CHAPTER 5
EQUIPMENT DESIGN
In this chapter, detailed equipment design and mechanical design of
5.1 Fixed Bed Catalytic Reactor Process Design:
Reaction temperature =250 0
C ( 523K)
Catalyst: γ - alumina
Density of catalyst particle: 1392 kg/m3
[8]
Catalyst porosity: 0.52 [8]
Type of reactor: Shell and tube heat exchanger type in which catalyst is placed inside the
tube.
Reaction is exothermic: It is carried out in isothermal manner. Water is to be circulated in
liquid form on shell side to maintain the isothermal condition.
Mass of catalyst required in commercial scale plant = 6579.711 kg
Superficial velocity of feed gas V=0.802 m/s
Capacity of plant =50000 MTA of diethyl ether (DEE)
Let no. of working days per annum=340 days
Production rate of diethyl ether (DEE) = (50000*1000)/(340*24)
=6127.45 Kg/hr
!""=
#$%%&'()*
2
&'()*
2
+ #1&'()*&,-(%
(5.1) [3]
"./03"4"=
#%(567%8%&'()*
&'()*
2
+ #1&'()*&,-(% + #2&'()*
2
+ #9&,-(%
2
Design equation (5.2) [3]
:
;
= <
!>
?@AB
CCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC?DE9B [4]
24
In table 5.1 conversion of ethanol and rate of reaction data is given. Unit of rate of reaction
is mol/(gm catalyst sec)
Table 5.1: rate of reaction and conversion data
r (total) 1/r
Ethanol
conversion
2.77216E-06 360729.1 0
2.24531E-06 445373.6 0.1
1.81423E-06 551197.8 0.2
1.45502E-06 687277 0.3
1.15111E-06 868729.7 0.4
8.90654E-07 1122770 0.5
8.31259E-07 1202994 0.525
4.67523E-07 2138934 0.7
2.9333E-07 3409130 0.8
From the graph (appendix A)
Area= 340000 unit
Weight of catalyst= 6579711 gm
= 6579.711 Kg
Bulk density =0.9333 gm/cc [8]
Volume = 6579.711/9333
= 7.049942 m3
Feed rate = 0.1382 Kmol/sec
= 0.1382 x 43.312
= 5.99 Kg/sec
25
Density = PM/RT
= (1500 x 43.312) / ( 8.314 x 523 )
= 14.94 Kg/m3
Feed rate = 5.99 / 14.94
= 0.401 m3
/sec
Superficial velocity = 0.805 m/sec
Total Crosse section area = feed rate / space
= 0.401 / 0.805
= 0.499 m2
MOC of tube = Stainless steel
Tube OD = 0.0508 m
Tube ID = 0.04328 m
Crosse section area of tube = (∏/4) x ID2
= (∏/4) x (0.04328)2
= 0.00147 m2
Total number of tube required
N = Total Crosse section area / Crosse section area of tube
= 0.499/0.00147
= 340
Length of the tube (L) =total volume / (N x Crosse section area of tube)
= 7.05 / (340 x 0.00147)
= 14 m
26
Area = N x ∏ x OD x L
= 340 x ∏ x 0.0508 x 14
= 764.78 m2
Heat duty (Q) = 2445180.91 J/sec
Calculation of fixed bed side film coefficient hi ;
dp = diameter of catalyst
= 0.003 m
Pipe diameter
dt = 0.04328 m
dp/dt = 0.003/0.04328
= 0.06931
(hidt /k) =0.813 e-6dp/dt
( dp G/µ) 0.9
Thermal conductivity K = 0.04366 W/mK
Viscosity µ = 1.58235 x 10-5
pa.sec
Mass velocity G = 0.87 Kg/m2
sec
On calculation
hi = 416.32637 W/m2
K
hi dp/k = 3.6(dpG/µ ε)0.365
on calculation
hi = 49.789923 W/m2
K
Take lesser value
hi = 49.789923 W/m2
K
27
Calculation of shell side heat transfer, h0
Shell side heat transfer coefficient calculated here [11]
Tube pitch Pt =1.25d0
=1.25 x 0.0508
= 0.0635 m
Type of arrangement = Equilateral triangular
Equivalent diameter de = 1.1/d0 (Pt – 0.907 d0
2
)
= 1.1/0.0508[0.06352
– 0.907*0.0508 2
]
= 0.03663 m
Shell side mass flow rate m ;
∆H = m*Cp*∆T
Here coolant used is dowtherm Q because operating temperature is 523 K and dowtherm Q is
