This is a concepts document to assist in the planning and management of
merger or acquisition implementation projects. Information in this
document is based on our experience as management consultants and
sources we consider reliable. There are no further warranties about
accuracy or applicability. It contains neither legal nor financial advice. For
that, consult appropriate professionals.




                                             http://lpf.com       hal@lpf.com
                                             November 2008




                                                                                 2
Agenda:

 Merger Implementation Assumptions
 Four step implementation process:
   Step 1: Management structure
   Step 2: Inventory
   Step 3: Plan the implementation
   Step 4: Implement the plan

 Conclusion

                                      3
Merger Implementation Assumptions

 Objectives:
       Minimize time & costs
       Retain customers
       Retain key employees
 The merger will capture and integrate the best
    products and systems of both companies
   The implementation will be staged rather than a
    “big bang”


                                                      4
Four step implementation process:

 A merger implementation process can be defined
  in four steps:
                   Management structure,
     Structure     processes and tools


       Inventory


                   Plan


                                  Implement the Plan

                                                       5
Step 1: Management structure

 Project is generally structured around lines of
    business with exceptions for facilities, such as
    networks, that are shared by multiple lines
   Within a line of business, structured by major
    functions: business, systems and operations
   A Project Management Office to provide process
    expertise, coordination, and communication at
    the project level and major lines of business



                                                       6
Expand the structure as required

 Staff members of the merging companies know
    the markets, products and systems
   Consultants can provide additional:
     PMO and project management resources and
      expertise
     Merger implementation structures, guidelines and
      processes from initial planning to implementation
     System integration and data transformation resources
      and expertise



                                                         7
Step 2: Inventory


   Structure

                    What organizations, products,
     Inventory      systems etc. does each
                    company have?

                 Plan


                                Implement the Plan



                                                     8
Inventory products, systems, ops

 The inventory process will move through a series
  of phases, each adding greater detail

 Pre-close
 Pre-close is
 constrained in
 terms of the data   Strategic
 that can be         Strategic level meetings between the
 exchanged –         companies specifically to exchange
 attorneys provide   information. Becomes an iterative process of
 guidelines          planning then inventory then more planning
                                       Tactical
                                       Increasing levels of detail to
                                       support plans and implementation

                                                                     9
Inventory assumptions

 There is great deal of information required for
  the merger integration:
   Find it or develop it
   Test and update as needed
   Make it available in data bases for the project team
    and the planners
 The planning process will be driven by the
  amount and quality of the information that is
  available to the lines of business, systems, and
  operations
                                                           10
Pre-close: inventory major activities

 Identify the available information about your
  company’s products, systems and operations
 Define, build and begin to populate the data
  bases that will be used over the life of the
  merger project
 Use public sources and sources approved by
  your attorneys to develop information about
  the other company
 Prepare for strategic exchange of information
  immediately after the close
                                                  11
Inventory information management

 Develop one or more data bases to deal with and
  link the following data topics:
   Organizational structure and product ownership
   Products – a critical element of the planning process
   Computer centers – where, what do they do, …
   Operations centers – where, what do they do, …
   Communication networks – connect, capacity, …
   Data bases used – feed to and/or draw from …
   Potential issues related to expansion or termination
    including civic, leases, utilities …

                                                            12
Information management - issues
   The first level of planning will be based on major products to
    be carried forward, integrated or terminated; product
    information is critical to the process
   The same product name may be used by more that one
    business unit and by the two companies to refer to
    significantly different products; provide for multiple names
    for the same product and sufficient detail to differentiate
    products with the same name
   Look at current demand and capacity as a baseline plus the
    other company plus growth to find opportunities for
    consolidation
   Allow for different organizational structures for the ownership
    of products – changes will have to be coordinated
   Test databases, particularly older ones, to assure actual data
    content maps to data documentation

                                                                  13
Step 3: Plan the implementation

   Structure



    Inventory

                       Line of business will nominate
                       products; systems and operations will
                Plan   assess; all three will select which to
                       carry forward and the sequence.



