                                   Problems in Queuing Theory
1. (Case 1) A computing system has a single printer attached to print out the output of the users. The
   operating system software sends an average of 20 requests per hour to the printer. The printer is
   capable of printing out 35 jobs per hour on the average. Assume that the job arrival rate and the
   printing rate are Poisson distributed.
   a. On the average, how many jobs are in the output queue waiting to be printed out?
   b. How many jobs are in the “printer output system” on the average?
   c. How long can a user expect to wait to have his or her job printed out once it has been sent to the
       printer?
   d. Once a job enters the output queue, how long does it take before printing begins on the job?
   e. What percentage of time will the printer be busy doing print jobs?
   f. (Case 2) Assume that a second printer is added to the system. Answer questions 1.1 to 1.5,
       assuming that the two printers are identical.

2. (Case 1) Telephone calls arrive at a particular small-scale paging system at the Poisson rate of 20 per
   hour. The calls are transferred to an operator that can handle an average of 25 calls per hour,
   following an exponential distribution. The operator can handle only one caller at a time; if the
   operator is busy, arriving calls are put on hold and the callers are assumed to be patient.
   a. Assume that no limit is placed on the number of calls that can be put on hold:
       1) What percentage of the time is the operator busy?
       2) On the average, how many callers are on hold?
       3) On the average, how long can a caller expect to spend on the telephone when calling this
           office?
   b. (Don’t do this) Suppose that with the single operator, only a maximum of two calls can be put on
       hold. How does this affect your answers in 2.1?
   c. (Case 2) Suppose that an additional operator is hired, with no limit on the number of calls on
       hold:
       1) What percentage of the time are both operators busy?
       2) On the average, how many callers are on hold?
       3) On the average, how long can a caller expect to spend on the telephone when calling this
           office?
   d. (Case 2) Suppose that the office management feels that, in order to provide good customer
       service, a caller should not have to wait more than 10 seconds on hold. How many telephone
       operators should be hired to answer calls?

3. Orders for a firm’s products arrive at the rate of 200 a week. A single clerk is assigned to process the
   orders at an average of 250 orders per week. The cost of delaying an average shipment for 1 week is
   P500. If a clerk costs P300 per week, how many clerks should be assigned to process the
   paperwork?

4. Moonlight Travel Reservation Service has one agent and 3 telephone lines. When the agent is busy,
   the next caller is placed on hold on one of the remaining lines. When all three lines are busy, callers
   receive a busy signal and call elsewhere for reservations. Service appears to be exponentially
   distributed, with a mean of three minutes. Calls arrive randomly at a Poisson rate of 15/hour.
   a. What is the probability that a caller receives a busy signal?
   b. What is the average number of customers put on hold at any given time?
   c. What is the probability that a customer is placed on hold?
   d. How long, on the average, will a customer be on hold before the agent can attend to him?
   e. If a caller makes three attempts before finally calling elsewhere for reservations, what fraction of
        the customers will be able to do business with Moonlight Travel Reservation Service?
5. (Case 1) Customers arrive at a one-person barber shop with an average interarrival time of 20
   minutes. The average time for a haircut is 12 minutes, exponentially distributed.
   a. The owner wishes to have enough seats in the waiting area so that on the average no more than
       5% of the arriving customers will have to stand. How many seats should be provided?
   b. Suppose that there is only sufficient space in the waiting area for five seats. What is the
       probability that an arriving customer will not find a seat?

6. A plant distributes its products by truck. The exponential average loading time per truck at the
   loading facility is 20 minutes. Trucks arrive at a rate of 2/hour. Management feels that the existing
   loading facility is more than adequate. However, the drivers complain that they have to wait more
   than half of the time. Analyze the situation and find how much money the company can save if the
   waiting time of a truck is figured at P10/hr and the plant is in operation 8 hours per day. An
   automatic device that can load 10 trucks per hour is available at a cost of P90/day over the cost of the
   existing facility.

7. Campers arrive at the County Park at a Poisson rate of 100 per month. The time spent in the park by
   a camper varies according to an exponential distribution with a mean of 0.10 month. Since the park
   is very large, campers have no problem finding a campsite. However, the state recreation officials
   have a policy of maintaining a certain level of forest-ranger workforce for the convenience and safety
   of the campers. The current policy is to have one ranger per 10 campers at any given time.
   a. How many campers are using the park on the average?
   b. What percentage of the time is the park empty?
   c. How many forest rangers should the state employ at the County Park?

8. A gasoline station is served by 1 employee who is capable of serving 30 customers per hour, varying
   according to an exponential distribution. There is a maximum space for five cars in the station,
   including those served and in line. Cars arrive at the station at an average rate of every 3 minutes.
   Cars that do not have parking spaces leave and do not return. Find:
   a. The average number of cars waiting for service.
   b. The probability of finding no car in the station.
   c. The average waiting time in line for each car.
   d. The probability of finding 3 cars in the station at any given time.
   e. It was proposed to increase the space so that 10 cars would be accommodated. The investment
        would entail P5 per car space per hour. A car that leaves the station means a loss of P10.
        Should the space be enlarged or not?

9. A shop utilizes 10 identical machines. The profit per machine is P40 per hour of operation. Each
   machine breaks down on the average once every 7 hours. One person can repair a machine in 4 hours
   on the average, but the actual repair time varies according to a Poisson distribution. The repairman’s
   salary is P60/hour. Determine:
   a. The number of repairmen that will minimize cost.
    b. The number of repairmen needed so that the expected number of broken machines at any given
       time is less than 4.
   c. The number of repairmen needed so that the expected delay time until a machine is repaired is
       less than 4 hours.

10. (Case 2) Students arriving at the computing center can wait either at a small table in the center
    (which will seat four students) or if the table is full they can go to a nearby student lounge or they
    can wait in the hall. What percentage of time will the waiting area inside the computing center be
    sufficient to accommodate the waiting students?

11. The city of Manila operates a large fleet of police squad cars. When a car breaks down due to a
    minor malfunction it is sent to a single-garage repair facility where it is repaired by a crew of
mechanics. The crew foreman, Jim, must put in a request to hire her team mechanics. If n
    mechanics work on a single car together, repair time for minor repairs is approximately constant at
    20/n minutes. Disabled squad cars arrive at the repair facility at the Poisson rate of five cars per
    hour. The police chief tells Joanne that on the average he does not want a squad car to be out of
    commission for longer than 15 minutes.
    a. What is the minimum number of mechanics Joanne should hire?
    b. On the average, how many squad cars are out of commission?

12. Solve Joanne’s facility design problem (exercise 11 above) under the assumption that the reapir time
    of 20/n minutes is a mean exponential time. Answer both parts (a) and (b) of the problem.

13. The manufacturing Supervisor of Hardpress Industries must decide between three makers of forklift
    trucks to use on the plant floor. The truck will be used to move raw materials from storage bins to
    work centers in a section of the plant. Request from these work centers occur according to a poisson
    process at a mean rate of eight per hour. The time to move raw materials is exponentially distributed.
    The service rates per hour for each of the truck under consideration is given in the table along with
    estimated costs per hour (operating costs plus depreciation). For each hour a work center is idle
    waiting for raw materials, an average cost of P100 is incurred (wages plus lost productivity).

                                                  Table
                     Truck                Service Rate (jobs/hr)             Cost (P/hr)
                       1                           10                            30
                       2                           15                            50
                       3                           18                            40

     Which truck would you purchase based on queueing analysis? (Be sure to specify clearly the
     queueing model you are using.)

14. In exercise 13, would your purchase choice change if the Manufacturing Supervisor felt that the
    service times of the forklift trucks were (more or less) constant times? That is, Truck 1 can service
    work centers at the constant rate of 10 jobs per hour, Truck 2 at 15 per hour, and Truck 3 at 18 per
    hour. (What would be the total cost per hour of using each of the trucks?)

15. (Case 1) The state operates a weigh station for trucks traveling on the highway. Every truck must
    pull off the highway, enter the weigh station, and undergo state inspection procedures before
    counting on. Trucks arrive at this station at a poisson rate of seven per hour. The time to
    inspect/weigh a truck varies, having an exponential probability density with a mean of 7 minutes.
    a. How many trucks are detained at the station on the average?
    b. How long can a truck expect to be detained?
    c. How many trucks are lined up in front of the station on the average?
    d. How long on the average does a truck driver have to wait in line for the truck to be inspected?