stable up to 603 K ( Properties from dowtherm Q product technical data)
Properties of dowtherm Q
Cp = 1811 J/Kg K
Viscosity µ = 1.28 x 10-3
pa.sec
Thermal conductivity K = 0.1156 W/mK
∆T= 60 K
m = 2445180.91/(1811 x 60)
= 22.5 Kg/s
Density = 927.6 Kg/ m3
Circulation rate qv = (22.5/927.6)
= 0.024 m3
/sec
28
Shell inside diameter, Ds :
Db =d0 (Nt /K1 )1/n1
K1 = 0.319 and n1 = 2.142
Db = 50.8(340/0.319)1/2.142
= 1.315m
Let clearance between shell internal dia and bundle (Db),
Db = 15 mm
Let Ds= 1.315 + 0.015 m
= 1.330 m
Baffle spacing
Bs= 0.4Ds
= 0.4 x 1.33
= 0.532m
Shell side flow area As = (Pt-d0)DsBs/Pt
= (0.0635-0.0508)/0.0635(1.330 x 0.532)
= 0.1416 m2
Gs = m/As
= 22.5 / 0.1416
= 158.83 kg/m2
sec
Reynolds number,
Re = deGs/µ
= 0.03669 x 158.83 / 0.00128
= 4545.36
Prandlt number,
Pr = Cp µ/K
29
= 1811 x 0.00128 / 0.1156
= 20.05
(h0 de/k)= 0.027 Re0.8
Pr0.3
From calculation
h0 = 150.50 W/m2
K
Overall heat transfer coefficient U0 ;
1/ U0 =1/h0+1/h0d +d0 ln(d0 /di)/2Kw+d0 l/di hid +d0 l/di hi
=1/150.50 + 1/5000 + {0.0508 ln(0.0508/0.04328)}/(2*16) +
(0.0508/0.04328)*(1/5000) + 0.0508/(0.04328 x 49.78)
U0 = 37.06 W/m2
K
Shell side pressure drop
Ps =8 Jf(Ds/de)(L/Bs)(ρsus
2
/2)
Jf = 0.07 from Jf vs Nre graph [11]
us= Gs/ρs
= 158.83 / 927.6
= 0.171 m/sec
= 8*0.07 x (1.330/0.03663) x (14/0.5323) x ( 985.728 x 0.0692
/2)
= 7335.7 Pa
Tube Side pressure drop
Pt =8 Jf(L/di)(ρsus
2
/2)
Jf = 0.03 from Jf vs Nre graph [11]
=8 x 0.03 x (14/0.04328) x (14.95 x 0.8022
)/2
= 0.3760672 KPa
Pressure drop across the bed
Blake – plummer equation
!
="
1.75(1 # $)%&
'
$*+,
"
P = 18.07 KPa
30
Total tube side pressure drop
Pt = 18.45 KPa
5.1.1 Mechanical Design of reactor
Shell and tube type reactor [6]
(a) Shell side
Material carbon steel - (Corrosion allowance- 3mm)
Number of passes – 1
Fluid – dowtherm Q
Working pressure – 0.3 N/mm2
Design pressure – 0.33 N/mm2
Inlet temperature – 25 0
C
Outlet temperature – 85 0
C
Segmental baffles (25% cut ) with tie rods and spacers
Maximum allowable stress - 80 N/mm2
Shell thickness; [6]
ts =PD/(2fJ+P)
= 0.33 x 1400/((2 x 80 x 0.85)+0.33) + 3 mm
= 6.38 mm
Nozzle thickness (diameter -75mm)
tn=PD/(2fJ-P)
= 0.33 x 75/( 2 x 80 – 0.33)
= 0.155 mm + 3 mm
= 3.155 mm
Head
Head thickness (th) = PCrW/2fJ
Crown radius = 1400 mm
Knuckle radius = 140 mm
31
W=1/4(3+ (Rc/R1)1/2
)
= 1/4(3 + (1400/140)1/2
)
= 1.54
th = 0.33 x 1400 x 1.54 / (2 x 0.85 x 80) + 3mm
= 8.23mm
Transverse Baffles
Spacing between baffles= 0.4Ds
= 0.4 x 1.4
= 0.56m
Thickness of baffles = 5mm
Tube Side [6]
Tube and tube sheet material - stainless steel
Number of tubes – 340
Outside diameter – 50.8 mm
Length – 14m
Tube pitch - 0.0635m
Working pressure – 1.5 N/mm2
Design pressure – 1.65 N/mm2
Inlet temperature – 2500
C
Outlet temperature - 2500
C
Permissible stress – 74.5 N/mm2
tf =PD0/(2fJ+P)
= 1.65 x 50.8 / (2 x 74.5 x 0.85 + 1.65)
= 0.65 mm
No corrosion allowance, since the tubes are of stainless steel.
Design of Gasket and Bolt Size [6]
Gasket material – flat metal jacketed, asbestos fill (iron or soft steel)
Gasket factor, m= 3.75
Minimum design stress = 52.4 N/mm2
32
Basic gasket seating width – b 0
Internal dia. Of Gasket – 1400 mm
Do/Di = ((Y-Pm)/(Y-P(m+1)))0.5
