๏‚— Construction of Guide Wall along the periphery of Diaphragm wall.
๏‚— Boring of Diaphragm wall.
๏‚— Cutting/bending and Trading of reinforcement Steel, fixing of diaphragm
wall reinforcement cage & Cage Lowering.
๏‚— Concreting of Diaphragm wall.
๏‚— Anchor Preparation
๏‚— Anchoring to the Diaphragm Wall
๏‚— Stepwise Excavation for Basement .
๏‚— Dewatering..
Construction sequence to be adopted at site
Complete Construction Sequences of Diaphragm wall
๏‚— Construction of Guide Wall along the periphery of Diaphragm wall.
๏‚— The RCC guide walls shall be constructed as per the dimensions and with reinforcement as shown in
the drawing.
๏‚— Guide wall shall be 250 mm thick and 1.50m depth and made of reinforced concrete, and shall
represent the reference lines.
๏‚— Minimum clearance between finished diaphragm wall and guide shall be 25-50 mm.
๏‚— The finished faces of the guide walls towards the trench shall be vertical.
๏‚— Guide wall after construction should be suitably propped to maintain specified tolerance.
๏‚— The level of Polymer slurry in the trench shall not less than 1 m from the top of Guide wall.
๏‚— Guide wall get support from adjoining panels and therefore, their construction should be done
continuously.
๏‚— These guide walls stabilize the soil in the upper diaphragm level and provide a stable guide-way for
the grab.
Methodology to be adopted at site
Marking of Survey Reference for Guide Wall
Boring of Diaphragm wall.
Boring operation shall be started by using hydraulic/ mechanical grab in
sequential manner as per shape. First two Cut shall be extreme end of diaphragm
wall. 3rd cut shall be middle portion Diaphragm wall . Polymer slurry is used to
protect the sides of the soil. The slurry will produce a great lateral pressure
sufficient enough to retain the vertical soil.
Polymer Slurry Preparation:- Tanks of suitable sizes and slurry pump of suitable
capacity for storage. Mixing and circulation of Polymer Slurry at site. A separate
pump may be used for water supply to slurry tank. Equipment for sampling the
slurry from trenches and testing its concentrations, viscosity, pH value & hardness
of ground water in which the Polymer slurry and concrete are prepared.
๏‚— Boring of Diaphragm wall (Cont..)
๏‚— Joining for the diaphragm wall panel โ€“ Diaphragm wall cannot be constructed
continually for a very long section due to limitation and size of the mechanical
plant. The wall is usually constructed in alternative section. First panel is called
as primary panel in which two stop end will be placed at the ends of the
excavated trench before concreting. The stop ends are withdrawn at the same
time of concreting so that a groove can be formed. Wall sections are formed
alternatively leaving an intermediate section in between. The in-between
sections are built similarly afterward but without the stop end. At the end a
continual diaphragm wall is constructed with the panel sections tightly joined
by the groove.
1 st Panel
Panel progress Sequence Panel progress Sequence
Schematic drawing of Boring activity of Diaphragm
wall
Hydraulic Grab
Boring
(Stage 1)
Boring
(Stage 2)
Boring
(Stage 3)
Boring for Diaphragm Wall with Hydraulic HR-180 Rig
Boring for Diaphragm Wall
๏‚— Verticality check for Boring of Diaphragm wall:-
๏‚— Ultrasonic Instrument called Koden, shall be used for verticality check
of Bored diaphragm wall panels.
๏‚— The Deviation of the bore trench from the perpendicular and any
surface cavities in the bore hole or trench wall shall be measured.
๏‚— The ultrasonic measurement probe is suspended vertically from a cable
and lowered into the object to be surveyed.
๏‚— At the same time, orthogonal waves are continuously emitted from the
device and reflected from the walls.
๏‚— The reflected waves are registered by measurement sensors. The
distances, calculated as a function of wave speed and reflection time,
are presented in graphic form.
Verticality Checking with KODEN
๏‚— Reinforcement Fabrication for Diaphragm Panels:-
๏‚— Steel cutting , bending & fixing shall be done as per drawing. Proper laps, Dowels
shall be insure while fixing of cage.
๏‚— If required extra reinforcement shall be adequately provided fixed to avoid
displacement and to maintain minimum specified cover during concreting.
๏‚— Concrete Cover blocks shall be circular and tied to rebar cage at regular interval
๏‚— Welding shall be provided to avoid displacement while shifting, lifting & lowering.
๏‚— After ensuring the welding & safety checklist of entire cage, cage shall be lifted
with the help of cranes.
๏‚— Lifted diaphragm wall cage shall be lowered in bored trench of diaphragm wall.