16. Refer to exercise 15, the truck driver traveling the route passing the weigh station have complained
    of long waiting time at the inspection point. The major phase of the inspection procedure consists of
    weighing-in the truck. The state highway commissioner has decided to look into ways of reducing
    the average time a trucker must spend at the weigh station to 25 minutes or less. The commissioner
    is considering the purchase of new digital solid waste weighing scale that should reduce the weighing
    time. Three manufacturer’ products are available: (1) model 1 costs P10000 and could check 10
    trucks per hour, (2) model 2 costs P12000 and would have an average service time of 5.5 minutes,
    and (3) model 3 costs P8500 and would have an average service time of 6.5 minutes.
    a. Determine which model to purchase.
    b. For the decision made in part (a), determine system operating characteristics P0, L, Lq, W and Wq.

17. A recent increase in consumer complaints at Jersey Electric Authority has led to a decision to assign
one person to receive the complaints. Complaints are phoned in at a rate of 20 per hour and are
    poisson distributed. Call can handled at a rate of 40 per hour. Service times vary considerably and
    have been found to be exponentially distributed. Jersey Electric would like to make sure that no
    more than 5% of the calls receive busy signals. If the operator is busy, calls can be placed on a
    “hold” line. How many hold lines should be provided to ensure that the 5% target will be reached?

18. The mean arrival rate at each of two identical service systems is 21 per day. Both systems operate
    independently and have service rates of 30 customers per day. The cost of 1 day of waiting time is
    P50 per customer. Assume that it is possible to consolidate the two servers into a multiple-channel
    system. Determine the reduction in waiting cost that such a move would accomplish.

19. A service facility has a poisson arrival rate of 9 customers per hour. There is no room for customers
    to wait for service , and arrivals encountering a busy system are forced to balk. If service times are
    exponentially distributed and the rate of service is 10 per hour, what percent of the customers will be
    unable to join the system? What percent will be lost if room is provided for 1 customer to wait? If
    room is provided for 2 customers to wait? If room is provided for 3 customers to wait?

20. Eastern Machine Company has a tool room with two clerks. Both clerks issue spare parts and tools
    to maintenance workers. Maintenance workers arrive at a rate of 20 per hour, each wanting either a
    part (40 percent) or a tool (60 percent), but not both. The arrival follow the poisson distribution.
    The average issuing time is five minutes per order (service by one clerk). This service time has been
    observed to be exponentially distributed. Each clerk currently issues both parts and tools. A
    maintenance worker not at his bench costs the company P5 per hour.
    a. What is the average time a maintenance worker is not at his bench?
    b. What is the probability that both clerks are busy with no one waiting in line?
    c. It was proposed that the two clerks be specialized. Namely: one will issue spare parts only, and
        the other will issue tools only.
        1) Would you advise specialization if the service time is reduced to four minutes per order?
        2) What is the probability that both clerks are observed to be busy in 2 out of 10 observed times
            if the proposal is implemented?

21. An airline firm is attempting to determine the number of reservation clerks required at one of its
    reservation offices. Incoming calls are put on hold for the first available clerk. Customer calls arrive
    randomly in a poisson manner at the mean rate of 4 per minute and service time tends to be
    exponentially distributed with a mean time of 40 seconds per call.
    a. What is the minimum number if clerks needed if management has decided that a customer should
        not wait more than 60 seconds, on the average, before being connected with a clerk?
    b. The airlines pays its reservation clerks P6 per hour. Customer time is valued at P6 per hour.
        What is the optimal number if reservation clerk?

22. Workfor metals purchases metals to be recycled from several sources. These metals consist of steel
    bars and sheets, aluminum shapes, and iron plates. Truckload shipments of scrap metals arrive at
    Workfor at an average rate of 1 truckload per day. These trucks are owned and operated by Workfor.
    Each shipment must be unloaded by a crew workers. A crew of n workers can unload 0.8n
    trucks/day. For each day that a truck is detained in unloading, a cost of P300 is incurred (due to lack
    productive use of the truck and hourly wages of truck drivers and his assistant). Each worker in the
    unloading crew is paid P105 per day. Determine the optimal no. of crew members to hire assuming
    the arrival and service rates are poisson.

23. (Case 2) Students arriving at a student registration center of university must have their registration
    materials processed by an operator seated at a computer terminal. The system design calls for 4
    operators to be on duty with each operator performing an identical service. Students arrive according
    to a poisson process at an average rate of 90 per hour, Each operator can process 30 students per
    hour. The service time is exponential.
a. What fraction of the time are there no students in the registration center?
    b. If the waiting area can comfortably accommodate 3 students, what is the probability that there
       will be students lined up outside the building.
    c. How long is the line of students waiting to register?
    d. A students arrives at 4:58 pm. The closing time is strictly set at 5:00 pm. Can we expect the
       student to finish the whole registration process?

24. Machinist at a firm periodically need a wide range of special purpose tools, which are stored at 3
    locations on the plant floor. Each tool room is staffed by one clerk, who checks the tools in and out.
    Arrivals at each tool room are poisson distributed with a mean of 15 employees per hour. Service
    times are exponential and average 3 minutes. It has been proposed that the 3 tool rooms be
    consolidated into a single centrally located facility staffed by 3 clerks. Travel time it takes for a
    machinist to walk to and from the work area to a tool room would be increased by an average of 2
    minutes. Each hour that a machinist spends away from the work area has been estimated to cost P10
    per hour. Service costs will not be reduced by the move to a single tool room. Evaluate the
    proposal.

25. Superchopper Supermarket operate two types of checkout lanes, an express lane (for purchases less
    than or equal to 8) and a regular lane. The person at the express lane cash register can check out 15
    customers per hour and a person working at the regular check out lane can service 11 customers per
    hour. The average arrival rate of customers at the checkout area is 15 per hour, 60% of these have
    over 8 grocery items. Assume poisson arrival and exponential service rate. Analyze the steady state
    system behavior.

26. A service system has an average inter arrival time of two minutes, poisson distributed. The system
    has one server. Determine and compare the steady state queueing statistics under the following
    cases:
    I.      Service time is constant at 1 minute.
    II.     Service time has a continuous density function
            f(t) = t/2               0<t<2
    III.    Service time is normal with a mean of 1 minute. It takes more than 1.5 minutes to service in
            about 1% of the time.

27. Suppershopper Inc. has 20 customers entering per hour. The customer spends an exponentially
    distributed amount of time shopping. The average time spent shopping is 15 minutes.
    a. How many customers will you expect to find shopping in the aisles?
    b. What is the probability of 8 customers entering during the period 1:00-1:15 pm?
    c. What is the probability of finding at least 3 customers in the aisles in at least one of two observed
         times?

28. A barber shop has 3 barbers and 2 additional chairs for waiting customers. Customers arrive at an
    average rate of 8/hour and haircuts take an average of 15 minutes with an exponential distribution.
    Arrivals who find the barber shop busy and 2 customers waiting leave at once.
    a. What fraction of the time are the barbers idle?
    b. Determine the mean time a customer spends in the barber shop.

29. A small store has a parking lot of 6 spaces. Potential customers arrive at a rate of 10/hour and leave
    immediately if no parking space is available. Occupancy of parking space is 30 min. on the average
    and tends to be exponential.
    a. What is the probability that a customer leaves at once?
    b. What is the average fraction of empty spaces?

30. Mildred’s Tools and Die Shop has a central tool cage manned by a single clerk, who takes an
    average of 5 minutes to check and carry parts to each machinist who requests them. The machinists
arrive once every 8 min. on the average. Times between arrivals and for service are assumed to both
    have exponential distributions. A machinist’s time is valued at P15 per hour; a clerk’s time is valued
    at P9 per hour. What are the average hourly queueing system costs associated with the tool cage
    operation?

31. C.A. Gopher and Sons is to excavate a site from which 100,000 cubic yards of dirt must be removed.
    Gopher has the choice of using a scoop loader or a shovel crane. A scoop loader costs P40 per hour,
    and a shovel crane costs P60 per hour. Once work has been started, the trucks will arrive according
    to a poisson process at a mean rte of 7 trucks per hour. Truck-filling times are approximately
    exponentially distributed. A scoop loader can fill an average of 10 trucks per hour. The shovel crane
    is faster and is capable of filling 15 trucks per hour on the average, (For simplicity, we will assume
    that the truck arrival rate is the same, regardless of the equipment used.)

    Since the number of truck arrivals required to excavate the site is fixed by the amount of dirt to be
    removed, the optimal choice of filling equipment will be the one that minimizes the combined
    average hourly costs of unproductive truck time plus the cost of the filling equipment. Determine the
    optimal choice.

