SlideShare una empresa de Scribd logo
1 de 30
Descargar para leer sin conexión
Logistics Report on a BH UTEM 4 Survey
in
Elliot Lake, Ontario area
for
International Montoro Resources, Inc.
June 2015
Bruce McMonnies, P.Geo.
Christina Demerling, M.Sc.
Property Boreholes
Elliot Lake P-15-22
Table of Contents
INTRODUCTION 3
SURVEY DESIGN 4
FIELD WORK 5
Table 1: Survey Summary 5
Appendix A: Production Log 6
Appendix B: BH UTEM 4 Plot Profiles 8
BH UTEM 4 Plot Profiles―Elliot Lake 9
Appendix C: BH UTEM 4 Vector Plots 15
BH UTEM 4 Vector Plots―Elliot Lake 16
Appendix D: The BHUTEM 4 SYSTEM 19
Appendix E: Note on sources of anomalous Ch1 28
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "2
INTRODUCTION
A BH UTEM 4 survey was conducted by Lamontagne Geophysics Ltd. personnel on behalf
of International Montoro Resources Inc. from April 22nd through to April 24th, 2015.  During
this time, one borehole was surveyed (see Figure 1), with a total of 1000 m of production.  The
purpose of this survey was to locate and define any conductors present in the vicinity of the
borehole.
This report documents all survey logistics.  Results, presented as BH UTEM 4 profiles and
vector plots, are attached as appendices.
Figure 1: UTEM 4 BH survey locations in the Elliot Lake area for International Montoro Resources
Inc. in April, 2015.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "3
SURVEY DESIGN
Elliot Lake (see Figure 2)
Figure 2: Loop and borehole location map for P-15-22.
Borehole P-15-22 was surveyed at a frequency of 3.872Hz using Loop 1501 (measuring
approximately 1200m by 1200m).
For the above BH UTEM 4 coverage, measurements of the axial (Hw) and the two
transverse (Hs and Hn) components of the electromagnetic field were taken at each station. 
Also, at each station, three component magnetometer, three component accelerometer and
temperature data were collected.  The nominal station spacing was forty metres (40m) for the
top portion of the hole.  The spacing was decreased to ten or twenty metres for the bottom
portion of the hole and further to five metres if it was thought necessary to better define an
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "4
anomalous zone.  At every station, thirteen channel data were collected with a minimum stack
of 512 half cycles recorded at every station.  Repeat readings were taken regularly to ensure
the repeatability of the data.
For additional information on aspects of BH UTEM 4 survey design and the Data
Presentation and reduction schemes used during this survey, see Appendix D.
FIELD WORK
The Lamontagne Geophysics crew commenced operations in the Elliot Lake area on April
22nd and continued until April 24th, 2015.  The crew consisted of B. O’Bomsawin, R. Fox, J.
Savage, J. Young, C. Carrier, J. Pichler.  Operations were based out of the Lamontagne Sudbury
Office in Chelmsford, Ontario.
The survey equipment consisted of one UTEM 4 transmitter, one UTEM 4 receiver, two BH
UTEM 4 probes, one borehole winch system, fiber optic cables and all accessories and support
equipment.  A field computer (iMac) was used for all reduction and plotting of the survey data
while on site.  This data was delivered to International Montoro Resources Inc. on a timely
basis.
A description of the daily field work is provided in the Production Log that follows in
Appendix A.  All production is summarized in Table 1.  Site-specific details of all data
acquisition activities are provided below.  Geometric control for all transmitter loops was
achieved with a hand-held GPS system.
Elliot Lake
Borehole P-15-22 was dummied to a depth of 1005m and surveyed to a depth of 1000m.
Table 1: Survey Summary
Project Area Borehole
Name
Survey
Depth (m)
Dummy
Depth (m)
Loop
Number
Frequency
Elliot Lake P-15-22 1000 1005 1501 3.872 Hz
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "5
 
 
 
 
 
 
Appendix A: Production Log
 
 
 
 
 
 
 
 
 
 
 
BH UTEM 4 Survey
Elliot Lake area, Ontario, Canada
for
International Montoro Resources Inc.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "6
Production Log (1512)
International Montoro Resources Inc.
Elliot Lake, ON
LEGEND
Date Rate Production Comments
Apr 22 1.25 L-5 - Went out by helicopter to Elliot Lake and laid out the entire
Loop 1501. The equipment was slung in from airport
while the loop was being laid.
Crew: B. O’Bomsawin, R. Fox, J. Savage, J. Pichler, J.Young.
Apr 23 1.25 SP-4 1000m Delivered the BH UTEM equipment to Creighton Mine
which was tagged for transportation underground
for surveying the next day. Then notified the client
(Brian Langlois) that everything was ready to go
down overnight.
Crew: B. O’Bomsawin, T. Pinkerton, R. Fox.
Read: Hole P-15-22 Loop 1501 1000m 3.872Hz
at Elliot Lake.
Flew in from Elliot Lake airport.
Dummied Hole P-15-22 (1005m).
Slung the transmitter equipment from the hole to the loop.
After survey, got all the equipment was slung out to
the trucks at the airport. Loop 1501 will be retrieved
tomorrow.
Crew: B. O’Bomsawin, J. Savage, C. Carrier, J. Young.
Apr 24 L-2 - Picked up Loop 1501. The chopper came in on shift change
to pick up the crew.
Crew: J. Savage, C. Carrier.
Code Meaning
SP(4)-x Short Production (UTEM 4 Tx) - # of personnel <1400m depth
L(4)-x Looping (UTEM 4 Tx) - # of personnel
S(4)-x Stand By (UTEM 4 Tx) - # of personnel
D-x Down - # of personnel
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "7
 
 
 
 
 
 
Appendix B: BH UTEM 4 Plot Profiles
 
 
 
 
 
 
 
 
 
 
 
BH UTEM 4 Survey
Elliot Lake area, Ontario, Canada
for
International Montoro Resources Inc.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "8
BH UTEM 4 Plot Profiles―Elliot Lake
Project Area Borehole Loop Number Frequency (Hz)
Elliot Lake P-15-22 1501 3.872
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "9


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "10
Hw
-100% 100%
-100% 100%
Hw
-25% 25%
-25% 25%
Hw
-25% 25%
-25% 25%
Hw
-25% 25%
Acc Mag
200
400
600
800
1000
400
800
1200
1600
2000
2400
2800
3200
100
200
300
400
500
600
700
800
900
1000
S 360°; N 90°
Cpt: Hw
Lp: 1501; Job: 150
Hole: P-15-22
Gain factor: -1
Base freq: 30.974 Hz
Cont norm @ ∆z:0m
Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake
For: International Montoro Resources Inc.
Plot: 17/6/15
Red : 4/5/15
Surv: 23/4/15