= ((52.4 – 0.33 x 3.75)/(52.4 – 0.33 x 4.75))0.5
= 1.0032
Do = 1.4045 m
N = (1.4045-1400)/2 = 0.0022648mm use 35mm
b0 = ½N = 0.0175mm
G= (1.4045+1400)/2
= 1.4022m
Effective Gasket seating width, b= 0.5b0
1/2
= 2.09 mm
Bolts
Minimum bolt load at atm. Condition, Wm1 = 3.14bGYa
= 3.14 x 2.09 x 1402.2 x 52.4
= 483360.87 N
At operating condition,
Wm2=3.14(2b)GmP+3.14G2
P
= 3.14 x 2 x 2.09 x 1402.2 x 3.75 x 0.33 +3.14 x 1402.22
x 0.33
= 532176.24 N
Wm1 < Wm2 so Wm2 is controlling load
Number of bolts = 1402.2/(2.5*10)
= 56
Am2= 532176.24/80 = 6652.203 mm2
33
Diameter of bolts = [(Am2/no. of bolts) x 3.14/4]1/2
= [(6652.203)/56 x (4/3.14)]1/2
=12.29 mm
Bolt area, Ab = 2 x 3.14 x YaGN/fa
= 2 x 3.14 x 52.48 x 1402.2 x 35 / 80
=202204.36 mm2
Pitch of bolts = 4.75*18
= 85.6 mm
Pitch circle dia.= (85.6*56)/3.14
=1526.62mm
Flange Thickness,
K= 1/[0.3+1.5WmhG/HG]
= 1/[0.3 + 1.5 x 532176.24 x 62.52136 /( 509382.1 X 1402.2)]
= 2.7
tf = G(p/kf)1/2
+c
= 1402.2 x (0.33/2.7/80) ½
+ 3
= 70.62 mm
5.2 Heat exchanger Design
For heat exchanger tube side is waste water and shell side is cooling water is used. Here we
assume over all heat transfer coefficient (U) is 800 W/m2
K.In table 5.1 tube side and shell
side fluid inlet, outlet temperature and mass flowrate values given. [11]
Table 5.2: tube side and shell side flowrate and temperature
tube side shell side
flow rate(Kg/sec) 0.6714 6.12
inlet temperature(K) 401 308
outlet temperature(K) 310 318
34
U=800 W/m2
K (assumed) [11]
LMTD= [(401-318)-(310-308)/ln((401-318)/(310-308))]
= 21.74 K
Q = 256454.44 J/sec
Q = UA(LMTD)
A=256454.44/(800 x 21.74)
= 14.74 m2
Material of construction (MOC) of tube = Stainless steel
Tube OD = 0.02 m
Tube ID = 0.016 m
Length of tube (L) = 5 m
Area of tube = ∏ x ID x L
= ∏ x (0.04328) x 5
= 0.303 m2
Total number of tube required
N = total area / area of tube
= 14.74/0.303
= 49
Tube side heat transfer coefficient
Cross section area = n x (∏/4) x ID2
= 49 x (∏/4) x (0.016)2
= 0.0098 m2
Velocity (u) = 0.000692/0.0098
= 0.0706 m/sec
35
Density = 969.972 Kg/m3
Viscosity = 0.000345 Pa.sec
hi = 4200(1.35 + 0.02t)u0.8
/ID0.2
= 4200 (1.35 + 0.02 x 82.5) (0.0706)0.8
/(0.016)0.2
= 3466.1561
Shell side
Water flow rate = 6.12 Kg/sec
Pitch (P) = 1.25 x OD
= 1.25 x 0.02
= 0.025 m
Equivalent diameter de = 1.1/d0 (Pt – 0.907 d0
2
)
= 1.1/0.02[0.0252
– 0.907*0.022
]
= 0.0144 m
Shell inside diameter, Ds :
Db =d0 (Nt /K1 )1/n1
K1 = 0.319 and n1 = 2.142
Db = 0.02(49/0.319)1/2.142
= 0.21 m
Let clearance between shell internal dia and bundle (Db),
Db = 15 mm
Let Ds= 0.21 + 0.015 m
= 0.225 m
Baffle spacing
Bs= 0.4Ds
= 0.4 x 0.225 = 0.09 m
36
Shell side flow area As = (Pt-d0)DsBs/Pt
= (0.025-0.02)/0.025(0.225 x 0.09)
= 0.00405 m2
Gs = m/As
= 6.12 / 0.00405
= 1530 kg/m2
s
Reynolds number,
Re = deGs/µ
= 0.0144 x 1530 / 0.000853
= 25815.515
Prandlt number,
Pr = Cp µ/K
= 4184 x 0.000853 / 0.610
= 5.85
(h0 de/k)= 0.023 Re0.8
Pr0.3
From calculation
h0 = 5594.0996 W/m2
K
Overall heat transfer coefficient U0 ;
1/ U0 =1/h0+1/h0d +d0 ln(d0 /di)/2Kw+d0 l/di hid +d0 l/di hi
=1/5594.0996 + 1/5000 + {0.02 ln(0.02/0.016)}/(2*16) +
(0.02/0.016) x (1/5000) + 0.02/(0.016 x 3466.1561)
U0 = 1648.18 W/m2
K
Shell side pressure drop
Ps =8 Jf(Ds/de)(L/Bs)(ρsus
2
/2)
Jf = 0.03
us= Gs/ρs
