ACTIVITY
Project Management ATLAS




Activity Project Management Training
commissioned by Activity Consolidated
Odijk, March 2000

Version: 2.0
ACTIVITY AND THE ATLAS

Activity is an organization that is growing rapidly. At the end of 1997, Activity had a staff of 50;
there are now some 125 professionals, each with their own unique background. We expect this
number to grow substantially in the near future. Not only is the number of staff growing, the
number of clients and the quality of the orders is rising too.

These developments have resulted in a large variety of people, clients and orders in ACTIVITY.
This also increases the importance of forming a common frame of reference for project
management and disseminating it where necessary.

Over the years, ACTIVITY has built up extensive knowledge and experience with working
schematically, project style. Part of this knowledge and experience has been laid down in the
ATLAS.


ATLAS applications

The ATLAS used internally: Common frame of reference
One important aim of the ATLAS is to create a common frame of reference. It is important for
internal communication that we speak the same language. This ATLAS is therefore not only
aimed at junior project managers, but also experienced project managers, project assistants,
account managers, staff executives and supporting staff. At ACTIVITY, when we speak about
how and why we must work schematically, the definitions laid down in ATLAS must be the
points of departure.

The ATLAS used externally: support or methodology
The Project Management Process on which the ATLAS is based is a tried and tested method of
working schematically. The knowledge and experience recorded in the ATLAS can be used by
other ACTIVITY project managers when executing projects for clients. If a client indicates that it
does not have a method of its own, the ATLAS can serve as the foundation for a tailor-made
method to suit the organization.

Points of departure
The following points of departure were used to develop the ATLAS:
 ACTIVITY does not impose any method upon the client. The method usually employed by
   the client is decisive. However, if and insofar the client‟s method is less suitable, or if the
   client indicates that it wishes to use the ACTIVITY method, the ATLAS may prove useful.
 The ATLAS is a generic model; it can be applied to projects in all sorts of environments.
 Practical suitability is the key factor. Existing publications contain more specific background
   information on the various subjects. The ATLAS is a guide with practical checklists and tools.

The ATLAS in development
The Atlas is an ongoing project. It is fed from practical experience. Because knowledge and
experience are constantly being interchanged, the ATLAS will continue to develop. There will
therefore be regular updates of the ATLAS in the form of new releases.




© ACTIVITY Consolidated                                                                                2
BIBLIOGRAPHY

The following titles are referred to in this ATLAS.


   Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus)
    Author: Activity Project Management Training, February 2000


   Projectmatig Creëren (Creating Schematically)
    J. Bos and E. Harting (editors)
    Scriptum Books, Schiedam, 1998
    ISBN: 90 5594 122 0 / NUGI 684


   A guide to the Project Management Body of Knowledge
    PMI Standards Committee, 1996
    ISBN: 1-880410-12-5




© ACTIVITY Consolidated                                                               3
D
                   e       Defining the problem
                   s
                   i         Defining the result            First think ....
                   g
                   n        Overall risk analysis

                                  Phasing

                                Breakdown


                               Organization                 ...then plan....
                   S
                   u             Milestones
                   r
                   e            Cost estimate
                   t
                   i         Information control
                                                            ...approve...
                   e
                   s           Quality control

                          Management Project Team
                              and enviroment
                                                             ... then get going....
                                Risk control

                                 Approval                            Management
                                                                        cycle
                                                         Action:                 Take stock
                   C                                   implement                 of matters
                   o                                    activities
                               Fine-planning
                   n
                   t        MEASURING AND
                   r      CHECKING PROGRESS
                   o                                Measures:
                   l          Steering progess      - steer
                                                                                  Compare
                                                    - do nothing
                                                    - stop
                                  Delivery

                                                           - Re-plan
                   W                                                                             Norm/plan
                   i                                                                            with margins
                   n             Transfer
                   d                                                    Closure and
                   i             Evaluation                               learning
                   n
                   g              Closure

                   u
                   p




© ACTIVITY Consolidated                                                                     4
DEFINITION OF THE PROBLEM                                                                                   INTRODUCTION
                                                                                  DESIGN
                                                                                                    DEFINITION OF PROBLEM
Key issues
What is the problem or the opportunity?                                                              DEFINITION OF RESULT
Should we handle this order schematically?
                                                                                                OVERALL RISK ANALYSIS

Content                                                                                                          PHASING
The first point of interest for a project manager is to gain insight into what                               BREAKDOWN
precisely the problem is and in which direction to seek the solution.             SURETIES
                                                                                                            ORGANIZATION
Result                                                                                                        MILESTONES
 General definition of the problem
                                                                                                           COST ESTIMATE
 Endorsement on drawing up project task
                                                                                                    INFORMATION CONTROL
BIBLIOGRAPHY                                                                                            QUALITY CONTROL
 Syllabus Het Projectmanagement Proces (The Project Management
                                                                                        PROJECT TEAM AND ENVIRONMENT
   Process Syllabus)                                                                                     MANAGEMENT
   Chapter 1: Definition of the problem
                                                                                                            RISK CONTROL
   Projectmatig Creëren (Creating Schematically)
                                                                                                               APPROVAL
    Chapter 1: The essence of creating schematically Korset of ruggengraat        MANAGEMENT
    (corset or backbone)                                                                                   FINE-PLANNING
    Chapter 2: Commitment and creating. From Wanting to Choosing
                                                                                    MEASURING AND CHECKING PROGRESS
   A guide to the Project Management Body of Knowledge                                               STEERING PROGRESS
    Paragraph 5.1: Initiation
                                                                                                                DELIVERY

                                                                                  WINDING UP

                                                                                                               TRANSFER

                                                                                                              EVALUATION

                                                                                                             CONCLUSION

                                                                                  TOOLS




DEFINITION OF THE PROBLEM

Formulating the problem
   Ask the client to describe the problem as precisely as possible.
   Make a list of questions regarding the problem.
   Emphasise the necessity of preliminary research.
   After the preliminary research, describe the problem as specifically as possible.
   Check the formulation of the problem with the client and end users; reformulate if necessary.
   Do not talk big.



© ACTIVITY Consolidated                                                                                          5
    Formulate in one sentence .

Questions to assist in defining the problem
   Whose problem is it (client‟s)?
   Why is it a problem?
   How urgent is the problem?
   Is there a problem underlying the problem?
   What is its (strategic) significance?
   Which potential causes and solutions have already been considered?




Pitfalls in determining the problem

    Vague and incoherent problems.
    Coming up with a solution prematurely.
    Not clear who is involved in the problem.
    Analysing the needs of the wrong target group.
    Not setting priorities in case of several problems.
    Selectively filtering problems.




© ACTIVITY Consolidated                                                  6
DEFINITION OF THE RESULT                                                                              INTRODUCTION
                                                                                 DESIGN
                                                                                              DEFINITION OF PROBLEM
Key issues
What must be achieved?                                                                         DEFINITION OF RESULT
Why must this be achieved?                                                                    OVERALL RISK ANALYSIS
What are the preconditions?
                                                                                                            PHASING
What are the criteria for success?
                                                                                                       BREAKDOWN
Content                                                                          SURETIES
                                                                                                      ORGANIZATION
As soon as we have a clear definition of the problem, we can describe in
empirical terms what must be achieved by the project and what the criteria for                          MILESTONES
success are. A preliminary estimate of the costs and time schedule are made.                         COST ESTIMATE
The client then formally endorses this.
                                                                                              INFORMATION CONTROL

Result                                                                                                QUALITY CONTROL
 Project order
                                                                                     PROJECT TEAM AND ENVIRONMENT
                                                                                                      MANAGEMENT
Bibliography
                                                                                                      RISK CONTROL
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                                     APPROVAL
                                                                                 MANAGEMENT
    Chapter 2: Definition of the result                                                               FINE-PLANNING
   Projectmatig Creëren (Creating Schematically)                                MEASURING AND CHECKING PROGRESS
    Chapter 3: The project contract. A business and tactic agreement between
                                                                                                STEERING PROGRESS
    the project team and the client
    Chapter 4: The project definition: From orders to engagements                                          DELIVERY

   A guide to the Project Management Body of Knowledge                          WINDING UP
    Paragraph 5.2: Scope planning.                                                                        TRANSFER

                                                                                                        EVALUATION
Tools
 Project order                                                                                        CONCLUSION

                                                                                 TOOLS




DEFINITION OF THE PROJECT RESULT

Tips for defining the project result
     Formulate the result as specifically as possible (using nouns).
     Clearly indicate the preconditions and criteria for success.
     Indicate what is still unknown.
     Formulate SMART
        -                        Specific
        -                        Measurable
        -                        Acceptable
        -                        Realistic
        -                        Time-related

Questions to assist in defining the result
   What is complete when it is complete?
   What will change for whom?
   What will you delegate to whom?
   What are the key requirements and wishes?
   What does not pertain to the project (demarcation)?




© ACTIVITY Consolidated                                                                                     7
Pitfalls in defining the project result
     Ideas have not been sufficiently worked out and are unstable.
     Coming up with solutions before the problem has been properly analysed.
     Too general (“a working system”).
     Too specific.




© ACTIVITY Consolidated                                                         8
IINTRODUCTION
OVERALL RISK ANALYSIS                                                              DESIGN
                                                                                                DEFINITION OF PROBLEM

                                                                                                 DEFINITION OF RESULT
Key issues
                                                                                                OVERALL RISK ANALYSIS
How do I set to work on the project in general?
Which control factors require additional attention?                                                           PHASING
What expectations must the project manager fulfil?                                                       BREAKDOWN
                                                                                   SURETIES
                                                                                                        ORGANIZATION
Content                                                                                                   MILESTONES
Using a checklist, an overall risk analysis is performed. This will help
                                                                                                       COST ESTIMATE
determine the most suitable approach to the project. The profile for the project
manager can then be determined.                                                                 INFORMATION CONTROL

                                                                                                        QUALITY CONTROL

Result                                                                                 PROJECT TEAM AND ENVIRONMENT
                                                                                                        MANAGEMENT
 Overview of risks related to control factors.
 The profile of the project manager.                                                                   RISK CONTROL
 Overall risk analysis                                                                                     APPROVAL
                                                                                   MANAGEMENT
                                                                                                        FINE-PLANNING
Bibliography                                                                       MEASURING AND CHECKING PROGRESS
 Syllabus Het Projectmanagement Proces (The Project Management                                   STEERING PROGRESS
    Process Syllabus)
    Chapter 3: Overall risk analysis                                                                         DELIVERY

                                                                                   WINDING UP

                                                                                                            TRANSFER
Tools
 Project classification                                                                                  EVALUATION

                                                                                                         CONCLUSION

                                                                                   TOOLS




© ACTIVITY Consolidated                                                                                       9
PHASING                                                                                                    INTRODUCTION
                                                                                      DESIGN
                                                                                                   DEFINITION OF PROBLEM
Key issues
How can I split up the project life cycle?                                                          DEFINITION OF RESULT
How do I keep the client involved?                                                                 OVERALL RISK ANALYSIS

                                                                                                                 PHASING

Content                                                                                                     BREAKDOWN
Phasing is splitting up a project into logical, systematic stages. Phasing gives an   SURETIES
                                                                                                           ORGANIZATION
overview of the project and enables better steering and control. After
completion of each phase comes the decision point. The next phase may only                                   MILESTONES
commence after the client has approved the phase in hand. Depending on the                                COST ESTIMATE
type of project, standard phasing, minimal phasing or custom-made phasing
may be applied.                                                                                    INFORMATION CONTROL

                                                                                                           QUALITY CONTROL

                                                                                          PROJECT TEAM AND ENVIRONMENT
Result                                                                                                     MANAGEMENT
 Phasing with decision points.
                                                                                                           RISK CONTROL

                                                                                                               APPROVAL
Bibliography                                                                          MANAGEMENT
                                                                                                           FINE-PLANNING
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                 MEASURING AND CHECKING PROGRESS

    Chapter 4: Phasing the project life cycle.                                                       STEERING PROGRESS

   Projectmatig Creëren (Creating Schematically)                                                               DELIVERY
    Chapter 5: The project structure. Introducing structure, staying flexible and
                                                                                      WINDING UP
    channelling energy.
                                                                                                               TRANSFER
   A guide to the Project Management Body of Knowledge
    Paragraph 2.1: Project phases and the project life cycle                                                 EVALUATION

                                                                                                            CONCLUSION

                                                                                      TOOLS
Tools
 Phasing



PHASING THE PROJECT LIFE CYCLE

Standard phasing consists of the following phases and decision points:

a) Initiative phase                  start: the idea/initiative
activities                           - determine the status quo;
                                     - study the general problem issues;
                                     - give a general definition of desired result;
                                     - demarcate the project;
                                     - indicate project phasing;
                                     - describe the modus operandi;
                                     - draw up the project order;

                                     end situation: approved, decision document: Project order




© ACTIVITY Consolidated                                                                                        10
b) Definition phase       start: approved Project order
activities                - collect the basic material;
                          - determine project boundaries;
                          - determine project requirements:
                               preconditions;
                               functional requirements;
                               operational requirements;
                               restrictions of the design;
                          - set up a list of activities;
                          - set up the order of activities;
                          - set up the operating structure (defining sub-projects);
                          - establish contact with third parties (designers);
                          - draw up a project programme.