๏‚— Cage shall be rest with help of resting bars on the guide wall.
ITD Cem
๏‚— Concreting of Diaphragm wall.
๏‚— Concreting:-Concreting shall be done by tremmie method
๏‚— Tremmie pipes shall be clean, watertight & with a minimum internal diameter of 200 mm
๏‚— Tremmie shall be lowered up to the bottom of the trench through the slurry column.
๏‚— After lowering tremmie the hopper will be fixed on the top of tremmie pipe & plug will be
placed bottom of hopper, after plugging the hopper will fill with concrete up to the top of
hopper then the tremmie pipe shall be raised slowly and remove the plug from hopper so
that concrete in a single continuous flow.
๏‚— Care shall be taken so that bottom end of tremmie pipe remains immerse at least 1.5 m below
in concrete during casting. Concrete shall be continued till the overflow at least 0.6 m over the
cutoff level of the Diaphragm Wall as shown on the drawing. Once concreting is started it
shall be continued without break. The permissible time gap between consecutive shall be so
adjusted that on initial setting of concrete takes place before it reaches its final position.
During concreting, continuous raising and removal of segments of tremmie pipes shall be
ensured.
๏‚— After reaching concrete its initial setting time, Stop end pipe shall be removed from the bore
and boring for secondary panel shall be started.
Removing of Stoppend by
Hydraulic Jack System
Removing of Stoppend by
Hydraulic Jack System.
Anchoring
๏‚— Sequence of Anchoring
๏‚— Setting of Drill Rig at Location and Align
๏‚— Driving Casing into Overburdens and Drilling for Fixed Length
๏‚— Initial Grouting of Drilled Holes
๏‚— Redrilling of Grouted Holes
๏‚— Water Testing of Redrilled Holes
๏‚— Fabrication of Cables
๏‚— Homing of Cable into the Drilled Hole and Fixed Length Grouting
๏‚— Stressing of Cable
๏‚— Grout the free length Portion
๏‚— Cutting extra Length of Strand and Concreting the Pocket
Setting of Drill Rig at Location and Align
๏‚— Suitable rig is shifted to the anchor location and the rig is positioned to drill a
selected hole .
Driving the Casing into Overburden and Drilling for
Fixed Length
๏‚— After the rig is positioned and aligned, drilling is taken up. Drilling of 150 mm dia.
hole in silty sand / clay shall be carried out by Rotary Percussive DTH system or
simultaneous casing driven method.
๏‚— After fixing the casing in overburden, further drilling shall be continued by rotary
percussive by using DTH. As soon as drilling reaches its desired depth, the drill tubes
shall be withdrawn from the hole and machine shall be shifted to next location.
Initial Grouting of drilled holes
๏‚— The drilled holes shall be pressure grouted with neat cement grout to fill the voids,
joints, fissures etc around the anchor hole and to reduce the permeability.
๏‚— Single packer with mechanically expanded rubber ring shall be fixed at the collar of
the hole. The minimum diameter of the grout intake pipe shall be 25mm. An
assembly with grout intake, bleeder valve, pressure gauge with gauge saver shall be
fixed on to the packer for grouting.
๏‚— The hole shall be taken for grouting and shall be grouted to refusal at required
pressure as detailed in the subsequent paras.
๏‚— After grouting is completed the packer is removed only after ensuring that there is
no back flow of grout from the hole.
Fabrication of Cable
The cable shall be fabricated using required calculated number of HT strands of 15.2 mm dia. with UTS as
per BS 8081: 1989.
๏‚— The HT strand shall be cut to required length.
๏‚— Bond length of the cable shall be cleaned and applied with two coats of epoxy and quartz sand shall be
sprinkled when the second coat is tacky to increase the bond strength.
๏‚— Free length shall be cleaned thoroughly and shall be applied with two coats of epoxy based paint.
๏‚— Cable shall be tied with GI binding wire by providing the MS spacer at regular interval to space the strand
in equidistance and in the bottom MS cap shall be provided.
๏‚— After tied up the cable, the HDPE duct shall be encased and plug the upper and bottom end so
that grout will not be leaked out.
๏‚— Free length, HDPE pipe (plain sheath) shall be encased to individual strand pushed with grease
and plugged the lower end with suitable PVC tape so that while grouting the bond length grout
will not be entered into the duct. After encasing the duct to the tendons, shall be tied with
providing spacer at 2.0 m C/c.
HT Strand Cut at Required Length
Application of Sand and Quartz
Fixing of Spacer , Grout Pipe, &
Tieng with GI wire
HDPE Ducting

