Adopting Effective Project Controls Strategies




      Dr. Anamaria Popescu, PE,PSP,PMP
   McLachlan Lister - Hill International Australia
               www.hillintl.com
My Profile


•   Associate Director-McLL in Brisbane
•   Project Auditing Services
•   Project Controls Implementation
•   Construction Claims Expertise
•   Forensic Schedule Analysis
•   Joined Hill International in 2011
•   Consulting to the Oil and Gas Industry
•   University of Texas at Austin
•   Civil Engineering/CEPM Program
•   PhD in Schedule Analysis
•   PM at Enron
A Good Indication….
     ….that Your Project Controls System was Ineffective!!!
Project Characteristics

•   Coalbed Methane Natural Gas Drilling Program
•   Gas Field: 1.9 Trillion Cubic Feet of Gas
•   13 Year Period
•   1000 Wells
•   2+ Billion Investment ($US)
•   Environmental Sensitive Area
•   Minimize Environmental Impact
•   Use Existing Infrastructure
Situation


• Project in Feasibility Phase
• No Project Controls People
• No Cost Control or
  Schedule Existed
• Wanted a Schedule to
  “Pass Through” Gate
  Review
• Wanted it in Two Weeks
• Did Not Have a Software
  Platform
• “Power Point” as the
  Panacea
• Huge Political Pressures
  for Success
Our Scope…to Develop:

•   A standard WBS for the project
•   An Integrated Schedule
•   Re-Alignment of Cost Estimate with WBS
•   Risk Allocation/Contingency Management
•   Earned Value System
•   The basis for the cost and schedule baseline
Step 1: Work Breakdown Structure Development

 FIRST THINGS FIRST…..What is a WBS
 Anyway?

 • Grouping of Project Elements
 • Defines the Total Scope of Work
 • Each Level More Detailed than Previous

                               .
WBS Development Benefits

•   Scope Capture Check
•   Promotes Consistency of Cost and Schedule Data
•   Rollup for Reporting Requirements
•   Cost Breakdown Structure Framework
•   Earned Value is Actually Possible!




         $       $       $
WBS Development: What We Did…

•   Got a Plotter (A BIG One!)
•   Became Visio Experts
•   Had One-on-One Meetings…Lots of Them!
•   WBS Wallpaper
•   Captive Audience
•   Comment Period of One Week
•   Graffiti Allowed!
•   Custom Pen Colors!
•   True Integration Effort
•   Transparency in SOW
•   “Light Bulbs” Went Off
•    Made Changes…Replotted…Rehung
•   Not Very “Green” but Very Vital
WBS Requirements & Questions for Consideration

 •    Number of levels in the WBS
 •    Define Each Level
 •    Schedule Activities Captured at Level X
 •    Costs Captured at Level X
 •    Numbering Structure: Alpha/Numeric


     Critical that the Team “Buys-In” and “Owns” the WBS
WBS Structure for Project

                       Level 1
                       Project
                      Level 2
                   Delivery Area
                       Level 3
                 Facility Package
                       Level 4
               Facility Type/Rig No.
                       Level 5
            Specific Facility/Well Name
                       Level 6
                       Phase
                       Level 7
                     Discipline
WBS Structure: Levels 1-4
WBS Structure: Levels 5-6
Step 2a: OBS Development
• Definition: The identification of project participants and
  their hierarchical relationship.
• Assigned in P6 Directly
Step 2b: OBS Assignment
• Intersection of OBS and WBS Creates:
Step 3: Activity Development

                   Activity Elements



                       Calendar



       Interface                       Relation-
        Points                          ships



                      Activity

                                       Durations
        Codes
                                          (3)



                       WBS No.
Activity Development: What We Did….