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "11
Hs
-100% 100%
-100% 100%
Hs
-25% 25%
-25% 25%
Hs
-25% 25%
-25% 25%
Hs
-25% 25%
Acc Mag
200
400
600
800
1000
400
800
1200
1600
2000
2400
2800
3200
100
200
300
400
500
600
700
800
900
1000
S 360°; N 90°
Cpt: Hs
Lp: 1501; Job: 150
Hole: P-15-22
Gain factor: -1
Base freq: 30.974 Hz
Cont norm @ ∆z:0m
Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake
For: International Montoro Resources Inc.
Plot: 17/6/15
Red : 4/5/15
Surv: 23/4/15


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "12
Hn
-100% 100%
-100% 100%
Hn
-25% 25%
-25% 25%
Hn
-25% 25%
-25% 25%
Hn
-25% 25%
Acc Mag
200
400
600
800
1000
400
800
1200
1600
2000
2400
2800
3200
100
200
300
400
500
600
700
800
900
1000
S 360°; N 90°
Cpt: Hn
Lp: 1501; Job: 150
Hole: P-15-22
Gain factor: -1
Base freq: 30.974 Hz
Cont norm @ ∆z:0m
Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake
For: International Montoro Resources Inc.
Plot: 17/6/15
Red : 4/5/15
Surv: 23/4/15


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "13
Hw
-100% 100%
-100% 100%
Hn
-100% 100%
-100% 100%
Hs
-100% 100%
-100% 100%
Acc Mag
Acc Mag
200
400
600
800
1000
400
800
1200
1600
2000
2400
2800
3200
100
200
300
400
500
600
700
800
900
1000
S 360°; N 90°
Cpt: Hs,Hn,Hw
Lp: 1501; Job: 150
Hole: P-15-22
Gain factor: -1
Base freq: 30.974 Hz
Cont norm @ ∆z:0m
Total, Chn/|Hp| BHUTEM-4 Survey at: Elliot Lake
For: International Montoro Resources Inc.
Plot: 17/6/15
Red : 4/5/15
Surv: 23/4/15


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "14
60000nT
60000nT
60000nT
60000nT
0.25g
0.25g
0.25g
0.25g
-1°C 1°C
-1°C 1°C
Acc Mag
Acc Mag
100
200
300
400
500
600
700
800
900
1000
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
3000
3200
100
200
300
400
500
600
700
800
900
1000
S 360°; N 90°
Cpt:
Lp: 1501; Job: 150
Hole: P-15-22
Gain factor: -1
Base freq: 30.974 Hz
Cont norm @ ∆z:0m
Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake
For: International Montoro Resources Inc.
Plot: 17/6/15
Red : 4/5/15
Surv: 23/4/15
Appendix C: BH UTEM 4 Vector Plots
 
 
 
 
 
 
 
 
 
 
 
BH UTEM 4 Survey
Elliot Lake area, Ontario, Canada
for
International Montoro Resources Inc.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "15
BH UTEM 4 Vector Plots―Elliot Lake
Loop Boreholes View
1501 P-15-22 Plan,
Section
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "16


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "17


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "18
Appendix D: The BHUTEM 4 SYSTEM
Data Reduction and Plotting Conventions
Data Presentation
 
 
 
 
 
 
 
 
 
 
BH UTEM 4 Survey
Elliot Lake area, Ontario, Canada
for
International Montoro Resources Inc.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "19
INTRODUCTION
The BHUTEM 4 downhole system is a three-axis downhole transient EM system which
incorporates a low-noise coincident three-axis coil design, fully digital down the hole
encoding and a fibre-optic probe-to-surface data link.  The system allows three components of
the transient magnetic field to be simultaneously averaged and stored.  Probe orientation
within the hole is monitored by integrated 3-axis magnetometer and 3-axis accelerometer
devices.  Temperature measurements taken to correct the accelerometer package can also be
used to detect the thermal signature of ore bodies.
Waveform and Sampling
The UTEM transmitter passes a low-frequency (~1 Hz to 90 Hz) current of a precisely
regulated waveform through the transmitter loop. The frequency may be set to any value
within the operating range of the transmitter, but is usually set at 31 Hz so as to minimize
power line effects (60 Hz noise).  Lower base frequencies are used to survey highly conductive
bodies with time constants much larger than the 16ms half-cycle.
Since the receiver coil responds to the time derivative of this magnetic field, it is said that
the system really "sees" the step response of the ground. In practice, the transmitted waveform
is tailored to optimize signal to noise and deconvolution techniques are employed within the
system to produce an equivalent to this conceptual “step response” at the receiver. UTEM is
the only time domain system which measures the step response of the ground.  All other
T.D.E.M. systems, to date, transmit a modified step current so that they "see" the (im)pulse
response of the ground at the receiver.
While the channel time gates are programmable, a standard set of 13 time gates which fully
sample the waveform are usually used as shown in Figure 2.  The time gates are described
with respect to a system of units where the length of the half-cycle is 1062 units.  Ten of the
thirteen channels are plotted and used for standard interpretation.  Figure 1 shows the
plotting symbols used for these channels.  The latest of these is designated as channel 1 and it
occupies almost the entire second half of the half-cycle, from 512 -1024 units.  Channels 2-10
are arranged in a binary progression, each occupying one half of the time interval remaining
from the beginning of the half cycle.  Thus channel 2 is from 256 to 512 units, channel 3 is from
128 to 256units, etc.  Channels 11 and 12 are only one unit wide (15 microseconds @ 31 Hz)
and they occupy opposite sides of the waveform transition.  They are used primarily for the
purposes of monitoring phase drift between the transmitter and receiver clocks.  Channel 13
occupies the 37 unit wide interval from the end of channel 1, 1024 units, to 1061 units.  While
this is later than channel 1, this channel is much narrower and hence less precise.  It is used in
quality control and in some processing techniques but is not usually displayed.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "20
Probe Orientation
Because the probe is rotating freely in the hole the raw transverse components must be
“rotated” to point in a consistent direction along the hole.  The rotation process is a
mathematical one which is performed after the data are collected but which requires a
knowledge of the actual orientation of the probe in the hole at each station.  The determination
of the probe orientation is achieved using two independent tools; a three-axis magnetometer
and a 3-axis accelerometer.  Data from these devices are collected before each EM stack.  In
ideal situations, such as an inclined hole directed well away from magnetic north and away
from large magnetic anomalies, either tool is capable of precise orientation of the probe.  In a
near vertical hole, the accelerometer becomes incapable of determining the probe orientation,
while in a hole directed along the earth’s magnetic field, the same is true for the
magnetometer.  The data reduction software uses the best combination of the estimates
derived by these two devices.
Coordinate Systems
The three observed components of the transient magnetic field are designated as Hu, Hv
and Hw with: Hw being the axial component pointing down the hole and Hu and Hv
oriented in a right-handed system with respect to Hw. The coordinate systems used to orient
these transverse three-axis data are based on the concept of a drill section.  The drill section is
a vertical plane perpendicular to the geological strike and is in general the plane in which
inclined holes would be drilled.  It is specified by the drill section azimuth which is the
azimuth of the positive coordinate direction within the plane.  For a north-south section plane,
for instance, the drill section azimuth would be zero (due north) while for an east west section
plane, it would be 090 (east).  Usually a section azimuth is adopted for an entire survey area,
even if the actual azimuths of individual holes are slightly different.  Once the section is
determined by the section azimuth, the out of section direction is 90 degrees clockwise from
the section azimuth as seen in plan.
UTEM 4 data are presented in one of two coordinate
systems.  The coordinate system used to express the data is
identified by the notation used for the components.
Hole based coordinate system
This is the most commonly used system.  In this system
the components are designated as Hs, Hn and Hw.  Hw is
the axial component and as such is independent of the
orientation of the probe in the hole.  The Hn component
lies on the plane perpendicular to the section plane.  Hs lies
as close as possible to the designated drill section plane
while being perpendicular to the other two components.  Note that Hs and the designated
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "21
drill section plane are coincident only if the local hole azimuth is exactly the same as the
designated section azimuth.
The hole based coordinate system is useful for several reasons.  It is easiest to interpret the
orientation of a conductive body relative to the trajectory of the hole, rather than in absolute
terms.  In this respect a hole-relative coordinate system is much easier to use.  A second
important reason is that the axial component has a substantially higher signal/noise than the
transverse components.  In the hole based system, the axial component is plotted as is and is
not required to be combined with the transverse components.
Cartesian coordinate system
This is not a standard presentation.  It may, however, be useful from time-to-time to present
the data in the Cartesian system.  In this system the HS component is in the section
direction, the HN component is in the out of section direction, and the HZ direction is
down.  Note that in the Cartesian system, except in a vertical hole, every component is a
linear combination of the three raw observed components.

