SlideShare una empresa de Scribd logo
1 de 18
Estimating
Using Effort and Duration
Project Management
Introduction to Estimation
• Estimating is argued to be one of the most difficult tasks in Project Scheduling
• This is due to the lack of available specific data regarding product resources i.e.
how much a product will cost, how long it will take etc.
• The lack of this data means that project managers can only provide estimates
• These estimates are usually wide ranging
• Wide ranging estimates are better than specific estimates which are likely to be
wrong
Estimating Project costs with Duration
and Effort
• Before the start of a project three things must be estimated:

• Duration: time the project will take
• Effort: the amount of work
• Cost: how much the project will cost financially
Estimating Project Costs with Duration
and Effort
• Effort must be estimated first
• Duration can be estimated from the amount of effort required and
the resources which are available
• Once effort and duration have been establish project costs can be
estimated using labour and non-labour items
Techniques for Estimating
• Quantitatively based or Parametric Estimating
• Analogous Estimating or As-buts
• Bottom-up Estimating
• Using Learning Curve Effects
• Wishful thinking
• Expert judgement
Parametric Estimating
• Works best when there is existing experience of similar projects
• Project is broken down into units which can then be estimated using independent
variables
• These variables are often standard or previously known variables
• Costs can be estimated from knowledge of what work is being undertaken
• Relies on repetition in previous projects
• Similar to Analogous estimating but follows a more statistical approach

• The accuracy of the data/known variables effects the accuracy of this approach
Analogues Estimating or As….Buts
•
•
•
•

Useful for early project estimates
The organisation uses previous experience which is similar to make an estimate
Use costs from previous experience as a guideline for estimation
If previous projects are not reviewed then the accuracy of previous estimates is
unknown
• Therefore previous costs etc. might not provide valuable valid estimates
• This may cause mistakes to be repeated as no learning has occurred
• Previous estimates can be used if they are reviewed and augmented
Bottom-up Estimating
• The project is broken down into estimated components
• Each component is broken down further to allow for greater understanding
• The costs of each work component is summed from the bottom up to provide an
estimation for the whole project.
Learning Curve Effects
• There will be areas of repetition in projects, repetition decreases the time
required for tasks as they are known and learning has already occurred
• Subsequent improvements in speed are seen to become smaller over time
• This can be quantified using the following formula:
Yx = Kxn
where
• x = the number of times the task has been carried out
• Yx = time taken to carry out the task the xth time
• K = time taken to carry out the task the first time
• n = log b/log 2 where b = learning rate
Wishful Thinking
Some causes of wishful thinking occurring are:
• Optimism Bias: being over-optimistic regarding timeframes and costs
• Politics: for examples when objectives are regarded as being more
important than costs
• Failure to be systematic about planning: i.e. people making estimates
can be complacent and/or unqualified
Expert Judgement
• Estimation requires a degree of expert judgement
• There is a degree of expert judgement required in the project and of the business
area.
• The project manager is assumed to have expert judgement
Problems with Estimates
• Inappropriate use of estimates: i.e. rough estimates may be used as
definitive estimates.
• Inappropriate data used to generate estimates: such as irrelevant past
experience
• Estimates are taken out of context: for example initial estimates are
used when changes have been made to the project
Nature, Role and Accuracy of Estimate
Types
Name
Nature
Role
Accuracy
Rough/Ballpark

Much uncertainty as to
what is involved

Early check on feasibility
of brief

As-buts

As was carried out
With an appropriate
previously but with some contingency factor, can
amendments
be used for proposals

Moderate

Detailed Estimates

Some initial work is
carried out to determine
what the likely problems
are going to be

Proposals

Moderate

To Finish

Much of the Project is
completed and
additional funding is
needed to complete the
tasks

Additional fund requests

High

Source: Maylor. 2010. Project Management

Very low
Parkinson’s Law
• An activity will expand to fill the time available
• A critical review of Parkinson’s Law and it’s implications can be found
in the article below
Genaro J. Gutierrez and Panagiotis Kouvelis, Parkinson's Law and Its
Implications for Project Management. Management Science. Vol. 37,
No. 8 (Aug., 1991), pp. 990-1001
Techniques for Accuracy
1.
2.
3.
4.
5.
6.

Clarify the project priorities, understand the scope of the project
Incorporate time to generate estimates in the project plan
Break the project down into detailed tasks
Use learning from previous projects
Avoid making estimates to please management
Refine the project scope throughout the duration of the project to
improve accuracy
7. Use multiple estimating techniques
Techniques for Accuracy
• Bottom up estimating and Parametric estimating offer the highest
levels of accuracy
• Bottom up estimating: provides the highest level of accuracy when
there is suitable detail regarding the components
• Parametric Estimating: provides high levels of accuracy when the data
is of good quality and due to the statistical nature of the approach
Further Reading
• Maylor: Project Management, 4th ed, Chapter 6 & 8