= 1530 / 1000
= 1.53 m/sec
= 8 x 0.07 x (0.225/0.0144) x (5/0.09) x (1000 x 1.532
/2) = 234.28 KPa
37
Tube Side pressure drop
Pt = (8Jf(L/di) + 2.5)(ρtut
2
/2)
= ( 8 x 0.008 x (5/0.016) + 2.5)(969.69 x 0.0712
/2)
= 54.99 Pa
5.2.1 Mechanical Design for heat exchanger
Shell and tube type heat exchanger [6]
(a) Shell side
Material carbon steel - (Corrosion allowance- 3mm)
Number of passes – 1
Fluid – water
Working pressure – 0.4 N/mm2
Design pressure – 0.44 N/mm2
Inlet temperature – 25 0
C
Outlet temperature – 85 0
C
Segmental baffles (25% cut ) with tie rods and spacers
Shell thickness;
ts =PD/(2fJ+P)
= 0.44 x 300/((2 x 80 x 0.85)+0.44) + 3 mm
= 3.96 mm
Nozzle thickness (diameter -75mm)
tn=PD/(2fJ-P)
= 0.44 x 75/( 2 x 80 – 0.44)
= 0.21 mm + 3 mm
= 3.21 mm
Head
Head thickness (th) = PCrW/2fJ
Crown radius = 300 mm
Knuckle radius = 30 mm
38
W=1/4(3+ (Rc/R1)1/2
)
= 1/4(3 + (300/30)1/2
)
= 1.54
th = 0.44 x 300 x 1.54 / (2 x 0.85 x 80) + 3mm
= 4.49 mm
Transverse Baffles
Spacing between baffles= 0.4Ds
= 0.4 x 0.3
= 0.12 m
Thickness of baffles = 5mm
Tube Side
Tube and tube sheet material - stainless steel
Number of tubes – 49
Outside diameter – 20 mm
Length – 5 m
Tube pitch - 0.025 m
Working pressure – 0.5 N/mm2
Design pressure – 0.55 N/mm2
Inlet temperature – 1280
C
Outlet temperature - 370
C
Permissible stress – 74.5 N/mm2
tf =PD0/(2fJ+P)
= 0.55 x 20 / (2 x 74.5 x 0.85 + 0.55)
= 0.086 mm
No corrosion allowance, since the tubes are of stainless steel.
Design of Gasket and Bolt Size [6]
Gasket material – flat metal jacketed, asbestos fill (iron or soft steel)
Gasket factor, m= 3.75
39
Minimum design stress = 52.4 N/mm2
Basic gasket seating width – b 0
Internal dia. Of Gasket – 300 mm
Do/Di = ((Y-Pm)/(Y-P(m+1)))0.5
= ((52.4 – 0.44 x 3.75)/(52.4 – 0.44 x 4.75))0.5
= 1.0043
Do = 301.29 m
N = (301.29 - 300)/2 = 0.502 mm use 35mm
b0 = ½N = 0.0175 m
G= (301.29 + 300)/2
= 300.65 mm
Effective Gasket seating width, b= 0.5b0
1/2
= 2.09 mm
Bolts
Minimum bolt load at atm. Condition, Wm1 = 3.14bGYa
= 3.14 x 2.09 x 300.65 x 52.4
= 103635.28 N
At operating condition,
Wm2=3.14(2b)GmP+3.14G2
P
= 3.14 x 2 x 2.09 x 300.65 x 3.75 x 0.44 +3.14 x 301.652
x 0.44
= 131402.52 N
Wm1 < Wm2 so Wm2 is controlling load
Number of bolts= 300.65/(2.5*10)
= 12
40
Am2= 131402.52/80
= 1642.53 mm2
Diameter of bolts= [(Am2/no. of bolts) x 3.14/4]1/2
= [(1642.53)/12 x (4/3.14)]1/2
=13.19 mm
Bolt area, Ab = 2 x 3.14 x YaGN/fa
= 2 x 3.14 x 52.48 x 300.65 x 35 / 80
= 43350.36 mm2
Pitch of bolts = 4.75*18
= 85.6 mm
Pitch circle dia.= (85.6*12)/3.14
= 327.13 mm
Flange Thickness,
K= 1/[0.3+1.5WmhG/HG]
= 1/[0.3 + 1.5 x 131402.52 x 13.4 /( 31221.65 X 300.65)]
= 1.75
tf = G(p/kf)1/2
+c
= 300.65 x (0.44/1.75/80) ½
+ 3
= 23.99 mm
Use 24 mm
5.3 Distillation column Design:
Operating pressure at top = 1 atm = 101.325 KPa
Reflux ratio = 3.49
Number of plates = 40
Distillation molar rate D = 0.0327 Kmol/sec
Liquid molar rate L= D x R
= 0.0327 x 3.49
= 0.114 Kmol/sec
41
Vapor molar rate = D x (R + 1)
= 0.0327 x (3.49 + 1)
= 0.1468 Kmol/sec
Vapor density ρv = 3.91 Kg/m3
Liquid density ρl = 653.64 Kg/m3
Vapor and liquid flowrate is given in table 5.2
Table 5.3: vapor and liquid flowrate
vapor liquid
molar flow rate 0.1468 0.1141