International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "22


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "23
Figures 3 and 4 show the main features of the geometry conventions and terminology
used.  In Figure 3 the transient field vector is designated as H, which is resolved into the axial,
Hw, and the transverse, Htr, components.  The transverse Htr is resolved into the Hs and Hn
components where: Hn lies in the plane perpendicular to the designated drill section
clockwise from Hs as seen in plan and Hs is perpendicular to both Hn and Hw   Note that the
drill hole itself does not lie in the designated drill section.  Because of this the Hs component
will not be exactly in the designated drill section in this example.  The designated drill section
itself is specified by the section azimuth, measured clockwise from geographic north.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "24
Figure 4 shows the relationship of the hole geometry to the magnetic and gravitational
fields used for orienting the probe.  The magnetometer and accelerometer are both resolved
into axial (Aw,Mw) and transverse (Atr,Mtr) components.  For each device, it is the resolution
of the computed transverse field direction with the two observed transverse signals which
determines the probe orientation.  The precision of orientation is greatest when the transverse
field is a large component of the total.
Orientation Device Selection
The factors which limit the precision of the magnetometer and accelerometer devices as
orientation tools are:
While these factors cannot be tracked individually on a routine basis, the total transverse
magnetic and gravitational fields are independent of the rotation of the probe in the hole and
they can be compared to their predicted values.  The discrepancy between these is a measure
of the “error” of the device as far as its use as an orientation tool and it forms a basis for the
orientation tradeoff parameter, a.  This is a parameter which varies from +1.0 for pure
magnetometer, to -1.0 for pure accelerometer.  In between, a linear weighted average between
the probe orientations as determined by the mag and accelerometer is used.
Data Reduction
The kind of reduction applied to the raw data is indicated on each plot in the second field
of the title block.  The observed UTEM data represents a sum of the signal directly from the
transmitter loop (Primary field) and the field resulting from eddy currents induced in
conductive bodies and/or a conductive host rock (Secondary field).  In the case of a Total Field
plot the observed data are simply expressed as a percentage of a normalizing field which is
either the primary field magnitude at a fixed point in space (Point Normalization) or the
primary field magnitude at each station (Continuous Normalization).  The Secondary Field is of
most interest from an interpretive point of view.  As such an estimate of the primary field
must be determined and subtracted from the data.  There are two ways in which this is done:
Magnetometer Accelerometer
magnetic anomalies gravitational anomalies (insignificant)
errors in magnetic declination and
inclination
orientation of gravitation field is known
precisely
errors in surveyed azimuth and dip of hole errors in surveyed azimuth and dip of hole
no significant temperature dependence temperature calibration of accelerometer
incorrect
magnetic tensor calibration accelerometer tensor calibration
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "25
1. Primary Field Reduction:            The computed primary field is subtracted from all
channels.  This is designated by the formula (Chn-Hpc)/(|Hp|) in the title block of the
plot.
2. Channel 1 Reduction:            The computed primary field is subtracted from Channel 1.
For all earlier channels, channel 1 is subtracted as an estimate of the primary field.  This
is designated by the formula (Chn-Ch1)/(|Hp|) in the title block of the plot.
As in the Total field case, the |Hp| primary field magnitude in the denominator is either
evaluated at a fixed point in space (Point Normalization) or at each station (Continuous
Normalization).
Standard BHUTEM 4 Plot Suite
The UTEM 4 3-axis data are usually presented as a set of five profile plots for each hole and
loop surveyed.  The data are plotted as a function of the distance down the hole.  The depth
axes are always labelled in metres but are also labelled in feet on imperial grids.  Each axis
which displays EM data indicates the component according to the conventions discussed
above (Hs, Hn, Hw).  As well, the component is indicated graphically by the direction of the
arrow in the small coordinate axis system plotted at the end of each axis.  To understand this
system, consider that the plot is oriented with the axis down, that the section plane is the
plane of the paper and that the section direction is to the right.  The out of section component
is then out of the page.  The value of the geographic section azimuth is indicated in the second
field of the title block of each of the plots along with the type of reduction and normalization. 
All plots include as well a profile on the lowest axis which shows the orientation tradeoff
parameter used to derive the probe orientation.  The plot set is comprised of:
• 3 plots of channel 1 reduced secondary field: one each for components Hs, Hn and Hw. 
These plots have the early, intermediate and latest time channels plotted on separate
axes.  The computed primary field in the direction of the component is also plotted as a
solid curve on the upper axis with the early time channels.
• 1 total field plot: with all channels of each of the three components on a different axis. 
Each axis includes as well a plot of the primary field as a solid curve.  In most cases the
following of the primary field curve of each of the components by its respective channel
1 indicates that the basic geometry of the hole relative to the loop is correct.  This may
not be true, however in very conductive environments where a large response persists in
channel 1.
• 1 plot comprised of magnetometer data on the top axis, accelerometer data on the
middle axis and temperature data on the lower axis.  For the mag and accelerometer
plots, three curves are presented.  In black, the observed axial (symbol W) and total
transverse (symbol R) are plotted, while in grey, the expected total transverse is plotted. 
Discrepancies between the expected and the observed total transverse mag and
accelerometer components can point to a number of problems including: incorrect hole
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "26
dip, incorrect hole azimuth, poor mag/acc device calibration, magnetic anomalies and
incorrect magnetic declination and/or inclination.
The raw temperature profile taken down the hole is dominated by the geothermal gradient
of about 18°C per kilometre of depth.  Superimposed on this are small amplitude anomalies
which may be beneficial in locating thermally conductive dipping ore bodies.  The curve that
is plotted is the residual temperature after the removal of a best fitting polynomial.  The order
of the polynomial used in indicated in the axis label of the plot.  For example, “Temp-P(2)”,
indicates that a second order polynomial has been subtracted.