                        Implement the Plan

                                                         14
The planning process
   Line of business, systems and ops select products
    based on product benefits and system costs
   They select implementation sequence based on
    market benefits and system costs
   The planning process will move through a series of
    levels, each in greater detail

      Initial               select major            implemen-
      Review               and sequence             tation plan


            Subsequent        select next            implemen-
                   Initial
             Reviews Initial sequence major tation plan
                            and       select               Implemen-
                  Review                     select major
                                     and sequence          tationImplemen-
                                                                  plan
                       Review              and sequence          tation plan

                                                                               15
Planning assumptions

 The selection of products will drive the
    requirements for systems and operations
   The planning process will be driven by the
    information from the inventory that is available
    to each line of business, systems, and operations




                                                    16
Planning management - issues
   The first level of planning will be based on major products to
    be carried forward, integrated or terminated; product and
    relative cost information is critical to the process
   Subsequent planning will select additional products and
    respond to new information about products that have been
    selected
   The same product name may be used by the two companies to
    refer to significantly different products; provide for multiple
    names for the same product and sufficient detail to
    differentiate products with the same name
   Planning for products may force consideration of changes in
    the organization of one company or the other

                                                                  17
Step 4: Implement the plan

   Structure



    Inventory



                Plan




                       Implement the Plan

                                            18
The implementation - assumptions

 The implementation will be done in phases and
    will probably be structured geographically
   The process will be driven by:
      Time and resources available to make changes
      Market impact of changes and their sequence
      Systems impact of changes and their sequence




                                                  19
Implementation issues

 Change management is critical to deal with
    market factors, new information, unforeseen
    problems, lack of resources, etc.
   Changes must be coordinated widely to manage
    expectations and to integrate elements as
    planned
   All elements must be thoroughly tested; failures
    will be public
   Delivery must meet market commitments

                                                       20
Implementation issues

 Change management is critical to deal with
    market factors, new information, unforeseen
    problems, lack of resources, etc.
   Changes must be coordinated widely to manage
    expectations and to integrate elements as
    planned
   All elements must be thoroughly tested; failures
    will be public
   Delivery must meet market commitments

                                                       21
Four step implementation process:

 Structure will reduce the complexity of the
  merger implementation and provide greater
  control

   Structure


     Inventory


                 Plan


                          Implement the Plan
                                                22
Planning and processes must be built in

 Objectives:
     Minimize time & costs
     Retain customers
     Retain key employees
 It is almost impossible to meet these objectives
  unless planning and processes are built in at the
  start of the project and then managed to
  completion.



                                                      23
Lyon, Popanz & Forester

                                The white spaces of organizations occur on
                       organization charts between internal departments,
We work in the        in contractual ambiguity and regulatory complexity.
                                                     They are places where
white space of                        functional misunderstandings occur,
                   communication falters, roles change, priorities conflict,
                              rewards are unclear, risks are unknown, and
organizations …           managers sometimes see threats to their careers
                                           that outweigh the opportunities.
including merger                          We work in those white spaces to
                                    define problems so they can be solved,
implementation           design solutions so they can be implemented, and
                          structure implementation so it can be managed.


                                           http://lpf.com      hal@lpf.com




                                                                         24

Más contenido relacionado

La actualidad más candente

Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...
Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...
Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...fabiolabaron1
 
BSC - Introduction, Architecture, Strategy Formulation Guide & Templates
BSC - Introduction, Architecture, Strategy Formulation Guide & TemplatesBSC - Introduction, Architecture, Strategy Formulation Guide & Templates
BSC - Introduction, Architecture, Strategy Formulation Guide & Templatesngaungsan
 
Strategic Management Mission and Vision Statement ppt_02
Strategic Management Mission and Vision Statement ppt_02Strategic Management Mission and Vision Statement ppt_02
Strategic Management Mission and Vision Statement ppt_02Masroor Soomro
 
Project Leadership and Change Management
Project Leadership and Change Management Project Leadership and Change Management
Project Leadership and Change Management Charles Cotter, PhD
 
Strategic management.Chapter 3
Strategic management.Chapter 3Strategic management.Chapter 3
Strategic management.Chapter 3Khurram468
 
Corporate strategy and parenting theory
Corporate strategy and parenting theoryCorporate strategy and parenting theory
Corporate strategy and parenting theoryEnzoGorlomi
 