32. The manager of a Way Safe market with 10 checkout counters wishes to determine how many
    counters to operate on Saturday morning. His decision will be determined in part by the costs
    assigned to each additional minute that a customer spends checking out of the store. In a special
    experiment in obsolete stores about to be closed, customers were forced to wait in line for an
    abnormally long time. The study concluded that an average of P0.05 in future profits is lost for
    every minute that a customer spends waiting.

    Assume that Way Safe customer arrivals at the checkout area are approximated by a poisson process
    with a mean rate of 2 per minute, that each attendant can check out customers at a mean rate of 0.5
    per minute, and that the service time is exponentially distributed.
    a. What is the minimum number of checker required for the service capacity to exceed the demand
         for service? Determine the mean customer waiting time when that many checkers are providing
         service.
    b. What is the mean customer waiting time is one more checker is added?
    c. The salary expense for each checker is P10 per hour. What number of checkers will minimize
         the total hourly queueing system cost – the number in (a) or in (b)? (Ignore service time, since
         no penalty applies for actual checkout time spent.)

33. A toll gate at the Highway is staffed by one attendant. The time it takes him to collect the toll from a
    car is exactly 30 seconds. Cars arrive at the toll booth at a poisson rate of 75 cars per hour.
    a. What percentage of the time is the attendant free to read magazines?
    b. On the average, how many cars are lined up on the highway waiting to approach the toll booth?
    c. What is the expected number of cars tied up at the bridge due to the toll gate bottleneck?
    d. What is the average length of time a traveler can expect to wait before paying the toll/
    e. How long on the average is a car detained on the highway due to the toll gate operation?

34. A manufacturing facility operates a central tool crib for its machinists. The crib operates like an (M/
    M/s) system. Arrivals occur at an average rate of 30 machinists requiring tools per hour. Each
    worker behind the tool counter can service the requests of 15 machinists per hour on the average and
    is paid an hourly wage of P8.50. The machinists’ wages run P15.75 per hour on the average.
    a. How many tool crib attendants should be hired?
    b. For the system resulting from your analysis of part (a), determine the following, how many
        machinists are idle (at the tool crib) on the average? How long can a machinist expect to spend at
        the tool crib?

35. Patients arrive at a medical clinic at a poisson rate of 10 per hour. The small clinic is staffed by one
doctor, assisted by several nurses. Patients wait in the waiting room until the doctor can see them.
    The time the doctor spends with a patient has an exponential probability density with a mean of 5
    minutes.
    a. How many patients are in the clinic on the average?
    b. How long must a patient wait before seeing the doctor?
    c. How long can a patient expect to spend in the clinic?
    d. On the average how many patients are in the waiting room?

36. Students arrive at the university’s computer center at a poisson rate of 20 per hour. The center has
    six on-line terminals for student use. The time a student spends at a terminal appears to follow an
    exponential probability density with a mean of 0.20 hours (12 minutes).
    a. On the average, how many students are at the computing system?
    b. How many students are waiting to use a terminal?
    c. How long can a student expect to spend at the center?
    d. What is the average wait time for a student before having access to a terminal?
    e. What percentage of time is the center busy?

37. A single crew is provided for unloading and/or loading each truck that arrives at the loading dock of
    a warehouse. These trucks arrive according to a poisson input process at a mean rate of one per hour.
    The time required by a crew to unload and/or load a truck has an exponential distribution (regardless
    of the crew size). The expected time required by a one-man crew would be 1 hour.

    The cost of providing each additional member of the crew is P10 per hour. The cost is attributable to
    having a truck not in use (i.e., truck standing at the loading dock) is estimated to be P15/hour.
    a. Assume that the mean service rate of the crew is proportional to its size. What should the size be
        to minimize the expected total cost per hour?
    b. Assume that the mean service rate of the crew is proportional to the square root of its size. What
        should the size be to minimize expected total cost per hour?

38. A machine shop contains a grinder for sharpening the machine cutting tools. A decision must now
    be made on the speed at which to set the grinder.
    The grinding time required by a machine operator to sharpen his cutting tool has an exponential
    distribution, where the mean 1/µ can be set at anything from ½ to 2 minutes, depending upon the
    speed of the grinder. The running and maintenance costs goes up rapidly with the speed of the
    grinder, so the estimated cost per minute for providing a mean of 1/µ is P(0.10µ2).

    The machine operators arrive to sharpen their tools according to a poisson process at a mean rate of
    one every 2 minutes. The estimated cost of an operator being away from his machine to the grinder
    is P0.20/min.

    Plot the total expected cost per minute E(TC) vs. µ over the feasible range for µ to solve graphically
    for the minimizing value of µ.

39. Two repairmen are attending five machines in a workshop. Each machine breaks down according to
    a poisson distribution with a mean of 3 per hour. The repair time per machine is exponential with a
    mean of 15 minutes.
    a. Find the probability that the two repairmen are idle. That one repairman is idle.
    b. What is expected number of idle machines not being repaired?
Sample Problems for Queueing

1. Joe's Service Station operates a single gas pump. Cars arrive according to a Poisson distribution at
   an average rate of 15 cars per hour. Joe can service cars at the rate of 20 cars per hour with service
   time following an exponential distribution.
   a. What fraction of the time is Joe busy servicing cars?
   b. How many cars can Joe expect to find at his station?
   c. What is the probability that there are at least 2 cars in the station?
   d. How long can a driver expect to wait before his car enters the service facility?
   e. If you need to put in gas at Joe's service station, how long will it take you, on the average?

2. In the previous example, Joe is planning to set an area of land near the service facility to park cars
   waiting to be serviced. If each car requires 200 square feet on the average, how much space would
   be required?

3. Students arriving at a student registration center of a university must have their registration materials
   processed by an operator seated at a computer terminal. The systems design calls for 4 operators to
   be on duty, each operator performing an identical service. Students arrive according to a Poisson
   process at an average rate of 100 per hour. Each operator can process 40 students per hour with
   service time being exponentially distributed.
   a. What fraction of the time that there are no students in the registration center?
   b. If the waiting area inside the center building will comfortably accommodate five students, what
       percentage of time will there be students lined up outside the building?
   c. How long does an average student spend in the center building?
   d. On the average, can we expect a student arriving 3 minutes before closing time to make it just
       before closing? (He is able to register)
   e. How long is the line of students waiting to register?

4. Arrivals at the AAA Transmission Repair are observed to be random at the Poisson rate of 1.5 per
   day. The time required to repair transmission varies and the probability distribution is given below:
                      Service Time (days)                        Probability
                               0.25                                 0.274
                               0.50                                 0.548
                               0.75                                 0.110
                               1.00                                 0.068
   Determine the steady state statistics of this system.

5. Supershopper Supermarket has 15 customers entering per hour. The customer spends an
   exponentially distributed amount of time shopping. The average time spent shopping is 20 minutes.
   a. On the average, how many customers can be found shopping in the aisles?
   b. What is the average length of time a customer spends shopping in the aisles?
   c. Find the probability of there being 6 or more customers in the aisles.

6. The owner of a small full-service gas station operates it by himself. On Friday afternoon, customers
   arrive at the rate of 12 per hour. On the average, service takes 3 minutes and tends to be exponential.
   The space allows the accommodation of only 3 cars at one time (including the one being serviced).
   a. What is the mean number of customers in the station?
   b. What fraction of the time will the owner be idle?
   c. What fraction of customers will be lost?
   d. What is the mean customer waiting time?
   e. What is the probability that a customer waits?
7. Consider a barbershop with 3 barbers and 2 additional chairs for waiting customers. Customers
   arrive randomly at an average rate of 8 per hour, and haircuts take an average of 15 minutes, with an
   exponential distribution. Arriving customers who find the barbershop busy and 2 customers waiting
leave immediately.
    a. What is the mean number of customers waiting at any time?
    b. What is the mean time a customer spends in the barbershop?
    c. Determine the mean number of customers in the barbershop?
    d. What fraction of the time are the barbers idle?

8. A firm operates a single-server maintenance storeroom where electrical repair persons check out
   needed spare parts and equipment. Repair persons arrive at a rate of 8 per hour. The service rate is
   10 per hour. Arrivals are Poisson distributed and service completion times follow the exponential
   model. The cost of waiting is Php 9 per hour. The company is considering giving the stock clerk a
   helper which would increase the service rate to 12 per hour. The cost of the helper is Php 6 per hour.
   What do you recommend?