• Chapman., and Ward. 2003. Constructively Simple Estimating: a
Project Management Example. Journal of the Operation Research
Society. 54. 1050-1058.
References
• Maylor, H., 2010. Project Management. 4th ed. Chester: Pearson
• Tom Mochal, 2006. Estimate project costs after you have estimated effort and duration. [Online]
Available at: http://www.techrepublic.com/article/estimate-/project-costs-after-you-haveestimated-effort-and-duration/ [Accessed: 07/11/13]
• CHRIS O'HALLORAN, 2013. Project Estimation Techniques and Templates. [Online] Available at:
http://strikingprojectmanagement.com/project-estimation/ [Accessed 07/11/13]
• Adele Sommers, 2013. 12 Tips for Accurate Project Estimating. [Online] Availbale at:
http://www.projectsmart.co.uk/12-tips-for-accurate-project-estimating.html [Accessed 07/11/13]

• MindTools, 2013. Estimating Time Accurately. [Online] Available at:
http://www.mindtools.com/pages/article/newPPM_01.htm [Accessed 07/11/13]

Más contenido relacionado

La actualidad más candente

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project schedulingVaibhav Khanna
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
It's not a bug, it's a feature!
It's not a bug, it's a feature!It's not a bug, it's a feature!
It's not a bug, it's a feature!SPC Adriatics
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costsmairemic
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 
Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?SPC Adriatics
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and trackingComputer_ at_home
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)anjalatchi
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 

La actualidad más candente (19)

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
It's not a bug, it's a feature!
It's not a bug, it's a feature!It's not a bug, it's a feature!
It's not a bug, it's a feature!
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?
 
Ch03
Ch03Ch03
Ch03
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
 
Is Sks7000
Is Sks7000Is Sks7000
Is Sks7000
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 

Destacado

8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8Warui Maina
 
Risk management profesional presentation
Risk management profesional presentationRisk management profesional presentation
Risk management profesional presentationKarim El-Dash
 
Iwsm2014 why cant people estimate (dan galorath)
Iwsm2014   why cant people estimate (dan galorath)Iwsm2014   why cant people estimate (dan galorath)
Iwsm2014 why cant people estimate (dan galorath)Nesma
 
Complexity in projects
Complexity in projectsComplexity in projects
Complexity in projectsLeon Dohmen
 
Day 3 Analogous, estimates and semantics for process
Day 3   Analogous, estimates and semantics for process Day 3   Analogous, estimates and semantics for process
Day 3 Analogous, estimates and semantics for process Arun
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Scaling Agile at Spotify (representation)
Scaling Agile at Spotify (representation)Scaling Agile at Spotify (representation)
Scaling Agile at Spotify (representation)Vlad Mysla
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterYudha Pratama, PMP
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 

Destacado (13)

8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
 
Risk management profesional presentation
Risk management profesional presentationRisk management profesional presentation
Risk management profesional presentation
 
Iwsm2014 why cant people estimate (dan galorath)
Iwsm2014   why cant people estimate (dan galorath)Iwsm2014   why cant people estimate (dan galorath)
Iwsm2014 why cant people estimate (dan galorath)
 
Complexity in projects
Complexity in projectsComplexity in projects
Complexity in projects
 
Day 3 Analogous, estimates and semantics for process
Day 3   Analogous, estimates and semantics for process Day 3   Analogous, estimates and semantics for process
Day 3 Analogous, estimates and semantics for process
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
full-stack agile - Scrum Basics
full-stack agile -  Scrum Basicsfull-stack agile -  Scrum Basics
full-stack agile - Scrum Basics
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Scaling Agile at Spotify (representation)
Scaling Agile at Spotify (representation)Scaling Agile at Spotify (representation)
Scaling Agile at Spotify (representation)
 
Agile at Spotify
Agile at SpotifyAgile at Spotify
Agile at Spotify
 
Complex project management
Complex project managementComplex project management
Complex project management
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charter
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 

Similar a Estimating in Project Scheduling

Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and consPragnendra Rahevar
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfAnatole9
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planningShruti Kunwar
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss19UBCA020HARIHARANK
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptxdotco
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptxgezaegebre1
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 

Similar a Estimating in Project Scheduling (20)

Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdf
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptx
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Adamson "Project Management, Predictive Planning"
Adamson "Project Management, Predictive Planning"Adamson "Project Management, Predictive Planning"
Adamson "Project Management, Predictive Planning"
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 

Más de Nicola2903

Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureNicola2903
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 

Más de Nicola2903 (12)

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Estimating
EstimatingEstimating
Estimating
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 

Último

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 

Último (20)