                          end situation: approved, decision document: Project plan
c) Design phase           start: approved Project plan
activities                - detail the project programme;
                          - contract third parties (designers);
                          - seek solutions/designs for each sub-project;
                          - seek or design project tools;
                          - fine-tune sub-projects and project tools;
                          - test sub-designs;
                          - adjust sub-designs;
                          - draw up the project design (down to the most basic level):
                                          sub-projects;
                                          tools.

                          end situation: approved, decision document: Project design

d) Preparation phase      start: approved Project design
activities                - draw up implementation instructions, etc.
                          - purchase/make tools (quantitative);
                          - contract third parties (suppliers);
                          - train the implementation organization;
                          - draw up the implementation programme (scenario).

                          end situation: approved, decision document: Implementation plan

e) Implementation phase           start: approved Implementation plan
activities                - deliver project result;
                          - implement as per programme;
                          - adjust programme.

                          end situation: approved Project result

f) Follow-up phase        start: approved, decision document: Follow-up programme
activities                - conclude project;
                          - put completed project into service;
                          - maintain completed project ;
                          - maintain tools;
                          - evaluation.

                          end situation: project evaluation.




© ACTIVITY Consolidated                                                                     11
BREAKING DOWN INTO COMPONENTS                                                                             INTRODUCTION
                                                                                     DESIGN
Key issues                                                                                        DEFINITION OF PROBLEM
How do I break down the larger whole into manageable parts?                                        DEFINITION OF RESULT

                                                                                                  OVERALL RISK ANALYSIS

Content                                                                                                         PHASING
In order to gain more insight into what must be done and who must be
                                                                                                           BREAKDOWN
involved, the project manager breaks down the project result into orderly units.     SURETIES
In larger projects, the total project is broken down into sub-projects, and a                             ORGANIZATION
Work Breakdown Structure can be set up for each sub-project. Subsequently,
                                                                                                            MILESTONES
each activity can be allocated to an organizational section or person in charge.
This results in the Organizational Breakdown Structure. The activities allocated                         COST ESTIMATE
to a person or department in charge are called “work packages”.                                   INFORMATION CONTROL

                                                                                                          QUALITY CONTROL

Result                                                                                    PROJECT TEAM AND ENVIRONMENT
 WBS                                                                                                      MANAGEMENT

 OBS                                                                                                     RISK CONTROL

                                                                                                              APPROVAL
                                                                                     MANAGEMENT
Bibliography                                                                                              FINE-PLANNING
 Syllabus Het Projectmanagement Proces (The Project Management                       MEASURING AND CHECKING PROGRESS
    Process Syllabus)
                                                                                                    STEERING PROGRESS
    Chapter 5: Breaking down into components
                                                                                                               DELIVERY
    Projectmatig Creëren (Creating Schematically)
     Chapter 5: The project structure. Introducing structure, staying flexible and   WINDING UP
     channelling energy.
                                                                                                              TRANSFER
    A guide to the Project Management Body of Knowledge                                                    EVALUATION
     Paragraph 5.3.2: Tools and techniques for Scope Definition
                                                                                                           CONCLUSION

                                                                                     TOOLS
Tools
 Planning matrix



THE WORK BREAKDOWN STRUCTURE

Conditions which a WBS must meet

1:        There must be a strict hierarchy of activities.

2:        There must be no overlap between activities; each activity is an independent entity.

3:        Each activity must result in a demonstrable product.

4:        Each activity must have an apparent throughput time.

5:        Each activity must have calculable costs.

To what degree must entities be broken down?
   Until all elements can be univocally allocated to a specific section of the organization.
     Until all products have been defined in terms of activities.
     No further than five levels deep.



© ACTIVITY Consolidated                                                                                       12
Project




             Sub-project                 Sub-project              Sub-project




      Act.            Act.      Act.        Act.        Act.      Act.          Act.




     Dep./P.         Dep./P.   Dep./P.    Dep./P.      Dep./P.   Dep./P.    Dep./P.




© ACTIVITY Consolidated                                                                13
ORGANIZATION
Key issues                                                                         DESIGN
                                                                                                 DEFINITION OF PROBLEM
How do I obtain the right people and resources?
                                                                                                      DEFINITION OF RESULT

                                                                                                 OVERALL RISK ANALYSIS
Content
                                                                                                                  PHASING
This step is geared to drawing up a workable and manageable project
organization. This includes obtaining the manpower and material resources                                     BREAKDOWN
needed for the project and establishing tasks, responsibilities and powers. The    SURETIES
                                                                                                            ORGANIZATION
relation between the project and the rest of the organization is also described.
                                                                                                              MILESTONES

                                                                                                            COST ESTIMATE
Result
 Project organization.                                                                           INFORMATION CONTROL
 Diagram of the relation.                                                                                  QUALITY CONTROL
 Tasks, Powers and Responsibilities.
                                                                                        PROJECT TEAM AND ENVIRONMENT
                                                                                                         MANAGEMENT

Bibliography                                                                                                RISK CONTROL

 Syllabus Het Projectmanagement Proces (The Project Management                                                 APPROVAL
                                                                                   MANAGEMENT
    Process Syllabus)                                                                                       FINE-PLANNING
    Chapter 6: Organization
                                                                                    MEASURING AND CHECKING PROGRESS
   Projectmatig Creëren (Creating Schematically)
                                                                                                      STEERING PROGRESS
    Chapter 10: The project organization. The organizational structure as a
    custom-made suit.                                                                                            DELIVERY

   A guide to the Project Management Body of Knowledge                            WINDING UP
    Paragraph 7.1: Resource Planning
                                                                                                                TRANSFER
    Paragraph 9.1: Organizational Planning
    Paragraph 9.2: Staff Acquisition                                                                          EVALUATION

                                                                                                              CONCLUSION

                                                                                   TOOLS




PROJECT ORGANIZATION

Questions to assist in defining the organization
   Who does what?
   Who has what powers?
   How is decision-making arranged?
   How is the relation between the project organization and the rest of the organization arranged?

Resources for the organization
   OBS
   Project organogram
   Project environment chart – informal (relation)
   Powers and Responsibilities.
   Escalation procedure




© ACTIVITY Consolidated                                                                                         14
INTRODUCTION
MILESTONES                                                                         DESIGN
                                                                                                DEFINITION OF PROBLEM

                                                                                                 DEFINITION OF RESULT
Key issues
When must which interim results be achieved?                                                    OVERALL RISK ANALYSIS

                                                                                                              PHASING

Content                                                                                                  BREAKDOWN
                                                                                   SURETIES
In cooperation with the persons involved, the interim project targets                                   ORGANIZATION
(milestones) are described in terms of specific, measurable results. These
milestones are fixed, verifiable controls used during the project to assess                               MILESTONES

whether the project is still on course. The milestone plan indicates the logical                       COST ESTIMATE
mutual connections between the milestones and the activities to be executed for
                                                                                                INFORMATION CONTROL
steady progress from one milestone to the next.
                                                                                                        QUALITY CONTROL

                                                                                       PROJECT TEAM AND ENVIRONMENT
Result                                                                                                  MANAGEMENT
 Milestone plan                                                                                        RISK CONTROL

                                                                                                            APPROVAL
                                                                                   MANAGEMENT
Bibliography                                                                                            FINE-PLANNING
 Syllabus Het Projectmanagement Proces (The Project Management
                                                                                   MEASURING AND CHECKING PROGRESS
    Process Syllabus)
    Chapter 7: Milestones                                                                         STEERING PROGRESS

   Projectmatig Creëren (Creating Schematically)                                                            DELIVERY

    Chapter 7: Project planning - Making feasible plans.                           WINDING UP

                                                                                                            TRANSFER

Tools                                                                                                     EVALUATION
 Milestone plan                                                                                         CONCLUSION

                                                                                   TOOLS




MILESTONE PLAN

Milestone characteristics
 Represent important decision points.
 Are natural
 Are measurable
 Are progressively closer to the project result
 Can be interdependent (milestone plan)
 The intervening periods are manageable


Inventory of milestones
 Brainstorm with involved parties based on the WBS:
      - contribution of knowledge;
      - collective perception of the result and approach;
      - list of task allocation and dependencies.
 Make a thorough redefinition:
      - indicate only the "what" – do not impose the "how";
      - maintain a provisional list of activities.




© ACTIVITY Consolidated                                                                                     15
Definition of milestones
    Milestone             :   description
    Status                :   version number
    Results               :   concise description of the products/services to be delivered for this milestone
    Quality               :   requirements the result must meet
    Time                  :   start / end: early - late
    Funds                 :   estimated costs
    Responsibility        :   organizational department + staff
    Dependency            :   previous milestones, who is waiting for the result?
    Risks                 :   anticipated bottlenecks and precautionary measures
    Endorsement           :   signing and dating of planning and milestone by the persons in charge




© ACTIVITY Consolidated                                                                                     16
COST ESTIMATE                                                                                           INTRODUCTION
                                                                                   DESIGN
                                                                                                DEFINITION OF PROBLEM
Key issues
How do I estimate and monitor the project costs?                                                 DEFINITION OF RESULT

                                                                                                OVERALL RISK ANALYSIS

                                                                                                              PHASING
Content
The project manager draws up a realistic cost estimate so that he has a standard                         BREAKDOWN
by which to monitor the incurred costs during the course of the project. The       SURETIES
                                                                                                        ORGANIZATION
work packages (see Breaking down) form the point of departure for drawing up
a cost estimate.                                                                                          MILESTONES

                                                                                                       COST ESTIMATE

Result                                                                                          INFORMATION CONTROL

 Cost estimate                                                                                         QUALITY CONTROL
 Project budget
                                                                                       PROJECT TEAM AND ENVIRONMENT
                                                                                                        MANAGEMENT

                                                                                                        RISK CONTROL
Bibliography
 Syllabus Het Projectmanagement Proces (The Project Management                                             APPROVAL
                                                                                   MANAGEMENT
    Process Syllabus)                                                                                   FINE-PLANNING
    Chapter 8: Cost estimate
                                                                                   MEASURING AND CHECKING PROGRESS
   Projectmatig Creëren (Creating Schematically)
                                                                                                  STEERING PROGRESS
    Chapter 8: Funds. The various ways in which money can
    be obtained for/roll into a project                                                                      DELIVERY

   A guide to the Project Management Body of Knowledge                            WINDING UP
    Paragraph 7.2: Cost Estimating                                                                          TRANSFER
    Paragraph 7.3: Cost Budgeting
    Paragraph 7.4: Cost Control                                                                           EVALUATION

                                                                                                         CONCLUSION

                                                                                   TOOLS
Tools
 Costs matrix



COST ESTIMATE

The project budget

The project budget
    consists of costs that can be influenced by the project manager, for:
          manpower;
          resources;
          materials;
    serves as a basis for project control;
    is drawn up and approved as early as possible.

The cost estimate

The cost estimate comprises the calculation of all costs components:
    Gives an idea of the costs of the project result.
    Serves as a basis for decision-making by the management.




© ACTIVITY Consolidated                                                                                     17
Drawing up a project budget
    When drawing up a budget, we distinguish between costs and investments. Costs are subdivided into direct and indirect
    costs; investments are subdivided into movables and immovables.


    Step 1: Inventory of costs

    Direct project costs
        Determine which costs are directly attributable to the project.
        Classify these costs into a number of main groups which together cover all the direct costs.

    Indirect project costs
        Determine which costs are indirectly attributable to the project.
        Consider for instance the secondary resources that are vital for the project‟s success.

    Movables
       Mention the specific movables and determine the associated costs.
       Determine the economic life span and the necessary maintenance costs. Maintenance costs must be entered as direct
        costs if the maintenance costs are directly attributable to the project (otherwise enter as indirect costs).

    Immovables
       Mention the specific immovables and determine the associated costs.
       Determine the economic life span and the necessary maintenance costs. Maintenance costs must be entered as direct
        costs if the maintenance costs are directly attributable to the project (otherwise enter as indirect costs).



    The above can be depicted in the following diagram:


                          Costs                                                          Investments


Direct costs                     Indirect costs           Movables                             Immovables
     Consultancy                  Workplace                Purchase of production equipment    Purchase of production premises
     Travel and accommodation      (Computer/Printer)
      costs
     Office supplies              Office space              Purchase price: NLG 140,000          Purchase price: NLG 600,000
     Maintenance costs            Telephone/fax costs       Economic life span:                  Economic life span: 20 years
                                                              4 years
                                                              Monthly maintenance costs:           Monthly maintenance costs:
                                                              NLG 1,000 (see direct costs)         NLG 500 (see direct costs)




    © ACTIVITY Consolidated                                                                                           18
Step 2: Cost planning in time

The costs are then plotted in time. The time units are given on the vertical (Y) axis and the different cost categories on the
X-axis.

            Direct costs                              Indirect costs                                   Movable     Immovable
                                                                                                       investments investments
             Consultancy     Travel and       Office Maintenan Workplace        Office Telephone/fa       Production        Production
                           accommodat       supplies        ce                  space        x costs      equipment           premises
                               ion costs
March            20,000             200         100           0         1,500    2,000        1,000
April            40,000             400         200       1,000         2,000    2,500        1,250         140,000
May              50,000             400         200       1,000         2,000    2,500        1,500
June             50,000             600         400       1,000         2,000    2,500        1,500
July             50,000             600         400       1,500         2,000    2,500        1,500                           600,000
August           30,000             400         200       1,500         2,000    2,500        1,500
total           240,000           2,600       1,500       6,000        11,500   14,500        8,250         140,000           600,000

Total expenses made for the project in the period March through August : 1,024,350


Step 3: Approval
After the cost estimate has been drawn up, it is presented to the client for approval.