mass rate 10.8649 8.4451
vol. rate 2.7750 0.0129
Vload = Q [ρv / (ρl - ρv)]0.5
= 2.77 [ 3.91/(653.64 – 3.91)]0.5
= 0.2154 m3
/sec
q = 0.0129 m3
/sec
Single pass
Dt = 1.7 m (from graph of Vload and liquid flowrate)
System factor S = 1
Flooding factor = 0.8 ( 80 % flooding)
Flow path length L = 0.75 x Dt / number of pass
= 0.75 x 1.7 / 1
= 1.275 m
C* = 0.125
C = S x C*
= 1 x 0.125
= 0.125
Aamin = [ vapor load + 1.36qL]/ (C x F)
= [ 0.2154 + 1.36 x 0.0129 x 1.275 ]/(0.125 x 0.8) = 2.37 m2
42
U* = 0.170 m/sec
U* = 0.007(ρl - ρv)0.5
= 0.007 x (653.64 – 3.91)
= 0.178 m/sec
U* = 0.008 x (Ts (ρl - ρv)) 0.5
= 0.008 x ( 0.457 (653.64 – 3.91)) 0.5
= 0.137 m/sec
Use smallest value
U* = 0.137 m/sec
u = U* x S
= 0.137 x 1
= 0.137 m/sec
Admin = q/(u x f)
= 0.0129/(0.137 x 0.8)
= 0.1171 m2
Admin < 0.11 x Aa
0.1171 < 0.11 x 0.1171 m2
0.1171 < 0.2607 m2
Admin = 2 x 0.1171
= 0.2342 m2
At = Aamin + 2 Admin
= 2.37 + 2 x 0.2342
= 2.84 m2
Atmin = 1.28 Vload /(0.8 x 0.125)
= 1.28 x 0.2154/ (0.8 x 0.125)
= 2.75 m2
At > Atmin
Take At = 2.84 m2
43
Diameter = (At x 4 / 3.14)0.5
= (2.84 x 4 / 3.14)0.5
= 1.9 m
Ad/(AtN) = 0.2342/(2.84 x 1)
= 0.0823
Weir length
Lw/Dt = 0.657
Lw = 0.657 x 1.9
= 1.25 m
Weir hight
H/ Dt = 0.12
H = 0.12 x 1.9
= 0.228 m
Number of valve units
Assume 120-175 units/ m2
active area
Active area = 2.37 m2
Number of units = 285 to 417 units/plate
Assume
Number of units = 350 units/plate
Holes area = 350/845
= 0.4142 m2
Pressure drop
Tray MOC – MS density = 7700 kg/m3
Thickness of tray = 14 gauge = 0.188cm
Type of valve V4 K1 = 2.73 K2 = 13.6
∆Pdry = 0.135 tn (ρm /ρl) + K1Vn
2
(ρv /ρl)
= 0.135 (0.188)(7700/653.64) + 2.73 (6.692
)(3.91/653.64)
= 1.032 cm liquid
44
∆Pdry = K2Vn
2
(ρv /ρl)
= 13.6 (6.692
)(3.91/653.64)
= 3.65 cm liquid
∆Pt = ∆Pdry + 55.4(q/Lw)0.67
+ 0.04hw
= 3.65 + 55.4(0.0129/1.25)0.67
+ 0.04 x 50
= 8.44 cm liquid
= 0.076 psi
Hde = 55.4(q/Lw)0.67
+ 0.1 hw + (∆Pt + 1.66)( ρl / (ρl - ρv))
= 55.4(0.0129/1.25)0.67
+ 0.1 x 50 + (8.44 + 1.66)(653.64/(653.64-3.91))
= 17.96 cm liquid < 0.6 TS
%Flooding = Vload / (0.78ATC)
= 0.2154 / (0.78 x 2.84 x0.125)
= 77.60%
5.3.1 Mechanical design of distillation column
Mechanical design of distillation column including support. [14]
Operating pressure = 101.325 Kpa
Design pressure = 1.1 x 101.325 = 111.45 Kpa = 0.11145 N/mm2
Design temperature = 423 K
MOC = carbon steel
Diameter = 1900 mm
Thickness of the column
tc = PD/(2fJ - P)
= 0.44 x 300/((2 x 80 x 0.85) - 0.44) + 3 mm
= 3.065 mm
But take 8mm
Head
Torispherical head [6]
Head thickness (th) = PCrW/2fJ
Crown radius = 1900 mm
45
Knuckle radius = 190 mm
W=1/4(3+ (Rc/R1)1/2
)
= 1/4(3 + (1900/190)1/2
)
= 1.54
th = 0.11145 x 1900 x 1.54 / (2 x 0.85 x 80) + 3mm
= 5.39 mm
Use 8 mm same as column diameter
Total vessel dead load
!=("!+0.8#$ )%&'
= 1.15 x 3.14 x 1.9 x (19 + 0.8 x 1.9) x 0.008 x 7700 x 9.81
= 119736.89 N
Column support design
Skirt diameter = 1900mm
Stress due to dead load
Fds = W/(D + t)t
= 119736.89/(3.14 x (1900 + t) x t)
Stress due to wind load
Fws = 11071.56/(3.14 x (1900 + t) x t)
Total compressive stess = Fds + Fws
Maximum stress = 0.125Et/D = Fds + Fws
E = 190 N/mm2
By solving this
t = 41.42 mm
So take thickness 45 mm
For this thickness
Fcompressive < Fs
Ftensile < Fs