More Related Content

What's hot

Chapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsChapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsMohsin Siddique
ย 
River engineering
River engineeringRiver engineering
River engineeringSandra4Smiley
ย 
Pile foundations
Pile foundationsPile foundations
Pile foundationsSameer Thaiyam
ย 
DESIGN OF CANAL REGULATOR USING HTML
DESIGN OF CANAL REGULATOR USING HTMLDESIGN OF CANAL REGULATOR USING HTML
DESIGN OF CANAL REGULATOR USING HTMLS.m. Kumar
ย 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipatorsRahul Gupta
ย 
Dam outlet works lecture 2
Dam outlet works lecture 2Dam outlet works lecture 2
Dam outlet works lecture 2Vidhi Khokhani
ย 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methodsHalim Rahman
ย 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGEAbhinay Saraswat
ย 
Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Bilal Mirani
ย 
weir & barrage
weir & barrageweir & barrage
weir & barrageRaj Daxini
ย 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningRamanuj Jaldhari
ย 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysisAna Debbarma
ย 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateHarish Mahavar
ย 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance systemmarif tahayy
ย 
Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)Shekh Muhsen Uddin Ahmed
ย 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
ย 

What's hot (20)

Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
ย 
Chapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsChapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipators
ย 
River engineering
River engineeringRiver engineering
River engineering
ย 
Pile foundations
Pile foundationsPile foundations
Pile foundations
ย 
Regulation Works
Regulation WorksRegulation Works
Regulation Works
ย 
DESIGN OF CANAL REGULATOR USING HTML
DESIGN OF CANAL REGULATOR USING HTMLDESIGN OF CANAL REGULATOR USING HTML
DESIGN OF CANAL REGULATOR USING HTML
ย 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipators
ย 
Dam outlet works lecture 2
Dam outlet works lecture 2Dam outlet works lecture 2
Dam outlet works lecture 2
ย 
PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
ย 
Canal design
Canal designCanal design
Canal design
ย 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
ย 
Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Design of stilling basin and roughness devices
Design of stilling basin and roughness devices
ย 
weir & barrage
weir & barrageweir & barrage
weir & barrage
ย 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
ย 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysis
ย 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimate
ย 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance system
ย 
Under Ground water tank design including estimation and costing
Under Ground  water tank design including estimation and costingUnder Ground  water tank design including estimation and costing
Under Ground water tank design including estimation and costing
ย 
Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)
ย 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
ย 

Similar to Construction Sequence.pptx

CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksKumarS250747
ย 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationKumarS250747
ย 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
ย 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptxErLavKushPrasad
ย 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
ย 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnelsHimanshu Batra
ย 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
ย 
Board pile method
Board pile methodBoard pile method
Board pile methodDharmendra Kumar
ย 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
ย 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
ย 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer lineRAMPRASAD KUMAWAT
ย 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
ย 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wallGhanashyam Prajapati
ย 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxHirenThakkar31
ย 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
ย 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationIshwar Chauhan
ย 

Similar to Construction Sequence.pptx (20)

CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
ย 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
ย 
Method Statement D Wall
Method Statement D WallMethod Statement D Wall
Method Statement D Wall
ย 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
ย 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ย 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
ย 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
ย 
mbl
mblmbl
mbl
ย 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
ย 
Board pile method
Board pile methodBoard pile method
Board pile method
ย 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
ย 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
ย 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
ย 
Anantpur Report
Anantpur ReportAnantpur Report
Anantpur Report
ย 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
ย 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
ย 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
ย 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
ย 
sample.pptx
sample.pptxsample.pptx
sample.pptx
ย 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
ย 

Recently uploaded

NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .DerechoLaboralIndivi
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
ย 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoordharasingh5698
ย 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
ย 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
ย 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
ย 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
ย 

Recently uploaded (20)

NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
ย 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
ย 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
ย 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
ย 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ย 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
ย 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
ย 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
ย 