Step 4: Periodical analysis

The actual costs and any costs yet to be incurred are compared with the approved budget per period. Note: In the
cost analysis, the investments and depreciations must be included for all the above-mentioned expenses.

Drawing up a budget
 Identify the cost centres.
 Determine cost types per cost centre.
 Gather „hard” information (time investments, rates, offers, price lists, etc.).
 If no “hard” information is available, have those executing the project draw up the cost estimate.
 Determine what can be accurately estimated (5%) and what can be broadly estimated (10%-30%).
 Determine the margin
 Have the cost estimate approved for budget release.


Cost types / cost centres
 Time investment by company personnel / other personnel.
 Contractor‟s costs (subsequent calculation or fixed price).
 Material costs (building blocks, resources).

         cost centre
                               MS A            MS B               MS C          MS D               Total
cost type
Contractor                         20,000        135,000            75,000           15,000              245,000
Company personnel                   1,400          2,000             1,800              800                6,000
Other personnel                       300            150               750            2,500                3,700
Material                            3,000            500               600            1,200                5,300
Total                              24,700        137,650            78,150           19,500              260,000

                       MS = Milestone




© ACTIVITY Consolidated                                                                                                19
INFORMATION CONTROL                                                                                         INTRODUCTION
                                                                                     DESIGN
                                                                                                   DEFINITION OF PROBLEM

Key issues                                                                                           DEFINITION OF RESULT
Who must I inform about what and when?
                                                                                                   OVERALL RISK ANALYSIS

                                                                                                                   PHASING
Content                                                                                                       BREAKDOWN
To ensure that it is clear to everyone what is meant and who must do something       SURETIES
with which information, the project manager draws up an information matrix                                  ORGANIZATION
and (for large, complex projects), a communication plan. Furthermore, it is the                               MILESTONES
project manager‟s responsibility to ensure that the information is unequivocal
                                                                                                           COST ESTIMATE
and recognizable (for instance: final or draft status) and can be found in the
files.                                                                                              INFORMATION CONTROL

                                                                                                            QUALITY CONTROL

Result                                                                                    PROJECT TEAM AND ENVIRONMENT
                                                                                                           MANAGEMENT
 Information matrix
 Communication plan                                                                                        RISK CONTROL

                                                                                                                  APPROVAL
                                                                                     MANAGEMENT
Bibliography                                                                                                FINE-PLANNING

 Syllabus Het Projectmanagement Proces (The Project Management                       MEASURING AND CHECKING PROGRESS
    Process Syllabus)                                                                                 STEERING PROGRESS
    Chapter 9: Information control
                                                                                                                  DELIVERY
   Projectmatig Creëren (Creating Schematically)
    Chapter 11: Information. The mustiest management aspect?                         WINDING UP

   A guide to the Project Management Body of Knowledge                                                           TRANSFER

    Paragraph 10.1: Communications Planning                                                                   EVALUATION
    Paragraph 10.2: Information Distribution
                                                                                                              CONCLUSION

Tools                                                                                TOOLS

 Action points
 Decisions list
 Information matrix


INFORMATION CONTROL

Information control is geared to monitoring the clarity and univocality of the project information by means of:
 coding documents;
 aligning document structure to match content of and coherence with other documents;
 distributing documents;
 releasing documents and amending them in accordance with the procedures;
 filing documents;
 keeping documents for at least 10 years (this is a legal requirement).


Tips for information control
 Strive for completeness and up-to-dateness.
 Keep the set-up simple.
 Be aware of individual information needs.
 Avoid a personal set-up.
 Record agreements in writing.
 Go for an attractive design.




© ACTIVITY Consolidated                                                                                           20
Information matrix


                       Client               Account      Internal             Project        Sub-project      Project office
                                            manager    commissioner         organization       leader


Project                               Compiles
order                                 Distributes



Project plan                                           Determines           Compiles                          Files



Delivery           Accepts                             Determines           Compiles                          Files
document


Offers             Accepts            Compiles         Determines
                                      Distributes
                                                                                                              Distributes
Progress                                                                    Compiles                          Files
reports

                                                                                                              Compiles
Sub-project                                                                                Determines         Distributes
reports                                                                                                       Files




Information flow chart



                                                      Project information

                             Uncontrolled
                                                                                            not recorded
                                                                              no
                                                         Record ?                          (e.g. verbally)


                                                                 ja
                             Retrievable
                                                            Central           no          decentralized
                                                           control ?                   (eg private records)

                                                                 ja
                             Controlled                       Central
                                                          project records



                                                        Company records

               `




© ACTIVITY Consolidated                                                                                                21
QUALITY CONTROL                                                                                                INTRODUCTION
                                                                                          DESIGN
                                                                                                       DEFINITION OF PROBLEM
Key issues
How do I meet the agreed quality requirements?                                                          DEFINITION OF RESULT

                                                                                                       OVERALL RISK ANALYSIS

                                                                                                                    PHASING
Content
At the end of the project, a product or service must be delivered that meets the                                BREAKDOWN
client‟s demands. The project manager ensures that delivery takes place in time           SURETIES
                                                                                                               ORGANIZATION
and at the agreed price, and that it meets the agreed quality (both product and
process quality). The agreements made on quality are laid down in product                                        MILESTONES
specifications and/or a quality plan.                                                                         COST ESTIMATE

                                                                                                       INFORMATION CONTROL

Result                                                                                                      QUALITY CONTROL
 Product specifications
                                                                                              PROJECT TEAM AND ENVIRONMENT
 Quality plan                                                                                                 MANAGEMENT

                                                                                                               RISK CONTROL

Bibliography                                                                                                      APPROVAL
                                                                                          MANAGEMENT
 Syllabus Het Projectmanagement Proces (The Project Management                                                FINE-PLANNING
    Process Syllabus)
    Chapter 10: Quality control                                                           MEASURING AND CHECKING PROGRESS

                                                                                                         STEERING PROGRESS
   Projectmatig Creëren (Creating Schematically)
    Chapter 9: Quality. True quality resides in people.                                                            DELIVERY

   A guide to the Project Management Body of Knowledge                                   WINDING UP
    Paragraph 8.1: Quality Planning                                                                                TRANSFER
    Paragraph 8.2: Quality Assurance
    Paragraph 8.3: Quality Control                                                                               EVALUATION

                                                                                                                CONCLUSION

                                                                                          TOOLS




QUALITY CONTROL

Two activities can be distinguished in the quality control process:
1: Drawing up the quality plan
         overall result
         requirements / wishes
         product specifications

2: Progress checks
       Interim testing and monitoring of the quality of
          the product
          the project management process

Key principle for quality: the sooner a flaw is found, the less it will cost to remedy.




© ACTIVITY Consolidated                                                                                            22
Quality management

The process can be depicted as follows:



                                                QUALITY MANAGEMENT

                                        (Overall description of the project result)


                                                Requirements and wishes

                        Norm/
                        specification             Product specifications

                         Progress
                         control
                                                       Interim testing


                                                        Endorsement
                                                        Project result




Quality plan
 Tasks include: translating the intrinsic requirements into measurable quality requirements.
 Methods: testing.
 Procedures for advising and giving approval.
 Test plan: who, what, when, where and how?
 Aim for a flawless design.


Progress checks
 Who will test what to the requirements set?


Specification requirements
 Objective
 Valid
 Reliable
 Desired level (of quality/quantity)
 Indication for „measuring costs‟




© ACTIVITY Consolidated                                                                         23
PROJECT TEAM AND ENVIRONMENT MANAGEMENT                                                                INTRODUCTION
                                                                                  DESIGN
                                                                                               DEFINITION OF PROBLEM
Key issues
How do I keep all parties on course?                                                            DEFINITION OF RESULT

                                                                                               OVERALL RISK ANALYSIS

Content                                                                                                      PHASING
The project manager closely consults with and steers the project team and other                         BREAKDOWN
involved parties from the moment he joins the project till the moment it is       SURETIES
wound up. Social aspects like managing, negotiating, team role management                              ORGANIZATION
and conflict management are obviously critical success factors in a project.                             MILESTONES

                                                                                                      COST ESTIMATE

Result                                                                                         INFORMATION CONTROL
 Defined cooperation                                                                                  QUALITY CONTROL

                                                                                      PROJECT TEAM AND ENVIRONMENT
                                                                                                       MANAGEMENT
Bibliography
                                                                                                       RISK CONTROL
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                                      APPROVAL
    Chapter 11: Project team and environment management                           MANAGEMENT
                                                                                                       FINE-PLANNING
   Projectmatig Creëren (Creating Schematically)
                                                                                  MEASURING AND CHECKING PROGRESS
    Chapter 13: Forces and interests in and connected with projects
    Chapter 15: The project team                                                                 STEERING PROGRESS
    Chapter 17: Project and parent organization                                                             DELIVERY

   A guide to the Project Management Body of Knowledge                           WINDING UP
    Paragraph 9.3: Team Development
                                                                                                           TRANSFER

                                                                                                         EVALUATION
Tools                                                                                                   CONCLUSION
 Analyse the project environment
                                                                                  TOOLS




© ACTIVITY Consolidated                                                                                    24
INTRODUCTION
RISK CONTROL                                                                          DESIGN
                                                                                                     DEFINITION OF PROBLEM

                                                                                                      DEFINITION OF RESULT
Key issues
What must definitely not go wrong in a project?                                                      OVERALL RISK ANALYSIS
How can I prevent or take care of any setbacks?                                                                    PHASING

Content                                                                                                       BREAKDOWN
                                                                                      SURETIES
An overall risk analysis is carried out at the beginning of a project (see the                               ORGANIZATION
process step „overall risk analysis‟). Later on in the project, when the path of
the project has become more defined, a more detailed risk analysis is                                          MILESTONES

performed. The purpose is to take precautionary measures and prevent                                        COST ESTIMATE
problems or compile a list of corrective measures early on in the project. A risk
                                                                                                     INFORMATION CONTROL
factor that requires special attention is the legal side of matters, for instance,
how is liability arranged.                                                                                   QUALITY CONTROL

Result:                                                                                      PROJECT TEAM AND ENVIRONMENT
                                                                                                              MANAGEMENT
 Preventive/corrective action
 Risk-proof project plan                                                                                    RISK CONTROL

                                                                                                                  APPROVAL
Bibliography                                                                          MANAGEMENT
                                                                                                             FINE-PLANNING
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                  MEASURING AND CHECKING PROGRESS
    Chapter 12: Risk control                                                                           STEERING PROGRESS
   Projectmatig Creëren (Creating Schematically)                                                                 DELIVERY
    Chapter 19: Risk management
    Chapter 20: Creative problem-solving                                              WINDING UP

   A guide to the Project Management Body of Knowledge                                                           TRANSFER

    Paragraph 11.1: Risk Identification                                                                        EVALUATION
    Paragraph 11.2: Risk Quantification
                                                                                                              CONCLUSION
    Paragraph 11.3: Risk Response Development
    Paragraph 11.4: Risk Response Control                                             TOOLS


Tools
 Dealing with potential bottlenecks
 Cause-Consequence analysis
 Impact analysis

RISK ANALYSIS AND RISK REDUCTION

Risk limitation
Risk limitation encompasses two general activities. The risk is identified during the analysis phase and neutralised
during the reduction phase. Risk limitation is thus a particularly valuable control instrument.

Questions to assist in defining risk analysis
1.    What can go wrong with the project result, the milestones, etc.
2.    What are the potential consequences?
3.    What is the chance of failure?

Measuring and assessing the risks

Chance of occurring              X         Severity of the                           Score         Risk
                                           consequences
Almost nil                1            1   Hardly any consequences                   1-2           Low risk
Small chance              2            2   Limited consequences                      3-9           Average risk
Reasonable chance         3            3   Fairly serious consequences               10-25         High risk
Is sure to occur          4            4   Fatal consequences
Cannot be estimated       5            5   Cannot be estimated



© ACTIVITY Consolidated                                                                                           25
Questions to assist in defining risk limitation
   What is the most plausible cause?
   Which preventive measures can be taken?
   Is the remaining risk component acceptable?
   Which reactive measures can be taken?
   Who will do what and when?