9. The FNB has decided to operate its lobby service according to an (M/M/S) model. Customer arrive
   at the bank at an average of 40 per hour. Each bank teller can serve 10 people per hour. How many
   bank teller should be hired so that the average time a customer spends waiting in the queue does not
   exceed 0.75 minutes?

10. A machine in a plant is designed to perform various operations. Process time of a job is exponential
    with a mean of 5 minutes. Job arrivals are poisson with a mean of 7 per hour. Jobs waiting are
    placed in a storage area in front of machine. If this area fills up, the arriving jobs must be placed in
    an aisle next to a wall. Each waiting machine occupies 9 square feet. How much floor space should
    be planned for the storage area if it is to be adequate 80% of the time? (It is to include job being
    processed)

11. Workfor Metals purchases metal to be recycled from several sources. These metals consist of steel
    bars and sheets aluminum shapes, and iron plates. Truckload shipments of scrap metals arrive at
    Workfor in more or less random pattern at an average rate of one truckload per day. These trucks are
    owned and operated by Workfor Metals. Each shipment must be unloaded by a crew of workers. A
    combination of unloading operations is used: simple dumping, use of crane or forklift, and direct
    manual labor. A crew of n workers can unload 0.8n per day. For each day that a truck is detained in
    unloading, a cost of Php 300 is incurred (due to lost productive use of the truck and hourly wages of
    track driver and his assistant). Each worker in the unloading crew is paid Php 105 per day.
    Determine the optimal number of crew members to hire, assuming the arrival and service rates are
    poisson.

12. An engineering design firm is replacing its scientific computer, which is sued to solve problems
    encountered in design projects. The list of alternatives has been narrowed to 3 computers.
              Computer Type                      Lease Cost/day            No. of problems solved per day
                     A                                 600                               20
                     B                                 750                               25
                     C                                1050                               35
    Computation times are exponential and arrivals of problems at the computer center follow a poisson
    distribution at mean rate if 15 per day. Progress on a project is delayed until a problem is solved.
    The daily cost of delaying a project is Php 250. Which computer should be selected?

Más contenido relacionado

La actualidad más candente

Queuing theory
Queuing theoryQueuing theory
Queuing theoryAmit Sinha
 
Unit 4 queuing models
Unit 4 queuing modelsUnit 4 queuing models
Unit 4 queuing modelsraksharao
 
Clinic management system
Clinic management systemClinic management system
Clinic management systemMike Taylor
 
OR (JNTUK) III Mech Unit 8 simulation
OR (JNTUK) III Mech Unit 8  simulationOR (JNTUK) III Mech Unit 8  simulation
OR (JNTUK) III Mech Unit 8 simulationNageswara Rao Thots
 
Unit 4 simulation and queing theory(m/m/1)
Unit 4  simulation and queing theory(m/m/1)Unit 4  simulation and queing theory(m/m/1)
Unit 4 simulation and queing theory(m/m/1)DevaKumari Vijay
 
Inventory Managment
Inventory ManagmentInventory Managment
Inventory Managmentsai prakash
 
Simulation of water reservoir
Simulation of water reservoirSimulation of water reservoir
Simulation of water reservoirmegersaoljira
 
Markov analysis
Markov analysisMarkov analysis
Markov analysisganith2k13
 
Simulation with ARENA - SM Paints
Simulation with ARENA - SM PaintsSimulation with ARENA - SM Paints
Simulation with ARENA - SM Paintshrishik26
 
Opersea report waiting lines and queuing theory
Opersea report waiting lines and queuing theoryOpersea report waiting lines and queuing theory
Opersea report waiting lines and queuing theoryIsaac Andaya
 
Queing theory and delay analysis
Queing theory and delay analysisQueing theory and delay analysis
Queing theory and delay analysisPriyanka Negi
 
Waiting line system
Waiting line systemWaiting line system
Waiting line systemNsbmUcd
 
Online supply inventory system
Online supply inventory systemOnline supply inventory system
Online supply inventory systemrokista
 

La actualidad más candente (20)

Unit 3 des
Unit 3 desUnit 3 des
Unit 3 des
 
Queuing theory
Queuing theoryQueuing theory
Queuing theory
 
Queuing theory
Queuing theoryQueuing theory
Queuing theory
 
Unit 4 queuing models
Unit 4 queuing modelsUnit 4 queuing models
Unit 4 queuing models
 
Queuing theory
Queuing theoryQueuing theory
Queuing theory
 
Clinic management system
Clinic management systemClinic management system
Clinic management system
 
Queuing theory
Queuing theoryQueuing theory
Queuing theory
 
OR (JNTUK) III Mech Unit 8 simulation
OR (JNTUK) III Mech Unit 8  simulationOR (JNTUK) III Mech Unit 8  simulation
OR (JNTUK) III Mech Unit 8 simulation
 
Unit 4 simulation and queing theory(m/m/1)
Unit 4  simulation and queing theory(m/m/1)Unit 4  simulation and queing theory(m/m/1)
Unit 4 simulation and queing theory(m/m/1)
 
Inventory Managment
Inventory ManagmentInventory Managment
Inventory Managment
 
Simulation of water reservoir
Simulation of water reservoirSimulation of water reservoir
Simulation of water reservoir
 
Markov analysis
Markov analysisMarkov analysis
Markov analysis
 
Simulation with ARENA - SM Paints
Simulation with ARENA - SM PaintsSimulation with ARENA - SM Paints
Simulation with ARENA - SM Paints
 
Opersea report waiting lines and queuing theory
Opersea report waiting lines and queuing theoryOpersea report waiting lines and queuing theory
Opersea report waiting lines and queuing theory
 
Queuing theory
Queuing theoryQueuing theory
Queuing theory
 
Queing theory and delay analysis
Queing theory and delay analysisQueing theory and delay analysis
Queing theory and delay analysis
 
Waiting line system
Waiting line systemWaiting line system
Waiting line system
 
Modelling and simulation
Modelling and simulationModelling and simulation
Modelling and simulation
 
Online supply inventory system
Online supply inventory systemOnline supply inventory system
Online supply inventory system
 
Queuing Theory
Queuing TheoryQueuing Theory
Queuing Theory
 

Destacado

Waiting Line Management
Waiting Line ManagementWaiting Line Management
Waiting Line ManagementRaman Kumar
 
Queueing theory eq
Queueing theory eqQueueing theory eq
Queueing theory eqKoko Bakhat
 
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...IOSR Journals
 
Assignment Chapter - Q & A Compilation by Niraj Thapa
Assignment Chapter  - Q & A Compilation by Niraj ThapaAssignment Chapter  - Q & A Compilation by Niraj Thapa
Assignment Chapter - Q & A Compilation by Niraj ThapaCA Niraj Thapa
 
Kellogg Logic Model Guide[1]
Kellogg Logic Model Guide[1]Kellogg Logic Model Guide[1]
Kellogg Logic Model Guide[1]lnvan9
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
General purpose simulation System (GPSS)
General purpose simulation System (GPSS)General purpose simulation System (GPSS)
General purpose simulation System (GPSS)Tushar Aneyrao
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpmJulius Cuaresma
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balanceSudhir Reddy
 
Dynamic Programming
Dynamic ProgrammingDynamic Programming
Dynamic ProgrammingNilam Kabra
 
Top 50 case-studies of airlines and airports excelling in social media
Top 50 case-studies of airlines and airports excelling in social mediaTop 50 case-studies of airlines and airports excelling in social media
Top 50 case-studies of airlines and airports excelling in social mediaSimpliFlying
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational ResearchNeha Sharma
 
Quantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagesQuantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagestaniyakhurana
 
QUEUING THEORY
QUEUING THEORYQUEUING THEORY
QUEUING THEORYavtarsingh
 

Destacado (20)

Waiting Line Management
Waiting Line ManagementWaiting Line Management
Waiting Line Management
 
OR Unit 5 queuing theory
OR Unit 5 queuing theoryOR Unit 5 queuing theory
OR Unit 5 queuing theory
 
Waiting lines 2
Waiting lines 2Waiting lines 2
Waiting lines 2
 
Queueing theory eq
Queueing theory eqQueueing theory eq
Queueing theory eq
 
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...
Solving Of Waiting Lines Models in the Bank Using Queuing Theory Model the Pr...
 