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 

Estimating in Project Scheduling

  • 1. Estimating Using Effort and Duration Project Management
  • 2. Introduction to Estimation • Estimating is argued to be one of the most difficult tasks in Project Scheduling • This is due to the lack of available specific data regarding product resources i.e. how much a product will cost, how long it will take etc. • The lack of this data means that project managers can only provide estimates • These estimates are usually wide ranging • Wide ranging estimates are better than specific estimates which are likely to be wrong
  • 3. Estimating Project costs with Duration and Effort • Before the start of a project three things must be estimated: • Duration: time the project will take • Effort: the amount of work • Cost: how much the project will cost financially
  • 4. Estimating Project Costs with Duration and Effort • Effort must be estimated first • Duration can be estimated from the amount of effort required and the resources which are available • Once effort and duration have been establish project costs can be estimated using labour and non-labour items
  • 5. Techniques for Estimating • Quantitatively based or Parametric Estimating • Analogous Estimating or As-buts • Bottom-up Estimating • Using Learning Curve Effects • Wishful thinking • Expert judgement
  • 6. Parametric Estimating • Works best when there is existing experience of similar projects • Project is broken down into units which can then be estimated using independent variables • These variables are often standard or previously known variables • Costs can be estimated from knowledge of what work is being undertaken • Relies on repetition in previous projects • Similar to Analogous estimating but follows a more statistical approach • The accuracy of the data/known variables effects the accuracy of this approach
  • 7. Analogues Estimating or As….Buts • • • • Useful for early project estimates The organisation uses previous experience which is similar to make an estimate Use costs from previous experience as a guideline for estimation If previous projects are not reviewed then the accuracy of previous estimates is unknown • Therefore previous costs etc. might not provide valuable valid estimates • This may cause mistakes to be repeated as no learning has occurred • Previous estimates can be used if they are reviewed and augmented
  • 8. Bottom-up Estimating • The project is broken down into estimated components • Each component is broken down further to allow for greater understanding • The costs of each work component is summed from the bottom up to provide an estimation for the whole project.
  • 9. Learning Curve Effects • There will be areas of repetition in projects, repetition decreases the time required for tasks as they are known and learning has already occurred • Subsequent improvements in speed are seen to become smaller over time • This can be quantified using the following formula: Yx = Kxn where • x = the number of times the task has been carried out • Yx = time taken to carry out the task the xth time • K = time taken to carry out the task the first time • n = log b/log 2 where b = learning rate
  • 10. Wishful Thinking Some causes of wishful thinking occurring are: • Optimism Bias: being over-optimistic regarding timeframes and costs • Politics: for examples when objectives are regarded as being more important than costs • Failure to be systematic about planning: i.e. people making estimates can be complacent and/or unqualified
  • 11. Expert Judgement • Estimation requires a degree of expert judgement • There is a degree of expert judgement required in the project and of the business area. • The project manager is assumed to have expert judgement
  • 12. Problems with Estimates • Inappropriate use of estimates: i.e. rough estimates may be used as definitive estimates. • Inappropriate data used to generate estimates: such as irrelevant past experience • Estimates are taken out of context: for example initial estimates are used when changes have been made to the project
  • 13. Nature, Role and Accuracy of Estimate Types Name Nature Role Accuracy Rough/Ballpark Much uncertainty as to what is involved Early check on feasibility of brief As-buts As was carried out With an appropriate previously but with some contingency factor, can amendments be used for proposals Moderate Detailed Estimates Some initial work is carried out to determine what the likely problems are going to be Proposals Moderate To Finish Much of the Project is completed and additional funding is needed to complete the tasks Additional fund requests High Source: Maylor. 2010. Project Management Very low
  • 14. Parkinson’s Law • An activity will expand to fill the time available • A critical review of Parkinson’s Law and it’s implications can be found in the article below Genaro J. Gutierrez and Panagiotis Kouvelis, Parkinson's Law and Its Implications for Project Management. Management Science. Vol. 37, No. 8 (Aug., 1991), pp. 990-1001
  • 15. Techniques for Accuracy 1. 2. 3. 4. 5. 6. Clarify the project priorities, understand the scope of the project Incorporate time to generate estimates in the project plan Break the project down into detailed tasks Use learning from previous projects Avoid making estimates to please management Refine the project scope throughout the duration of the project to improve accuracy 7. Use multiple estimating techniques
  • 16. Techniques for Accuracy • Bottom up estimating and Parametric estimating offer the highest levels of accuracy • Bottom up estimating: provides the highest level of accuracy when there is suitable detail regarding the components • Parametric Estimating: provides high levels of accuracy when the data is of good quality and due to the statistical nature of the approach
  • 17. Further Reading • Maylor: Project Management, 4th ed, Chapter 6 & 8 • Chapman., and Ward. 2003. Constructively Simple Estimating: a Project Management Example. Journal of the Operation Research Society. 54. 1050-1058.
  • 18. References • Maylor, H., 2010. Project Management. 4th ed. Chester: Pearson • Tom Mochal, 2006. Estimate project costs after you have estimated effort and duration. [Online] Available at: http://www.techrepublic.com/article/estimate-/project-costs-after-you-haveestimated-effort-and-duration/ [Accessed: 07/11/13] • CHRIS O'HALLORAN, 2013. Project Estimation Techniques and Templates. [Online] Available at: http://strikingprojectmanagement.com/project-estimation/ [Accessed 07/11/13] • Adele Sommers, 2013. 12 Tips for Accurate Project Estimating. [Online] Availbale at: http://www.projectsmart.co.uk/12-tips-for-accurate-project-estimating.html [Accessed 07/11/13] • MindTools, 2013. Estimating Time Accurately. [Online] Available at: http://www.mindtools.com/pages/article/newPPM_01.htm [Accessed 07/11/13]