Risk analysis

CAN ANYTHING GO WRONG?                                   NO RISK
                                                  NO


  YES



SPECIFY PROBLEM




CAN WE ESTIMATE THE RISK?                                 FURTHER PROBLEM ANALYSIS
                                                  NO



 YE
 S


 IS THE RISK LARGE ENOUGH TO HAVE TO TACKLE?              CALCULATED RISK
                                                  NO



  YE
  S


 TAKE PRECAUTIONARY MEASURES




 IS THE REMAINING RISK ACCEPTABLE                         REDUCED RISK
                                                   YES



  NO



  MAKE CONTINGENCY PLANS




 CAN THE DAMAGE BE SUFFICIENTLY CONTAINED?                COVERED RISK
                                                   YES



  NO



PERMANENT RISK




© ACTIVITY Consolidated                                                        26
APPROVAL                                                                                                 INTRODUCTION
                                                                                    DESIGN
                                                                                                 DEFINITION OF PROBLEM
Key issues
How do I get approval for the decision documents?                                                 DEFINITION OF RESULT
Who must approve the decision documents?
                                                                                                 OVERALL RISK ANALYSIS

Content                                                                                                        PHASING
The client remains closely involved with the project for the duration of the                              BREAKDOWN
project. After all, the client must approve specifications and planning and         SURETIES
provide the necessary resources (staff, funds and material). The client must also                        ORGANIZATION
make choices (continue, modify or stop) if plans lose touch with reality. The                              MILESTONES
client‟s role must therefore be clearly defined.
                                                                                                        COST ESTIMATE
In addition to the client, all others involved in the project must be able to
approve the project plan. This is expressed in the shape of acceptance,                          INFORMATION CONTROL
commitment, motivation and involvement. Without this support basis, it is                                QUALITY CONTROL
almost impossible to complete a project successfully.
                                                                                        PROJECT TEAM AND ENVIRONMENT
                                                                                                         MANAGEMENT

Result                                                                                                   RISK CONTROL
 Approved decision documents                                                                                APPROVAL
 Commitment from those involved                                                    MANAGEMENT
                                                                                                         FINE-PLANNING

                                                                                    MEASURING AND CHECKING PROGRESS
Bibliography
                                                                                                   STEERING PROGRESS
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                                         DELIVERY

    Chapter 13: Approval                                                            WINDING UP
   Projectmatig Creëren (Creating Schematically)                                                            TRANSFER
    Chapter 16: The client
                                                                                                           EVALUATION

                                                                                                          CONCLUSION

Tools                                                                               TOOLS
 Project plan
 Project design




© ACTIVITY Consolidated                                                                                      27
FINE-PLANNING                                                                                         INTRODUCTION
                                                                                 DESIGN
                                                                                              DEFINITION OF PROBLEM

Key issues                                                                                     DEFINITION OF RESULT
Who must do what and when in the next phase?
                                                                                              OVERALL RISK ANALYSIS

                                                                                                            PHASING
Content                                                                                                BREAKDOWN
As soon as it is known when execution of the work can commence, fine-            SURETIES
planning for the first phase can commence. The overall planning will continue                         ORGANIZATION

to apply for the later phases. Only after completion of each phase is the next                          MILESTONES
phase fine-planned. These schedules can be depicted visually in a network or
                                                                                                     COST ESTIMATE
bar-chart planning.
                                                                                              INFORMATION CONTROL

                                                                                                      QUALITY CONTROL
Result
 Activities plan                                                                    PROJECT TEAM AND ENVIRONMENT
                                                                                                      MANAGEMENT

                                                                                                      RISK CONTROL
Bibliography                                                                                              APPROVAL
 Syllabus Het Projectmanagement Proces (The Project Management                  MANAGEMENT
                                                                                                      FINE-PLANNING
    Process Syllabus)
    Chapter 14: Fine-planning                                                    MEASURING AND CHECKING PROGRESS

   Projectmatig Creëren (Creating Schematically)                                               STEERING PROGRESS
    Chapter 7: Project planning                                                                            DELIVERY

   A guide to the Project Management Body of Knowledge                          WINDING UP
    Paragraph 6.1: Activity Definition
                                                                                                          TRANSFER
    Paragraph 6.2: Activity Sequencing
    Paragraph 6.3: Activity Duration Estimating                                                         EVALUATION
    Paragraph 6.4: Schedule Development
                                                                                                       CONCLUSION

                                                                                 TOOLS

Tools
 Implementation programme




© ACTIVITY Consolidated                                                                                   28
INTRODUCTION
MEASURING AND CHECKING PROGRESS                                                      DESIGN
                                                                                                  DEFINITION OF PROBLEM
Key issues
                                                                                                   DEFINITION OF RESULT
On what basis do I evaluate the project progress?
How do I keep all those involved informed of the project progress?                                OVERALL RISK ANALYSIS

                                                                                                                PHASING

Content                                                                                                    BREAKDOWN
                                                                                     SURETIES
There will be continuous feedback on the planning during execution of the                                 ORGANIZATION
project. The project manager will be kept up-to-date on the project via progress
reports and will test this against the plan (or the norm). In order to implement                            MILESTONES

this step of the process properly, criteria must be laid down and it must be clear                       COST ESTIMATE
who is reporting on what and when.
                                                                                                  INFORMATION CONTROL

                                                                                                          QUALITY CONTROL
Result                                                                                   PROJECT TEAM AND ENVIRONMENT
 Criteria                                                                                                MANAGEMENT
 Progress reports                                                                                        RISK CONTROL

                                                                                                              APPROVAL
                                                                                     MANAGEMENT
Bibliography                                                                                              FINE-PLANNING
 Syllabus Het Projectmanagement Proces (The Project Management
                                                                                     MEASURING AND CHECKING PROGRESS
    Process Syllabus)
    Chapter 15: Measuring and checking                                                              STEERING PROGRESS

   Projectmatig Creëren (Creating Schematically)                                                              DELIVERY

    Chapter 6: Project control                                                       WINDING UP

   A guide to the Project Management Body of Knowledge                                                       TRANSFER
    Paragraph 6.5: Schedule Control
                                                                                                            EVALUATION

                                                                                                           CONCLUSION

Tools                                                                                TOOLS
 Quick scan project control
 Progress reports




© ACTIVITY Consolidated                                                                                       29
STEERING PROGRESS                                                                                        INTRODUCTION
                                                                                    DESIGN
                                                                                                 DEFINITION OF PROBLEM

Key issues                                                                                        DEFINITION OF RESULT
How do I achieve the agreed end result?                                                          OVERALL RISK ANALYSIS
How do I ensure that the end result is used effectively?
                                                                                                               PHASING

                                                                                                          BREAKDOWN
Content                                                                             SURETIES
                                                                                                         ORGANIZATION
If progress appears to be drifting away from the planning, the project manager
must take steps to align planning and reality. He can do this by steering, re-                             MILESTONES
planning or, if the worst comes to the worst, he may even decide to put a halt to                       COST ESTIMATE
the entire project. For the project manager, the point of departure is always to
achieve the desired end result.                                                                  INFORMATION CONTROL

                                                                                                         QUALITY CONTROL

                                                                                        PROJECT TEAM AND ENVIRONMENT
Result                                                                                                   MANAGEMENT
 Part results
 Acceptance                                                                                             RISK CONTROL

                                                                                                             APPROVAL
                                                                                    MANAGEMENT
                                                                                                         FINE-PLANNING
Bibliography
 Syllabus Het Projectmanagement Proces (The Project Management                     MEASURING AND CHECKING PROGRESS

    Process Syllabus)                                                                              STEERING PROGRESS
    Chapter 16: Steering
                                                                                                              DELIVERY
   Projectmatig Creëren (Creating Schematically)
                                                                                    WINDING UP
    Chapter 6: Project control – the art of playing the Bermuda triangle
                                                                                                             TRANSFER

                                                                                                           EVALUATION

                                                                                                          CONCLUSION

                                                                                    TOOLS




CHECKING THE PROJECT PROGRESS

Content of the progress report
 Retrospect
        State of affairs in connection with the plan
        With respect to content and control
 Preview
        Approach of next phase (in detail)
        Approach of subsequent phase (in detail)
        With respect to content and control
 Periodical
        Milestone-dependent




© ACTIVITY Consolidated                                                                                      30
INTRODUCTION
DELIVERY                                                                              DESIGN
                                                                                                    DEFINITION OF PROBLEM
Key issues
                                                                                                      DEFINITION OF RESULT
How do I get endorsement of the project result from the client?
                                                                                                    OVERALL RISK ANALYSIS

                                                                                                                   PHASING
Content
Delivery of the project result to the client is confirmed by the Delivery                                     BREAKDOWN
                                                                                      SURETIES
document. With this document, the client declares in writing that all agreed                                 ORGANIZATION
project results have indeed been delivered. The conditions under which the
project result is accepted are laid down in the initial phase of the project. Final                            MILESTONES

signing of the Delivery document marks the end of the project. The winding-up                               COST ESTIMATE
phase can then commence.
                                                                                                     INFORMATION CONTROL

                                                                                                             QUALITY CONTROL
Result                                                                                    PROJECT TEAM AND ENVIRONMENT
 Delivery document                                                                                        MANAGEMENT

                                                                                                             RISK CONTROL

Bibliography                                                                                                     APPROVAL
                                                                                      MANAGEMENT
 Syllabus Het Projectmanagement Proces (The Project Management                                             FINE-PLANNING
    Process Syllabus)
                                                                                      MEASURING AND CHECKING PROGRESS
    Chapter 17: Delivery
                                                                                                       STEERING PROGRESS

                                                                                                                  DELIVERY
Tools
                                                                                      WINDING UP
 Delivery document
 Follow-up programme                                                                                            TRANSFER

                                                                                                               EVALUATION

                                                                                                              CONCLUSION

                                                                                      TOOLS




PROJECT DELIVERY


Content of the Delivery document
 Description of the project result as realised (based on the offer, the project plan and any proposals for changes)

 Description of the follow-up programme (indicate who in the organization is to maintain the project result,
  guarantee terms, maintenance contracts, any adaptations/expansions).

 Overview of remaining obligations, additional and less work.

 Endorsement by the client that the project result has been achieved in accordance with the offer presented and
  that the contractor has met all obligations.




© ACTIVITY Consolidated                                                                                          31
TRANSFER                                                                                               INTRODUCTION
                                                                                  DESIGN
                                                                                               DEFINITION OF PROBLEM
Key issues
How do I guarantee the project result in the organization?                                      DEFINITION OF RESULT

                                                                                               OVERALL RISK ANALYSIS

                                                                                                             PHASING
Content
After the project result has been achieved in accordance with the requirements,                         BREAKDOWN
the project manager must transfer the project result to a person in charge of     SURETIES
                                                                                                       ORGANIZATION
management and maintenance. This person must ensure that the project result is
used optimally in the organization. The project manager supplies the required                            MILESTONES
information in order to fulfil this task optimally.                                                   COST ESTIMATE

                                                                                               INFORMATION CONTROL

Result                                                                                                 QUALITY CONTROL
 Follow-up is embedded
                                                                                      PROJECT TEAM AND ENVIRONMENT
                                                                                                       MANAGEMENT

                                                                                                       RISK CONTROL
Bibliography
 Syllabus Het Projectmanagement Proces (The Project Management                                            APPROVAL
                                                                                  MANAGEMENT
    Process Syllabus)                                                                                  FINE-PLANNING
    Chapter 18: Transfer
                                                                                  MEASURING AND CHECKING PROGRESS

                                                                                                 STEERING PROGRESS

                                                                                                            DELIVERY

                                                                                  WINDING UP

                                                                                                           TRANSFER

                                                                                                         EVALUATION

                                                                                                        CONCLUSION

                                                                                  TOOLS




PROJECT TRANSFER

 Plan the transfer together with those involved:
        who are involved?
        which formalities must be taken into account?
 Convince yourself that the end users accept the product
 Formulate training requirements for end users
 Have the client sign a statement of agreement




© ACTIVITY Consolidated                                                                                    32
EVALUATION                                                                                               INTRODUCTION
                                                                                    DESIGN
                                                                                                 DEFINITION OF PROBLEM
Key issues
How can we learn from our project experiences?                                                    DEFINITION OF RESULT

                                                                                                 OVERALL RISK ANALYSIS

Content                                                                                                        PHASING
The purpose of a structured evaluation is not only to highlight the successes and                         BREAKDOWN
failures of a completed project. Even more important is to use the evaluation as    SURETIES
a means of looking ahead towards subsequent projects and therefore being able                            ORGANIZATION
to avoid problems and pitfalls.                                                                            MILESTONES

                                                                                                        COST ESTIMATE

Result                                                                                           INFORMATION CONTROL
 Evaluation report                                                                                      QUALITY CONTROL

                                                                                        PROJECT TEAM AND ENVIRONMENT
                                                                                                         MANAGEMENT
Bibliography
                                                                                                         RISK CONTROL
 Syllabus Het Projectmanagement Proces (The Project Management
    Process Syllabus)                                                                                        APPROVAL
    Chapter 19: Evaluation                                                          MANAGEMENT
                                                                                                         FINE-PLANNING
   Projectmatig Creëren (Creating Schematically)
                                                                                    MEASURING AND CHECKING PROGRESS
    Chapter 23: Project evaluation and Audit, learning from what went right
    and what went wrong                                                                            STEERING PROGRESS

                                                                                                              DELIVERY

                                                                                    WINDING UP
Tools
 Evaluation                                                                                                 TRANSFER

                                                                                                           EVALUATION

                                                                                                              CLOSURE

                                                                                    TOOLS




© ACTIVITY Consolidated                                                                                      33
Project Management ATLAS Training

More Related Content

What's hot

NG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateNG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateLeanleaders.org
 
NG BB 28 MEASURE Tollgate
NG BB 28 MEASURE TollgateNG BB 28 MEASURE Tollgate
NG BB 28 MEASURE TollgateLeanleaders.org
 
NG BB 43 Standardized Work
NG BB 43 Standardized WorkNG BB 43 Standardized Work
NG BB 43 Standardized WorkLeanleaders.org
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 
NG BB 55 CONTROL Tollgate
NG BB 55 CONTROL TollgateNG BB 55 CONTROL Tollgate
NG BB 55 CONTROL TollgateLeanleaders.org
 
NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project CharterLeanleaders.org
 
NG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessNG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessLeanleaders.org
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapLeanleaders.org
 
