turbines and made into
electricity
• Simoda, West Virginia
has the potential to
create a new
sustainable industry
http://exploringgreentechnology.com/wind-energy/how-does-
wind-energy-work/
Scope Plan
Scope of the Project
• Not concerned with
where specifically the
electricity goes
• The construction details
are assumed to be
worked out by the
construction company
Stakeholders
Work Breakdown Structure
Assessment Requirements
Requirement Identifier Key
Project Designator
WF = Wind Farm
WT = Wind Turbine
Objective Designator
A = Assessment
P = Performance
Requirement or Verification Type
C = Component
E = Energy
L = Location
Requirement or Verification Designator
R = Requirement
Req. # Req. Identifier Requirement Description
1 WT-PE-R01 The Wind Turbines shall produce energy
harnessed for electricity.
2 WF-AL-R01 Simoda, West Virginia shall be assessed for
the Wind Farm.
10 WF-AL-R02 The Wind Farm shall be located in Simoda,
West Virginia.
11 WF-AC-R01 The Wind Farm shall be funded by General
Electric (GE).
Construction Requirements
Req. # Req. Identifier Requirement Description
3 WT-DC-R01 The Wind Turbine base shall be
constructed.
4 WT-DC-R02 The Wind Turbines shall connect to the
power grid.
5 WT-DC-R03 The Wind Turbines shall have a maximum
tip height of 120 meters.
Requirement Identifier Key
Project Designator
WF = Wind Farm
WT = Wind Turbine
Objective Designator
D = Design
Requirement or Verification Type
C = Component
Requirement or Verification Designator
R = Requirement
Operation Requirements
Requirement Identifier Key
Project Designator
WF = Wind Farm
WT = Wind Turbine
Objective Designator
M = Maintenance
P = Performance
Requirement or Verification Type
C = Component
E = Energy
W = Power
Requirement or Verification Designator
R = Requirement
Req. # Req. Identifier Requirement Description
6 WT-PW-R01 The Wind Turbines shall transmit power to a
power station.
7 WT-PW-R02 The Wind Turbines shall produce a minimum
of 80-megawatt hour.
8 WT-PE-R02 The Wind Turbines shall be operable
continuously.
9 WF-MC-R01 The Wind Farm shall be monitored on a
regular basis.
Schedule Plan
Task Name Duration Start Finish
1 Assesment 321 days Mon 4/14/14 Mon 7/6/15
2 Location Selection 15 days Mon 4/14/14 Fri 5/2/14
3 Wind Resource
Measurements
262 days Mon 5/5/14 Tue 5/5/15
4 Enviornmental
Consultants
14 days Wed 5/6/15 Mon 5/25/15
5 Legal Documentation 30 days Tue 5/26/15 Mon 7/6/15
6 Construction 337 days Tue 7/7/15 Wed 10/19/16
7 Clearing the Area 60 days Tue 7/7/15 Mon 9/28/15
8 Creating a Base 30 days Tue 9/29/15 Mon 11/9/15
9 Wiring Turbines 30 days Tue 11/10/15 Mon 12/21/15
0 Installing Turbines 217 days Tue 12/22/15 Wed 10/19/16
1 Wind Farm Components 380 days Tue 7/7/15 Mon 12/19/16
2 Access roads 52 days Tue 7/7/15 Wed 9/16/15
3 Build Substation 54 days Tue 7/7/15 Fri 9/18/15
4 Electrical Wiring 43 days Thu 10/20/16 Mon 12/19/16
5 Transmission Lines 36 days Tue 7/7/15 Tue 8/25/15
6 Operation 29 days Thu 10/20/16 Tue 11/29/16
7 Hiring Maintenance 14 days Thu 10/20/16 Tue 11/8/16
8 Test and Evaluation 29 days Thu 10/20/16 Tue 11/29/16
9
5/26 8/25 11/24 2/23 5/25 8/24 11/23 2/22 5/24 8/23 11/22 2/21 5/22 8/21 11/20 2/19 5/
January 11 July 21 February 1 August 11 February 21 September 1March 11 September 21April
Task
Split
Milestone
Summary
Project Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Deadline
Baseline
Baseline Milestone
Baseline Summary
Progress
oject: Gantt Chart
ate: Sun 11/17/13
Milestone List
• Acquire the land in Simoda, West Virginia
• Analyze the data required for the one year assessment
phase and verify the project’s location
• Get contracts from the relevant supply and transport
companies
• Installment of wind turbine
• Wiring the turbines and building the substation
• Integration testing i.e. checking if the energy being
transmitted from the wind turbine is being received by
the substation
PERT Chart
Cost Management Plan
Wind Farm Cost
• 1.5 MW turbine chosen
• High Efficiency
• Most widely used
• $3 Million/Wind Turbine installed
• 100 turbines = 150 MW
• $300 Million for wind farm
Project Team Budget
Category
Hourly Labor
Rate Hours Personnel Totals
8 Technicians $ 25.00 5200 $ 389,028.21
Project Manager $ 150 700 $ 312,599.71
Environmental
Engineer $ 38 400 $ 45,252.53
2 Analyst $ 32 700 $ 66,687.94
2 Construction
Manager $ 125 700 $ 260,499.76
7700 $ 25,000.00
Project Subtotals $ 1,103,388.15
Revenue
Quality Management Plan
• The Wind Farm shall be assessed to check whether it is
operating in compliance with the specified requirements.
• An audit report containing information of the audit tests
made on the wind farm shall be drafted.
• The audit shall be performed by an independent party.
• The audit report shall be made available to all the
stakeholders
• The report shall be reviewed and necessary action to
improve the faults found during the tests shall be taken.
Audit Plan
• The wind farm shall be constructed and operated according
to the project plan by starting on time and on budget
• All equipments shall be tested prior to their delivery and
installed according to the accepted engineering rules and
regulations
• A team of experts lead by the Project Quality Manager shall