International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "27
Appendix E: Note on sources of anomalous Ch1
BH UTEM 4 Survey
Elliot Lake area, Ontario, Canada
for
International Montoro Resources Inc.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "28
Note on sources of anomalous Ch1
This section outlines the possible sources of anomalous channel 1 which is not correlated to
the Ch2-10 data plotted on the upper axes of a channel 1 normalized  plot.
1) Mislocation of the transmitter loop and/or survey stations
Mislocating the transmitter loop and/or the survey stations results in an error in the
calculated primary field at the station and appears as an anomalous Ch1 value not correlated
to channel 1 normalized Ch2-10.  The effect is amplified near the loop front.  This can be seen in
the profiles - the error in Ch1 generally increases approaching the loop.  As a rule a 1% error in
measurement of the distance from the loop will result in, for outside the loop surveys, an error
in Ch1 of:
• 1% near the loop front (long-wire field varies as 1/r)
• 3% at a distance from the loop front (dipolar field varies as 1/r3)
• 2% at intermediate distances (intermediate field varies as ~1/r2)
Errors in elevation result in smaller errors but as they often affect the chainage they
accumulate along the line. 
The in-loop survey configuration generally  diminishes geometric error since the field
gradients are very low.  At the centre of the loop the gradient in the vertical field is essentially
zero so it is difficult to introduce geometric anomalies near the loop centre.  Near the loop
sides and at the closest approach of the lines to the wire mislocation of the loop and the station
becomes more critical.  Typically loop sides are designed to be >200m from any survey
stations.
2)  Magnetostatic UTEM responses
Magnetostatic UTEM responses  arise over rocks which generate magnetic anomalies. 
Such magnetic materials will amplify the total (primary + secondary) field of the UTEM
transmitter which is sensed by the receiver coil.  The secondary field is generated by
subtracting a computed primary which does  not include magnetic effects.  This can give rise
to strong and abrupt channel 1 anomalies when the source of the magnetics is at surface.  This
is the case in a number of places on these grids.  UTEM magnetostatic anomalies differ from
DC magnetic anomalies in the following three major ways:
1. In the case of DC magnetics the field is dipping N and is very uniform over the scale of the survey
area while the UTEM field inside the loop is vertical and it is stronger near the loop edges.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "29
2. Most aeromagnetics are collected as total field while with UTEM we measure a given (in this case
generally z,x) component.
3. DC magnetic instruments observe the total magnetization of the causative body which is due to its
susceptibility as well as any remnant magnetization. An AC method such as UTEM will not
respond to the remnant portion of the magnetization.
The larger amplitude of the UTEM Ch1 response is explained by the fact that the UTEM
primary field is often more favourably coupled (magnetostatically speaking) to  magnetic
mineralization as compared to the earths field.  Another factor could be the presence of a
reverse remnant component to the magnetization.
Note that positive (negative) magnetic anomalies will cause:
• positive (negative) Ch1 anomalies in data collected outside the loop
• negative (positive) Ch1 anomalies in data collected inside the loop
3) Extremely good conductors
An extremely good conductor will be characterized by a time constant much longer than
the half-period (@ 30Hz >>16ms).  This will give rise to an anomalous Ch1 which is not
correlated to the Ch2-10 data plotted on the upper axes of a channel 1 normalized plot.
International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "30

Más contenido relacionado

Similar a Lamontage down hole probe data pecors

Investigation of Observed Seismicity in the Horn River Basin
Investigation of Observed Seismicity in the Horn River BasinInvestigation of Observed Seismicity in the Horn River Basin
Investigation of Observed Seismicity in the Horn River BasinMarcellus Drilling News
 
Site 28 In Situ Abiotic/Biotic Treatability Study Implementation
Site 28 In Situ Abiotic/Biotic Treatability Study ImplementationSite 28 In Situ Abiotic/Biotic Treatability Study Implementation
Site 28 In Situ Abiotic/Biotic Treatability Study ImplementationSteve Williams
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportToronto Public Consultation Unit
 
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...inventionjournals
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Society of Petroleum Engineers
 
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...Luke Elliott
 
Aldergrove Aquifer Issues
Aldergrove Aquifer IssuesAldergrove Aquifer Issues
Aldergrove Aquifer Issuesjgabateman
 
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...Iwl Pcu
 
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LAND
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LANDFR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LAND
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LANDgrssieee
 
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...Adrian Frantescu
 
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTRAPHAEL AGORUA
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design ReportRAPHAEL AGORUA
 
SLIPP SC TT PAC meeting June 2010 with ECE update
SLIPP SC TT PAC meeting June 2010 with ECE updateSLIPP SC TT PAC meeting June 2010 with ECE update
SLIPP SC TT PAC meeting June 2010 with ECE updateErin Vieira
 
Aquatic pollution in port qasim creeks
Aquatic pollution in port qasim creeks Aquatic pollution in port qasim creeks
Aquatic pollution in port qasim creeks TayyabaIrfan2
 
M. Lyons Resume to Present 6-4-2015
M. Lyons Resume to Present  6-4-2015M. Lyons Resume to Present  6-4-2015
M. Lyons Resume to Present 6-4-2015Morgan Lyons
 
Linking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseLinking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseMatthew Hahm
 

Similar a Lamontage down hole probe data pecors (20)

TRB presentation 4
TRB presentation 4TRB presentation 4
TRB presentation 4
 
Rich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources incRich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources inc
 
Investigation of Observed Seismicity in the Horn River Basin
Investigation of Observed Seismicity in the Horn River BasinInvestigation of Observed Seismicity in the Horn River Basin
Investigation of Observed Seismicity in the Horn River Basin
 
Site 28 In Situ Abiotic/Biotic Treatability Study Implementation
Site 28 In Situ Abiotic/Biotic Treatability Study ImplementationSite 28 In Situ Abiotic/Biotic Treatability Study Implementation
Site 28 In Situ Abiotic/Biotic Treatability Study Implementation
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File Report
 
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...
Application of GIS in Evaluationof Coastal River Bathymetry, A Case Study of ...
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
 
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...
The Object Detection Capabilities of the Bathymetry Systems Utilised for the ...
 