Chapter7[1]
Chapter7[1]Chapter7[1]
Chapter7[1]
 
Assignment Chapter - Q & A Compilation by Niraj Thapa
Assignment Chapter  - Q & A Compilation by Niraj ThapaAssignment Chapter  - Q & A Compilation by Niraj Thapa
Assignment Chapter - Q & A Compilation by Niraj Thapa
 
Kellogg Logic Model Guide[1]
Kellogg Logic Model Guide[1]Kellogg Logic Model Guide[1]
Kellogg Logic Model Guide[1]
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
General purpose simulation System (GPSS)
General purpose simulation System (GPSS)General purpose simulation System (GPSS)
General purpose simulation System (GPSS)
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
Queueing theory
Queueing theoryQueueing theory
Queueing theory
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balance
 
Dynamic Programming
Dynamic ProgrammingDynamic Programming
Dynamic Programming
 
Top 50 case-studies of airlines and airports excelling in social media
Top 50 case-studies of airlines and airports excelling in social mediaTop 50 case-studies of airlines and airports excelling in social media
Top 50 case-studies of airlines and airports excelling in social media
 
Game theory
Game theoryGame theory
Game theory
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational Research
 
Game theory
Game theoryGame theory
Game theory
 
Quantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagesQuantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pages
 
QUEUING THEORY
QUEUING THEORYQUEUING THEORY
QUEUING THEORY
 

Similar a Queuing problems

Waiting Line Management
Waiting Line Management Waiting Line Management
Waiting Line Management Joshua Miranda
 
Om problems waiting line management
Om problems   waiting line managementOm problems   waiting line management
Om problems waiting line managementvideoaakash15
 
Selection and economics of farm machines and equipments
Selection and economics of farm machines and equipmentsSelection and economics of farm machines and equipments
Selection and economics of farm machines and equipmentsagriyouthnepal
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Hossam Shafiq I
 
Which of the following is an input to the master production schedule (mps)
Which of the following is an input to the master production schedule (mps)Which of the following is an input to the master production schedule (mps)
Which of the following is an input to the master production schedule (mps)ramuaa130
 
BUSN 603 Problem Set 6
BUSN 603 Problem Set 6BUSN 603 Problem Set 6
BUSN 603 Problem Set 6AllenMcCarty
 
Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018ramuaa124
 
Lpp formulations - 2018 - 1
Lpp  formulations  - 2018 - 1Lpp  formulations  - 2018 - 1
Lpp formulations - 2018 - 1Utshav Chaudhary
 
Stimulating Work Patterns
Stimulating Work Patterns Stimulating Work Patterns
Stimulating Work Patterns Su Butcher
 
Queueing Theory- Waiting Line Model, Heizer and Render
Queueing Theory- Waiting Line Model, Heizer and RenderQueueing Theory- Waiting Line Model, Heizer and Render
Queueing Theory- Waiting Line Model, Heizer and RenderAi Lun Wu
 
Unit 5 mechanisation.pptx
Unit 5 mechanisation.pptxUnit 5 mechanisation.pptx
Unit 5 mechanisation.pptxssuser112f91
 
Which of the following is considered a primary report in an mrp system
Which of the following is considered a primary report in an mrp systemWhich of the following is considered a primary report in an mrp system
Which of the following is considered a primary report in an mrp systemramuaa130
 
The centroid method for plant location uses which of the following data
The centroid method for plant location uses which of the following dataThe centroid method for plant location uses which of the following data
The centroid method for plant location uses which of the following dataramuaa128
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...ramuaa127
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsramuaa127
 

Similar a Queuing problems (20)

Presentation3 modified
Presentation3 modifiedPresentation3 modified
Presentation3 modified
 
Waiting Line Management
Waiting Line Management Waiting Line Management
Waiting Line Management
 
Om problems waiting line management
Om problems   waiting line managementOm problems   waiting line management
Om problems waiting line management
 
Logistics Management Homework Help
Logistics Management Homework HelpLogistics Management Homework Help
Logistics Management Homework Help
 
Regional Airlines - telephone reservation system analysis
Regional Airlines - telephone reservation system analysisRegional Airlines - telephone reservation system analysis
Regional Airlines - telephone reservation system analysis
 
Tn7 wtg.line+mgt
Tn7 wtg.line+mgtTn7 wtg.line+mgt
Tn7 wtg.line+mgt
 
Tn7 wtg.line mgt
Tn7 wtg.line mgtTn7 wtg.line mgt
Tn7 wtg.line mgt
 
Selection and economics of farm machines and equipments
Selection and economics of farm machines and equipmentsSelection and economics of farm machines and equipments
Selection and economics of farm machines and equipments
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
 
Which of the following is an input to the master production schedule (mps)
Which of the following is an input to the master production schedule (mps)Which of the following is an input to the master production schedule (mps)
Which of the following is an input to the master production schedule (mps)
 
BUSN 603 Problem Set 6
BUSN 603 Problem Set 6BUSN 603 Problem Set 6
BUSN 603 Problem Set 6
 
Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018
 
Lpp formulations - 2018 - 1
Lpp  formulations  - 2018 - 1Lpp  formulations  - 2018 - 1
Lpp formulations - 2018 - 1
 
Stimulating Work Patterns
Stimulating Work Patterns Stimulating Work Patterns
Stimulating Work Patterns
 
Queueing Theory- Waiting Line Model, Heizer and Render
Queueing Theory- Waiting Line Model, Heizer and RenderQueueing Theory- Waiting Line Model, Heizer and Render
Queueing Theory- Waiting Line Model, Heizer and Render
 
Unit 5 mechanisation.pptx
Unit 5 mechanisation.pptxUnit 5 mechanisation.pptx
Unit 5 mechanisation.pptx
 
Which of the following is considered a primary report in an mrp system
Which of the following is considered a primary report in an mrp systemWhich of the following is considered a primary report in an mrp system
Which of the following is considered a primary report in an mrp system
 
The centroid method for plant location uses which of the following data
The centroid method for plant location uses which of the following dataThe centroid method for plant location uses which of the following data
The centroid method for plant location uses which of the following data
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
 

Más de De La Salle University-Manila

Chapter3 general principles of discrete event simulation
Chapter3   general principles of discrete event simulationChapter3   general principles of discrete event simulation
Chapter3 general principles of discrete event simulationDe La Salle University-Manila
 

Más de De La Salle University-Manila (20)

Verfication and validation of simulation models
Verfication and validation of simulation modelsVerfication and validation of simulation models
Verfication and validation of simulation models
 
Markov exercises
Markov exercisesMarkov exercises
Markov exercises
 
Markov theory
Markov theoryMarkov theory
Markov theory
 
Game theory problem set
Game theory problem setGame theory problem set
Game theory problem set
 
Decision theory handouts
Decision theory handoutsDecision theory handouts
Decision theory handouts
 
Sequential decisionmaking
Sequential decisionmakingSequential decisionmaking
Sequential decisionmaking
 
Decision theory
Decision theoryDecision theory
Decision theory
 
Decision theory blockwood
Decision theory blockwoodDecision theory blockwood
Decision theory blockwood
 
Decision theory
Decision theoryDecision theory
Decision theory
 
Random variate generation
Random variate generationRandom variate generation
Random variate generation
 
Random number generation
Random number generationRandom number generation
Random number generation
 
Monte carlo simulation
Monte carlo simulationMonte carlo simulation
Monte carlo simulation
 
Input modeling
Input modelingInput modeling
Input modeling
 
Conceptual modeling
Conceptual modelingConceptual modeling
Conceptual modeling
 
Chapter3 general principles of discrete event simulation
Chapter3   general principles of discrete event simulationChapter3   general principles of discrete event simulation
Chapter3 general principles of discrete event simulation
 
Comparison and evaluation of alternative designs
Comparison and evaluation of alternative designsComparison and evaluation of alternative designs
Comparison and evaluation of alternative designs
 
Chapter2
Chapter2Chapter2
Chapter2
 
Chapter1
Chapter1Chapter1
Chapter1
 
Variance reduction techniques (vrt)
Variance reduction techniques (vrt)Variance reduction techniques (vrt)
Variance reduction techniques (vrt)
 
Validation and verification
Validation and verificationValidation and verification
Validation and verification
 

Último

Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 

Último (20)

Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 

Queuing problems

  • 1. OPERES3 Problems in Queuing Theory 1. (Case 1) A computing system has a single printer attached to print out the output of the users. The operating system software sends an average of 20 requests per hour to the printer. The printer is capable of printing out 35 jobs per hour on the average. Assume that the job arrival rate and the printing rate are Poisson distributed. a. On the average, how many jobs are in the output queue waiting to be printed out? b. How many jobs are in the “printer output system” on the average? c. How long can a user expect to wait to have his or her job printed out once it has been sent to the printer? d. Once a job enters the output queue, how long does it take before printing begins on the job? e. What percentage of time will the printer be busy doing print jobs? f. (Case 2) Assume that a second printer is added to the system. Answer questions 1.1 to 1.5, assuming that the two printers are identical. 2. (Case 1) Telephone calls arrive at a particular small-scale paging system at the Poisson rate of 20 per hour. The calls are transferred to an operator that can handle an average of 25 calls per hour, following an exponential distribution. The operator can handle only one caller at a time; if the operator is busy, arriving calls are put on hold and the callers are assumed to be patient. a. Assume that no limit is placed on the number of calls that can be put on hold: 1) What percentage of the time is the operator busy? 2) On the average, how many callers are on hold? 3) On the average, how long can a caller expect to spend on the telephone when calling this office? b. (Don’t do this) Suppose that with the single operator, only a maximum of two calls can be put on hold. How does this affect your answers in 2.1? c. (Case 2) Suppose that an additional operator is hired, with no limit on the number of calls on hold: 1) What percentage of the time are both operators busy? 2) On the average, how many callers are on hold? 3) On the average, how long can a caller expect to spend on the telephone when calling this office? d. (Case 2) Suppose that the office management feels that, in order to provide good customer service, a caller should not have to wait more than 10 seconds on hold. How many telephone operators should be hired to answer calls? 3. Orders for a firm’s products arrive at the rate of 200 a week. A single clerk is assigned to process the orders at an average of 250 orders per week. The cost of delaying an average shipment for 1 week is P500. If a clerk costs P300 per week, how many clerks should be assigned to process the paperwork? 4. Moonlight Travel Reservation Service has one agent and 3 telephone lines. When the agent is busy, the next caller is placed on hold on one of the remaining lines. When all three lines are busy, callers receive a busy signal and call elsewhere for reservations. Service appears to be exponentially distributed, with a mean of three minutes. Calls arrive randomly at a Poisson rate of 15/hour. a. What is the probability that a caller receives a busy signal? b. What is the average number of customers put on hold at any given time? c. What is the probability that a customer is placed on hold? d. How long, on the average, will a customer be on hold before the agent can attend to him? e. If a caller makes three attempts before finally calling elsewhere for reservations, what fraction of the customers will be able to do business with Moonlight Travel Reservation Service?
  • 2. 5. (Case 1) Customers arrive at a one-person barber shop with an average interarrival time of 20 minutes. The average time for a haircut is 12 minutes, exponentially distributed. a. The owner wishes to have enough seats in the waiting area so that on the average no more than 5% of the arriving customers will have to stand. How many seats should be provided? b. Suppose that there is only sufficient space in the waiting area for five seats. What is the probability that an arriving customer will not find a seat? 6. A plant distributes its products by truck. The exponential average loading time per truck at the loading facility is 20 minutes. Trucks arrive at a rate of 2/hour. Management feels that the existing loading facility is more than adequate. However, the drivers complain that they have to wait more than half of the time. Analyze the situation and find how much money the company can save if the waiting time of a truck is figured at P10/hr and the plant is in operation 8 hours per day. An automatic device that can load 10 trucks per hour is available at a cost of P90/day over the cost of the existing facility. 7. Campers arrive at the County Park at a Poisson rate of 100 per month. The time spent in the park by a camper varies according to an exponential distribution with a mean of 0.10 month. Since the park is very large, campers have no problem finding a campsite. However, the state recreation officials have a policy of maintaining a certain level of forest-ranger workforce for the convenience and safety of the campers. The current policy is to have one ranger per 10 campers at any given time. a. How many campers are using the park on the average? b. What percentage of the time is the park empty? c. How many forest rangers should the state employ at the County Park? 8. A gasoline station is served by 1 employee who is capable of serving 30 customers per hour, varying according to an exponential distribution. There is a maximum space for five cars in the station, including those served and in line. Cars arrive at the station at an average rate of every 3 minutes. Cars that do not have parking spaces leave and do not return. Find: a. The average number of cars waiting for service. b. The probability of finding no car in the station. c. The average waiting time in line for each car. d. The probability of finding 3 cars in the station at any given time. e. It was proposed to increase the space so that 10 cars would be accommodated. The investment would entail P5 per car space per hour. A car that leaves the station means a loss of P10. Should the space be enlarged or not? 9. A shop utilizes 10 identical machines. The profit per machine is P40 per hour of operation. Each machine breaks down on the average once every 7 hours. One person can repair a machine in 4 hours on the average, but the actual repair time varies according to a Poisson distribution. The repairman’s salary is P60/hour. Determine: a. The number of repairmen that will minimize cost. b. The number of repairmen needed so that the expected number of broken machines at any given time is less than 4. c. The number of repairmen needed so that the expected delay time until a machine is repaired is less than 4 hours. 10. (Case 2) Students arriving at the computing center can wait either at a small table in the center (which will seat four students) or if the table is full they can go to a nearby student lounge or they can wait in the hall. What percentage of time will the waiting area inside the computing center be sufficient to accommodate the waiting students? 11. The city of Manila operates a large fleet of police squad cars. When a car breaks down due to a minor malfunction it is sent to a single-garage repair facility where it is repaired by a crew of
  • 3. mechanics. The crew foreman, Jim, must put in a request to hire her team mechanics. If n mechanics work on a single car together, repair time for minor repairs is approximately constant at 20/n minutes. Disabled squad cars arrive at the repair facility at the Poisson rate of five cars per hour. The police chief tells Joanne that on the average he does not want a squad car to be out of commission for longer than 15 minutes. a. What is the minimum number of mechanics Joanne should hire? b. On the average, how many squad cars are out of commission? 12. Solve Joanne’s facility design problem (exercise 11 above) under the assumption that the reapir time of 20/n minutes is a mean exponential time. Answer both parts (a) and (b) of the problem. 13. The manufacturing Supervisor of Hardpress Industries must decide between three makers of forklift trucks to use on the plant floor. The truck will be used to move raw materials from storage bins to work centers in a section of the plant. Request from these work centers occur according to a poisson process at a mean rate of eight per hour. The time to move raw materials is exponentially distributed. The service rates per hour for each of the truck under consideration is given in the table along with estimated costs per hour (operating costs plus depreciation). For each hour a work center is idle waiting for raw materials, an average cost of P100 is incurred (wages plus lost productivity). Table Truck Service Rate (jobs/hr) Cost (P/hr) 1 10 30 2 15 50 3 18 40 Which truck would you purchase based on queueing analysis? (Be sure to specify clearly the queueing model you are using.) 14. In exercise 13, would your purchase choice change if the Manufacturing Supervisor felt that the service times of the forklift trucks were (more or less) constant times? That is, Truck 1 can service work centers at the constant rate of 10 jobs per hour, Truck 2 at 15 per hour, and Truck 3 at 18 per hour. (What would be the total cost per hour of using each of the trucks?) 15. (Case 1) The state operates a weigh station for trucks traveling on the highway. Every truck must pull off the highway, enter the weigh station, and undergo state inspection procedures before counting on. Trucks arrive at this station at a poisson rate of seven per hour. The time to inspect/weigh a truck varies, having an exponential probability density with a mean of 7 minutes. a. How many trucks are detained at the station on the average? b. How long can a truck expect to be detained? c. How many trucks are lined up in front of the station on the average? d. How long on the average does a truck driver have to wait in line for the truck to be inspected? 16. Refer to exercise 15, the truck driver traveling the route passing the weigh station have complained of long waiting time at the inspection point. The major phase of the inspection procedure consists of weighing-in the truck. The state highway commissioner has decided to look into ways of reducing the average time a trucker must spend at the weigh station to 25 minutes or less. The commissioner is considering the purchase of new digital solid waste weighing scale that should reduce the weighing time. Three manufacturer’ products are available: (1) model 1 costs P10000 and could check 10 trucks per hour, (2) model 2 costs P12000 and would have an average service time of 5.5 minutes, and (3) model 3 costs P8500 and would have an average service time of 6.5 minutes. a. Determine which model to purchase. b. For the decision made in part (a), determine system operating characteristics P0, L, Lq, W and Wq. 17. A recent increase in consumer complaints at Jersey Electric Authority has led to a decision to assign