oversee the quality related to specific aspects of the project
• Internal project reviews, testing and inspection shall be done
on a regular basis before, during and after the completion of
the project.
Process Improvement Plan
• ISO 9001:2008 principles:
1. Customer Focus
2. Leadership
3. Involvement of people
4. Process Approach
5. System Approach to Management
6. Continual improvement
7. Factual Approach to Decision Making
8. Mutually beneficial supplier relationships
Quality Approach
• The wind farm shall be tested for quality according to the
Quality Management System ISO 9001:2008 standards.
• Performance measurements for power shall be made in
order to maintain the efficiency and also to improve the
grid compatibility of the wind farm.
• Unit and integration tests shall be performed.
Quality Testing
Life Cycle
Testing
Tasks
Human Resources Plan
Resource Staffing Plan
Role Authority Responsibility Competency
Project
Manager
Can make decisions at any level of
the project that does not involve
funding or the special interests of
the investor and program manager
Oversee the project’s success
and manage all of the different
components which go into the
project.
Project management
experience
Possible technical
background
Systems
Engineer
Has control over any technical
decisions made; is in charge of
anything having to do with an
engineering component
Coordinate all technical aspects
of the project and properly asses
what engineering needs to be
accomplished to meet the
overarching objectives
Wide range of technical
knowledge
Systems
Analyst
Is in charge of the analysis
component of our Wind Farm;
Assesses the data collected and
works at improving any
inefficiencies
Decision maker when it comes
to specs of equipment and any
analysis that needs to be
completed
Must be someone who
understands the system at a
whole and is able to
understand individual
technical components as
well; involves critical
thinking
Relations
Coordinator
Coordinates all contracts and
outside vendors
In charge of signing off on
contractor agreements and
negotiating schedules; soliciting
pricing for outside vendors
Needs to be organized and
have good communication
and people skills
Project Organization Chart
Communications Plan
Communications Plan
Stakeholders
Frequency of meetings Type of communication
Status
updateWeekly Monthly Yearly Once
In person
meetings
Emails
Memos &
Information
posted on
website
Project
Manager
X X X X
Team
Members
X X X X
General
Electric
X X X X
Department of
Environment
X X X
Department of
Energy
X X X
Town Council
of Simoda, VA
X X X
Communication Plan Continued
Stakeholders
Frequency of meetings Type of communication
Provide
status
update
Weekly Monthly Yearly Once
In person
meetings
Emails
Memos &
Information
posted on
website
Environmentalists X X
Local supply
companies
X X
Local transport
companies
X X
Family members of
Project Manager
Birds and Bats
Department of
Agriculture
X X
Trade Unions X X
Consumers &
Residents
Association
X X
Department of
Aviation
X X
EPA & WWF X
Ecologists in Action X X
Competing
companies
Risk Management Plan
High Risk Items
RISK
Timeframe
Start
Timeframe End I Po (%)Borda Rank R Manage/Mitigate
Insufficient
revenue
29 Nov 2016 29 Nov 2036 Mo 21% 2 MHire outside experts to analyze
alternatives to possiblly increase
revenue
Wind Turbine
Part Failure
07 Jul 2015 29 Nov 2036 Mo 15% 3 MFabricate additional parts/1.5
MW has most available spare
parts
Transmission
of energy
from Turbine
to Substation
is less than
40%
25 Aug 2015 29 Nov 2016 Mo 15% 3 MAssess wind speed for 12 months
prior/ alternate options for
transmitting energy to substation
Running
behind
schedule
04 Apr 2014 29 Nov 2016 Mo 15% 3 MSchedule allows for re-planning/
slight flexibility
Extreme Wind 17 Jul 2015 29 Nov 2016 S 10% 0 MTransferred, Insurance
Bird/Bat
mortality
collisions with
turbine rotos
29 Nov 2016 N/A Mo 10% 9 L MERLIN avian radar detection
system
Lower Risk Items
RISK
Timeframe
Start
Timeframe End I
Po
(%)
Borda Rank R Manage/Mitigate
Personnel Losses 14 Apr 2014 29 Nov 2016 S 10% 0 MStaffing plan in place,
alternate staff identified
Motivation
Decreases with
employees
14 Apr 2014 29 Nov 2016 Mo 8% 11 L Incentive opportunities/
staffing plan in place and
alternate staff identified
Natural Disasters 17 Jul 2015 N/A S 5% 3 MTransferred, Insurance
Wind speed less
than desirable
05 May 2015 N/A S 5% 3 MWind Speed will be re-
assessed at alternate
location for additional 12
months
Noise Complaints 29 Nov 2016 31 Dec 2020 Mo 4% 12 L Budget surplus set aside to
re-locate individuals
Aesthetic
complaints
19 Oct 2016 31 Dec 2020 Mo 3% 13 L Budget surplus set aside to
re-locate individuals
Over budget 04 Apr 2014 29 Nov 2016 S 2% 10 MContract with GE is set at
$300 million, budget will
not go over
GE unable to
fully fund project
07 Jul 2015 29 Nov 2105 C 1% 8 MVestas will be set to take
over project
Procurement Plan
Make or Buy Decision List
Item Make or Buy Company
Wind Turbine Make GE
Wind Energy
Storage
Make GE
Transmission
Lines
Buy WV Electricity
Company
Data Collection
System
Buy Femway
Bat and Bird Radar Buy DeTect, Inc.
Supplier Management Plan