•   Set Up Excel Templates        •   3 Durations
•   Emailed to Team Leads         •   Import into P6
•   One Tab per WBS Element       •   “Live” Logic Ties
•   Team Brainstorming Sessions   •   Schedule Projected on
•   No Dates!                         Screen
Activity Development: Standardization of Well
   Activities
Well No. 1




                                                   18
Step 4: Schedule Integrity Check

• Assess through
  Metrics
• Don’t Skip!
• CP should not be
  published
• P6 Schedule
  Report or Fuse
Step 5: Critical Path Review
•   Plotted Out both CP and NCP
•   Grouped by Top 10 Float Paths (Top 10 Wells)
•   Graphically Could See the Critical Path
•   Took Up Four Walls of Conference Room- “BAG”
•   Each Team Had a Different Colored Pen
•   Marked Up and Changed Logic Ties
•   Had Collaborative Discussions about Sequencing
•   Made Changes “Live” in P6
•   Re-plotted Top 3 Paths
•   Management Accepted “The Answer”
•   Not Thrilled but Convinced!
Step 5: Critical Path Review
• Achievable project completion date set!
• Avoided……….
Step 6: Incorporating Risk into the Schedule

  •     Interactive workshop with various disciplines to
        come up with the risks.
  •     Develop a Risk Register
  •     Risk Matrix- Likelihood of Occurrence vs. Impact
  •     Running a risk analysis on the baseline
        schedule in Pertmaster
  •     Probability of achieving expected completion
        date
  •     Schedule Contingency Management-Buffers
Step 6: Incorporating Risk into the Schedule




                   Risk Register
                 Mitigation Strategies
Step 6: Incorporating Risk into the Schedule
Likelihood of Occurrence




                           Risk Assessment Matrix
Step 6: Incorporating Risk into the Schedule
Step 6: Incorporating Risk into the Schedule




             Forecasted Project Duration
                  with Probability
Step 6: Incorporating Risk into the
Cost Estimate
Forecasted
Project Total
    Cost
     by
 Probability
Step 6: Cost and Schedule Sensitivity Index




  Pareto Principle :
    80% of Risks
   Originate from
 20% of the Activities
Step 6: Cost and Schedule Sensitivity Index
                                                      Cost Sensitivity




  H007 - RR Flagging & Administration                                                            64%




           D001 - Detailed Engineering                                                     44%




            H002 - General Conditions                                                39%




                        H004 - Inflation                                         38%




               H006 - CA&I Incidentals                                          37%




              H003 - Overhead & Profit                                         36%




              H001 - Balance of Scope                                    25%




                     D002 - Permitting                          19%




C009 - Electrical Service & Distribution         8%




            C011 - Membrane Roofing        -7%
Step 6: Contingency Management

• CP shows only the early date for project completion.
• The next step will be to determine the late dates for project
  completion
• The project will have two completion dates:
    • a finish date without contingency (the early date)
    • a finish date with contingency (the late date).
• Paradigm shift for most companies-usually mange to only one
  finish date & no contingency




                                                                  30
Step 6: Contingency Boxes

• This step is based on the organizational structure of
  the project and the company.
• The person with authority to distribute a portion of the
  project float needs to be assigned a contingency box.
• These boxes are represented as activities in the
  schedule-tied in series
• The schedule will now have two finish dates:
   • the early target finish date, preceding the contingency
   • the late target finish date that succeeds the boxes.




                                                               31
Step 6: Contingency Boxes (Continued)




              +
              +
                     +
                           =
                                        32
Step 6: Calculate the Contingency

• Choose the % of Contingency to Allocate based on:
     •  The corporate culture of the company.
     •  How much risk the leadership team is willing to take.
     •  Risk management plan
     •  Monte Carlo Simulation (PERT) of the baseline schedule using the
        three durations
     • Pert Master ©
     • “What-If” Scenarios using all 3 durations
     • Benchmark Data
     • “Cutting Edge Technology” vs. “Tried and True” Projects
     • Length of Project
     • Phase of Project
   Calculate contingency duration based on Total Duration of Longest
    Path x %
     – From Start Milestone to Early Finish Date of Project
                                                                       33
Step 6: Percentage Allocation

• Distribute the contingency to each box based on the
  amount of authority the three team leaders have on
  the project.
• Percentage distributed to each box.
• DOES NOT HAVE TO BE EQUALLY
  APPORTIONED.
• Formal Float Distribution Process-Float is not
  “Scattered” throughout