Aldergrove Aquifer Issues
Aldergrove Aquifer IssuesAldergrove Aquifer Issues
Aldergrove Aquifer Issues
 
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...
Source Apportionment of Nitrogen and Phosphorous Inputs into the Aquatic Envi...
 
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LAND
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LANDFR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LAND
FR1.L10.1: OVERVIEW OF SMOS RETRIEVALS OVER LAND
 
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...
1.43.3.1 2009-hartland-landfill-groundwater-surface-water-and-leachate-monito...
 
Remote sensing and census data water productivity analysis for limpopo basin
Remote sensing and census data water productivity analysis for limpopo basinRemote sensing and census data water productivity analysis for limpopo basin
Remote sensing and census data water productivity analysis for limpopo basin
 
Magness Sess12 102609
Magness Sess12 102609Magness Sess12 102609
Magness Sess12 102609
 
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design Report
 
SLIPP SC TT PAC meeting June 2010 with ECE update
SLIPP SC TT PAC meeting June 2010 with ECE updateSLIPP SC TT PAC meeting June 2010 with ECE update
SLIPP SC TT PAC meeting June 2010 with ECE update
 
Aquatic pollution in port qasim creeks
Aquatic pollution in port qasim creeks Aquatic pollution in port qasim creeks
Aquatic pollution in port qasim creeks
 
M. Lyons Resume to Present 6-4-2015
M. Lyons Resume to Present  6-4-2015M. Lyons Resume to Present  6-4-2015
M. Lyons Resume to Present 6-4-2015
 
Linking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseLinking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land Use
 

Más de Follow me on Twitter @Stockshaman

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...Follow me on Twitter @Stockshaman
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Follow me on Twitter @Stockshaman
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...Follow me on Twitter @Stockshaman
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryFollow me on Twitter @Stockshaman
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...Follow me on Twitter @Stockshaman
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...Follow me on Twitter @Stockshaman
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...Follow me on Twitter @Stockshaman
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...Follow me on Twitter @Stockshaman
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...Follow me on Twitter @Stockshaman
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...Follow me on Twitter @Stockshaman
 
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...Follow me on Twitter @Stockshaman
 
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...Follow me on Twitter @Stockshaman
 

Más de Follow me on Twitter @Stockshaman (20)

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
 
Imt black fly mobilization and permit
Imt black fly mobilization and permitImt black fly mobilization and permit
Imt black fly mobilization and permit
 
PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
 
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
 
Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018
 
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
 
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...
Duhamel,Quebec,Canada #Vanadium #Chromium #Cobalt #Titanium #Copper #Nickel I...
 
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...
BELMONT & MGX MINERALS RECEIVE ENCOURAGING ASSAYS UP TO 580 PPM LITHIUM IN FI...
 

Último

Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdftaxlinkcpa
 
Best investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingBest investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingFalcon Invoice Discounting
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000Sapana Sha
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCRSapana Sha
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024Hector Del Castillo, CPM, CPMM
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityJohanAspro
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel Paul
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024nicola_mining
 

Último (19)

Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdf
 
Best investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingBest investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discounting
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
 
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Serviceyoung  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
 
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCRCall Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
 
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
 
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Serviceyoung call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024
 
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Serviceyoung Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanity
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024
 