Item Contract and Negotiation Deadline Delivery Date
Wind Turbine April 14, 2014 July 7, 2015
Wind Energy
Storage
July 7, 2015 October 19, 2016
Transmission
Lines
April 14, 2014 July 7, 2015
Data Collection
System
July 7, 2015 December 22,
2015
Bat and Bird
Radar
As Needed
Configuration and
Change Control Plan
Change Control Plan
In order to incorporate any changes, the Project Manager must:
(i) ensure that changes to the project have a strong business
justification.
(ii) monitor and control the cost and other impacts of approved
changes.
(iii) obtain the appropriate level of approval for changes.
(iv) ensure that project changes are understood and that team
members do not begin work on new or unplanned tasks before
change requests are approved.
(v) maintain a clear and accurate record of changes made over the
life of the project
Conclusions
• Simoda, West Virginia
would benefit from a
Wind Farm in their
community
• Wind Energy is
environmentally friendly
and a step towards a
more sustainable future
• General Electric would be
making a good
investment
http://chrismaddencartoons.wordpress.co
m/category/environment/energy-fuel-
power/
References
A Guide to the Project Management Body of Knowledge (PMBOK Guide). Newtown Square, Penn.,
USA: Project Management Institute, 2000. Print.
"Centre for Wind Energy Technology." Centre for Wind Energy Technology. Web. 12 Nov. 2013.
<http://www.cwet.tn.nic.in/html/departments_wtt.html>.
Change Control Plan Preparation Guidelines. Rep. Qatar National Project Management, n.d. Web.
"Frequently Asked Questions." Wind Energy America. Web. 10 Oct. 2013.
<http://www.windenergyamerica.com/faqs.html>.
"GE Energy." GE Energy. Web. 02 Nov. 2013. <http://www.ge-energy.com/wind>.
GE. Web. 8 Nov. 2013. <http://www.ge.com/about-us/building>.
"GE Wind." GE Energy. GE Energy. Web. 22 Sept. 2013. <www.ge-
energy.com/content/multimedia/_files/downloads/wind_energy_basics.pdf>.
"Google Maps." Google Maps. Web. 22 Sept. 2013. <https://maps.google.com/maps?client=safari>.
"How Long Does It Take to Build a Wind Farm?" GWEC. Web. 11 Oct. 2013.
<http://www.gwec.net/faq/how-long-take-build-wind-farm/>.
"Installed Wind Capacity." Wind Powering America: U.S. U.S. Deparment of Energy. Web. 18 Sept.
2013.
Kosmann, William. Google Lunar X Prize Project - Moon Buggy. Rep. Print.
29 May 2008.
Kosmann, Dr. William J. "Quality Management." George Washington University. Lecture.
"Map of West Virginia (Map Population Density)" Map of West Virginia (Map Population Density) :
Worldofmaps.net. Worldofmaps.net, 2010. Web. 22 Sept. 2013.
<http://www.worldofmaps.net/en/north-america/west-virginia-usa/map-population-density-west-
virginia.htm>.
References
Montana. NRDC: Renewable Energy in. Retrieved November 5, 2013, from
http://www.nrdc.org/energy/renewables/montana.asp
"Renewable / Wind Energy Project Management." Renewable / Wind Energy Project
Management. Web. 22 Sept. 2013. <http://www.absconsulting.com/wind-
energy-project-management.cfm>.
“Quality Management Principles.” <http://www.iso.org/iso/qmp_2012.pdf>.
"Quantifying Economic Benefits | State and Local | US EPA." EPA. Environmental
Protection Agency, Web. 02 Nov. 2013.
<http://www.epa.gov/statelocalclimate/state/activities/quantifying-econ.html>.
"U.S. Wind Turbines Kill 1.4 Million Birds and Bats Every Year." Heartlander Magazine.
N.p., n.d. Web. 02 Nov. 2013. <http://news.heartland.org/newspaper-
article/2013/07/24/us-wind-turbines-kill-14-million-birds-and-bats-every-year>.
Vestas - American Wind Technology Inc. Vestas - American Wind Technology. Web.
<http://www1.eere.energy.gov/tribalenergy/guide/pdfs/developingwindpower.pdf>.
"West Virginia’s Wind Projects (Operating and Permitted)." Wind Maps. West Virginia
Commerce. Web. 22 Sept. 2013.
<http://www.wvcommerce.org/energy/renewable_energy/wind.aspx>.
References
"WIND ENERGY BIRD & BAT MORTALITY RISK ASSESSMENT, MONITORING &
MITIGATION SYSTEMS." DeTect, Inc. N.p., n.d. Web. 19 Nov. 2013. <http://detect-
inc.com/wind.html>.
"Wind Energy | Energy and Global Climate Change in New England | US EPA." EPA.
Environmental Protection Agency, Web. 02 Nov. 2013.
<http://www.epa.gov/region1/eco/energy/re-wind.html>.
"Wind Energy System Data Collection and Storage." COMTROL Corp. Web. 18 Nov. 2013.
<http://www.comtrol.com/applications/energy/energy-application-stories/wind-energy-system-
data-collection-and-storage>.
"Wind Farms." 11 Steps to Planning and Building a Wind Farm. Canwea. Web. 22 Sept. 2013.
<http://www.canwea.ca/farms/planning_e.php>.
"Wind Farms Audit." Wind Farms Audit. Web. 12 Nov. 2013.
<http://www.planning.nsw.gov.au/Default.aspx?tabid=574>,
"Wind Turbine Feasibility Report." Scribd. Web. 03 Nov. 2013.
<http://www.scribd.com/doc/29244732/Wind-Turbine-Feasibility-Report>.
"Wind Turbine Testing Facility." Clemson University, South Carolina. Web. 12 Nov. 2013.
<http://www.clemson.edu/facilities/energy-awareness/projects/windturbine.html>.
Zucchino, David. "West Virginia Families See the Dangers of Coal Mining." Los Angeles Times.
Los Angeles Times, 08 Apr. 2010. Web. 02 Nov. 2013.
<http://articles.latimes.com/2010/apr/08/nation/la-na-coal-mine-color8-2010apr08>.