Adaptive Strategy Combining OKR and Lean Portfolio Management
Adaptive Strategy Combining OKR and Lean Portfolio ManagementAdaptive Strategy Combining OKR and Lean Portfolio Management
Adaptive Strategy Combining OKR and Lean Portfolio ManagementEmiliano Soldi
 
Strategic management ch 05 by wajahat ali
Strategic management ch 05 by wajahat aliStrategic management ch 05 by wajahat ali
Strategic management ch 05 by wajahat aliWajahat Ali
 
Mba strategic management 2
Mba strategic management 2Mba strategic management 2
Mba strategic management 2Ahmed Hamza
 
Strategic planning
Strategic planningStrategic planning
Strategic planningBaby Faith
 
The Transformation Office - A new organisational capability for the digital e...
The Transformation Office - A new organisational capability for the digital e...The Transformation Office - A new organisational capability for the digital e...
The Transformation Office - A new organisational capability for the digital e...Rafael Lemaitre
 
Dynamic Capabilities: What Are They And How They Can Be Applied
Dynamic Capabilities: What Are They And How They Can Be AppliedDynamic Capabilities: What Are They And How They Can Be Applied
Dynamic Capabilities: What Are They And How They Can Be AppliedDavid Teece
 

La actualidad más candente (20)

Strategy Execution
Strategy ExecutionStrategy Execution
Strategy Execution
 
Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...
Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...
Elementos de la teoria de organizacion y la teoria gerencial, informe, ruth g...
 
BSC - Introduction, Architecture, Strategy Formulation Guide & Templates
BSC - Introduction, Architecture, Strategy Formulation Guide & TemplatesBSC - Introduction, Architecture, Strategy Formulation Guide & Templates
BSC - Introduction, Architecture, Strategy Formulation Guide & Templates
 
Strategic Management Mission and Vision Statement ppt_02
Strategic Management Mission and Vision Statement ppt_02Strategic Management Mission and Vision Statement ppt_02
Strategic Management Mission and Vision Statement ppt_02
 
Project Leadership and Change Management
Project Leadership and Change Management Project Leadership and Change Management
Project Leadership and Change Management
 
Strategic Leadership Defined
Strategic Leadership DefinedStrategic Leadership Defined
Strategic Leadership Defined
 
Balanced scorecard
Balanced scorecardBalanced scorecard
Balanced scorecard
 
Strategic management.Chapter 3
Strategic management.Chapter 3Strategic management.Chapter 3
Strategic management.Chapter 3
 
Corporate strategy and parenting theory
Corporate strategy and parenting theoryCorporate strategy and parenting theory
Corporate strategy and parenting theory
 
Adaptive Strategy Combining OKR and Lean Portfolio Management
Adaptive Strategy Combining OKR and Lean Portfolio ManagementAdaptive Strategy Combining OKR and Lean Portfolio Management
Adaptive Strategy Combining OKR and Lean Portfolio Management
 
Strategic management ch 05 by wajahat ali
Strategic management ch 05 by wajahat aliStrategic management ch 05 by wajahat ali
Strategic management ch 05 by wajahat ali
 
Mba strategic management 2
Mba strategic management 2Mba strategic management 2
Mba strategic management 2
 
St chap 1
St chap 1St chap 1
St chap 1
 
Disney Strategy Mergers & Acquisitions
Disney Strategy Mergers & AcquisitionsDisney Strategy Mergers & Acquisitions
Disney Strategy Mergers & Acquisitions
 
Strategic Management
Strategic ManagementStrategic Management
Strategic Management
 
Strategic planning
Strategic planningStrategic planning
Strategic planning
 
DT Case #2
DT Case #2DT Case #2
DT Case #2
 
The Transformation Office - A new organisational capability for the digital e...
The Transformation Office - A new organisational capability for the digital e...The Transformation Office - A new organisational capability for the digital e...
The Transformation Office - A new organisational capability for the digital e...
 