  • 4. one person to receive the complaints. Complaints are phoned in at a rate of 20 per hour and are poisson distributed. Call can handled at a rate of 40 per hour. Service times vary considerably and have been found to be exponentially distributed. Jersey Electric would like to make sure that no more than 5% of the calls receive busy signals. If the operator is busy, calls can be placed on a “hold” line. How many hold lines should be provided to ensure that the 5% target will be reached? 18. The mean arrival rate at each of two identical service systems is 21 per day. Both systems operate independently and have service rates of 30 customers per day. The cost of 1 day of waiting time is P50 per customer. Assume that it is possible to consolidate the two servers into a multiple-channel system. Determine the reduction in waiting cost that such a move would accomplish. 19. A service facility has a poisson arrival rate of 9 customers per hour. There is no room for customers to wait for service , and arrivals encountering a busy system are forced to balk. If service times are exponentially distributed and the rate of service is 10 per hour, what percent of the customers will be unable to join the system? What percent will be lost if room is provided for 1 customer to wait? If room is provided for 2 customers to wait? If room is provided for 3 customers to wait? 20. Eastern Machine Company has a tool room with two clerks. Both clerks issue spare parts and tools to maintenance workers. Maintenance workers arrive at a rate of 20 per hour, each wanting either a part (40 percent) or a tool (60 percent), but not both. The arrival follow the poisson distribution. The average issuing time is five minutes per order (service by one clerk). This service time has been observed to be exponentially distributed. Each clerk currently issues both parts and tools. A maintenance worker not at his bench costs the company P5 per hour. a. What is the average time a maintenance worker is not at his bench? b. What is the probability that both clerks are busy with no one waiting in line? c. It was proposed that the two clerks be specialized. Namely: one will issue spare parts only, and the other will issue tools only. 1) Would you advise specialization if the service time is reduced to four minutes per order? 2) What is the probability that both clerks are observed to be busy in 2 out of 10 observed times if the proposal is implemented? 21. An airline firm is attempting to determine the number of reservation clerks required at one of its reservation offices. Incoming calls are put on hold for the first available clerk. Customer calls arrive randomly in a poisson manner at the mean rate of 4 per minute and service time tends to be exponentially distributed with a mean time of 40 seconds per call. a. What is the minimum number if clerks needed if management has decided that a customer should not wait more than 60 seconds, on the average, before being connected with a clerk? b. The airlines pays its reservation clerks P6 per hour. Customer time is valued at P6 per hour. What is the optimal number if reservation clerk? 22. Workfor metals purchases metals to be recycled from several sources. These metals consist of steel bars and sheets, aluminum shapes, and iron plates. Truckload shipments of scrap metals arrive at Workfor at an average rate of 1 truckload per day. These trucks are owned and operated by Workfor. Each shipment must be unloaded by a crew workers. A crew of n workers can unload 0.8n trucks/day. For each day that a truck is detained in unloading, a cost of P300 is incurred (due to lack productive use of the truck and hourly wages of truck drivers and his assistant). Each worker in the unloading crew is paid P105 per day. Determine the optimal no. of crew members to hire assuming the arrival and service rates are poisson. 23. (Case 2) Students arriving at a student registration center of university must have their registration materials processed by an operator seated at a computer terminal. The system design calls for 4 operators to be on duty with each operator performing an identical service. Students arrive according to a poisson process at an average rate of 90 per hour, Each operator can process 30 students per hour. The service time is exponential.
  • 5. a. What fraction of the time are there no students in the registration center? b. If the waiting area can comfortably accommodate 3 students, what is the probability that there will be students lined up outside the building. c. How long is the line of students waiting to register? d. A students arrives at 4:58 pm. The closing time is strictly set at 5:00 pm. Can we expect the student to finish the whole registration process? 24. Machinist at a firm periodically need a wide range of special purpose tools, which are stored at 3 locations on the plant floor. Each tool room is staffed by one clerk, who checks the tools in and out. Arrivals at each tool room are poisson distributed with a mean of 15 employees per hour. Service times are exponential and average 3 minutes. It has been proposed that the 3 tool rooms be consolidated into a single centrally located facility staffed by 3 clerks. Travel time it takes for a machinist to walk to and from the work area to a tool room would be increased by an average of 2 minutes. Each hour that a machinist spends away from the work area has been estimated to cost P10 per hour. Service costs will not be reduced by the move to a single tool room. Evaluate the proposal. 25. Superchopper Supermarket operate two types of checkout lanes, an express lane (for purchases less than or equal to 8) and a regular lane. The person at the express lane cash register can check out 15 customers per hour and a person working at the regular check out lane can service 11 customers per hour. The average arrival rate of customers at the checkout area is 15 per hour, 60% of these have over 8 grocery items. Assume poisson arrival and exponential service rate. Analyze the steady state system behavior. 26. A service system has an average inter arrival time of two minutes, poisson distributed. The system has one server. Determine and compare the steady state queueing statistics under the following cases: I. Service time is constant at 1 minute. II. Service time has a continuous density function f(t) = t/2 0<t<2 III. Service time is normal with a mean of 1 minute. It takes more than 1.5 minutes to service in about 1% of the time. 27. Suppershopper Inc. has 20 customers entering per hour. The customer spends an exponentially distributed amount of time shopping. The average time spent shopping is 15 minutes. a. How many customers will you expect to find shopping in the aisles? b. What is the probability of 8 customers entering during the period 1:00-1:15 pm? c. What is the probability of finding at least 3 customers in the aisles in at least one of two observed times? 28. A barber shop has 3 barbers and 2 additional chairs for waiting customers. Customers arrive at an average rate of 8/hour and haircuts take an average of 15 minutes with an exponential distribution. Arrivals who find the barber shop busy and 2 customers waiting leave at once. a. What fraction of the time are the barbers idle? b. Determine the mean time a customer spends in the barber shop. 29. A small store has a parking lot of 6 spaces. Potential customers arrive at a rate of 10/hour and leave immediately if no parking space is available. Occupancy of parking space is 30 min. on the average and tends to be exponential. a. What is the probability that a customer leaves at once? b. What is the average fraction of empty spaces? 30. Mildred’s Tools and Die Shop has a central tool cage manned by a single clerk, who takes an average of 5 minutes to check and carry parts to each machinist who requests them. The machinists
  • 6. arrive once every 8 min. on the average. Times between arrivals and for service are assumed to both have exponential distributions. A machinist’s time is valued at P15 per hour; a clerk’s time is valued at P9 per hour. What are the average hourly queueing system costs associated with the tool cage operation? 31. C.A. Gopher and Sons is to excavate a site from which 100,000 cubic yards of dirt must be removed. Gopher has the choice of using a scoop loader or a shovel crane. A scoop loader costs P40 per hour, and a shovel crane costs P60 per hour. Once work has been started, the trucks will arrive according to a poisson process at a mean rte of 7 trucks per hour. Truck-filling times are approximately exponentially distributed. A scoop loader can fill an average of 10 trucks per hour. The shovel crane is faster and is capable of filling 15 trucks per hour on the average, (For simplicity, we will assume that the truck arrival rate is the same, regardless of the equipment used.) Since the number of truck arrivals required to excavate the site is fixed by the amount of dirt to be removed, the optimal choice of filling equipment will be the one that minimizes the combined average hourly costs of unproductive truck time plus the cost of the filling equipment. Determine the optimal choice. 32. The manager of a Way Safe market with 10 checkout counters wishes to determine how many counters to operate on Saturday morning. His decision will be determined in part by the costs assigned to each additional minute that a customer spends checking out of the store. In a special experiment in obsolete stores about to be closed, customers were forced to wait in line for an abnormally long time. The study concluded that an average of P0.05 in future profits is lost for every minute that a customer spends waiting. Assume that Way Safe customer arrivals at the checkout area are approximated by a poisson process with a mean rate of 2 per minute, that each attendant can check out customers at a mean rate of 0.5 per minute, and that the service time is exponentially distributed. a. What is the minimum number of checker required for the service capacity to exceed the demand for service? Determine the mean customer waiting time when that many checkers are providing service. b. What is the mean customer waiting time is one more checker is added? c. The salary expense for each checker is P10 per hour. What number of checkers will minimize the total hourly queueing system cost – the number in (a) or in (b)? (Ignore service time, since no penalty applies for actual checkout time spent.) 33. A toll gate at the Highway is staffed by one attendant. The time it takes him to collect the toll from a car is exactly 30 seconds. Cars arrive at the toll booth at a poisson rate of 75 cars per hour. a. What percentage of the time is the attendant free to read magazines? b. On the average, how many cars are lined up on the highway waiting to approach the toll booth? c. What is the expected number of cars tied up at the bridge due to the toll gate bottleneck? d. What is the average length of time a traveler can expect to wait before paying the toll/ e. How long on the average is a car detained on the highway due to the toll gate operation? 34. A manufacturing facility operates a central tool crib for its machinists. The crib operates like an (M/ M/s) system. Arrivals occur at an average rate of 30 machinists requiring tools per hour. Each worker behind the tool counter can service the requests of 15 machinists per hour on the average and is paid an hourly wage of P8.50. The machinists’ wages run P15.75 per hour on the average. a. How many tool crib attendants should be hired? b. For the system resulting from your analysis of part (a), determine the following, how many machinists are idle (at the tool crib) on the average? How long can a machinist expect to spend at the tool crib? 35. Patients arrive at a medical clinic at a poisson rate of 10 per hour. The small clinic is staffed by one