Más contenido relacionado

La actualidad más candente

kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CVkiran kumar Reddy
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Sagar Tilwani
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Wind farm development and operation - A case study
Wind farm development and operation - A case studyWind farm development and operation - A case study
Wind farm development and operation - A case studyLeonardo ENERGY
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectignitetribes
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesSlideTeam
 
Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Daniel X. O'Neil
 
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6p6academy
 
Project Manager CV -Rev
Project Manager CV -RevProject Manager CV -Rev
Project Manager CV -RevThanki M.L
 
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)Sunrator Technologies LLP
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02Mario Fonseca
 

La actualidad más candente (20)

kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CV
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
Wind farm development and operation - A case study
Wind farm development and operation - A case studyWind farm development and operation - A case study
Wind farm development and operation - A case study
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_project
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation Slides
 
Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008
 
Piping Engineer CV
Piping Engineer CVPiping Engineer CV
Piping Engineer CV
 
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
 
Resume for Pipeline Designer
Resume for Pipeline DesignerResume for Pipeline Designer
Resume for Pipeline Designer
 
Project Manager CV -Rev
Project Manager CV -RevProject Manager CV -Rev
Project Manager CV -Rev
 
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 

Destacado

Windstream - Wind Mills of Change
Windstream - Wind Mills of ChangeWindstream - Wind Mills of Change
Windstream - Wind Mills of ChangeKaren Ostromecki
 
Wind Power Point Presentation
Wind Power Point PresentationWind Power Point Presentation
Wind Power Point PresentationKurt Kublbeck
 
9M FY15 Investor Presentation
9M FY15 Investor Presentation9M FY15 Investor Presentation
9M FY15 Investor PresentationSuzlon Group
 
Resource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniquesResource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniquesRemi Roques
 
Critical path method
Critical path methodCritical path method
Critical path methodShubhi Verma
 
Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)S. Ali Hasheminejad
 
Multiple project's management in service industry
Multiple project's management in service industryMultiple project's management in service industry
Multiple project's management in service industrySamit Jain
 
Opportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in IndiaOpportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in India Devesh Gautam
 
Project organization
Project organizationProject organization
Project organizationAbdal Babar
 
Construction of CNG station project final report.
Construction of CNG station project final report.Construction of CNG station project final report.
Construction of CNG station project final report.Hagi Sahib
 
Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Hagi Sahib
 

Destacado (20)

Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Windstream - Wind Mills of Change
Windstream - Wind Mills of ChangeWindstream - Wind Mills of Change
Windstream - Wind Mills of Change
 
Wind Power Point Presentation
Wind Power Point PresentationWind Power Point Presentation
Wind Power Point Presentation
 
9M FY15 Investor Presentation
9M FY15 Investor Presentation9M FY15 Investor Presentation
9M FY15 Investor Presentation
 
Cpm
CpmCpm
Cpm
 
Resource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniquesResource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniques
 
Project Managment Framework
Project Managment FrameworkProject Managment Framework
Project Managment Framework
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)
 
Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015Wind Energy - Make In India, 2015
Wind Energy - Make In India, 2015
 
Multiple project's management in service industry
Multiple project's management in service industryMultiple project's management in service industry
Multiple project's management in service industry
 
Opportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in IndiaOpportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in India
 
Project organization
Project organizationProject organization
Project organization
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Project charter j
Project charter jProject charter j
Project charter j
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Construction of CNG station project final report.
Construction of CNG station project final report.Construction of CNG station project final report.
Construction of CNG station project final report.
 
Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.Construction & esstablishment of cattle farm project report.
Construction & esstablishment of cattle farm project report.
 