Bcg, ge & ansoff
Bcg, ge & ansoffBcg, ge & ansoff
Bcg, ge & ansoff
 
Dynamic Capabilities: What Are They And How They Can Be Applied
Dynamic Capabilities: What Are They And How They Can Be AppliedDynamic Capabilities: What Are They And How They Can Be Applied
Dynamic Capabilities: What Are They And How They Can Be Applied
 

Similar a Merger Implementation Steps+Issues

19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittalsatyaragha786
 
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfSabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfBrion Carroll (II)
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Logitrain: New Zealand
 
Successfully Implementing an Aggregate Spend Solution
Successfully Implementing an Aggregate Spend SolutionSuccessfully Implementing an Aggregate Spend Solution
Successfully Implementing an Aggregate Spend SolutionHuron Consulting Group
 
Module 4.1 - Operation management
Module 4.1 - Operation managementModule 4.1 - Operation management
Module 4.1 - Operation managementszpinter
 
Con8154 controlling for multiple erp systems with oracle advanced controls
Con8154 controlling for multiple erp systems with oracle advanced controlsCon8154 controlling for multiple erp systems with oracle advanced controls
Con8154 controlling for multiple erp systems with oracle advanced controlsOracle
 
Customers talk about controlling access for multiple erp systems with oracle ...
Customers talk about controlling access for multiple erp systems with oracle ...Customers talk about controlling access for multiple erp systems with oracle ...
Customers talk about controlling access for multiple erp systems with oracle ...Oracle
 
Trintech current strategies for optimizing bal sheet certification 8 29-2011
Trintech current strategies for optimizing bal sheet certification 8 29-2011Trintech current strategies for optimizing bal sheet certification 8 29-2011
Trintech current strategies for optimizing bal sheet certification 8 29-2011Eric Perry
 
Lessons learned comm_industry
Lessons learned comm_industryLessons learned comm_industry
Lessons learned comm_industryfrmichler
 
Navigating a Project to Product Shift - Walsh FiveWhyz LLC
Navigating a Project to Product Shift - Walsh FiveWhyz LLCNavigating a Project to Product Shift - Walsh FiveWhyz LLC
Navigating a Project to Product Shift - Walsh FiveWhyz LLCDaniel Walsh
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiativesureshgk
 
PPT AnalyticsCloud0415
PPT AnalyticsCloud0415PPT AnalyticsCloud0415
PPT AnalyticsCloud0415Inspirage
 
Capacity Planning and Demand Management
Capacity Planning and Demand ManagementCapacity Planning and Demand Management
Capacity Planning and Demand ManagementLawrence Putnam Jr
 

Similar a Merger Implementation Steps+Issues (20)

19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal19701759 project-report-on-railway-reservation-system-by-amit-mittal
19701759 project-report-on-railway-reservation-system-by-amit-mittal
 
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfSabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)
 
Successfully Implementing an Aggregate Spend Solution
Successfully Implementing an Aggregate Spend SolutionSuccessfully Implementing an Aggregate Spend Solution
Successfully Implementing an Aggregate Spend Solution
 
Module 4.1 - Operation management
Module 4.1 - Operation managementModule 4.1 - Operation management
Module 4.1 - Operation management
 
ERP ppt.ppt
ERP ppt.pptERP ppt.ppt
ERP ppt.ppt
 
Workflow tecnologies
Workflow tecnologiesWorkflow tecnologies
Workflow tecnologies
 
Chapter 02
Chapter 02Chapter 02
Chapter 02
 
Con8154 controlling for multiple erp systems with oracle advanced controls
Con8154 controlling for multiple erp systems with oracle advanced controlsCon8154 controlling for multiple erp systems with oracle advanced controls
Con8154 controlling for multiple erp systems with oracle advanced controls
 
Customers talk about controlling access for multiple erp systems with oracle ...
Customers talk about controlling access for multiple erp systems with oracle ...Customers talk about controlling access for multiple erp systems with oracle ...
Customers talk about controlling access for multiple erp systems with oracle ...
 
Trintech current strategies for optimizing bal sheet certification 8 29-2011
Trintech current strategies for optimizing bal sheet certification 8 29-2011Trintech current strategies for optimizing bal sheet certification 8 29-2011
Trintech current strategies for optimizing bal sheet certification 8 29-2011
 
1 project management framework
1  project management framework1  project management framework
1 project management framework
 
Lessons learned comm_industry
Lessons learned comm_industryLessons learned comm_industry
Lessons learned comm_industry
 
Erp
ErpErp
Erp
 
Navigating a Project to Product Shift - Walsh FiveWhyz LLC
Navigating a Project to Product Shift - Walsh FiveWhyz LLCNavigating a Project to Product Shift - Walsh FiveWhyz LLC
Navigating a Project to Product Shift - Walsh FiveWhyz LLC
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiative
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Ch2 op.str & comp.
Ch2 op.str & comp.Ch2 op.str & comp.
Ch2 op.str & comp.
 