Más contenido relacionado

La actualidad más candente

Diethyl Ether (DEE): Cost estimation of Plant
Diethyl Ether (DEE): Cost estimation of PlantDiethyl Ether (DEE): Cost estimation of Plant
Diethyl Ether (DEE): Cost estimation of PlantPratik Patel
 
Ethylene Plant Design Considerations
Ethylene Plant Design ConsiderationsEthylene Plant Design Considerations
Ethylene Plant Design ConsiderationsGerard B. Hawkins
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments DesignPratik Patel
 
reactive distillation
 reactive distillation reactive distillation
reactive distillationJayJawalge
 
Design of-absorption-column
Design of-absorption-columnDesign of-absorption-column
Design of-absorption-columnAli Hassan
 
Process Calculation - simple distillation
Process Calculation - simple distillationProcess Calculation - simple distillation
Process Calculation - simple distillationChandran Udumbasseri
 
Diethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutDiethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutPratik Patel
 
Adipic Acid Plant Energy Balance
Adipic Acid Plant Energy BalanceAdipic Acid Plant Energy Balance
Adipic Acid Plant Energy BalanceIshaneeSharma
 
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
Episode 43 :  DESIGN of Rotary Vacuum Drum Filter Episode 43 :  DESIGN of Rotary Vacuum Drum Filter
Episode 43 : DESIGN of Rotary Vacuum Drum Filter SAJJAD KHUDHUR ABBAS
 
Design of packed columns
Design of packed columnsDesign of packed columns
Design of packed columnsalsyourih
 
Design of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxDesign of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxAathiraS10
 
Shell and tube heat Exchanger Design.pptx
Shell and tube heat Exchanger Design.pptxShell and tube heat Exchanger Design.pptx
Shell and tube heat Exchanger Design.pptxsandeepsharma432939
 
VLE Data - Selection and Use
VLE Data - Selection and UseVLE Data - Selection and Use
VLE Data - Selection and UseGerard B. Hawkins
 
Methanol Plant Design
Methanol Plant DesignMethanol Plant Design
Methanol Plant DesignMaan M
 
Chemical Design of Extraction Column
Chemical Design of Extraction ColumnChemical Design of Extraction Column
Chemical Design of Extraction ColumnAmirul Izan
 

La actualidad más candente (20)

Diethyl Ether (DEE): Cost estimation of Plant
Diethyl Ether (DEE): Cost estimation of PlantDiethyl Ether (DEE): Cost estimation of Plant
Diethyl Ether (DEE): Cost estimation of Plant
 
Ethylene Plant Design Considerations
Ethylene Plant Design ConsiderationsEthylene Plant Design Considerations
Ethylene Plant Design Considerations
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments Design
 
Process calculation condensation
Process calculation  condensationProcess calculation  condensation
Process calculation condensation
 
289109277 design-project-1-final
289109277 design-project-1-final289109277 design-project-1-final
289109277 design-project-1-final
 
reactive distillation
 reactive distillation reactive distillation
reactive distillation
 
Design of-absorption-column
Design of-absorption-columnDesign of-absorption-column
Design of-absorption-column
 
Process Calculation - simple distillation
Process Calculation - simple distillationProcess Calculation - simple distillation
Process Calculation - simple distillation
 
Antoine coefficient table
Antoine coefficient tableAntoine coefficient table
Antoine coefficient table
 
Diethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutDiethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant Layout
 
conversion and reactor sizing
conversion and reactor sizingconversion and reactor sizing
conversion and reactor sizing
 
Adipic Acid Plant Energy Balance
Adipic Acid Plant Energy BalanceAdipic Acid Plant Energy Balance
Adipic Acid Plant Energy Balance
 
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
Episode 43 :  DESIGN of Rotary Vacuum Drum Filter Episode 43 :  DESIGN of Rotary Vacuum Drum Filter
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
 
Design of packed columns
Design of packed columnsDesign of packed columns
Design of packed columns
 
Design of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptxDesign of Shell & tube Heat Exchanger.pptx
Design of Shell & tube Heat Exchanger.pptx
 
Packed bed flooding
Packed bed floodingPacked bed flooding
Packed bed flooding
 
Shell and tube heat Exchanger Design.pptx
Shell and tube heat Exchanger Design.pptxShell and tube heat Exchanger Design.pptx
Shell and tube heat Exchanger Design.pptx
 
VLE Data - Selection and Use
VLE Data - Selection and UseVLE Data - Selection and Use
VLE Data - Selection and Use
 
Methanol Plant Design
Methanol Plant DesignMethanol Plant Design
Methanol Plant Design
 
Chemical Design of Extraction Column
Chemical Design of Extraction ColumnChemical Design of Extraction Column
Chemical Design of Extraction Column
 

Destacado

Industrial production of diethyl ether
Industrial production of diethyl etherIndustrial production of diethyl ether
Industrial production of diethyl etherrita martin
 
Diethyl Ether (DEE): Introduction
Diethyl Ether (DEE): IntroductionDiethyl Ether (DEE): Introduction
Diethyl Ether (DEE): IntroductionPratik Patel
 
Diethyl Ether (DEE): The Conclusion
Diethyl Ether (DEE): The ConclusionDiethyl Ether (DEE): The Conclusion
Diethyl Ether (DEE): The ConclusionPratik Patel
 
Diethyl Ether (DEE): Safety and Health Consideration
Diethyl Ether (DEE): Safety and Health ConsiderationDiethyl Ether (DEE): Safety and Health Consideration
Diethyl Ether (DEE): Safety and Health ConsiderationPratik Patel
 
Process design for chemical engineers
Process design for chemical engineersProcess design for chemical engineers
Process design for chemical engineersAmanda Ribeiro
 
Diesel Production: Material Balance
Diesel Production: Material BalanceDiesel Production: Material Balance
Diesel Production: Material BalancePratik Patel
 
Diesel Production: Process Flow Diagram
Diesel Production: Process Flow DiagramDiesel Production: Process Flow Diagram
Diesel Production: Process Flow DiagramPratik Patel
 
Diesel Production: Site Location
Diesel Production: Site LocationDiesel Production: Site Location
Diesel Production: Site LocationPratik Patel
 
Diesel Production: Energy Balance
Diesel Production: Energy BalanceDiesel Production: Energy Balance
Diesel Production: Energy BalancePratik Patel
 
Introduction to Diesel fuel
Introduction to Diesel fuelIntroduction to Diesel fuel
Introduction to Diesel fuelPratik Patel
 