Similar a Project management

Artificial intelligence based smart building Updated.pptx
Artificial intelligence based smart building Updated.pptxArtificial intelligence based smart building Updated.pptx
Artificial intelligence based smart building Updated.pptxIzukuMidoriya131438
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
Resume (Umar AKbar)
Resume (Umar AKbar)Resume (Umar AKbar)
Resume (Umar AKbar)Umar Akbar
 
Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq Ahmad
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONmaheshvkat1972
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02jitendra kumar biswas
 
Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial reportChirag Jain
 
Session 17 project management & monitoring
Session 17   project management & monitoringSession 17   project management & monitoring
Session 17 project management & monitoringChirag Jain
 

Similar a Project management (20)

Artificial intelligence based smart building Updated.pptx
Artificial intelligence based smart building Updated.pptxArtificial intelligence based smart building Updated.pptx
Artificial intelligence based smart building Updated.pptx
 
Mari cv - office
Mari cv - officeMari cv - office
Mari cv - office
 
Adil Mansoor
Adil MansoorAdil Mansoor
Adil Mansoor
 
영문=10mw. fiji
영문=10mw. fiji영문=10mw. fiji
영문=10mw. fiji
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Resume (Umar AKbar)
Resume (Umar AKbar)Resume (Umar AKbar)
Resume (Umar AKbar)
 
Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)
 
Topic 1.ppt
Topic 1.pptTopic 1.ppt
Topic 1.ppt
 
CV
CVCV
CV
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
R.Kumar
R.KumarR.Kumar
R.Kumar
 
Samrat Khanorkar_Resume
Samrat Khanorkar_ResumeSamrat Khanorkar_Resume
Samrat Khanorkar_Resume
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
 
Ravi CV 2016
Ravi CV 2016Ravi CV 2016
Ravi CV 2016
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Session 21 preparation of techno commercial report
Session 21   preparation of techno commercial reportSession 21   preparation of techno commercial report
Session 21 preparation of techno commercial report
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05
 
Session 17 project management & monitoring
Session 17   project management & monitoringSession 17   project management & monitoring
Session 17 project management & monitoring
 
Gensol Lender's Engineer Services
Gensol Lender's Engineer ServicesGensol Lender's Engineer Services
Gensol Lender's Engineer Services
 

Último

PeerPreneur Straight Up Care Marketing 101
PeerPreneur Straight Up Care Marketing 101PeerPreneur Straight Up Care Marketing 101
PeerPreneur Straight Up Care Marketing 101mlicam615
 
Create A Workspace For Work From Home 1.pptx
Create A Workspace For Work From Home 1.pptxCreate A Workspace For Work From Home 1.pptx
Create A Workspace For Work From Home 1.pptxVanishasNews
 
Obersation Lab for understanding the customer.
Obersation Lab for understanding the customer.Obersation Lab for understanding the customer.
Obersation Lab for understanding the customer.ThomasWoart1
 
TRMNL4. StartUp Academy by Genesis and Meta.pdf
TRMNL4. StartUp Academy by Genesis and Meta.pdfTRMNL4. StartUp Academy by Genesis and Meta.pdf
TRMNL4. StartUp Academy by Genesis and Meta.pdfStartup Grind
 
data flow diagram for e commerce website
data flow diagram for e commerce websitedata flow diagram for e commerce website
data flow diagram for e commerce website33073
 
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptx
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptxDriving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptx
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptxPraloy Chowdhury
 
Introduction-to-United-States-Business-Registration
Introduction-to-United-States-Business-RegistrationIntroduction-to-United-States-Business-Registration
Introduction-to-United-States-Business-RegistrationUSBRI
 

Último (7)

PeerPreneur Straight Up Care Marketing 101
PeerPreneur Straight Up Care Marketing 101PeerPreneur Straight Up Care Marketing 101
PeerPreneur Straight Up Care Marketing 101
 
Create A Workspace For Work From Home 1.pptx
Create A Workspace For Work From Home 1.pptxCreate A Workspace For Work From Home 1.pptx
Create A Workspace For Work From Home 1.pptx
 
Obersation Lab for understanding the customer.
Obersation Lab for understanding the customer.Obersation Lab for understanding the customer.
Obersation Lab for understanding the customer.
 
TRMNL4. StartUp Academy by Genesis and Meta.pdf
TRMNL4. StartUp Academy by Genesis and Meta.pdfTRMNL4. StartUp Academy by Genesis and Meta.pdf
TRMNL4. StartUp Academy by Genesis and Meta.pdf
 
data flow diagram for e commerce website
data flow diagram for e commerce websitedata flow diagram for e commerce website
data flow diagram for e commerce website
 
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptx
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptxDriving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptx
Driving Bangladesh's Growth: Demand Soars for Quality Supply Chain Managers.pptx
 
Introduction-to-United-States-Business-Registration
Introduction-to-United-States-Business-RegistrationIntroduction-to-United-States-Business-Registration
Introduction-to-United-States-Business-Registration
 