                                                        34
Step 6: Percentage Allocation

                                15% Contingency
                                Total Project
                                 Duration=300 Days
                                Contingency:45 Days




                                      PM: 60%
                                     PGM: 30%
                                      PD: 10%




                                  “Drop Dead Date”
                                           35
Output: Integrated Baseline Schedule
Output: Overall Program Critical Path Drilling
Sequence




                                                 37
Step 7: Schedule Basis
•   Baseline AFTER critical path acceptance
•   Key step that is overlooked
•   Assumptions/Key decisions recorded
•   Provides validity to the schedule itself
•   Provides an understanding of team’s thought process
•   Allows team members to resist scrutiny/criticism
•   Basis for change management
•   Excusable Delay: Conditions Different than Assumptions
Step 8: Integrating Cost and Schedule: Earned
Value
Integrating Cost and Schedule: Earned Value
Value
•   Standardization of activities
•   Great Communication Tool: Everyone Spoke the Same Language
•   Integrated Software Platform: Primavera Enterprise
•   Schedule allowed for realistic and accurate well count by year
•   Contractor Payments-Virtually Eliminated Disputes
•   No management surprises!!!
•   Benchmarking – Setting standards for other drilling programs
•   Record actual times and adjusted future projections accordingly
•   Accuracy increased year by year
Conclusions

• Understand what the Client Needs vs.Wants (two very different
  things in this case)
• Don’t expect them to know terminology and benefits…educate
  them (Project Controls 101 Class)
• Hands-On Development of Project Schedule (face-time is key)
• Print out items for discussion and hunt people down….no passive
  emails..if you are an introvert, get over it! (also a six foot long
  schedule is hard to read on a screen)
• Let the teams mark stuff up, nothing is set in stone!!!!
• Have many integration meetings…live in a conference room, I
  did…
• Schedule Review Meetings should have strict time
  management…no more than 1 hour at a time…you will lose people
  and they never will come back! Respect their time and they will
  respect yours…..
Conclusions

• Have the team explain their scope and process on a “generic”
  project first
• Get them thinking Logic not Dates… they can’t cheat the schedule
  that way
• Set up different report templates to match their needs so they will
  actually use it….what a concept!
• Allow suppliers, engineering firms, etc. to attend the progress
  meetings and comment on the schedule… don’t worry about the
  contractual hierarchy
• Have a transition plan and implement it before you leave
• Momentum is Key….
•                             ….losing it can derail all of your efforts
Questions ?
Contact Information

               Dr.Anamaria Popescu, PE,PMP,PSP
                          Brisbane Office
                       2/19 Musgrave Street
                       West End, QLD, 4101
              Email: anamariap@mclachlanlister.com
                     Phone: 61 07 3255 0223


       Sydney Office                       Perth Office
  Level 1, 1 Hickson Road                189 Colin Place
  Phone: 61 02 9241 7328              Phone: 61 08 9480 0647

Más contenido relacionado

La actualidad más candente

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisLisa Dehner
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 

La actualidad más candente (20)

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 

Destacado

EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 

Destacado (6)

Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 

Similar a Adopting Effective Project Controls Strategies

Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9Syed Muhammad Hammad
 
Analytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk ManagementAnalytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk ManagementHannah Flynn
 
Project Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk ManagementProject Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk ManagementAggregage
 
Database Project management
Database Project managementDatabase Project management
Database Project managementAmin Chowdhury
 
Andy Chapell babcock international scl
Andy Chapell babcock international sclAndy Chapell babcock international scl
Andy Chapell babcock international sclGlobal Business Intel
 
Final spiralmodel97
Final spiralmodel97Final spiralmodel97
Final spiralmodel97akshay8835
 
Chapter 4 Software Project management.ppt
Chapter 4 Software Project management.pptChapter 4 Software Project management.ppt
Chapter 4 Software Project management.pptKenaAbera1
 
Agile & Lean @ MediaGeniX
Agile & Lean @ MediaGeniXAgile & Lean @ MediaGeniX
Agile & Lean @ MediaGeniXESUG
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics rightThomas Cream
 