PPT AnalyticsCloud0415
PPT AnalyticsCloud0415PPT AnalyticsCloud0415
PPT AnalyticsCloud0415
 
Capacity Planning and Demand Management
Capacity Planning and Demand ManagementCapacity Planning and Demand Management
Capacity Planning and Demand Management
 

Más de Hal Amens

Health insurance-pmo
Health insurance-pmoHealth insurance-pmo
Health insurance-pmoHal Amens
 
Risk & Opportunities: Healthcare Information
Risk & Opportunities: Healthcare InformationRisk & Opportunities: Healthcare Information
Risk & Opportunities: Healthcare InformationHal Amens
 
Anatomy of an EMR System
Anatomy of an EMR SystemAnatomy of an EMR System
Anatomy of an EMR SystemHal Amens
 
Introduction to EMR
Introduction to EMRIntroduction to EMR
Introduction to EMRHal Amens
 
Emr Exploration
Emr ExplorationEmr Exploration
Emr ExplorationHal Amens
 
Emr Where Start
Emr Where StartEmr Where Start
Emr Where StartHal Amens
 

Más de Hal Amens (7)

Health insurance-pmo
Health insurance-pmoHealth insurance-pmo
Health insurance-pmo
 
Risk & Opportunities: Healthcare Information
Risk & Opportunities: Healthcare InformationRisk & Opportunities: Healthcare Information
Risk & Opportunities: Healthcare Information
 
Anatomy of an EMR System
Anatomy of an EMR SystemAnatomy of an EMR System
Anatomy of an EMR System
 
Introduction to EMR
Introduction to EMRIntroduction to EMR
Introduction to EMR
 
Emr Exploration
Emr ExplorationEmr Exploration
Emr Exploration
 
Emr Where Start
Emr Where StartEmr Where Start
Emr Where Start
 
Enterprise2
Enterprise2Enterprise2
Enterprise2
 

Último

Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 

Último (20)

Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 

Merger Implementation Steps+Issues

  • 1. Merger Implementation Steps and Issues A concept document
  • 2. This is a concepts document to assist in the planning and management of merger or acquisition implementation projects. Information in this document is based on our experience as management consultants and sources we consider reliable. There are no further warranties about accuracy or applicability. It contains neither legal nor financial advice. For that, consult appropriate professionals. http://lpf.com hal@lpf.com November 2008 2
  • 3. Agenda:  Merger Implementation Assumptions  Four step implementation process:  Step 1: Management structure  Step 2: Inventory  Step 3: Plan the implementation  Step 4: Implement the plan  Conclusion 3
  • 4. Merger Implementation Assumptions  Objectives:  Minimize time & costs  Retain customers  Retain key employees  The merger will capture and integrate the best products and systems of both companies  The implementation will be staged rather than a “big bang” 4
  • 5. Four step implementation process:  A merger implementation process can be defined in four steps: Management structure, Structure processes and tools Inventory Plan Implement the Plan 5
  • 6. Step 1: Management structure  Project is generally structured around lines of business with exceptions for facilities, such as networks, that are shared by multiple lines  Within a line of business, structured by major functions: business, systems and operations  A Project Management Office to provide process expertise, coordination, and communication at the project level and major lines of business 6
  • 7. Expand the structure as required  Staff members of the merging companies know the markets, products and systems  Consultants can provide additional:  PMO and project management resources and expertise  Merger implementation structures, guidelines and processes from initial planning to implementation  System integration and data transformation resources and expertise 7
  • 8. Step 2: Inventory Structure What organizations, products, Inventory systems etc. does each company have? Plan Implement the Plan 8
  • 9. Inventory products, systems, ops  The inventory process will move through a series of phases, each adding greater detail Pre-close Pre-close is constrained in terms of the data Strategic that can be Strategic level meetings between the exchanged – companies specifically to exchange attorneys provide information. Becomes an iterative process of guidelines planning then inventory then more planning Tactical Increasing levels of detail to support plans and implementation 9
  • 10. Inventory assumptions  There is great deal of information required for the merger integration:  Find it or develop it  Test and update as needed  Make it available in data bases for the project team and the planners  The planning process will be driven by the amount and quality of the information that is available to the lines of business, systems, and operations 10
  • 11. Pre-close: inventory major activities  Identify the available information about your company’s products, systems and operations  Define, build and begin to populate the data bases that will be used over the life of the merger project  Use public sources and sources approved by your attorneys to develop information about the other company  Prepare for strategic exchange of information immediately after the close 11
  • 12. Inventory information management  Develop one or more data bases to deal with and link the following data topics:  Organizational structure and product ownership  Products – a critical element of the planning process  Computer centers – where, what do they do, …  Operations centers – where, what do they do, …  Communication networks – connect, capacity, …  Data bases used – feed to and/or draw from …  Potential issues related to expansion or termination including civic, leases, utilities … 12
  • 13. Information management - issues  The first level of planning will be based on major products to be carried forward, integrated or terminated; product information is critical to the process  The same product name may be used by more that one business unit and by the two companies to refer to significantly different products; provide for multiple names for the same product and sufficient detail to differentiate products with the same name  Look at current demand and capacity as a baseline plus the other company plus growth to find opportunities for consolidation  Allow for different organizational structures for the ownership of products – changes will have to be coordinated  Test databases, particularly older ones, to assure actual data content maps to data documentation 13
  • 14. Step 3: Plan the implementation Structure Inventory Line of business will nominate products; systems and operations will Plan assess; all three will select which to carry forward and the sequence. Implement the Plan 14
  • 15. The planning process  Line of business, systems and ops select products based on product benefits and system costs  They select implementation sequence based on market benefits and system costs  The planning process will move through a series of levels, each in greater detail Initial select major implemen- Review and sequence tation plan Subsequent select next implemen- Initial Reviews Initial sequence major tation plan and select Implemen- Review select major and sequence tationImplemen- plan Review and sequence tation plan 15
  • 16. Planning assumptions  The selection of products will drive the requirements for systems and operations  The planning process will be driven by the information from the inventory that is available to each line of business, systems, and operations 16
  • 17. Planning management - issues  The first level of planning will be based on major products to be carried forward, integrated or terminated; product and relative cost information is critical to the process  Subsequent planning will select additional products and respond to new information about products that have been selected  The same product name may be used by the two companies to refer to significantly different products; provide for multiple names for the same product and sufficient detail to differentiate products with the same name  Planning for products may force consideration of changes in the organization of one company or the other 17
  • 18. Step 4: Implement the plan Structure Inventory Plan Implement the Plan 18
  • 19. The implementation - assumptions  The implementation will be done in phases and will probably be structured geographically  The process will be driven by:  Time and resources available to make changes  Market impact of changes and their sequence  Systems impact of changes and their sequence 19
  • 20. Implementation issues  Change management is critical to deal with market factors, new information, unforeseen problems, lack of resources, etc.  Changes must be coordinated widely to manage expectations and to integrate elements as planned  All elements must be thoroughly tested; failures will be public  Delivery must meet market commitments 20
  • 21. Implementation issues  Change management is critical to deal with market factors, new information, unforeseen problems, lack of resources, etc.  Changes must be coordinated widely to manage expectations and to integrate elements as planned  All elements must be thoroughly tested; failures will be public  Delivery must meet market commitments 21
  • 22. Four step implementation process:  Structure will reduce the complexity of the merger implementation and provide greater control Structure Inventory Plan Implement the Plan 22
  • 23. Planning and processes must be built in  Objectives:  Minimize time & costs  Retain customers  Retain key employees  It is almost impossible to meet these objectives unless planning and processes are built in at the start of the project and then managed to completion. 23
  • 24. Lyon, Popanz & Forester The white spaces of organizations occur on organization charts between internal departments, We work in the in contractual ambiguity and regulatory complexity. They are places where white space of functional misunderstandings occur, communication falters, roles change, priorities conflict, rewards are unclear, risks are unknown, and organizations … managers sometimes see threats to their careers that outweigh the opportunities. including merger We work in those white spaces to define problems so they can be solved, implementation design solutions so they can be implemented, and structure implementation so it can be managed. http://lpf.com hal@lpf.com 24