Project management

  • 1. Project Team: Madeleine Brannon, Srija, Alexander Brill, Maithili Gaddam
  • 2. Agenda 1. Background 2. Scope Plan Stakeholders Work Breakdown Structure Top Level Requirements 3. Schedule Plan Schedule Performance Baseline Milestone List PERT Chart 4. Cost Plan Cost Performance Baseline 5. Quality Plan Audit Plan Process Improvement Plan 6. Human Resources Plan Resource Staffing Plan Project Organization Chart 7. Communication Plan Stakeholder Analysis Matrix 8. Risk Plan Risk Matrix 9. Procurement Plan Make or Buy Decisions Supplier Management Plan 10. Configuration Management Plan 11. Change Control Plan 12. Conclusion
  • 3. Background • Create a Wind Farm in Simoda, West Virginia • 100 1.5 MW wind turbines • Clean energy is produced from wind turbines and made into electricity • Simoda, West Virginia has the potential to create a new sustainable industry http://exploringgreentechnology.com/wind-energy/how-does- wind-energy-work/
  • 5. Scope of the Project • Not concerned with where specifically the electricity goes • The construction details are assumed to be worked out by the construction company
  • 8. Assessment Requirements Requirement Identifier Key Project Designator WF = Wind Farm WT = Wind Turbine Objective Designator A = Assessment P = Performance Requirement or Verification Type C = Component E = Energy L = Location Requirement or Verification Designator R = Requirement Req. # Req. Identifier Requirement Description 1 WT-PE-R01 The Wind Turbines shall produce energy harnessed for electricity. 2 WF-AL-R01 Simoda, West Virginia shall be assessed for the Wind Farm. 10 WF-AL-R02 The Wind Farm shall be located in Simoda, West Virginia. 11 WF-AC-R01 The Wind Farm shall be funded by General Electric (GE).
  • 9. Construction Requirements Req. # Req. Identifier Requirement Description 3 WT-DC-R01 The Wind Turbine base shall be constructed. 4 WT-DC-R02 The Wind Turbines shall connect to the power grid. 5 WT-DC-R03 The Wind Turbines shall have a maximum tip height of 120 meters. Requirement Identifier Key Project Designator WF = Wind Farm WT = Wind Turbine Objective Designator D = Design Requirement or Verification Type C = Component Requirement or Verification Designator R = Requirement
  • 10. Operation Requirements Requirement Identifier Key Project Designator WF = Wind Farm WT = Wind Turbine Objective Designator M = Maintenance P = Performance Requirement or Verification Type C = Component E = Energy W = Power Requirement or Verification Designator R = Requirement Req. # Req. Identifier Requirement Description 6 WT-PW-R01 The Wind Turbines shall transmit power to a power station. 7 WT-PW-R02 The Wind Turbines shall produce a minimum of 80-megawatt hour. 8 WT-PE-R02 The Wind Turbines shall be operable continuously. 9 WF-MC-R01 The Wind Farm shall be monitored on a regular basis.
  • 12. Task Name Duration Start Finish 1 Assesment 321 days Mon 4/14/14 Mon 7/6/15 2 Location Selection 15 days Mon 4/14/14 Fri 5/2/14 3 Wind Resource Measurements 262 days Mon 5/5/14 Tue 5/5/15 4 Enviornmental Consultants 14 days Wed 5/6/15 Mon 5/25/15 5 Legal Documentation 30 days Tue 5/26/15 Mon 7/6/15 6 Construction 337 days Tue 7/7/15 Wed 10/19/16 7 Clearing the Area 60 days Tue 7/7/15 Mon 9/28/15 8 Creating a Base 30 days Tue 9/29/15 Mon 11/9/15 9 Wiring Turbines 30 days Tue 11/10/15 Mon 12/21/15 0 Installing Turbines 217 days Tue 12/22/15 Wed 10/19/16 1 Wind Farm Components 380 days Tue 7/7/15 Mon 12/19/16 2 Access roads 52 days Tue 7/7/15 Wed 9/16/15 3 Build Substation 54 days Tue 7/7/15 Fri 9/18/15 4 Electrical Wiring 43 days Thu 10/20/16 Mon 12/19/16 5 Transmission Lines 36 days Tue 7/7/15 Tue 8/25/15 6 Operation 29 days Thu 10/20/16 Tue 11/29/16 7 Hiring Maintenance 14 days Thu 10/20/16 Tue 11/8/16 8 Test and Evaluation 29 days Thu 10/20/16 Tue 11/29/16 9 5/26 8/25 11/24 2/23 5/25 8/24 11/23 2/22 5/24 8/23 11/22 2/21 5/22 8/21 11/20 2/19 5/ January 11 July 21 February 1 August 11 February 21 September 1March 11 September 21April Task Split Milestone Summary Project Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Deadline Baseline Baseline Milestone Baseline Summary Progress oject: Gantt Chart ate: Sun 11/17/13
  • 13. Milestone List • Acquire the land in Simoda, West Virginia • Analyze the data required for the one year assessment phase and verify the project’s location • Get contracts from the relevant supply and transport companies • Installment of wind turbine • Wiring the turbines and building the substation • Integration testing i.e. checking if the energy being transmitted from the wind turbine is being received by the substation
  • 16. Wind Farm Cost • 1.5 MW turbine chosen • High Efficiency • Most widely used • $3 Million/Wind Turbine installed • 100 turbines = 150 MW • $300 Million for wind farm
  • 17. Project Team Budget Category Hourly Labor Rate Hours Personnel Totals 8 Technicians $ 25.00 5200 $ 389,028.21 Project Manager $ 150 700 $ 312,599.71 Environmental Engineer $ 38 400 $ 45,252.53 2 Analyst $ 32 700 $ 66,687.94 2 Construction Manager $ 125 700 $ 260,499.76 7700 $ 25,000.00 Project Subtotals $ 1,103,388.15
  • 20. • The Wind Farm shall be assessed to check whether it is operating in compliance with the specified requirements. • An audit report containing information of the audit tests made on the wind farm shall be drafted. • The audit shall be performed by an independent party. • The audit report shall be made available to all the stakeholders • The report shall be reviewed and necessary action to improve the faults found during the tests shall be taken. Audit Plan