Lamontage down hole probe data pecors

  • 1. Logistics Report on a BH UTEM 4 Survey in Elliot Lake, Ontario area for International Montoro Resources, Inc. June 2015 Bruce McMonnies, P.Geo. Christina Demerling, M.Sc. Property Boreholes Elliot Lake P-15-22
  • 2. Table of Contents INTRODUCTION 3 SURVEY DESIGN 4 FIELD WORK 5 Table 1: Survey Summary 5 Appendix A: Production Log 6 Appendix B: BH UTEM 4 Plot Profiles 8 BH UTEM 4 Plot Profiles―Elliot Lake 9 Appendix C: BH UTEM 4 Vector Plots 15 BH UTEM 4 Vector Plots―Elliot Lake 16 Appendix D: The BHUTEM 4 SYSTEM 19 Appendix E: Note on sources of anomalous Ch1 28 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "2
  • 3. INTRODUCTION A BH UTEM 4 survey was conducted by Lamontagne Geophysics Ltd. personnel on behalf of International Montoro Resources Inc. from April 22nd through to April 24th, 2015.  During this time, one borehole was surveyed (see Figure 1), with a total of 1000 m of production.  The purpose of this survey was to locate and define any conductors present in the vicinity of the borehole. This report documents all survey logistics.  Results, presented as BH UTEM 4 profiles and vector plots, are attached as appendices. Figure 1: UTEM 4 BH survey locations in the Elliot Lake area for International Montoro Resources Inc. in April, 2015. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "3
  • 4. SURVEY DESIGN Elliot Lake (see Figure 2) Figure 2: Loop and borehole location map for P-15-22. Borehole P-15-22 was surveyed at a frequency of 3.872Hz using Loop 1501 (measuring approximately 1200m by 1200m). For the above BH UTEM 4 coverage, measurements of the axial (Hw) and the two transverse (Hs and Hn) components of the electromagnetic field were taken at each station.  Also, at each station, three component magnetometer, three component accelerometer and temperature data were collected.  The nominal station spacing was forty metres (40m) for the top portion of the hole.  The spacing was decreased to ten or twenty metres for the bottom portion of the hole and further to five metres if it was thought necessary to better define an International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "4
  • 5. anomalous zone.  At every station, thirteen channel data were collected with a minimum stack of 512 half cycles recorded at every station.  Repeat readings were taken regularly to ensure the repeatability of the data. For additional information on aspects of BH UTEM 4 survey design and the Data Presentation and reduction schemes used during this survey, see Appendix D. FIELD WORK The Lamontagne Geophysics crew commenced operations in the Elliot Lake area on April 22nd and continued until April 24th, 2015.  The crew consisted of B. O’Bomsawin, R. Fox, J. Savage, J. Young, C. Carrier, J. Pichler.  Operations were based out of the Lamontagne Sudbury Office in Chelmsford, Ontario. The survey equipment consisted of one UTEM 4 transmitter, one UTEM 4 receiver, two BH UTEM 4 probes, one borehole winch system, fiber optic cables and all accessories and support equipment.  A field computer (iMac) was used for all reduction and plotting of the survey data while on site.  This data was delivered to International Montoro Resources Inc. on a timely basis. A description of the daily field work is provided in the Production Log that follows in Appendix A.  All production is summarized in Table 1.  Site-specific details of all data acquisition activities are provided below.  Geometric control for all transmitter loops was achieved with a hand-held GPS system. Elliot Lake Borehole P-15-22 was dummied to a depth of 1005m and surveyed to a depth of 1000m. Table 1: Survey Summary Project Area Borehole Name Survey Depth (m) Dummy Depth (m) Loop Number Frequency Elliot Lake P-15-22 1000 1005 1501 3.872 Hz International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "5
  • 6.             Appendix A: Production Log                       BH UTEM 4 Survey Elliot Lake area, Ontario, Canada for International Montoro Resources Inc. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "6
  • 7. Production Log (1512) International Montoro Resources Inc. Elliot Lake, ON LEGEND Date Rate Production Comments Apr 22 1.25 L-5 - Went out by helicopter to Elliot Lake and laid out the entire Loop 1501. The equipment was slung in from airport while the loop was being laid. Crew: B. O’Bomsawin, R. Fox, J. Savage, J. Pichler, J.Young. Apr 23 1.25 SP-4 1000m Delivered the BH UTEM equipment to Creighton Mine which was tagged for transportation underground for surveying the next day. Then notified the client (Brian Langlois) that everything was ready to go down overnight. Crew: B. O’Bomsawin, T. Pinkerton, R. Fox. Read: Hole P-15-22 Loop 1501 1000m 3.872Hz at Elliot Lake. Flew in from Elliot Lake airport. Dummied Hole P-15-22 (1005m). Slung the transmitter equipment from the hole to the loop. After survey, got all the equipment was slung out to the trucks at the airport. Loop 1501 will be retrieved tomorrow. Crew: B. O’Bomsawin, J. Savage, C. Carrier, J. Young. Apr 24 L-2 - Picked up Loop 1501. The chopper came in on shift change to pick up the crew. Crew: J. Savage, C. Carrier. Code Meaning SP(4)-x Short Production (UTEM 4 Tx) - # of personnel <1400m depth L(4)-x Looping (UTEM 4 Tx) - # of personnel S(4)-x Stand By (UTEM 4 Tx) - # of personnel D-x Down - # of personnel International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "7
  • 8.             Appendix B: BH UTEM 4 Plot Profiles                       BH UTEM 4 Survey Elliot Lake area, Ontario, Canada for International Montoro Resources Inc. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "8
  • 9. BH UTEM 4 Plot Profiles―Elliot Lake Project Area Borehole Loop Number Frequency (Hz) Elliot Lake P-15-22 1501 3.872 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "9
  • 10. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "10 Hw -100% 100% -100% 100% Hw -25% 25% -25% 25% Hw -25% 25% -25% 25% Hw -25% 25% Acc Mag 200 400 600 800 1000 400 800 1200 1600 2000 2400 2800 3200 100 200 300 400 500 600 700 800 900 1000 S 360°; N 90° Cpt: Hw Lp: 1501; Job: 150 Hole: P-15-22 Gain factor: -1 Base freq: 30.974 Hz Cont norm @ ∆z:0m Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake For: International Montoro Resources Inc. Plot: 17/6/15 Red : 4/5/15 Surv: 23/4/15
  • 11. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "11 Hs -100% 100% -100% 100% Hs -25% 25% -25% 25% Hs -25% 25% -25% 25% Hs -25% 25% Acc Mag 200 400 600 800 1000 400 800 1200 1600 2000 2400 2800 3200 100 200 300 400 500 600 700 800 900 1000 S 360°; N 90° Cpt: Hs Lp: 1501; Job: 150 Hole: P-15-22 Gain factor: -1 Base freq: 30.974 Hz Cont norm @ ∆z:0m Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake For: International Montoro Resources Inc. Plot: 17/6/15 Red : 4/5/15 Surv: 23/4/15
  • 12. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "12 Hn -100% 100% -100% 100% Hn -25% 25% -25% 25% Hn -25% 25% -25% 25% Hn -25% 25% Acc Mag 200 400 600 800 1000 400 800 1200 1600 2000 2400 2800 3200 100 200 300 400 500 600 700 800 900 1000 S 360°; N 90° Cpt: Hn Lp: 1501; Job: 150 Hole: P-15-22 Gain factor: -1 Base freq: 30.974 Hz Cont norm @ ∆z:0m Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake For: International Montoro Resources Inc. Plot: 17/6/15 Red : 4/5/15 Surv: 23/4/15
  • 13. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "13 Hw -100% 100% -100% 100% Hn -100% 100% -100% 100% Hs -100% 100% -100% 100% Acc Mag Acc Mag 200 400 600 800 1000 400 800 1200 1600 2000 2400 2800 3200 100 200 300 400 500 600 700 800 900 1000 S 360°; N 90° Cpt: Hs,Hn,Hw Lp: 1501; Job: 150 Hole: P-15-22 Gain factor: -1 Base freq: 30.974 Hz Cont norm @ ∆z:0m Total, Chn/|Hp| BHUTEM-4 Survey at: Elliot Lake For: International Montoro Resources Inc. Plot: 17/6/15 Red : 4/5/15 Surv: 23/4/15
  • 14. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "14 60000nT 60000nT 60000nT 60000nT 0.25g 0.25g 0.25g 0.25g -1°C 1°C -1°C 1°C Acc Mag Acc Mag 100 200 300 400 500 600 700 800 900 1000 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 100 200 300 400 500 600 700 800 900 1000 S 360°; N 90° Cpt: Lp: 1501; Job: 150 Hole: P-15-22 Gain factor: -1 Base freq: 30.974 Hz Cont norm @ ∆z:0m Secondary, (Chn-Ch1)/|Hp| BHUTEM-4 Survey at: Elliot Lake For: International Montoro Resources Inc. Plot: 17/6/15 Red : 4/5/15 Surv: 23/4/15
  • 15. Appendix C: BH UTEM 4 Vector Plots                       BH UTEM 4 Survey Elliot Lake area, Ontario, Canada for International Montoro Resources Inc. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "15
  • 16. BH UTEM 4 Vector Plots―Elliot Lake Loop Boreholes View 1501 P-15-22 Plan, Section International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "16
  • 17. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "17
  • 18. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "18
  • 19. Appendix D: The BHUTEM 4 SYSTEM Data Reduction and Plotting Conventions Data Presentation                     BH UTEM 4 Survey Elliot Lake area, Ontario, Canada for International Montoro Resources Inc. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "19