Agile 101 Basic Measurement
Agile 101 Basic MeasurementAgile 101 Basic Measurement
Agile 101 Basic MeasurementDhaval Panchal
 
NG BB 51 IMPROVE Tollgate
NG BB 51 IMPROVE TollgateNG BB 51 IMPROVE Tollgate
NG BB 51 IMPROVE TollgateLeanleaders.org
 
NG BB 40 Solution Selection
NG BB 40 Solution SelectionNG BB 40 Solution Selection
NG BB 40 Solution SelectionLeanleaders.org
 
NG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventNG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventLeanleaders.org
 
NG BB 49 Risk Assessment
NG BB 49 Risk AssessmentNG BB 49 Risk Assessment
NG BB 49 Risk AssessmentLeanleaders.org
 
NG BB 08 Change Management
NG BB 08 Change ManagementNG BB 08 Change Management
NG BB 08 Change ManagementLeanleaders.org
 
NovaTec Company Overview
NovaTec Company OverviewNovaTec Company Overview
NovaTec Company Overviewmichaelhofbauer
 

What's hot (20)

NG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateNG BB 14 DEFINE Tollgate
NG BB 14 DEFINE Tollgate
 
NG BB 28 MEASURE Tollgate
NG BB 28 MEASURE TollgateNG BB 28 MEASURE Tollgate
NG BB 28 MEASURE Tollgate
 
NG BB 43 Standardized Work
NG BB 43 Standardized WorkNG BB 43 Standardized Work
NG BB 43 Standardized Work
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 
Ft Amdec Planning
Ft Amdec PlanningFt Amdec Planning
Ft Amdec Planning
 
NG BB 26 Control Charts
NG BB 26 Control ChartsNG BB 26 Control Charts
NG BB 26 Control Charts
 
PRINCE2 Overview
PRINCE2 OverviewPRINCE2 Overview
PRINCE2 Overview
 
NG BB 55 CONTROL Tollgate
NG BB 55 CONTROL TollgateNG BB 55 CONTROL Tollgate
NG BB 55 CONTROL Tollgate
 
NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project Charter
 
NG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessNG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the Process
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE Roadmap
 
Agile 101 Basic Measurement
Agile 101 Basic MeasurementAgile 101 Basic Measurement
Agile 101 Basic Measurement
 
NG BB 51 IMPROVE Tollgate
NG BB 51 IMPROVE TollgateNG BB 51 IMPROVE Tollgate
NG BB 51 IMPROVE Tollgate
 
NG BB 40 Solution Selection
NG BB 40 Solution SelectionNG BB 40 Solution Selection
NG BB 40 Solution Selection
 
NG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventNG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement Event
 
NG BB 30 Basic Tools
NG BB 30 Basic ToolsNG BB 30 Basic Tools
NG BB 30 Basic Tools
 
NG BB 04 DEFINE Roadmap
NG BB 04 DEFINE RoadmapNG BB 04 DEFINE Roadmap
NG BB 04 DEFINE Roadmap
 
NG BB 49 Risk Assessment
NG BB 49 Risk AssessmentNG BB 49 Risk Assessment
NG BB 49 Risk Assessment
 
NG BB 08 Change Management
NG BB 08 Change ManagementNG BB 08 Change Management
NG BB 08 Change Management
 
NovaTec Company Overview
NovaTec Company OverviewNovaTec Company Overview
NovaTec Company Overview
 

Viewers also liked

A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...eSAT Journals
 
Identifying and Solving Personnel Issues
Identifying and Solving Personnel IssuesIdentifying and Solving Personnel Issues
Identifying and Solving Personnel IssuesKirkie44
 
Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...eSAT Journals
 
Humanside of project management
Humanside of project managementHumanside of project management
Humanside of project managementDMR Panda
 
Research Paper - Recruitment Issues in the Public Sector
Research Paper - Recruitment Issues in the Public SectorResearch Paper - Recruitment Issues in the Public Sector
Research Paper - Recruitment Issues in the Public SectorMarsha Noel
 
Carta recomendação SportImpact
Carta recomendação SportImpactCarta recomendação SportImpact
Carta recomendação SportImpactMiguel Silva
 
Datapolis Process System
Datapolis Process SystemDatapolis Process System
Datapolis Process SystemDatapolis
 
Ligatus content marketingstudie_2016
Ligatus content marketingstudie_2016Ligatus content marketingstudie_2016
Ligatus content marketingstudie_2016bbertling
 
L'AURORA BOREAL - SADIO
L'AURORA BOREAL - SADIOL'AURORA BOREAL - SADIO
L'AURORA BOREAL - SADIOrmateu15
 
Comunicación Política Digital con Pablo Gallego
Comunicación Política Digital con Pablo GallegoComunicación Política Digital con Pablo Gallego
Comunicación Política Digital con Pablo GallegoISDI Online
 
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...ScaleUp Partners LLC
 
Union Suisse :: Creating Value Together_#UnionGVA_002
Union Suisse :: Creating Value Together_#UnionGVA_002Union Suisse :: Creating Value Together_#UnionGVA_002
Union Suisse :: Creating Value Together_#UnionGVA_002Catalyx
 
Aproximación a Toys´rús
Aproximación a Toys´rúsAproximación a Toys´rús
Aproximación a Toys´rúsBeren Beren
 
Proyecto de intervención - "Encuentra lo auténtico"
Proyecto de intervención - "Encuentra lo auténtico"Proyecto de intervención - "Encuentra lo auténtico"
Proyecto de intervención - "Encuentra lo auténtico"Nora Gil Luri
 
Puro olor-a-incienso-seleccion-blog ericfluna
Puro olor-a-incienso-seleccion-blog ericflunaPuro olor-a-incienso-seleccion-blog ericfluna
Puro olor-a-incienso-seleccion-blog ericflunaEric F. Luna
 

Viewers also liked (20)

A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...
 
Identifying and Solving Personnel Issues
Identifying and Solving Personnel IssuesIdentifying and Solving Personnel Issues
Identifying and Solving Personnel Issues
 
Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...
 
Humanside of project management
Humanside of project managementHumanside of project management
Humanside of project management
 
Research Paper - Recruitment Issues in the Public Sector
Research Paper - Recruitment Issues in the Public SectorResearch Paper - Recruitment Issues in the Public Sector
Research Paper - Recruitment Issues in the Public Sector
 
Carta recomendação SportImpact
Carta recomendação SportImpactCarta recomendação SportImpact
Carta recomendação SportImpact
 
Datapolis Process System
Datapolis Process SystemDatapolis Process System
Datapolis Process System
 
Ligatus content marketingstudie_2016
Ligatus content marketingstudie_2016Ligatus content marketingstudie_2016
Ligatus content marketingstudie_2016
 
Social Media per la Formazione e il Lavoro: le Comunità di Apprendimento e di...
Social Media per la Formazione e il Lavoro: le Comunità di Apprendimento e di...Social Media per la Formazione e il Lavoro: le Comunità di Apprendimento e di...
Social Media per la Formazione e il Lavoro: le Comunità di Apprendimento e di...
 
L'AURORA BOREAL - SADIO
L'AURORA BOREAL - SADIOL'AURORA BOREAL - SADIO
L'AURORA BOREAL - SADIO
 
Comunicación Política Digital con Pablo Gallego
Comunicación Política Digital con Pablo GallegoComunicación Política Digital con Pablo Gallego
Comunicación Política Digital con Pablo Gallego
 
Aura Flamma Terra Aqua
Aura Flamma Terra AquaAura Flamma Terra Aqua
Aura Flamma Terra Aqua
 
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...
Inclusive Competitiveness: Winston Churchill Memorial Trust Report by Roger W...
 
Union Suisse :: Creating Value Together_#UnionGVA_002
Union Suisse :: Creating Value Together_#UnionGVA_002Union Suisse :: Creating Value Together_#UnionGVA_002
Union Suisse :: Creating Value Together_#UnionGVA_002
 
Aproximación a Toys´rús
Aproximación a Toys´rúsAproximación a Toys´rús
Aproximación a Toys´rús
 
Proyecto de intervención - "Encuentra lo auténtico"
Proyecto de intervención - "Encuentra lo auténtico"Proyecto de intervención - "Encuentra lo auténtico"
Proyecto de intervención - "Encuentra lo auténtico"
 
Geografía de la Salud- Boletín Informativo 11
Geografía de la Salud- Boletín Informativo 11Geografía de la Salud- Boletín Informativo 11
Geografía de la Salud- Boletín Informativo 11
 
auraline-iprinter
auraline-iprinterauraline-iprinter
auraline-iprinter
 
ISO ODF 標準應用展望
ISO ODF 標準應用展望ISO ODF 標準應用展望
ISO ODF 標準應用展望
 
Puro olor-a-incienso-seleccion-blog ericfluna
Puro olor-a-incienso-seleccion-blog ericflunaPuro olor-a-incienso-seleccion-blog ericfluna
Puro olor-a-incienso-seleccion-blog ericfluna
 

Similar to Project Management ATLAS Training

Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Beth Perez
 
Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Beth Perez
 
Pojectmanagementver4
Pojectmanagementver4Pojectmanagementver4
Pojectmanagementver4sami325
 
Assess Your Business Continuity Management Process
Assess Your Business Continuity Management ProcessAssess Your Business Continuity Management Process
Assess Your Business Continuity Management ProcessAnand Subramaniam
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk managementKannan Subbiah
 
Chevron Section1 V1
Chevron Section1 V1Chevron Section1 V1
Chevron Section1 V1mfeKEG
 
The consulting process models
The consulting process modelsThe consulting process models
The consulting process modelsSandhya Johnson
 
Lean Administration And Fast Closing
Lean Administration And Fast ClosingLean Administration And Fast Closing
Lean Administration And Fast Closingggiacoma
 
Vcw Cm Spezial Rz
Vcw Cm Spezial RzVcw Cm Spezial Rz
Vcw Cm Spezial Rzaloahe2
 
Vcw Cm Spezial Rz
Vcw Cm Spezial RzVcw Cm Spezial Rz
Vcw Cm Spezial Rzaloahe2
 
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...SeriousGamesAssoc
 
Drive Revenue And Profits
Drive Revenue And ProfitsDrive Revenue And Profits
Drive Revenue And Profitsgbalint
 
Value Chain Transformation
Value Chain TransformationValue Chain Transformation
Value Chain TransformationSteven Bonacorsi
 
Sloan Change+Management+Presentation
Sloan Change+Management+PresentationSloan Change+Management+Presentation
Sloan Change+Management+PresentationDavid Black
 
general project management
general project management general project management
general project management yasmine19
 
Hospital management consulting v1 client.
Hospital management consulting v1 client.Hospital management consulting v1 client.
Hospital management consulting v1 client.Kalpit Sanghvi
 
THofC - A Framework Approach to Change
THofC - A Framework Approach to ChangeTHofC - A Framework Approach to Change
THofC - A Framework Approach to Changeronleeman
 
DD Consulting One Pager
DD Consulting One PagerDD Consulting One Pager
DD Consulting One Pagerandrewscola
 
Project Management Activities Of Project Manager By Bhaskar
Project Management Activities Of Project Manager By BhaskarProject Management Activities Of Project Manager By Bhaskar
Project Management Activities Of Project Manager By Bhaskarbhaskarnarula
 

Similar to Project Management ATLAS Training (20)

Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)
 
Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)Speaking with facts tq & od project dimensions(1)
Speaking with facts tq & od project dimensions(1)
 
Pojectmanagementver4
Pojectmanagementver4Pojectmanagementver4
Pojectmanagementver4
 
Assess Your Business Continuity Management Process
Assess Your Business Continuity Management ProcessAssess Your Business Continuity Management Process
Assess Your Business Continuity Management Process
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Chevron Section1 V1
Chevron Section1 V1Chevron Section1 V1
Chevron Section1 V1
 
The consulting process models
The consulting process modelsThe consulting process models
The consulting process models
 
Lean Administration And Fast Closing
Lean Administration And Fast ClosingLean Administration And Fast Closing
Lean Administration And Fast Closing
 
Vcw Cm Spezial Rz
Vcw Cm Spezial RzVcw Cm Spezial Rz
Vcw Cm Spezial Rz
 
Vcw Cm Spezial Rz
Vcw Cm Spezial RzVcw Cm Spezial Rz
Vcw Cm Spezial Rz
 
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...
“Using Simulations to Train Future Project Leaders at NASA” By Lawrence Suda-...
 
Drive Revenue And Profits
Drive Revenue And ProfitsDrive Revenue And Profits
Drive Revenue And Profits
 
Value Chain Transformation
Value Chain TransformationValue Chain Transformation
Value Chain Transformation
 
Sloan Change+Management+Presentation
Sloan Change+Management+PresentationSloan Change+Management+Presentation
Sloan Change+Management+Presentation
 
general project management
general project management general project management
general project management
 
Project Management - Introduction
Project Management - IntroductionProject Management - Introduction
Project Management - Introduction
 
Hospital management consulting v1 client.
Hospital management consulting v1 client.Hospital management consulting v1 client.
Hospital management consulting v1 client.
 