  • 21. • The wind farm shall be constructed and operated according to the project plan by starting on time and on budget • All equipments shall be tested prior to their delivery and installed according to the accepted engineering rules and regulations • A team of experts lead by the Project Quality Manager shall oversee the quality related to specific aspects of the project • Internal project reviews, testing and inspection shall be done on a regular basis before, during and after the completion of the project. Process Improvement Plan
  • 22. • ISO 9001:2008 principles: 1. Customer Focus 2. Leadership 3. Involvement of people 4. Process Approach 5. System Approach to Management 6. Continual improvement 7. Factual Approach to Decision Making 8. Mutually beneficial supplier relationships Quality Approach
  • 23. • The wind farm shall be tested for quality according to the Quality Management System ISO 9001:2008 standards. • Performance measurements for power shall be made in order to maintain the efficiency and also to improve the grid compatibility of the wind farm. • Unit and integration tests shall be performed. Quality Testing
  • 26. Resource Staffing Plan Role Authority Responsibility Competency Project Manager Can make decisions at any level of the project that does not involve funding or the special interests of the investor and program manager Oversee the project’s success and manage all of the different components which go into the project. Project management experience Possible technical background Systems Engineer Has control over any technical decisions made; is in charge of anything having to do with an engineering component Coordinate all technical aspects of the project and properly asses what engineering needs to be accomplished to meet the overarching objectives Wide range of technical knowledge Systems Analyst Is in charge of the analysis component of our Wind Farm; Assesses the data collected and works at improving any inefficiencies Decision maker when it comes to specs of equipment and any analysis that needs to be completed Must be someone who understands the system at a whole and is able to understand individual technical components as well; involves critical thinking Relations Coordinator Coordinates all contracts and outside vendors In charge of signing off on contractor agreements and negotiating schedules; soliciting pricing for outside vendors Needs to be organized and have good communication and people skills
  • 29. Communications Plan Stakeholders Frequency of meetings Type of communication Status updateWeekly Monthly Yearly Once In person meetings Emails Memos & Information posted on website Project Manager X X X X Team Members X X X X General Electric X X X X Department of Environment X X X Department of Energy X X X Town Council of Simoda, VA X X X
  • 30. Communication Plan Continued Stakeholders Frequency of meetings Type of communication Provide status update Weekly Monthly Yearly Once In person meetings Emails Memos & Information posted on website Environmentalists X X Local supply companies X X Local transport companies X X Family members of Project Manager Birds and Bats Department of Agriculture X X Trade Unions X X Consumers & Residents Association X X Department of Aviation X X EPA & WWF X Ecologists in Action X X Competing companies
  • 32. High Risk Items RISK Timeframe Start Timeframe End I Po (%)Borda Rank R Manage/Mitigate Insufficient revenue 29 Nov 2016 29 Nov 2036 Mo 21% 2 MHire outside experts to analyze alternatives to possiblly increase revenue Wind Turbine Part Failure 07 Jul 2015 29 Nov 2036 Mo 15% 3 MFabricate additional parts/1.5 MW has most available spare parts Transmission of energy from Turbine to Substation is less than 40% 25 Aug 2015 29 Nov 2016 Mo 15% 3 MAssess wind speed for 12 months prior/ alternate options for transmitting energy to substation Running behind schedule 04 Apr 2014 29 Nov 2016 Mo 15% 3 MSchedule allows for re-planning/ slight flexibility Extreme Wind 17 Jul 2015 29 Nov 2016 S 10% 0 MTransferred, Insurance Bird/Bat mortality collisions with turbine rotos 29 Nov 2016 N/A Mo 10% 9 L MERLIN avian radar detection system
  • 33. Lower Risk Items RISK Timeframe Start Timeframe End I Po (%) Borda Rank R Manage/Mitigate Personnel Losses 14 Apr 2014 29 Nov 2016 S 10% 0 MStaffing plan in place, alternate staff identified Motivation Decreases with employees 14 Apr 2014 29 Nov 2016 Mo 8% 11 L Incentive opportunities/ staffing plan in place and alternate staff identified Natural Disasters 17 Jul 2015 N/A S 5% 3 MTransferred, Insurance Wind speed less than desirable 05 May 2015 N/A S 5% 3 MWind Speed will be re- assessed at alternate location for additional 12 months Noise Complaints 29 Nov 2016 31 Dec 2020 Mo 4% 12 L Budget surplus set aside to re-locate individuals Aesthetic complaints 19 Oct 2016 31 Dec 2020 Mo 3% 13 L Budget surplus set aside to re-locate individuals Over budget 04 Apr 2014 29 Nov 2016 S 2% 10 MContract with GE is set at $300 million, budget will not go over GE unable to fully fund project 07 Jul 2015 29 Nov 2105 C 1% 8 MVestas will be set to take over project