Software Project Management (lecture 4)
Software Project Management (lecture 4)Software Project Management (lecture 4)
Software Project Management (lecture 4)Syed Muhammad Hammad
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptxAhmedKayed6
 
EDM101: Implementation Practices - Project Management
EDM101: Implementation Practices - Project ManagementEDM101: Implementation Practices - Project Management
EDM101: Implementation Practices - Project ManagementLaserfiche
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)Syed Muhammad Hammad
 
Collaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfCollaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfTim McMahon
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 

Similar a Adopting Effective Project Controls Strategies (20)

Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
 
Analytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk ManagementAnalytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk Management
 
Project Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk ManagementProject Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk Management
 
Chapter 4
Chapter 4 Chapter 4
Chapter 4
 
Project management
Project managementProject management
Project management
 
Database Project management
Database Project managementDatabase Project management
Database Project management
 
Andy Chapell babcock international scl
Andy Chapell babcock international sclAndy Chapell babcock international scl
Andy Chapell babcock international scl
 
Final spiralmodel97
Final spiralmodel97Final spiralmodel97
Final spiralmodel97
 
Chapter 4 Software Project management.ppt
Chapter 4 Software Project management.pptChapter 4 Software Project management.ppt
Chapter 4 Software Project management.ppt
 
Agile & Lean @ MediaGeniX
Agile & Lean @ MediaGeniXAgile & Lean @ MediaGeniX
Agile & Lean @ MediaGeniX
 
day 3 PMP.pptx
day 3 PMP.pptxday 3 PMP.pptx
day 3 PMP.pptx
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
Software Project Management (lecture 4)
Software Project Management (lecture 4)Software Project Management (lecture 4)
Software Project Management (lecture 4)
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
EDM101: Implementation Practices - Project Management
EDM101: Implementation Practices - Project ManagementEDM101: Implementation Practices - Project Management
EDM101: Implementation Practices - Project Management
 
Software Project Management (lecture 3)
Software Project Management (lecture 3)Software Project Management (lecture 3)
Software Project Management (lecture 3)
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
Collaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfCollaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdf
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 

Último

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 

Último (20)