  • 20. INTRODUCTION The BHUTEM 4 downhole system is a three-axis downhole transient EM system which incorporates a low-noise coincident three-axis coil design, fully digital down the hole encoding and a fibre-optic probe-to-surface data link.  The system allows three components of the transient magnetic field to be simultaneously averaged and stored.  Probe orientation within the hole is monitored by integrated 3-axis magnetometer and 3-axis accelerometer devices.  Temperature measurements taken to correct the accelerometer package can also be used to detect the thermal signature of ore bodies. Waveform and Sampling The UTEM transmitter passes a low-frequency (~1 Hz to 90 Hz) current of a precisely regulated waveform through the transmitter loop. The frequency may be set to any value within the operating range of the transmitter, but is usually set at 31 Hz so as to minimize power line effects (60 Hz noise).  Lower base frequencies are used to survey highly conductive bodies with time constants much larger than the 16ms half-cycle. Since the receiver coil responds to the time derivative of this magnetic field, it is said that the system really "sees" the step response of the ground. In practice, the transmitted waveform is tailored to optimize signal to noise and deconvolution techniques are employed within the system to produce an equivalent to this conceptual “step response” at the receiver. UTEM is the only time domain system which measures the step response of the ground.  All other T.D.E.M. systems, to date, transmit a modified step current so that they "see" the (im)pulse response of the ground at the receiver. While the channel time gates are programmable, a standard set of 13 time gates which fully sample the waveform are usually used as shown in Figure 2.  The time gates are described with respect to a system of units where the length of the half-cycle is 1062 units.  Ten of the thirteen channels are plotted and used for standard interpretation.  Figure 1 shows the plotting symbols used for these channels.  The latest of these is designated as channel 1 and it occupies almost the entire second half of the half-cycle, from 512 -1024 units.  Channels 2-10 are arranged in a binary progression, each occupying one half of the time interval remaining from the beginning of the half cycle.  Thus channel 2 is from 256 to 512 units, channel 3 is from 128 to 256units, etc.  Channels 11 and 12 are only one unit wide (15 microseconds @ 31 Hz) and they occupy opposite sides of the waveform transition.  They are used primarily for the purposes of monitoring phase drift between the transmitter and receiver clocks.  Channel 13 occupies the 37 unit wide interval from the end of channel 1, 1024 units, to 1061 units.  While this is later than channel 1, this channel is much narrower and hence less precise.  It is used in quality control and in some processing techniques but is not usually displayed. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "20
  • 21. Probe Orientation Because the probe is rotating freely in the hole the raw transverse components must be “rotated” to point in a consistent direction along the hole.  The rotation process is a mathematical one which is performed after the data are collected but which requires a knowledge of the actual orientation of the probe in the hole at each station.  The determination of the probe orientation is achieved using two independent tools; a three-axis magnetometer and a 3-axis accelerometer.  Data from these devices are collected before each EM stack.  In ideal situations, such as an inclined hole directed well away from magnetic north and away from large magnetic anomalies, either tool is capable of precise orientation of the probe.  In a near vertical hole, the accelerometer becomes incapable of determining the probe orientation, while in a hole directed along the earth’s magnetic field, the same is true for the magnetometer.  The data reduction software uses the best combination of the estimates derived by these two devices. Coordinate Systems The three observed components of the transient magnetic field are designated as Hu, Hv and Hw with: Hw being the axial component pointing down the hole and Hu and Hv oriented in a right-handed system with respect to Hw. The coordinate systems used to orient these transverse three-axis data are based on the concept of a drill section.  The drill section is a vertical plane perpendicular to the geological strike and is in general the plane in which inclined holes would be drilled.  It is specified by the drill section azimuth which is the azimuth of the positive coordinate direction within the plane.  For a north-south section plane, for instance, the drill section azimuth would be zero (due north) while for an east west section plane, it would be 090 (east).  Usually a section azimuth is adopted for an entire survey area, even if the actual azimuths of individual holes are slightly different.  Once the section is determined by the section azimuth, the out of section direction is 90 degrees clockwise from the section azimuth as seen in plan. UTEM 4 data are presented in one of two coordinate systems.  The coordinate system used to express the data is identified by the notation used for the components. Hole based coordinate system This is the most commonly used system.  In this system the components are designated as Hs, Hn and Hw.  Hw is the axial component and as such is independent of the orientation of the probe in the hole.  The Hn component lies on the plane perpendicular to the section plane.  Hs lies as close as possible to the designated drill section plane while being perpendicular to the other two components.  Note that Hs and the designated International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "21
  • 22. drill section plane are coincident only if the local hole azimuth is exactly the same as the designated section azimuth. The hole based coordinate system is useful for several reasons.  It is easiest to interpret the orientation of a conductive body relative to the trajectory of the hole, rather than in absolute terms.  In this respect a hole-relative coordinate system is much easier to use.  A second important reason is that the axial component has a substantially higher signal/noise than the transverse components.  In the hole based system, the axial component is plotted as is and is not required to be combined with the transverse components. Cartesian coordinate system This is not a standard presentation.  It may, however, be useful from time-to-time to present the data in the Cartesian system.  In this system the HS component is in the section direction, the HN component is in the out of section direction, and the HZ direction is down.  Note that in the Cartesian system, except in a vertical hole, every component is a linear combination of the three raw observed components.
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "22
  • 23. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "23
  • 24. Figures 3 and 4 show the main features of the geometry conventions and terminology used.  In Figure 3 the transient field vector is designated as H, which is resolved into the axial, Hw, and the transverse, Htr, components.  The transverse Htr is resolved into the Hs and Hn components where: Hn lies in the plane perpendicular to the designated drill section clockwise from Hs as seen in plan and Hs is perpendicular to both Hn and Hw   Note that the drill hole itself does not lie in the designated drill section.  Because of this the Hs component will not be exactly in the designated drill section in this example.  The designated drill section itself is specified by the section azimuth, measured clockwise from geographic north. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "24