  • 35. Make or Buy Decision List Item Make or Buy Company Wind Turbine Make GE Wind Energy Storage Make GE Transmission Lines Buy WV Electricity Company Data Collection System Buy Femway Bat and Bird Radar Buy DeTect, Inc.
  • 36. Supplier Management Plan Item Contract and Negotiation Deadline Delivery Date Wind Turbine April 14, 2014 July 7, 2015 Wind Energy Storage July 7, 2015 October 19, 2016 Transmission Lines April 14, 2014 July 7, 2015 Data Collection System July 7, 2015 December 22, 2015 Bat and Bird Radar As Needed
  • 38. Change Control Plan In order to incorporate any changes, the Project Manager must: (i) ensure that changes to the project have a strong business justification. (ii) monitor and control the cost and other impacts of approved changes. (iii) obtain the appropriate level of approval for changes. (iv) ensure that project changes are understood and that team members do not begin work on new or unplanned tasks before change requests are approved. (v) maintain a clear and accurate record of changes made over the life of the project
  • 39. Conclusions • Simoda, West Virginia would benefit from a Wind Farm in their community • Wind Energy is environmentally friendly and a step towards a more sustainable future • General Electric would be making a good investment http://chrismaddencartoons.wordpress.co m/category/environment/energy-fuel- power/
  • 40. References A Guide to the Project Management Body of Knowledge (PMBOK Guide). Newtown Square, Penn., USA: Project Management Institute, 2000. Print. "Centre for Wind Energy Technology." Centre for Wind Energy Technology. Web. 12 Nov. 2013. <http://www.cwet.tn.nic.in/html/departments_wtt.html>. Change Control Plan Preparation Guidelines. Rep. Qatar National Project Management, n.d. Web. "Frequently Asked Questions." Wind Energy America. Web. 10 Oct. 2013. <http://www.windenergyamerica.com/faqs.html>. "GE Energy." GE Energy. Web. 02 Nov. 2013. <http://www.ge-energy.com/wind>. GE. Web. 8 Nov. 2013. <http://www.ge.com/about-us/building>. "GE Wind." GE Energy. GE Energy. Web. 22 Sept. 2013. <www.ge- energy.com/content/multimedia/_files/downloads/wind_energy_basics.pdf>. "Google Maps." Google Maps. Web. 22 Sept. 2013. <https://maps.google.com/maps?client=safari>. "How Long Does It Take to Build a Wind Farm?" GWEC. Web. 11 Oct. 2013. <http://www.gwec.net/faq/how-long-take-build-wind-farm/>. "Installed Wind Capacity." Wind Powering America: U.S. U.S. Deparment of Energy. Web. 18 Sept. 2013. Kosmann, William. Google Lunar X Prize Project - Moon Buggy. Rep. Print. 29 May 2008. Kosmann, Dr. William J. "Quality Management." George Washington University. Lecture. "Map of West Virginia (Map Population Density)" Map of West Virginia (Map Population Density) : Worldofmaps.net. Worldofmaps.net, 2010. Web. 22 Sept. 2013. <http://www.worldofmaps.net/en/north-america/west-virginia-usa/map-population-density-west- virginia.htm>.
  • 41. References Montana. NRDC: Renewable Energy in. Retrieved November 5, 2013, from http://www.nrdc.org/energy/renewables/montana.asp "Renewable / Wind Energy Project Management." Renewable / Wind Energy Project Management. Web. 22 Sept. 2013. <http://www.absconsulting.com/wind- energy-project-management.cfm>. “Quality Management Principles.” <http://www.iso.org/iso/qmp_2012.pdf>. "Quantifying Economic Benefits | State and Local | US EPA." EPA. Environmental Protection Agency, Web. 02 Nov. 2013. <http://www.epa.gov/statelocalclimate/state/activities/quantifying-econ.html>. "U.S. Wind Turbines Kill 1.4 Million Birds and Bats Every Year." Heartlander Magazine. N.p., n.d. Web. 02 Nov. 2013. <http://news.heartland.org/newspaper- article/2013/07/24/us-wind-turbines-kill-14-million-birds-and-bats-every-year>. Vestas - American Wind Technology Inc. Vestas - American Wind Technology. Web. <http://www1.eere.energy.gov/tribalenergy/guide/pdfs/developingwindpower.pdf>. "West Virginia’s Wind Projects (Operating and Permitted)." Wind Maps. West Virginia Commerce. Web. 22 Sept. 2013. <http://www.wvcommerce.org/energy/renewable_energy/wind.aspx>.
  • 42. References "WIND ENERGY BIRD & BAT MORTALITY RISK ASSESSMENT, MONITORING & MITIGATION SYSTEMS." DeTect, Inc. N.p., n.d. Web. 19 Nov. 2013. <http://detect- inc.com/wind.html>. "Wind Energy | Energy and Global Climate Change in New England | US EPA." EPA. Environmental Protection Agency, Web. 02 Nov. 2013. <http://www.epa.gov/region1/eco/energy/re-wind.html>. "Wind Energy System Data Collection and Storage." COMTROL Corp. Web. 18 Nov. 2013. <http://www.comtrol.com/applications/energy/energy-application-stories/wind-energy-system- data-collection-and-storage>. "Wind Farms." 11 Steps to Planning and Building a Wind Farm. Canwea. Web. 22 Sept. 2013. <http://www.canwea.ca/farms/planning_e.php>. "Wind Farms Audit." Wind Farms Audit. Web. 12 Nov. 2013. <http://www.planning.nsw.gov.au/Default.aspx?tabid=574>, "Wind Turbine Feasibility Report." Scribd. Web. 03 Nov. 2013. <http://www.scribd.com/doc/29244732/Wind-Turbine-Feasibility-Report>. "Wind Turbine Testing Facility." Clemson University, South Carolina. Web. 12 Nov. 2013. <http://www.clemson.edu/facilities/energy-awareness/projects/windturbine.html>. Zucchino, David. "West Virginia Families See the Dangers of Coal Mining." Los Angeles Times. Los Angeles Times, 08 Apr. 2010. Web. 02 Nov. 2013. <http://articles.latimes.com/2010/apr/08/nation/la-na-coal-mine-color8-2010apr08>.