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 

Adopting Effective Project Controls Strategies

  • 1. Adopting Effective Project Controls Strategies Dr. Anamaria Popescu, PE,PSP,PMP McLachlan Lister - Hill International Australia www.hillintl.com
  • 2. My Profile • Associate Director-McLL in Brisbane • Project Auditing Services • Project Controls Implementation • Construction Claims Expertise • Forensic Schedule Analysis • Joined Hill International in 2011 • Consulting to the Oil and Gas Industry • University of Texas at Austin • Civil Engineering/CEPM Program • PhD in Schedule Analysis • PM at Enron
  • 3. A Good Indication…. ….that Your Project Controls System was Ineffective!!!
  • 4. Project Characteristics • Coalbed Methane Natural Gas Drilling Program • Gas Field: 1.9 Trillion Cubic Feet of Gas • 13 Year Period • 1000 Wells • 2+ Billion Investment ($US) • Environmental Sensitive Area • Minimize Environmental Impact • Use Existing Infrastructure
  • 5. Situation • Project in Feasibility Phase • No Project Controls People • No Cost Control or Schedule Existed • Wanted a Schedule to “Pass Through” Gate Review • Wanted it in Two Weeks • Did Not Have a Software Platform • “Power Point” as the Panacea • Huge Political Pressures for Success
  • 6. Our Scope…to Develop: • A standard WBS for the project • An Integrated Schedule • Re-Alignment of Cost Estimate with WBS • Risk Allocation/Contingency Management • Earned Value System • The basis for the cost and schedule baseline
  • 7. Step 1: Work Breakdown Structure Development FIRST THINGS FIRST…..What is a WBS Anyway? • Grouping of Project Elements • Defines the Total Scope of Work • Each Level More Detailed than Previous .
  • 8. WBS Development Benefits • Scope Capture Check • Promotes Consistency of Cost and Schedule Data • Rollup for Reporting Requirements • Cost Breakdown Structure Framework • Earned Value is Actually Possible! $ $ $
  • 9. WBS Development: What We Did… • Got a Plotter (A BIG One!) • Became Visio Experts • Had One-on-One Meetings…Lots of Them! • WBS Wallpaper • Captive Audience • Comment Period of One Week • Graffiti Allowed! • Custom Pen Colors! • True Integration Effort • Transparency in SOW • “Light Bulbs” Went Off • Made Changes…Replotted…Rehung • Not Very “Green” but Very Vital
  • 10. WBS Requirements & Questions for Consideration • Number of levels in the WBS • Define Each Level • Schedule Activities Captured at Level X • Costs Captured at Level X • Numbering Structure: Alpha/Numeric Critical that the Team “Buys-In” and “Owns” the WBS
  • 11. WBS Structure for Project Level 1 Project Level 2 Delivery Area Level 3 Facility Package Level 4 Facility Type/Rig No. Level 5 Specific Facility/Well Name Level 6 Phase Level 7 Discipline
  • 14. Step 2a: OBS Development • Definition: The identification of project participants and their hierarchical relationship. • Assigned in P6 Directly
  • 15. Step 2b: OBS Assignment • Intersection of OBS and WBS Creates:
  • 16. Step 3: Activity Development Activity Elements Calendar Interface Relation- Points ships Activity Durations Codes (3) WBS No.
  • 17. Activity Development: What We Did…. • Set Up Excel Templates • 3 Durations • Emailed to Team Leads • Import into P6 • One Tab per WBS Element • “Live” Logic Ties • Team Brainstorming Sessions • Schedule Projected on • No Dates! Screen
  • 18. Activity Development: Standardization of Well Activities Well No. 1 18
  • 19. Step 4: Schedule Integrity Check • Assess through Metrics • Don’t Skip! • CP should not be published • P6 Schedule Report or Fuse
  • 20. Step 5: Critical Path Review • Plotted Out both CP and NCP • Grouped by Top 10 Float Paths (Top 10 Wells) • Graphically Could See the Critical Path • Took Up Four Walls of Conference Room- “BAG” • Each Team Had a Different Colored Pen • Marked Up and Changed Logic Ties • Had Collaborative Discussions about Sequencing • Made Changes “Live” in P6 • Re-plotted Top 3 Paths • Management Accepted “The Answer” • Not Thrilled but Convinced!
  • 21. Step 5: Critical Path Review • Achievable project completion date set! • Avoided……….
  • 22. Step 6: Incorporating Risk into the Schedule • Interactive workshop with various disciplines to come up with the risks. • Develop a Risk Register • Risk Matrix- Likelihood of Occurrence vs. Impact • Running a risk analysis on the baseline schedule in Pertmaster • Probability of achieving expected completion date • Schedule Contingency Management-Buffers
  • 23. Step 6: Incorporating Risk into the Schedule Risk Register Mitigation Strategies
  • 24. Step 6: Incorporating Risk into the Schedule Likelihood of Occurrence Risk Assessment Matrix
  • 25. Step 6: Incorporating Risk into the Schedule
  • 26. Step 6: Incorporating Risk into the Schedule Forecasted Project Duration with Probability
  • 27. Step 6: Incorporating Risk into the Cost Estimate Forecasted Project Total Cost by Probability
  • 28. Step 6: Cost and Schedule Sensitivity Index Pareto Principle : 80% of Risks Originate from 20% of the Activities