THofC - A Framework Approach to Change
THofC - A Framework Approach to ChangeTHofC - A Framework Approach to Change
THofC - A Framework Approach to Change
 
DD Consulting One Pager
DD Consulting One PagerDD Consulting One Pager
DD Consulting One Pager
 
Project Management Activities Of Project Manager By Bhaskar
Project Management Activities Of Project Manager By BhaskarProject Management Activities Of Project Manager By Bhaskar
Project Management Activities Of Project Manager By Bhaskar
 

Recently uploaded

Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024Matteo Carbone
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 

Recently uploaded (20)

Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 

Project Management ATLAS Training

  • 1. ACTIVITY Project Management ATLAS Activity Project Management Training commissioned by Activity Consolidated Odijk, March 2000 Version: 2.0
  • 2. ACTIVITY AND THE ATLAS Activity is an organization that is growing rapidly. At the end of 1997, Activity had a staff of 50; there are now some 125 professionals, each with their own unique background. We expect this number to grow substantially in the near future. Not only is the number of staff growing, the number of clients and the quality of the orders is rising too. These developments have resulted in a large variety of people, clients and orders in ACTIVITY. This also increases the importance of forming a common frame of reference for project management and disseminating it where necessary. Over the years, ACTIVITY has built up extensive knowledge and experience with working schematically, project style. Part of this knowledge and experience has been laid down in the ATLAS. ATLAS applications The ATLAS used internally: Common frame of reference One important aim of the ATLAS is to create a common frame of reference. It is important for internal communication that we speak the same language. This ATLAS is therefore not only aimed at junior project managers, but also experienced project managers, project assistants, account managers, staff executives and supporting staff. At ACTIVITY, when we speak about how and why we must work schematically, the definitions laid down in ATLAS must be the points of departure. The ATLAS used externally: support or methodology The Project Management Process on which the ATLAS is based is a tried and tested method of working schematically. The knowledge and experience recorded in the ATLAS can be used by other ACTIVITY project managers when executing projects for clients. If a client indicates that it does not have a method of its own, the ATLAS can serve as the foundation for a tailor-made method to suit the organization. Points of departure The following points of departure were used to develop the ATLAS:  ACTIVITY does not impose any method upon the client. The method usually employed by the client is decisive. However, if and insofar the client‟s method is less suitable, or if the client indicates that it wishes to use the ACTIVITY method, the ATLAS may prove useful.  The ATLAS is a generic model; it can be applied to projects in all sorts of environments.  Practical suitability is the key factor. Existing publications contain more specific background information on the various subjects. The ATLAS is a guide with practical checklists and tools. The ATLAS in development The Atlas is an ongoing project. It is fed from practical experience. Because knowledge and experience are constantly being interchanged, the ATLAS will continue to develop. There will therefore be regular updates of the ATLAS in the form of new releases. © ACTIVITY Consolidated 2
  • 3. BIBLIOGRAPHY The following titles are referred to in this ATLAS.  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) Author: Activity Project Management Training, February 2000  Projectmatig Creëren (Creating Schematically) J. Bos and E. Harting (editors) Scriptum Books, Schiedam, 1998 ISBN: 90 5594 122 0 / NUGI 684  A guide to the Project Management Body of Knowledge PMI Standards Committee, 1996 ISBN: 1-880410-12-5 © ACTIVITY Consolidated 3
  • 4. D e Defining the problem s i Defining the result First think .... g n Overall risk analysis Phasing Breakdown Organization ...then plan.... S u Milestones r e Cost estimate t i Information control ...approve... e s Quality control Management Project Team and enviroment ... then get going.... Risk control Approval Management cycle Action: Take stock C implement of matters o activities Fine-planning n t MEASURING AND r CHECKING PROGRESS o Measures: l Steering progess - steer Compare - do nothing - stop Delivery - Re-plan W Norm/plan i with margins n Transfer d Closure and i Evaluation learning n g Closure u p © ACTIVITY Consolidated 4
  • 5. DEFINITION OF THE PROBLEM INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues What is the problem or the opportunity? DEFINITION OF RESULT Should we handle this order schematically? OVERALL RISK ANALYSIS Content PHASING The first point of interest for a project manager is to gain insight into what BREAKDOWN precisely the problem is and in which direction to seek the solution. SURETIES ORGANIZATION Result MILESTONES  General definition of the problem COST ESTIMATE  Endorsement on drawing up project task INFORMATION CONTROL BIBLIOGRAPHY QUALITY CONTROL  Syllabus Het Projectmanagement Proces (The Project Management PROJECT TEAM AND ENVIRONMENT Process Syllabus) MANAGEMENT Chapter 1: Definition of the problem RISK CONTROL  Projectmatig Creëren (Creating Schematically) APPROVAL Chapter 1: The essence of creating schematically Korset of ruggengraat MANAGEMENT (corset or backbone) FINE-PLANNING Chapter 2: Commitment and creating. From Wanting to Choosing MEASURING AND CHECKING PROGRESS  A guide to the Project Management Body of Knowledge STEERING PROGRESS Paragraph 5.1: Initiation DELIVERY WINDING UP TRANSFER EVALUATION CONCLUSION TOOLS DEFINITION OF THE PROBLEM Formulating the problem  Ask the client to describe the problem as precisely as possible.  Make a list of questions regarding the problem.  Emphasise the necessity of preliminary research.  After the preliminary research, describe the problem as specifically as possible.  Check the formulation of the problem with the client and end users; reformulate if necessary.  Do not talk big. © ACTIVITY Consolidated 5
  • 6. Formulate in one sentence . Questions to assist in defining the problem  Whose problem is it (client‟s)?  Why is it a problem?  How urgent is the problem?  Is there a problem underlying the problem?  What is its (strategic) significance?  Which potential causes and solutions have already been considered? Pitfalls in determining the problem  Vague and incoherent problems.  Coming up with a solution prematurely.  Not clear who is involved in the problem.  Analysing the needs of the wrong target group.  Not setting priorities in case of several problems.  Selectively filtering problems. © ACTIVITY Consolidated 6
  • 7. DEFINITION OF THE RESULT INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues What must be achieved? DEFINITION OF RESULT Why must this be achieved? OVERALL RISK ANALYSIS What are the preconditions? PHASING What are the criteria for success? BREAKDOWN Content SURETIES ORGANIZATION As soon as we have a clear definition of the problem, we can describe in empirical terms what must be achieved by the project and what the criteria for MILESTONES success are. A preliminary estimate of the costs and time schedule are made. COST ESTIMATE The client then formally endorses this. INFORMATION CONTROL Result QUALITY CONTROL  Project order PROJECT TEAM AND ENVIRONMENT MANAGEMENT Bibliography RISK CONTROL  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) APPROVAL MANAGEMENT Chapter 2: Definition of the result FINE-PLANNING  Projectmatig Creëren (Creating Schematically) MEASURING AND CHECKING PROGRESS Chapter 3: The project contract. A business and tactic agreement between STEERING PROGRESS the project team and the client Chapter 4: The project definition: From orders to engagements DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 5.2: Scope planning. TRANSFER EVALUATION Tools  Project order CONCLUSION TOOLS DEFINITION OF THE PROJECT RESULT Tips for defining the project result  Formulate the result as specifically as possible (using nouns).  Clearly indicate the preconditions and criteria for success.  Indicate what is still unknown.  Formulate SMART - Specific - Measurable - Acceptable - Realistic - Time-related Questions to assist in defining the result  What is complete when it is complete?  What will change for whom?  What will you delegate to whom?  What are the key requirements and wishes?  What does not pertain to the project (demarcation)? © ACTIVITY Consolidated 7
  • 8. Pitfalls in defining the project result  Ideas have not been sufficiently worked out and are unstable.  Coming up with solutions before the problem has been properly analysed.  Too general (“a working system”).  Too specific. © ACTIVITY Consolidated 8
  • 9. IINTRODUCTION OVERALL RISK ANALYSIS DESIGN DEFINITION OF PROBLEM DEFINITION OF RESULT Key issues OVERALL RISK ANALYSIS How do I set to work on the project in general? Which control factors require additional attention? PHASING What expectations must the project manager fulfil? BREAKDOWN SURETIES ORGANIZATION Content MILESTONES Using a checklist, an overall risk analysis is performed. This will help COST ESTIMATE determine the most suitable approach to the project. The profile for the project manager can then be determined. INFORMATION CONTROL QUALITY CONTROL Result PROJECT TEAM AND ENVIRONMENT MANAGEMENT  Overview of risks related to control factors.  The profile of the project manager. RISK CONTROL  Overall risk analysis APPROVAL MANAGEMENT FINE-PLANNING Bibliography MEASURING AND CHECKING PROGRESS  Syllabus Het Projectmanagement Proces (The Project Management STEERING PROGRESS Process Syllabus) Chapter 3: Overall risk analysis DELIVERY WINDING UP TRANSFER Tools  Project classification EVALUATION CONCLUSION TOOLS © ACTIVITY Consolidated 9
  • 10. PHASING INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How can I split up the project life cycle? DEFINITION OF RESULT How do I keep the client involved? OVERALL RISK ANALYSIS PHASING Content BREAKDOWN Phasing is splitting up a project into logical, systematic stages. Phasing gives an SURETIES ORGANIZATION overview of the project and enables better steering and control. After completion of each phase comes the decision point. The next phase may only MILESTONES commence after the client has approved the phase in hand. Depending on the COST ESTIMATE type of project, standard phasing, minimal phasing or custom-made phasing may be applied. INFORMATION CONTROL QUALITY CONTROL PROJECT TEAM AND ENVIRONMENT Result MANAGEMENT  Phasing with decision points. RISK CONTROL APPROVAL Bibliography MANAGEMENT FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) MEASURING AND CHECKING PROGRESS Chapter 4: Phasing the project life cycle. STEERING PROGRESS  Projectmatig Creëren (Creating Schematically) DELIVERY Chapter 5: The project structure. Introducing structure, staying flexible and WINDING UP channelling energy. TRANSFER  A guide to the Project Management Body of Knowledge Paragraph 2.1: Project phases and the project life cycle EVALUATION CONCLUSION TOOLS Tools  Phasing PHASING THE PROJECT LIFE CYCLE Standard phasing consists of the following phases and decision points: a) Initiative phase start: the idea/initiative activities - determine the status quo; - study the general problem issues; - give a general definition of desired result; - demarcate the project; - indicate project phasing; - describe the modus operandi; - draw up the project order; end situation: approved, decision document: Project order © ACTIVITY Consolidated 10
  • 11. b) Definition phase start: approved Project order activities - collect the basic material; - determine project boundaries; - determine project requirements:  preconditions;  functional requirements;  operational requirements;  restrictions of the design; - set up a list of activities; - set up the order of activities; - set up the operating structure (defining sub-projects); - establish contact with third parties (designers); - draw up a project programme. end situation: approved, decision document: Project plan c) Design phase start: approved Project plan activities - detail the project programme; - contract third parties (designers); - seek solutions/designs for each sub-project; - seek or design project tools; - fine-tune sub-projects and project tools; - test sub-designs; - adjust sub-designs; - draw up the project design (down to the most basic level):  sub-projects;  tools. end situation: approved, decision document: Project design d) Preparation phase start: approved Project design activities - draw up implementation instructions, etc. - purchase/make tools (quantitative); - contract third parties (suppliers); - train the implementation organization; - draw up the implementation programme (scenario). end situation: approved, decision document: Implementation plan e) Implementation phase start: approved Implementation plan activities - deliver project result; - implement as per programme; - adjust programme. end situation: approved Project result f) Follow-up phase start: approved, decision document: Follow-up programme activities - conclude project; - put completed project into service; - maintain completed project ; - maintain tools; - evaluation. end situation: project evaluation. © ACTIVITY Consolidated 11
  • 12. BREAKING DOWN INTO COMPONENTS INTRODUCTION DESIGN Key issues DEFINITION OF PROBLEM How do I break down the larger whole into manageable parts? DEFINITION OF RESULT OVERALL RISK ANALYSIS Content PHASING In order to gain more insight into what must be done and who must be BREAKDOWN involved, the project manager breaks down the project result into orderly units. SURETIES In larger projects, the total project is broken down into sub-projects, and a ORGANIZATION Work Breakdown Structure can be set up for each sub-project. Subsequently, MILESTONES each activity can be allocated to an organizational section or person in charge. This results in the Organizational Breakdown Structure. The activities allocated COST ESTIMATE to a person or department in charge are called “work packages”. INFORMATION CONTROL QUALITY CONTROL Result PROJECT TEAM AND ENVIRONMENT  WBS MANAGEMENT  OBS RISK CONTROL APPROVAL MANAGEMENT Bibliography FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management MEASURING AND CHECKING PROGRESS Process Syllabus) STEERING PROGRESS Chapter 5: Breaking down into components DELIVERY  Projectmatig Creëren (Creating Schematically) Chapter 5: The project structure. Introducing structure, staying flexible and WINDING UP channelling energy. TRANSFER  A guide to the Project Management Body of Knowledge EVALUATION Paragraph 5.3.2: Tools and techniques for Scope Definition CONCLUSION TOOLS Tools  Planning matrix THE WORK BREAKDOWN STRUCTURE Conditions which a WBS must meet 1: There must be a strict hierarchy of activities. 2: There must be no overlap between activities; each activity is an independent entity. 3: Each activity must result in a demonstrable product. 4: Each activity must have an apparent throughput time. 5: Each activity must have calculable costs. To what degree must entities be broken down?  Until all elements can be univocally allocated to a specific section of the organization.  Until all products have been defined in terms of activities.  No further than five levels deep. © ACTIVITY Consolidated 12