Construction Sequence.pptx

  • 1.
  • 2. ๏‚— Construction of Guide Wall along the periphery of Diaphragm wall. ๏‚— Boring of Diaphragm wall. ๏‚— Cutting/bending and Trading of reinforcement Steel, fixing of diaphragm wall reinforcement cage & Cage Lowering. ๏‚— Concreting of Diaphragm wall. ๏‚— Anchor Preparation ๏‚— Anchoring to the Diaphragm Wall ๏‚— Stepwise Excavation for Basement . ๏‚— Dewatering.. Construction sequence to be adopted at site
  • 4. ๏‚— Construction of Guide Wall along the periphery of Diaphragm wall. ๏‚— The RCC guide walls shall be constructed as per the dimensions and with reinforcement as shown in the drawing. ๏‚— Guide wall shall be 250 mm thick and 1.50m depth and made of reinforced concrete, and shall represent the reference lines. ๏‚— Minimum clearance between finished diaphragm wall and guide shall be 25-50 mm. ๏‚— The finished faces of the guide walls towards the trench shall be vertical. ๏‚— Guide wall after construction should be suitably propped to maintain specified tolerance. ๏‚— The level of Polymer slurry in the trench shall not less than 1 m from the top of Guide wall. ๏‚— Guide wall get support from adjoining panels and therefore, their construction should be done continuously. ๏‚— These guide walls stabilize the soil in the upper diaphragm level and provide a stable guide-way for the grab. Methodology to be adopted at site
  • 5. Marking of Survey Reference for Guide Wall
  • 6.
  • 7.
  • 8. Boring of Diaphragm wall. Boring operation shall be started by using hydraulic/ mechanical grab in sequential manner as per shape. First two Cut shall be extreme end of diaphragm wall. 3rd cut shall be middle portion Diaphragm wall . Polymer slurry is used to protect the sides of the soil. The slurry will produce a great lateral pressure sufficient enough to retain the vertical soil. Polymer Slurry Preparation:- Tanks of suitable sizes and slurry pump of suitable capacity for storage. Mixing and circulation of Polymer Slurry at site. A separate pump may be used for water supply to slurry tank. Equipment for sampling the slurry from trenches and testing its concentrations, viscosity, pH value & hardness of ground water in which the Polymer slurry and concrete are prepared.
  • 9.
  • 10. ๏‚— Boring of Diaphragm wall (Cont..) ๏‚— Joining for the diaphragm wall panel โ€“ Diaphragm wall cannot be constructed continually for a very long section due to limitation and size of the mechanical plant. The wall is usually constructed in alternative section. First panel is called as primary panel in which two stop end will be placed at the ends of the excavated trench before concreting. The stop ends are withdrawn at the same time of concreting so that a groove can be formed. Wall sections are formed alternatively leaving an intermediate section in between. The in-between sections are built similarly afterward but without the stop end. At the end a continual diaphragm wall is constructed with the panel sections tightly joined by the groove. 1 st Panel Panel progress Sequence Panel progress Sequence
  • 11. Schematic drawing of Boring activity of Diaphragm wall Hydraulic Grab Boring (Stage 1) Boring (Stage 2) Boring (Stage 3)
  • 12. Boring for Diaphragm Wall with Hydraulic HR-180 Rig
  • 13.
  • 15. ๏‚— Verticality check for Boring of Diaphragm wall:- ๏‚— Ultrasonic Instrument called Koden, shall be used for verticality check of Bored diaphragm wall panels. ๏‚— The Deviation of the bore trench from the perpendicular and any surface cavities in the bore hole or trench wall shall be measured. ๏‚— The ultrasonic measurement probe is suspended vertically from a cable and lowered into the object to be surveyed. ๏‚— At the same time, orthogonal waves are continuously emitted from the device and reflected from the walls. ๏‚— The reflected waves are registered by measurement sensors. The distances, calculated as a function of wave speed and reflection time, are presented in graphic form.
  • 17. ๏‚— Reinforcement Fabrication for Diaphragm Panels:- ๏‚— Steel cutting , bending & fixing shall be done as per drawing. Proper laps, Dowels shall be insure while fixing of cage. ๏‚— If required extra reinforcement shall be adequately provided fixed to avoid displacement and to maintain minimum specified cover during concreting. ๏‚— Concrete Cover blocks shall be circular and tied to rebar cage at regular interval ๏‚— Welding shall be provided to avoid displacement while shifting, lifting & lowering. ๏‚— After ensuring the welding & safety checklist of entire cage, cage shall be lifted with the help of cranes. ๏‚— Lifted diaphragm wall cage shall be lowered in bored trench of diaphragm wall. ๏‚— Cage shall be rest with help of resting bars on the guide wall.