Diesel Production: Cost Estimation
Diesel Production: Cost EstimationDiesel Production: Cost Estimation
Diesel Production: Cost EstimationPratik Patel
 
Diesel Production: Plant Layout
Diesel Production: Plant LayoutDiesel Production: Plant Layout
Diesel Production: Plant LayoutPratik Patel
 
Diesel fuel Literature Review
Diesel fuel Literature ReviewDiesel fuel Literature Review
Diesel fuel Literature ReviewPratik Patel
 
Methanol Plant Dme Conversion Pdf
Methanol Plant Dme Conversion PdfMethanol Plant Dme Conversion Pdf
Methanol Plant Dme Conversion Pdfmkoenig1209
 
DME Production Process Flow Diagram
DME Production Process Flow DiagramDME Production Process Flow Diagram
DME Production Process Flow DiagramMari Price
 
Introduction to Chemical Engineering
Introduction to Chemical EngineeringIntroduction to Chemical Engineering
Introduction to Chemical EngineeringSAFFI Ud Din Ahmad
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxidepatrickconneran
 

Destacado (18)

Industrial production of diethyl ether
Industrial production of diethyl etherIndustrial production of diethyl ether
Industrial production of diethyl ether
 
Diethyl Ether (DEE): Introduction
Diethyl Ether (DEE): IntroductionDiethyl Ether (DEE): Introduction
Diethyl Ether (DEE): Introduction
 
Diethyl Ether (DEE): The Conclusion
Diethyl Ether (DEE): The ConclusionDiethyl Ether (DEE): The Conclusion
Diethyl Ether (DEE): The Conclusion
 
Diethyl Ether (DEE): Safety and Health Consideration
Diethyl Ether (DEE): Safety and Health ConsiderationDiethyl Ether (DEE): Safety and Health Consideration
Diethyl Ether (DEE): Safety and Health Consideration
 
Process design for chemical engineers
Process design for chemical engineersProcess design for chemical engineers
Process design for chemical engineers
 
Diesel Production: Material Balance
Diesel Production: Material BalanceDiesel Production: Material Balance
Diesel Production: Material Balance
 
Diesel Production: Process Flow Diagram
Diesel Production: Process Flow DiagramDiesel Production: Process Flow Diagram
Diesel Production: Process Flow Diagram
 
Diesel Production: Site Location
Diesel Production: Site LocationDiesel Production: Site Location
Diesel Production: Site Location
 
Diesel Production: Energy Balance
Diesel Production: Energy BalanceDiesel Production: Energy Balance
Diesel Production: Energy Balance
 
Introduction to Diesel fuel
Introduction to Diesel fuelIntroduction to Diesel fuel
Introduction to Diesel fuel
 
Diesel Production: Cost Estimation
Diesel Production: Cost EstimationDiesel Production: Cost Estimation
Diesel Production: Cost Estimation
 
Diesel Production: Plant Layout
Diesel Production: Plant LayoutDiesel Production: Plant Layout
Diesel Production: Plant Layout
 
Diesel fuel Literature Review
Diesel fuel Literature ReviewDiesel fuel Literature Review
Diesel fuel Literature Review
 
Dimethyl ether (dme)
Dimethyl ether (dme)Dimethyl ether (dme)
Dimethyl ether (dme)
 
Methanol Plant Dme Conversion Pdf
Methanol Plant Dme Conversion PdfMethanol Plant Dme Conversion Pdf
Methanol Plant Dme Conversion Pdf
 
DME Production Process Flow Diagram
DME Production Process Flow DiagramDME Production Process Flow Diagram
DME Production Process Flow Diagram
 
Introduction to Chemical Engineering
Introduction to Chemical EngineeringIntroduction to Chemical Engineering
Introduction to Chemical Engineering
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxide
 

Similar a Diethyl Ether (DEE): Equipments Design

LeadRubberBearing2.pptx
LeadRubberBearing2.pptxLeadRubberBearing2.pptx
LeadRubberBearing2.pptxTonyOng26
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingYash Patel
 
Manufacture of nitrobenzene
Manufacture of nitrobenzeneManufacture of nitrobenzene
Manufacture of nitrobenzeneparthdhurvey
 
Designofcondenser 130801223803-phpapp02
Designofcondenser 130801223803-phpapp02Designofcondenser 130801223803-phpapp02
Designofcondenser 130801223803-phpapp02ThamizhmaniT
 
Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU Bikash Gyawali
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical linerHridoy Saha
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3Kifayath Chowdhury
 
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdfVertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdfPrashantDubal2
 
Benzene Distillation column.pptx presenatation.pptx
Benzene Distillation column.pptx presenatation.pptxBenzene Distillation column.pptx presenatation.pptx
Benzene Distillation column.pptx presenatation.pptxHatifAlam2
 
Perancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionPerancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionRicco Riyan Kurniawan
 
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET Journal
 
Assignment [4] machining with solutions
Assignment [4]  machining with solutionsAssignment [4]  machining with solutions
Assignment [4] machining with solutionsmoradmoro
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Hamza Waheed
 

Similar a Diethyl Ether (DEE): Equipments Design (20)

Condenser design
Condenser designCondenser design
Condenser design
 
LeadRubberBearing2.pptx
LeadRubberBearing2.pptxLeadRubberBearing2.pptx
LeadRubberBearing2.pptx
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending Scheduling
 