  • 13. Project Sub-project Sub-project Sub-project Act. Act. Act. Act. Act. Act. Act. Dep./P. Dep./P. Dep./P. Dep./P. Dep./P. Dep./P. Dep./P. © ACTIVITY Consolidated 13
  • 14. ORGANIZATION Key issues DESIGN DEFINITION OF PROBLEM How do I obtain the right people and resources? DEFINITION OF RESULT OVERALL RISK ANALYSIS Content PHASING This step is geared to drawing up a workable and manageable project organization. This includes obtaining the manpower and material resources BREAKDOWN needed for the project and establishing tasks, responsibilities and powers. The SURETIES ORGANIZATION relation between the project and the rest of the organization is also described. MILESTONES COST ESTIMATE Result  Project organization. INFORMATION CONTROL  Diagram of the relation. QUALITY CONTROL  Tasks, Powers and Responsibilities. PROJECT TEAM AND ENVIRONMENT MANAGEMENT Bibliography RISK CONTROL  Syllabus Het Projectmanagement Proces (The Project Management APPROVAL MANAGEMENT Process Syllabus) FINE-PLANNING Chapter 6: Organization MEASURING AND CHECKING PROGRESS  Projectmatig Creëren (Creating Schematically) STEERING PROGRESS Chapter 10: The project organization. The organizational structure as a custom-made suit. DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 7.1: Resource Planning TRANSFER Paragraph 9.1: Organizational Planning Paragraph 9.2: Staff Acquisition EVALUATION CONCLUSION TOOLS PROJECT ORGANIZATION Questions to assist in defining the organization  Who does what?  Who has what powers?  How is decision-making arranged?  How is the relation between the project organization and the rest of the organization arranged? Resources for the organization  OBS  Project organogram  Project environment chart – informal (relation)  Powers and Responsibilities.  Escalation procedure © ACTIVITY Consolidated 14
  • 15. INTRODUCTION MILESTONES DESIGN DEFINITION OF PROBLEM DEFINITION OF RESULT Key issues When must which interim results be achieved? OVERALL RISK ANALYSIS PHASING Content BREAKDOWN SURETIES In cooperation with the persons involved, the interim project targets ORGANIZATION (milestones) are described in terms of specific, measurable results. These milestones are fixed, verifiable controls used during the project to assess MILESTONES whether the project is still on course. The milestone plan indicates the logical COST ESTIMATE mutual connections between the milestones and the activities to be executed for INFORMATION CONTROL steady progress from one milestone to the next. QUALITY CONTROL PROJECT TEAM AND ENVIRONMENT Result MANAGEMENT  Milestone plan RISK CONTROL APPROVAL MANAGEMENT Bibliography FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management MEASURING AND CHECKING PROGRESS Process Syllabus) Chapter 7: Milestones STEERING PROGRESS  Projectmatig Creëren (Creating Schematically) DELIVERY Chapter 7: Project planning - Making feasible plans. WINDING UP TRANSFER Tools EVALUATION  Milestone plan CONCLUSION TOOLS MILESTONE PLAN Milestone characteristics  Represent important decision points.  Are natural  Are measurable  Are progressively closer to the project result  Can be interdependent (milestone plan)  The intervening periods are manageable Inventory of milestones  Brainstorm with involved parties based on the WBS: - contribution of knowledge; - collective perception of the result and approach; - list of task allocation and dependencies.  Make a thorough redefinition: - indicate only the "what" – do not impose the "how"; - maintain a provisional list of activities. © ACTIVITY Consolidated 15
  • 16. Definition of milestones  Milestone : description  Status : version number  Results : concise description of the products/services to be delivered for this milestone  Quality : requirements the result must meet  Time : start / end: early - late  Funds : estimated costs  Responsibility : organizational department + staff  Dependency : previous milestones, who is waiting for the result?  Risks : anticipated bottlenecks and precautionary measures  Endorsement : signing and dating of planning and milestone by the persons in charge © ACTIVITY Consolidated 16
  • 17. COST ESTIMATE INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How do I estimate and monitor the project costs? DEFINITION OF RESULT OVERALL RISK ANALYSIS PHASING Content The project manager draws up a realistic cost estimate so that he has a standard BREAKDOWN by which to monitor the incurred costs during the course of the project. The SURETIES ORGANIZATION work packages (see Breaking down) form the point of departure for drawing up a cost estimate. MILESTONES COST ESTIMATE Result INFORMATION CONTROL  Cost estimate QUALITY CONTROL  Project budget PROJECT TEAM AND ENVIRONMENT MANAGEMENT RISK CONTROL Bibliography  Syllabus Het Projectmanagement Proces (The Project Management APPROVAL MANAGEMENT Process Syllabus) FINE-PLANNING Chapter 8: Cost estimate MEASURING AND CHECKING PROGRESS  Projectmatig Creëren (Creating Schematically) STEERING PROGRESS Chapter 8: Funds. The various ways in which money can be obtained for/roll into a project DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 7.2: Cost Estimating TRANSFER Paragraph 7.3: Cost Budgeting Paragraph 7.4: Cost Control EVALUATION CONCLUSION TOOLS Tools  Costs matrix COST ESTIMATE The project budget The project budget  consists of costs that can be influenced by the project manager, for:  manpower;  resources;  materials;  serves as a basis for project control;  is drawn up and approved as early as possible. The cost estimate The cost estimate comprises the calculation of all costs components:  Gives an idea of the costs of the project result.  Serves as a basis for decision-making by the management. © ACTIVITY Consolidated 17
  • 18. Drawing up a project budget When drawing up a budget, we distinguish between costs and investments. Costs are subdivided into direct and indirect costs; investments are subdivided into movables and immovables. Step 1: Inventory of costs Direct project costs  Determine which costs are directly attributable to the project.  Classify these costs into a number of main groups which together cover all the direct costs. Indirect project costs  Determine which costs are indirectly attributable to the project.  Consider for instance the secondary resources that are vital for the project‟s success. Movables  Mention the specific movables and determine the associated costs.  Determine the economic life span and the necessary maintenance costs. Maintenance costs must be entered as direct costs if the maintenance costs are directly attributable to the project (otherwise enter as indirect costs). Immovables  Mention the specific immovables and determine the associated costs.  Determine the economic life span and the necessary maintenance costs. Maintenance costs must be entered as direct costs if the maintenance costs are directly attributable to the project (otherwise enter as indirect costs). The above can be depicted in the following diagram: Costs Investments Direct costs Indirect costs Movables Immovables  Consultancy  Workplace  Purchase of production equipment  Purchase of production premises  Travel and accommodation (Computer/Printer) costs  Office supplies  Office space Purchase price: NLG 140,000 Purchase price: NLG 600,000  Maintenance costs  Telephone/fax costs Economic life span: Economic life span: 20 years 4 years Monthly maintenance costs: Monthly maintenance costs: NLG 1,000 (see direct costs) NLG 500 (see direct costs) © ACTIVITY Consolidated 18
  • 19. Step 2: Cost planning in time The costs are then plotted in time. The time units are given on the vertical (Y) axis and the different cost categories on the X-axis. Direct costs Indirect costs Movable Immovable investments investments Consultancy Travel and Office Maintenan Workplace Office Telephone/fa Production Production accommodat supplies ce space x costs equipment premises ion costs March 20,000 200 100 0 1,500 2,000 1,000 April 40,000 400 200 1,000 2,000 2,500 1,250 140,000 May 50,000 400 200 1,000 2,000 2,500 1,500 June 50,000 600 400 1,000 2,000 2,500 1,500 July 50,000 600 400 1,500 2,000 2,500 1,500 600,000 August 30,000 400 200 1,500 2,000 2,500 1,500 total 240,000 2,600 1,500 6,000 11,500 14,500 8,250 140,000 600,000 Total expenses made for the project in the period March through August : 1,024,350 Step 3: Approval After the cost estimate has been drawn up, it is presented to the client for approval. Step 4: Periodical analysis The actual costs and any costs yet to be incurred are compared with the approved budget per period. Note: In the cost analysis, the investments and depreciations must be included for all the above-mentioned expenses. Drawing up a budget  Identify the cost centres.  Determine cost types per cost centre.  Gather „hard” information (time investments, rates, offers, price lists, etc.).  If no “hard” information is available, have those executing the project draw up the cost estimate.  Determine what can be accurately estimated (5%) and what can be broadly estimated (10%-30%).  Determine the margin  Have the cost estimate approved for budget release. Cost types / cost centres  Time investment by company personnel / other personnel.  Contractor‟s costs (subsequent calculation or fixed price).  Material costs (building blocks, resources). cost centre MS A MS B MS C MS D Total cost type Contractor 20,000 135,000 75,000 15,000 245,000 Company personnel 1,400 2,000 1,800 800 6,000 Other personnel 300 150 750 2,500 3,700 Material 3,000 500 600 1,200 5,300 Total 24,700 137,650 78,150 19,500 260,000 MS = Milestone © ACTIVITY Consolidated 19
  • 20. INFORMATION CONTROL INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues DEFINITION OF RESULT Who must I inform about what and when? OVERALL RISK ANALYSIS PHASING Content BREAKDOWN To ensure that it is clear to everyone what is meant and who must do something SURETIES with which information, the project manager draws up an information matrix ORGANIZATION and (for large, complex projects), a communication plan. Furthermore, it is the MILESTONES project manager‟s responsibility to ensure that the information is unequivocal COST ESTIMATE and recognizable (for instance: final or draft status) and can be found in the files. INFORMATION CONTROL QUALITY CONTROL Result PROJECT TEAM AND ENVIRONMENT MANAGEMENT  Information matrix  Communication plan RISK CONTROL APPROVAL MANAGEMENT Bibliography FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management MEASURING AND CHECKING PROGRESS Process Syllabus) STEERING PROGRESS Chapter 9: Information control DELIVERY  Projectmatig Creëren (Creating Schematically) Chapter 11: Information. The mustiest management aspect? WINDING UP  A guide to the Project Management Body of Knowledge TRANSFER Paragraph 10.1: Communications Planning EVALUATION Paragraph 10.2: Information Distribution CONCLUSION Tools TOOLS  Action points  Decisions list  Information matrix INFORMATION CONTROL Information control is geared to monitoring the clarity and univocality of the project information by means of:  coding documents;  aligning document structure to match content of and coherence with other documents;  distributing documents;  releasing documents and amending them in accordance with the procedures;  filing documents;  keeping documents for at least 10 years (this is a legal requirement). Tips for information control  Strive for completeness and up-to-dateness.  Keep the set-up simple.  Be aware of individual information needs.  Avoid a personal set-up.  Record agreements in writing.  Go for an attractive design. © ACTIVITY Consolidated 20
  • 21. Information matrix Client Account Internal Project Sub-project Project office manager commissioner organization leader Project Compiles order Distributes Project plan Determines Compiles Files Delivery Accepts Determines Compiles Files document Offers Accepts Compiles Determines Distributes Distributes Progress Compiles Files reports Compiles Sub-project Determines Distributes reports Files Information flow chart Project information Uncontrolled not recorded no Record ? (e.g. verbally) ja Retrievable Central no decentralized control ? (eg private records) ja Controlled Central project records Company records ` © ACTIVITY Consolidated 21
  • 22. QUALITY CONTROL INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How do I meet the agreed quality requirements? DEFINITION OF RESULT OVERALL RISK ANALYSIS PHASING Content At the end of the project, a product or service must be delivered that meets the BREAKDOWN client‟s demands. The project manager ensures that delivery takes place in time SURETIES ORGANIZATION and at the agreed price, and that it meets the agreed quality (both product and process quality). The agreements made on quality are laid down in product MILESTONES specifications and/or a quality plan. COST ESTIMATE INFORMATION CONTROL Result QUALITY CONTROL  Product specifications PROJECT TEAM AND ENVIRONMENT  Quality plan MANAGEMENT RISK CONTROL Bibliography APPROVAL MANAGEMENT  Syllabus Het Projectmanagement Proces (The Project Management FINE-PLANNING Process Syllabus) Chapter 10: Quality control MEASURING AND CHECKING PROGRESS STEERING PROGRESS  Projectmatig Creëren (Creating Schematically) Chapter 9: Quality. True quality resides in people. DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 8.1: Quality Planning TRANSFER Paragraph 8.2: Quality Assurance Paragraph 8.3: Quality Control EVALUATION CONCLUSION TOOLS QUALITY CONTROL Two activities can be distinguished in the quality control process: 1: Drawing up the quality plan  overall result  requirements / wishes  product specifications 2: Progress checks Interim testing and monitoring of the quality of  the product  the project management process Key principle for quality: the sooner a flaw is found, the less it will cost to remedy. © ACTIVITY Consolidated 22