  • 19.
  • 20.
  • 21. ๏‚— Concreting of Diaphragm wall. ๏‚— Concreting:-Concreting shall be done by tremmie method ๏‚— Tremmie pipes shall be clean, watertight & with a minimum internal diameter of 200 mm ๏‚— Tremmie shall be lowered up to the bottom of the trench through the slurry column. ๏‚— After lowering tremmie the hopper will be fixed on the top of tremmie pipe & plug will be placed bottom of hopper, after plugging the hopper will fill with concrete up to the top of hopper then the tremmie pipe shall be raised slowly and remove the plug from hopper so that concrete in a single continuous flow. ๏‚— Care shall be taken so that bottom end of tremmie pipe remains immerse at least 1.5 m below in concrete during casting. Concrete shall be continued till the overflow at least 0.6 m over the cutoff level of the Diaphragm Wall as shown on the drawing. Once concreting is started it shall be continued without break. The permissible time gap between consecutive shall be so adjusted that on initial setting of concrete takes place before it reaches its final position. During concreting, continuous raising and removal of segments of tremmie pipes shall be ensured. ๏‚— After reaching concrete its initial setting time, Stop end pipe shall be removed from the bore and boring for secondary panel shall be started.
  • 22.
  • 23.
  • 24.
  • 25. Removing of Stoppend by Hydraulic Jack System Removing of Stoppend by Hydraulic Jack System.
  • 26. Anchoring ๏‚— Sequence of Anchoring ๏‚— Setting of Drill Rig at Location and Align ๏‚— Driving Casing into Overburdens and Drilling for Fixed Length ๏‚— Initial Grouting of Drilled Holes ๏‚— Redrilling of Grouted Holes ๏‚— Water Testing of Redrilled Holes ๏‚— Fabrication of Cables ๏‚— Homing of Cable into the Drilled Hole and Fixed Length Grouting ๏‚— Stressing of Cable ๏‚— Grout the free length Portion ๏‚— Cutting extra Length of Strand and Concreting the Pocket
  • 27. Setting of Drill Rig at Location and Align ๏‚— Suitable rig is shifted to the anchor location and the rig is positioned to drill a selected hole .
  • 28. Driving the Casing into Overburden and Drilling for Fixed Length ๏‚— After the rig is positioned and aligned, drilling is taken up. Drilling of 150 mm dia. hole in silty sand / clay shall be carried out by Rotary Percussive DTH system or simultaneous casing driven method. ๏‚— After fixing the casing in overburden, further drilling shall be continued by rotary percussive by using DTH. As soon as drilling reaches its desired depth, the drill tubes shall be withdrawn from the hole and machine shall be shifted to next location.
  • 29. Initial Grouting of drilled holes ๏‚— The drilled holes shall be pressure grouted with neat cement grout to fill the voids, joints, fissures etc around the anchor hole and to reduce the permeability. ๏‚— Single packer with mechanically expanded rubber ring shall be fixed at the collar of the hole. The minimum diameter of the grout intake pipe shall be 25mm. An assembly with grout intake, bleeder valve, pressure gauge with gauge saver shall be fixed on to the packer for grouting. ๏‚— The hole shall be taken for grouting and shall be grouted to refusal at required pressure as detailed in the subsequent paras. ๏‚— After grouting is completed the packer is removed only after ensuring that there is no back flow of grout from the hole.
  • 30.
  • 31. Fabrication of Cable The cable shall be fabricated using required calculated number of HT strands of 15.2 mm dia. with UTS as per BS 8081: 1989. ๏‚— The HT strand shall be cut to required length. ๏‚— Bond length of the cable shall be cleaned and applied with two coats of epoxy and quartz sand shall be sprinkled when the second coat is tacky to increase the bond strength. ๏‚— Free length shall be cleaned thoroughly and shall be applied with two coats of epoxy based paint. ๏‚— Cable shall be tied with GI binding wire by providing the MS spacer at regular interval to space the strand in equidistance and in the bottom MS cap shall be provided. ๏‚— After tied up the cable, the HDPE duct shall be encased and plug the upper and bottom end so that grout will not be leaked out. ๏‚— Free length, HDPE pipe (plain sheath) shall be encased to individual strand pushed with grease and plugged the lower end with suitable PVC tape so that while grouting the bond length grout will not be entered into the duct. After encasing the duct to the tendons, shall be tied with providing spacer at 2.0 m C/c.
  • 32. HT Strand Cut at Required Length
  • 33. Application of Sand and Quartz
  • 34. Fixing of Spacer , Grout Pipe, & Tieng with GI wire