  • 25. Figure 4 shows the relationship of the hole geometry to the magnetic and gravitational fields used for orienting the probe.  The magnetometer and accelerometer are both resolved into axial (Aw,Mw) and transverse (Atr,Mtr) components.  For each device, it is the resolution of the computed transverse field direction with the two observed transverse signals which determines the probe orientation.  The precision of orientation is greatest when the transverse field is a large component of the total. Orientation Device Selection The factors which limit the precision of the magnetometer and accelerometer devices as orientation tools are: While these factors cannot be tracked individually on a routine basis, the total transverse magnetic and gravitational fields are independent of the rotation of the probe in the hole and they can be compared to their predicted values.  The discrepancy between these is a measure of the “error” of the device as far as its use as an orientation tool and it forms a basis for the orientation tradeoff parameter, a.  This is a parameter which varies from +1.0 for pure magnetometer, to -1.0 for pure accelerometer.  In between, a linear weighted average between the probe orientations as determined by the mag and accelerometer is used. Data Reduction The kind of reduction applied to the raw data is indicated on each plot in the second field of the title block.  The observed UTEM data represents a sum of the signal directly from the transmitter loop (Primary field) and the field resulting from eddy currents induced in conductive bodies and/or a conductive host rock (Secondary field).  In the case of a Total Field plot the observed data are simply expressed as a percentage of a normalizing field which is either the primary field magnitude at a fixed point in space (Point Normalization) or the primary field magnitude at each station (Continuous Normalization).  The Secondary Field is of most interest from an interpretive point of view.  As such an estimate of the primary field must be determined and subtracted from the data.  There are two ways in which this is done: Magnetometer Accelerometer magnetic anomalies gravitational anomalies (insignificant) errors in magnetic declination and inclination orientation of gravitation field is known precisely errors in surveyed azimuth and dip of hole errors in surveyed azimuth and dip of hole no significant temperature dependence temperature calibration of accelerometer incorrect magnetic tensor calibration accelerometer tensor calibration International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "25
  • 26. 1. Primary Field Reduction:            The computed primary field is subtracted from all channels.  This is designated by the formula (Chn-Hpc)/(|Hp|) in the title block of the plot. 2. Channel 1 Reduction:            The computed primary field is subtracted from Channel 1. For all earlier channels, channel 1 is subtracted as an estimate of the primary field.  This is designated by the formula (Chn-Ch1)/(|Hp|) in the title block of the plot. As in the Total field case, the |Hp| primary field magnitude in the denominator is either evaluated at a fixed point in space (Point Normalization) or at each station (Continuous Normalization). Standard BHUTEM 4 Plot Suite The UTEM 4 3-axis data are usually presented as a set of five profile plots for each hole and loop surveyed.  The data are plotted as a function of the distance down the hole.  The depth axes are always labelled in metres but are also labelled in feet on imperial grids.  Each axis which displays EM data indicates the component according to the conventions discussed above (Hs, Hn, Hw).  As well, the component is indicated graphically by the direction of the arrow in the small coordinate axis system plotted at the end of each axis.  To understand this system, consider that the plot is oriented with the axis down, that the section plane is the plane of the paper and that the section direction is to the right.  The out of section component is then out of the page.  The value of the geographic section azimuth is indicated in the second field of the title block of each of the plots along with the type of reduction and normalization.  All plots include as well a profile on the lowest axis which shows the orientation tradeoff parameter used to derive the probe orientation.  The plot set is comprised of: • 3 plots of channel 1 reduced secondary field: one each for components Hs, Hn and Hw.  These plots have the early, intermediate and latest time channels plotted on separate axes.  The computed primary field in the direction of the component is also plotted as a solid curve on the upper axis with the early time channels. • 1 total field plot: with all channels of each of the three components on a different axis.  Each axis includes as well a plot of the primary field as a solid curve.  In most cases the following of the primary field curve of each of the components by its respective channel 1 indicates that the basic geometry of the hole relative to the loop is correct.  This may not be true, however in very conductive environments where a large response persists in channel 1. • 1 plot comprised of magnetometer data on the top axis, accelerometer data on the middle axis and temperature data on the lower axis.  For the mag and accelerometer plots, three curves are presented.  In black, the observed axial (symbol W) and total transverse (symbol R) are plotted, while in grey, the expected total transverse is plotted.  Discrepancies between the expected and the observed total transverse mag and accelerometer components can point to a number of problems including: incorrect hole International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "26
  • 27. dip, incorrect hole azimuth, poor mag/acc device calibration, magnetic anomalies and incorrect magnetic declination and/or inclination. The raw temperature profile taken down the hole is dominated by the geothermal gradient of about 18°C per kilometre of depth.  Superimposed on this are small amplitude anomalies which may be beneficial in locating thermally conductive dipping ore bodies.  The curve that is plotted is the residual temperature after the removal of a best fitting polynomial.  The order of the polynomial used in indicated in the axis label of the plot.  For example, “Temp-P(2)”, indicates that a second order polynomial has been subtracted. 
 International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "27
  • 28. Appendix E: Note on sources of anomalous Ch1 BH UTEM 4 Survey Elliot Lake area, Ontario, Canada for International Montoro Resources Inc. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "28
  • 29. Note on sources of anomalous Ch1 This section outlines the possible sources of anomalous channel 1 which is not correlated to the Ch2-10 data plotted on the upper axes of a channel 1 normalized  plot. 1) Mislocation of the transmitter loop and/or survey stations Mislocating the transmitter loop and/or the survey stations results in an error in the calculated primary field at the station and appears as an anomalous Ch1 value not correlated to channel 1 normalized Ch2-10.  The effect is amplified near the loop front.  This can be seen in the profiles - the error in Ch1 generally increases approaching the loop.  As a rule a 1% error in measurement of the distance from the loop will result in, for outside the loop surveys, an error in Ch1 of: • 1% near the loop front (long-wire field varies as 1/r) • 3% at a distance from the loop front (dipolar field varies as 1/r3) • 2% at intermediate distances (intermediate field varies as ~1/r2) Errors in elevation result in smaller errors but as they often affect the chainage they accumulate along the line.  The in-loop survey configuration generally  diminishes geometric error since the field gradients are very low.  At the centre of the loop the gradient in the vertical field is essentially zero so it is difficult to introduce geometric anomalies near the loop centre.  Near the loop sides and at the closest approach of the lines to the wire mislocation of the loop and the station becomes more critical.  Typically loop sides are designed to be >200m from any survey stations. 2)  Magnetostatic UTEM responses Magnetostatic UTEM responses  arise over rocks which generate magnetic anomalies.  Such magnetic materials will amplify the total (primary + secondary) field of the UTEM transmitter which is sensed by the receiver coil.  The secondary field is generated by subtracting a computed primary which does  not include magnetic effects.  This can give rise to strong and abrupt channel 1 anomalies when the source of the magnetics is at surface.  This is the case in a number of places on these grids.  UTEM magnetostatic anomalies differ from DC magnetic anomalies in the following three major ways: 1. In the case of DC magnetics the field is dipping N and is very uniform over the scale of the survey area while the UTEM field inside the loop is vertical and it is stronger near the loop edges. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "29
  • 30. 2. Most aeromagnetics are collected as total field while with UTEM we measure a given (in this case generally z,x) component. 3. DC magnetic instruments observe the total magnetization of the causative body which is due to its susceptibility as well as any remnant magnetization. An AC method such as UTEM will not respond to the remnant portion of the magnetization. The larger amplitude of the UTEM Ch1 response is explained by the fact that the UTEM primary field is often more favourably coupled (magnetostatically speaking) to  magnetic mineralization as compared to the earths field.  Another factor could be the presence of a reverse remnant component to the magnetization. Note that positive (negative) magnetic anomalies will cause: • positive (negative) Ch1 anomalies in data collected outside the loop • negative (positive) Ch1 anomalies in data collected inside the loop 3) Extremely good conductors An extremely good conductor will be characterized by a time constant much longer than the half-period (@ 30Hz >>16ms).  This will give rise to an anomalous Ch1 which is not correlated to the Ch2-10 data plotted on the upper axes of a channel 1 normalized plot. International Montoro Resources Inc.―BH UTEM 4 Survey―Elliot Lake –1512 Page "30