  • 23. Quality management The process can be depicted as follows: QUALITY MANAGEMENT (Overall description of the project result) Requirements and wishes Norm/ specification Product specifications Progress control Interim testing Endorsement Project result Quality plan  Tasks include: translating the intrinsic requirements into measurable quality requirements.  Methods: testing.  Procedures for advising and giving approval.  Test plan: who, what, when, where and how?  Aim for a flawless design. Progress checks  Who will test what to the requirements set? Specification requirements  Objective  Valid  Reliable  Desired level (of quality/quantity)  Indication for „measuring costs‟ © ACTIVITY Consolidated 23
  • 24. PROJECT TEAM AND ENVIRONMENT MANAGEMENT INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How do I keep all parties on course? DEFINITION OF RESULT OVERALL RISK ANALYSIS Content PHASING The project manager closely consults with and steers the project team and other BREAKDOWN involved parties from the moment he joins the project till the moment it is SURETIES wound up. Social aspects like managing, negotiating, team role management ORGANIZATION and conflict management are obviously critical success factors in a project. MILESTONES COST ESTIMATE Result INFORMATION CONTROL  Defined cooperation QUALITY CONTROL PROJECT TEAM AND ENVIRONMENT MANAGEMENT Bibliography RISK CONTROL  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) APPROVAL Chapter 11: Project team and environment management MANAGEMENT FINE-PLANNING  Projectmatig Creëren (Creating Schematically) MEASURING AND CHECKING PROGRESS Chapter 13: Forces and interests in and connected with projects Chapter 15: The project team STEERING PROGRESS Chapter 17: Project and parent organization DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 9.3: Team Development TRANSFER EVALUATION Tools CONCLUSION  Analyse the project environment TOOLS © ACTIVITY Consolidated 24
  • 25. INTRODUCTION RISK CONTROL DESIGN DEFINITION OF PROBLEM DEFINITION OF RESULT Key issues What must definitely not go wrong in a project? OVERALL RISK ANALYSIS How can I prevent or take care of any setbacks? PHASING Content BREAKDOWN SURETIES An overall risk analysis is carried out at the beginning of a project (see the ORGANIZATION process step „overall risk analysis‟). Later on in the project, when the path of the project has become more defined, a more detailed risk analysis is MILESTONES performed. The purpose is to take precautionary measures and prevent COST ESTIMATE problems or compile a list of corrective measures early on in the project. A risk INFORMATION CONTROL factor that requires special attention is the legal side of matters, for instance, how is liability arranged. QUALITY CONTROL Result: PROJECT TEAM AND ENVIRONMENT MANAGEMENT  Preventive/corrective action  Risk-proof project plan RISK CONTROL APPROVAL Bibliography MANAGEMENT FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) MEASURING AND CHECKING PROGRESS Chapter 12: Risk control STEERING PROGRESS  Projectmatig Creëren (Creating Schematically) DELIVERY Chapter 19: Risk management Chapter 20: Creative problem-solving WINDING UP  A guide to the Project Management Body of Knowledge TRANSFER Paragraph 11.1: Risk Identification EVALUATION Paragraph 11.2: Risk Quantification CONCLUSION Paragraph 11.3: Risk Response Development Paragraph 11.4: Risk Response Control TOOLS Tools  Dealing with potential bottlenecks  Cause-Consequence analysis  Impact analysis RISK ANALYSIS AND RISK REDUCTION Risk limitation Risk limitation encompasses two general activities. The risk is identified during the analysis phase and neutralised during the reduction phase. Risk limitation is thus a particularly valuable control instrument. Questions to assist in defining risk analysis 1. What can go wrong with the project result, the milestones, etc. 2. What are the potential consequences? 3. What is the chance of failure? Measuring and assessing the risks Chance of occurring X Severity of the Score Risk consequences Almost nil 1 1 Hardly any consequences 1-2 Low risk Small chance 2 2 Limited consequences 3-9 Average risk Reasonable chance 3 3 Fairly serious consequences 10-25 High risk Is sure to occur 4 4 Fatal consequences Cannot be estimated 5 5 Cannot be estimated © ACTIVITY Consolidated 25
  • 26. Questions to assist in defining risk limitation  What is the most plausible cause?  Which preventive measures can be taken?  Is the remaining risk component acceptable?  Which reactive measures can be taken?  Who will do what and when? Risk analysis CAN ANYTHING GO WRONG? NO RISK NO YES SPECIFY PROBLEM CAN WE ESTIMATE THE RISK? FURTHER PROBLEM ANALYSIS NO YE S IS THE RISK LARGE ENOUGH TO HAVE TO TACKLE? CALCULATED RISK NO YE S TAKE PRECAUTIONARY MEASURES IS THE REMAINING RISK ACCEPTABLE REDUCED RISK YES NO MAKE CONTINGENCY PLANS CAN THE DAMAGE BE SUFFICIENTLY CONTAINED? COVERED RISK YES NO PERMANENT RISK © ACTIVITY Consolidated 26
  • 27. APPROVAL INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How do I get approval for the decision documents? DEFINITION OF RESULT Who must approve the decision documents? OVERALL RISK ANALYSIS Content PHASING The client remains closely involved with the project for the duration of the BREAKDOWN project. After all, the client must approve specifications and planning and SURETIES provide the necessary resources (staff, funds and material). The client must also ORGANIZATION make choices (continue, modify or stop) if plans lose touch with reality. The MILESTONES client‟s role must therefore be clearly defined. COST ESTIMATE In addition to the client, all others involved in the project must be able to approve the project plan. This is expressed in the shape of acceptance, INFORMATION CONTROL commitment, motivation and involvement. Without this support basis, it is QUALITY CONTROL almost impossible to complete a project successfully. PROJECT TEAM AND ENVIRONMENT MANAGEMENT Result RISK CONTROL  Approved decision documents APPROVAL  Commitment from those involved MANAGEMENT FINE-PLANNING MEASURING AND CHECKING PROGRESS Bibliography STEERING PROGRESS  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) DELIVERY Chapter 13: Approval WINDING UP  Projectmatig Creëren (Creating Schematically) TRANSFER Chapter 16: The client EVALUATION CONCLUSION Tools TOOLS  Project plan  Project design © ACTIVITY Consolidated 27
  • 28. FINE-PLANNING INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues DEFINITION OF RESULT Who must do what and when in the next phase? OVERALL RISK ANALYSIS PHASING Content BREAKDOWN As soon as it is known when execution of the work can commence, fine- SURETIES planning for the first phase can commence. The overall planning will continue ORGANIZATION to apply for the later phases. Only after completion of each phase is the next MILESTONES phase fine-planned. These schedules can be depicted visually in a network or COST ESTIMATE bar-chart planning. INFORMATION CONTROL QUALITY CONTROL Result  Activities plan PROJECT TEAM AND ENVIRONMENT MANAGEMENT RISK CONTROL Bibliography APPROVAL  Syllabus Het Projectmanagement Proces (The Project Management MANAGEMENT FINE-PLANNING Process Syllabus) Chapter 14: Fine-planning MEASURING AND CHECKING PROGRESS  Projectmatig Creëren (Creating Schematically) STEERING PROGRESS Chapter 7: Project planning DELIVERY  A guide to the Project Management Body of Knowledge WINDING UP Paragraph 6.1: Activity Definition TRANSFER Paragraph 6.2: Activity Sequencing Paragraph 6.3: Activity Duration Estimating EVALUATION Paragraph 6.4: Schedule Development CONCLUSION TOOLS Tools  Implementation programme © ACTIVITY Consolidated 28
  • 29. INTRODUCTION MEASURING AND CHECKING PROGRESS DESIGN DEFINITION OF PROBLEM Key issues DEFINITION OF RESULT On what basis do I evaluate the project progress? How do I keep all those involved informed of the project progress? OVERALL RISK ANALYSIS PHASING Content BREAKDOWN SURETIES There will be continuous feedback on the planning during execution of the ORGANIZATION project. The project manager will be kept up-to-date on the project via progress reports and will test this against the plan (or the norm). In order to implement MILESTONES this step of the process properly, criteria must be laid down and it must be clear COST ESTIMATE who is reporting on what and when. INFORMATION CONTROL QUALITY CONTROL Result PROJECT TEAM AND ENVIRONMENT  Criteria MANAGEMENT  Progress reports RISK CONTROL APPROVAL MANAGEMENT Bibliography FINE-PLANNING  Syllabus Het Projectmanagement Proces (The Project Management MEASURING AND CHECKING PROGRESS Process Syllabus) Chapter 15: Measuring and checking STEERING PROGRESS  Projectmatig Creëren (Creating Schematically) DELIVERY Chapter 6: Project control WINDING UP  A guide to the Project Management Body of Knowledge TRANSFER Paragraph 6.5: Schedule Control EVALUATION CONCLUSION Tools TOOLS  Quick scan project control  Progress reports © ACTIVITY Consolidated 29
  • 30. STEERING PROGRESS INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues DEFINITION OF RESULT How do I achieve the agreed end result? OVERALL RISK ANALYSIS How do I ensure that the end result is used effectively? PHASING BREAKDOWN Content SURETIES ORGANIZATION If progress appears to be drifting away from the planning, the project manager must take steps to align planning and reality. He can do this by steering, re- MILESTONES planning or, if the worst comes to the worst, he may even decide to put a halt to COST ESTIMATE the entire project. For the project manager, the point of departure is always to achieve the desired end result. INFORMATION CONTROL QUALITY CONTROL PROJECT TEAM AND ENVIRONMENT Result MANAGEMENT  Part results  Acceptance RISK CONTROL APPROVAL MANAGEMENT FINE-PLANNING Bibliography  Syllabus Het Projectmanagement Proces (The Project Management MEASURING AND CHECKING PROGRESS Process Syllabus) STEERING PROGRESS Chapter 16: Steering DELIVERY  Projectmatig Creëren (Creating Schematically) WINDING UP Chapter 6: Project control – the art of playing the Bermuda triangle TRANSFER EVALUATION CONCLUSION TOOLS CHECKING THE PROJECT PROGRESS Content of the progress report  Retrospect  State of affairs in connection with the plan  With respect to content and control  Preview  Approach of next phase (in detail)  Approach of subsequent phase (in detail)  With respect to content and control  Periodical  Milestone-dependent © ACTIVITY Consolidated 30
  • 31. INTRODUCTION DELIVERY DESIGN DEFINITION OF PROBLEM Key issues DEFINITION OF RESULT How do I get endorsement of the project result from the client? OVERALL RISK ANALYSIS PHASING Content Delivery of the project result to the client is confirmed by the Delivery BREAKDOWN SURETIES document. With this document, the client declares in writing that all agreed ORGANIZATION project results have indeed been delivered. The conditions under which the project result is accepted are laid down in the initial phase of the project. Final MILESTONES signing of the Delivery document marks the end of the project. The winding-up COST ESTIMATE phase can then commence. INFORMATION CONTROL QUALITY CONTROL Result PROJECT TEAM AND ENVIRONMENT  Delivery document MANAGEMENT RISK CONTROL Bibliography APPROVAL MANAGEMENT  Syllabus Het Projectmanagement Proces (The Project Management FINE-PLANNING Process Syllabus) MEASURING AND CHECKING PROGRESS Chapter 17: Delivery STEERING PROGRESS DELIVERY Tools WINDING UP  Delivery document  Follow-up programme TRANSFER EVALUATION CONCLUSION TOOLS PROJECT DELIVERY Content of the Delivery document  Description of the project result as realised (based on the offer, the project plan and any proposals for changes)  Description of the follow-up programme (indicate who in the organization is to maintain the project result, guarantee terms, maintenance contracts, any adaptations/expansions).  Overview of remaining obligations, additional and less work.  Endorsement by the client that the project result has been achieved in accordance with the offer presented and that the contractor has met all obligations. © ACTIVITY Consolidated 31
  • 32. TRANSFER INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How do I guarantee the project result in the organization? DEFINITION OF RESULT OVERALL RISK ANALYSIS PHASING Content After the project result has been achieved in accordance with the requirements, BREAKDOWN the project manager must transfer the project result to a person in charge of SURETIES ORGANIZATION management and maintenance. This person must ensure that the project result is used optimally in the organization. The project manager supplies the required MILESTONES information in order to fulfil this task optimally. COST ESTIMATE INFORMATION CONTROL Result QUALITY CONTROL  Follow-up is embedded PROJECT TEAM AND ENVIRONMENT MANAGEMENT RISK CONTROL Bibliography  Syllabus Het Projectmanagement Proces (The Project Management APPROVAL MANAGEMENT Process Syllabus) FINE-PLANNING Chapter 18: Transfer MEASURING AND CHECKING PROGRESS STEERING PROGRESS DELIVERY WINDING UP TRANSFER EVALUATION CONCLUSION TOOLS PROJECT TRANSFER  Plan the transfer together with those involved:  who are involved?  which formalities must be taken into account?  Convince yourself that the end users accept the product  Formulate training requirements for end users  Have the client sign a statement of agreement © ACTIVITY Consolidated 32
  • 33. EVALUATION INTRODUCTION DESIGN DEFINITION OF PROBLEM Key issues How can we learn from our project experiences? DEFINITION OF RESULT OVERALL RISK ANALYSIS Content PHASING The purpose of a structured evaluation is not only to highlight the successes and BREAKDOWN failures of a completed project. Even more important is to use the evaluation as SURETIES a means of looking ahead towards subsequent projects and therefore being able ORGANIZATION to avoid problems and pitfalls. MILESTONES COST ESTIMATE Result INFORMATION CONTROL  Evaluation report QUALITY CONTROL PROJECT TEAM AND ENVIRONMENT MANAGEMENT Bibliography RISK CONTROL  Syllabus Het Projectmanagement Proces (The Project Management Process Syllabus) APPROVAL Chapter 19: Evaluation MANAGEMENT FINE-PLANNING  Projectmatig Creëren (Creating Schematically) MEASURING AND CHECKING PROGRESS Chapter 23: Project evaluation and Audit, learning from what went right and what went wrong STEERING PROGRESS DELIVERY WINDING UP Tools  Evaluation TRANSFER EVALUATION CLOSURE TOOLS © ACTIVITY Consolidated 33