Jeffrey Phillips, Electric Power Research Institute (EPRI) - Speaker at the marcus evans Generation Summit held in Dallas, TX, February 25-26, 2013, delivered his presentation entitled 21st Century Coal Power: Recent Developments in Coal Power Generation Technology
Similar a 21st Century Coal Power: Recent Developments in Coal Power Generation Technology - Jeffrey Phillips, Electric Power Research Institute (EPRI)
Similar a 21st Century Coal Power: Recent Developments in Coal Power Generation Technology - Jeffrey Phillips, Electric Power Research Institute (EPRI) (20)
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
21st Century Coal Power: Recent Developments in Coal Power Generation Technology - Jeffrey Phillips, Electric Power Research Institute (EPRI)
1. 21st Century Coal Power
Recent Developments in Coal Power Generation Technology
Dr. Jeffrey N. Phillips
Senior Research Manager
Generation Summit
February 25, 2013
27. FutureGen 2.0
Oxy-Combustion w/ CO2 Sequestration
• Meredosia, IL & Morgan Co., IL
• 167 MWe gross oxy-combustion
repowering of Ameren’s Meredosia
Unit 4 steam turbine
• 90% CO2 capture (cryogenic
separation) 1,000,000 tons CO2 /year
• Deep saline sequestration in Mt.
Simon formation ~30 miles east of
power plant
• Total Project: $1.65 Billion
DOE Share: $1.05 Billion
Status
Phase 1 (Pre-FEED) completed
Key Dates
Initial sequestration site
Complete FEED: Sep 2013 characterization completed
Construction: Sep 2014 Phase 2 (NEPA, Design and
Commercial Operation: Sept 2017 Permitting) initiated February 1, 2014
27
30. Southern Company Services, Inc. CCPI-2
Advanced IGCC with CO2 Capture
• Kemper County, MS Plant Site
• 582 MWe (net); 58 MWe duct firing; 2 TRIGTM
gasifiers, 2 Siemens combustion turbines, 1
Toshiba steam turbine
• Fuel: Mississippi lignite
• ~67-69% CO2 capture (Selexol® process);
3,000,000 tons CO2/year
• EOR; Denbury Onshore LLC, Treetop
Midstream Services LLC
• Total DOE Project: $2.01 Billion;
DOE Share: $270 Million (13%) Status
• Total estimated plant cost: ~ $3 Billion Plant construction >50% complete;
>4,000 construction workers on site
Key Dates CO2 off-take agreements signed
Project Awarded: Jan 30, 2006 Lignite mine under development
Project moved to MS: Dec 5, 2008 Subsystems (water treatment, cooling
NEPA Record of Decision: Aug 19, 2010 towers) to begin pre-commissioning
Initiate excavation work: Sept 27, 2010 Combustion turbine startup: Jul 2013
Operations: May 2014 Gasifier heat-up: Dec 2013
30