  • 29. Step 6: Cost and Schedule Sensitivity Index Cost Sensitivity H007 - RR Flagging & Administration 64% D001 - Detailed Engineering 44% H002 - General Conditions 39% H004 - Inflation 38% H006 - CA&I Incidentals 37% H003 - Overhead & Profit 36% H001 - Balance of Scope 25% D002 - Permitting 19% C009 - Electrical Service & Distribution 8% C011 - Membrane Roofing -7%
  • 30. Step 6: Contingency Management • CP shows only the early date for project completion. • The next step will be to determine the late dates for project completion • The project will have two completion dates: • a finish date without contingency (the early date) • a finish date with contingency (the late date). • Paradigm shift for most companies-usually mange to only one finish date & no contingency 30
  • 31. Step 6: Contingency Boxes • This step is based on the organizational structure of the project and the company. • The person with authority to distribute a portion of the project float needs to be assigned a contingency box. • These boxes are represented as activities in the schedule-tied in series • The schedule will now have two finish dates: • the early target finish date, preceding the contingency • the late target finish date that succeeds the boxes. 31
  • 32. Step 6: Contingency Boxes (Continued) + + + = 32
  • 33. Step 6: Calculate the Contingency • Choose the % of Contingency to Allocate based on: • The corporate culture of the company. • How much risk the leadership team is willing to take. • Risk management plan • Monte Carlo Simulation (PERT) of the baseline schedule using the three durations • Pert Master © • “What-If” Scenarios using all 3 durations • Benchmark Data • “Cutting Edge Technology” vs. “Tried and True” Projects • Length of Project • Phase of Project  Calculate contingency duration based on Total Duration of Longest Path x % – From Start Milestone to Early Finish Date of Project 33
  • 34. Step 6: Percentage Allocation • Distribute the contingency to each box based on the amount of authority the three team leaders have on the project. • Percentage distributed to each box. • DOES NOT HAVE TO BE EQUALLY APPORTIONED. • Formal Float Distribution Process-Float is not “Scattered” throughout 34
  • 35. Step 6: Percentage Allocation 15% Contingency Total Project Duration=300 Days Contingency:45 Days PM: 60% PGM: 30% PD: 10% “Drop Dead Date” 35
  • 37. Output: Overall Program Critical Path Drilling Sequence 37
  • 38. Step 7: Schedule Basis • Baseline AFTER critical path acceptance • Key step that is overlooked • Assumptions/Key decisions recorded • Provides validity to the schedule itself • Provides an understanding of team’s thought process • Allows team members to resist scrutiny/criticism • Basis for change management • Excusable Delay: Conditions Different than Assumptions
  • 39. Step 8: Integrating Cost and Schedule: Earned Value
  • 40. Integrating Cost and Schedule: Earned Value
  • 41. Value • Standardization of activities • Great Communication Tool: Everyone Spoke the Same Language • Integrated Software Platform: Primavera Enterprise • Schedule allowed for realistic and accurate well count by year • Contractor Payments-Virtually Eliminated Disputes • No management surprises!!! • Benchmarking – Setting standards for other drilling programs • Record actual times and adjusted future projections accordingly • Accuracy increased year by year
  • 42. Conclusions • Understand what the Client Needs vs.Wants (two very different things in this case) • Don’t expect them to know terminology and benefits…educate them (Project Controls 101 Class) • Hands-On Development of Project Schedule (face-time is key) • Print out items for discussion and hunt people down….no passive emails..if you are an introvert, get over it! (also a six foot long schedule is hard to read on a screen) • Let the teams mark stuff up, nothing is set in stone!!!! • Have many integration meetings…live in a conference room, I did… • Schedule Review Meetings should have strict time management…no more than 1 hour at a time…you will lose people and they never will come back! Respect their time and they will respect yours…..
  • 43. Conclusions • Have the team explain their scope and process on a “generic” project first • Get them thinking Logic not Dates… they can’t cheat the schedule that way • Set up different report templates to match their needs so they will actually use it….what a concept! • Allow suppliers, engineering firms, etc. to attend the progress meetings and comment on the schedule… don’t worry about the contractual hierarchy • Have a transition plan and implement it before you leave • Momentum is Key…. • ….losing it can derail all of your efforts
  • 45. Contact Information Dr.Anamaria Popescu, PE,PMP,PSP Brisbane Office 2/19 Musgrave Street West End, QLD, 4101 Email: anamariap@mclachlanlister.com Phone: 61 07 3255 0223 Sydney Office Perth Office Level 1, 1 Hickson Road 189 Colin Place Phone: 61 02 9241 7328 Phone: 61 08 9480 0647