  • 7. doctor, assisted by several nurses. Patients wait in the waiting room until the doctor can see them. The time the doctor spends with a patient has an exponential probability density with a mean of 5 minutes. a. How many patients are in the clinic on the average? b. How long must a patient wait before seeing the doctor? c. How long can a patient expect to spend in the clinic? d. On the average how many patients are in the waiting room? 36. Students arrive at the university’s computer center at a poisson rate of 20 per hour. The center has six on-line terminals for student use. The time a student spends at a terminal appears to follow an exponential probability density with a mean of 0.20 hours (12 minutes). a. On the average, how many students are at the computing system? b. How many students are waiting to use a terminal? c. How long can a student expect to spend at the center? d. What is the average wait time for a student before having access to a terminal? e. What percentage of time is the center busy? 37. A single crew is provided for unloading and/or loading each truck that arrives at the loading dock of a warehouse. These trucks arrive according to a poisson input process at a mean rate of one per hour. The time required by a crew to unload and/or load a truck has an exponential distribution (regardless of the crew size). The expected time required by a one-man crew would be 1 hour. The cost of providing each additional member of the crew is P10 per hour. The cost is attributable to having a truck not in use (i.e., truck standing at the loading dock) is estimated to be P15/hour. a. Assume that the mean service rate of the crew is proportional to its size. What should the size be to minimize the expected total cost per hour? b. Assume that the mean service rate of the crew is proportional to the square root of its size. What should the size be to minimize expected total cost per hour? 38. A machine shop contains a grinder for sharpening the machine cutting tools. A decision must now be made on the speed at which to set the grinder. The grinding time required by a machine operator to sharpen his cutting tool has an exponential distribution, where the mean 1/µ can be set at anything from ½ to 2 minutes, depending upon the speed of the grinder. The running and maintenance costs goes up rapidly with the speed of the grinder, so the estimated cost per minute for providing a mean of 1/µ is P(0.10µ2). The machine operators arrive to sharpen their tools according to a poisson process at a mean rate of one every 2 minutes. The estimated cost of an operator being away from his machine to the grinder is P0.20/min. Plot the total expected cost per minute E(TC) vs. µ over the feasible range for µ to solve graphically for the minimizing value of µ. 39. Two repairmen are attending five machines in a workshop. Each machine breaks down according to a poisson distribution with a mean of 3 per hour. The repair time per machine is exponential with a mean of 15 minutes. a. Find the probability that the two repairmen are idle. That one repairman is idle. b. What is expected number of idle machines not being repaired?
  • 8. Sample Problems for Queueing 1. Joe's Service Station operates a single gas pump. Cars arrive according to a Poisson distribution at an average rate of 15 cars per hour. Joe can service cars at the rate of 20 cars per hour with service time following an exponential distribution. a. What fraction of the time is Joe busy servicing cars? b. How many cars can Joe expect to find at his station? c. What is the probability that there are at least 2 cars in the station? d. How long can a driver expect to wait before his car enters the service facility? e. If you need to put in gas at Joe's service station, how long will it take you, on the average? 2. In the previous example, Joe is planning to set an area of land near the service facility to park cars waiting to be serviced. If each car requires 200 square feet on the average, how much space would be required? 3. Students arriving at a student registration center of a university must have their registration materials processed by an operator seated at a computer terminal. The systems design calls for 4 operators to be on duty, each operator performing an identical service. Students arrive according to a Poisson process at an average rate of 100 per hour. Each operator can process 40 students per hour with service time being exponentially distributed. a. What fraction of the time that there are no students in the registration center? b. If the waiting area inside the center building will comfortably accommodate five students, what percentage of time will there be students lined up outside the building? c. How long does an average student spend in the center building? d. On the average, can we expect a student arriving 3 minutes before closing time to make it just before closing? (He is able to register) e. How long is the line of students waiting to register? 4. Arrivals at the AAA Transmission Repair are observed to be random at the Poisson rate of 1.5 per day. The time required to repair transmission varies and the probability distribution is given below: Service Time (days) Probability 0.25 0.274 0.50 0.548 0.75 0.110 1.00 0.068 Determine the steady state statistics of this system. 5. Supershopper Supermarket has 15 customers entering per hour. The customer spends an exponentially distributed amount of time shopping. The average time spent shopping is 20 minutes. a. On the average, how many customers can be found shopping in the aisles? b. What is the average length of time a customer spends shopping in the aisles? c. Find the probability of there being 6 or more customers in the aisles. 6. The owner of a small full-service gas station operates it by himself. On Friday afternoon, customers arrive at the rate of 12 per hour. On the average, service takes 3 minutes and tends to be exponential. The space allows the accommodation of only 3 cars at one time (including the one being serviced). a. What is the mean number of customers in the station? b. What fraction of the time will the owner be idle? c. What fraction of customers will be lost? d. What is the mean customer waiting time? e. What is the probability that a customer waits? 7. Consider a barbershop with 3 barbers and 2 additional chairs for waiting customers. Customers arrive randomly at an average rate of 8 per hour, and haircuts take an average of 15 minutes, with an exponential distribution. Arriving customers who find the barbershop busy and 2 customers waiting
  • 9. leave immediately. a. What is the mean number of customers waiting at any time? b. What is the mean time a customer spends in the barbershop? c. Determine the mean number of customers in the barbershop? d. What fraction of the time are the barbers idle? 8. A firm operates a single-server maintenance storeroom where electrical repair persons check out needed spare parts and equipment. Repair persons arrive at a rate of 8 per hour. The service rate is 10 per hour. Arrivals are Poisson distributed and service completion times follow the exponential model. The cost of waiting is Php 9 per hour. The company is considering giving the stock clerk a helper which would increase the service rate to 12 per hour. The cost of the helper is Php 6 per hour. What do you recommend? 9. The FNB has decided to operate its lobby service according to an (M/M/S) model. Customer arrive at the bank at an average of 40 per hour. Each bank teller can serve 10 people per hour. How many bank teller should be hired so that the average time a customer spends waiting in the queue does not exceed 0.75 minutes? 10. A machine in a plant is designed to perform various operations. Process time of a job is exponential with a mean of 5 minutes. Job arrivals are poisson with a mean of 7 per hour. Jobs waiting are placed in a storage area in front of machine. If this area fills up, the arriving jobs must be placed in an aisle next to a wall. Each waiting machine occupies 9 square feet. How much floor space should be planned for the storage area if it is to be adequate 80% of the time? (It is to include job being processed) 11. Workfor Metals purchases metal to be recycled from several sources. These metals consist of steel bars and sheets aluminum shapes, and iron plates. Truckload shipments of scrap metals arrive at Workfor in more or less random pattern at an average rate of one truckload per day. These trucks are owned and operated by Workfor Metals. Each shipment must be unloaded by a crew of workers. A combination of unloading operations is used: simple dumping, use of crane or forklift, and direct manual labor. A crew of n workers can unload 0.8n per day. For each day that a truck is detained in unloading, a cost of Php 300 is incurred (due to lost productive use of the truck and hourly wages of track driver and his assistant). Each worker in the unloading crew is paid Php 105 per day. Determine the optimal number of crew members to hire, assuming the arrival and service rates are poisson. 12. An engineering design firm is replacing its scientific computer, which is sued to solve problems encountered in design projects. The list of alternatives has been narrowed to 3 computers. Computer Type Lease Cost/day No. of problems solved per day A 600 20 B 750 25 C 1050 35 Computation times are exponential and arrivals of problems at the computer center follow a poisson distribution at mean rate if 15 per day. Progress on a project is delayed until a problem is solved. The daily cost of delaying a project is Php 250. Which computer should be selected?