Manufacture of nitrobenzene
Manufacture of nitrobenzeneManufacture of nitrobenzene
Manufacture of nitrobenzene
 
Design of condenser
Design of condenserDesign of condenser
Design of condenser
 
Designofcondenser 130801223803-phpapp02
Designofcondenser 130801223803-phpapp02Designofcondenser 130801223803-phpapp02
Designofcondenser 130801223803-phpapp02
 
Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical liner
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3
 
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdfVertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
 
Benzene Distillation column.pptx presenatation.pptx
Benzene Distillation column.pptx presenatation.pptxBenzene Distillation column.pptx presenatation.pptx
Benzene Distillation column.pptx presenatation.pptx
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
Perancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionPerancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene Production
 
Baja kuda kuda
Baja kuda kudaBaja kuda kuda
Baja kuda kuda
 
Sm chap01
Sm chap01Sm chap01
Sm chap01
 
project ppt
project pptproject ppt
project ppt
 
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
 
Assignment [4] machining with solutions
Assignment [4]  machining with solutionsAssignment [4]  machining with solutions
Assignment [4] machining with solutions
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
 
Panel h
Panel hPanel h
Panel h
 

Último

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Último (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

Diethyl Ether (DEE): Equipments Design

  • 1. 23 CHAPTER 5 EQUIPMENT DESIGN In this chapter, detailed equipment design and mechanical design of 5.1 Fixed Bed Catalytic Reactor Process Design: Reaction temperature =250 0 C ( 523K) Catalyst: γ - alumina Density of catalyst particle: 1392 kg/m3 [8] Catalyst porosity: 0.52 [8] Type of reactor: Shell and tube heat exchanger type in which catalyst is placed inside the tube. Reaction is exothermic: It is carried out in isothermal manner. Water is to be circulated in liquid form on shell side to maintain the isothermal condition. Mass of catalyst required in commercial scale plant = 6579.711 kg Superficial velocity of feed gas V=0.802 m/s Capacity of plant =50000 MTA of diethyl ether (DEE) Let no. of working days per annum=340 days Production rate of diethyl ether (DEE) = (50000*1000)/(340*24) =6127.45 Kg/hr !""= #$%%&'()* 2 &'()* 2 + #1&'()*&,-(% (5.1) [3] "./03"4"= #%(567%8%&'()* &'()* 2 + #1&'()*&,-(% + #2&'()* 2 + #9&,-(% 2 Design equation (5.2) [3] : ; = < !> ?@AB CCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC?DE9B [4]
  • 2. 24 In table 5.1 conversion of ethanol and rate of reaction data is given. Unit of rate of reaction is mol/(gm catalyst sec) Table 5.1: rate of reaction and conversion data r (total) 1/r Ethanol conversion 2.77216E-06 360729.1 0 2.24531E-06 445373.6 0.1 1.81423E-06 551197.8 0.2 1.45502E-06 687277 0.3 1.15111E-06 868729.7 0.4 8.90654E-07 1122770 0.5 8.31259E-07 1202994 0.525 4.67523E-07 2138934 0.7 2.9333E-07 3409130 0.8 From the graph (appendix A) Area= 340000 unit Weight of catalyst= 6579711 gm = 6579.711 Kg Bulk density =0.9333 gm/cc [8] Volume = 6579.711/9333 = 7.049942 m3 Feed rate = 0.1382 Kmol/sec = 0.1382 x 43.312 = 5.99 Kg/sec
  • 3. 25 Density = PM/RT = (1500 x 43.312) / ( 8.314 x 523 ) = 14.94 Kg/m3 Feed rate = 5.99 / 14.94 = 0.401 m3 /sec Superficial velocity = 0.805 m/sec Total Crosse section area = feed rate / space = 0.401 / 0.805 = 0.499 m2 MOC of tube = Stainless steel Tube OD = 0.0508 m Tube ID = 0.04328 m Crosse section area of tube = (∏/4) x ID2 = (∏/4) x (0.04328)2 = 0.00147 m2 Total number of tube required N = Total Crosse section area / Crosse section area of tube = 0.499/0.00147 = 340 Length of the tube (L) =total volume / (N x Crosse section area of tube) = 7.05 / (340 x 0.00147) = 14 m
  • 4. 26 Area = N x ∏ x OD x L = 340 x ∏ x 0.0508 x 14 = 764.78 m2 Heat duty (Q) = 2445180.91 J/sec Calculation of fixed bed side film coefficient hi ; dp = diameter of catalyst = 0.003 m Pipe diameter dt = 0.04328 m dp/dt = 0.003/0.04328 = 0.06931 (hidt /k) =0.813 e-6dp/dt ( dp G/µ) 0.9 Thermal conductivity K = 0.04366 W/mK Viscosity µ = 1.58235 x 10-5 pa.sec Mass velocity G = 0.87 Kg/m2 sec On calculation hi = 416.32637 W/m2 K hi dp/k = 3.6(dpG/µ ε)0.365 on calculation hi = 49.789923 W/m2 K Take lesser value hi = 49.789923 W/m2 K
  • 5. 27 Calculation of shell side heat transfer, h0 Shell side heat transfer coefficient calculated here [11] Tube pitch Pt =1.25d0 =1.25 x 0.0508 = 0.0635 m Type of arrangement = Equilateral triangular Equivalent diameter de = 1.1/d0 (Pt – 0.907 d0 2 ) = 1.1/0.0508[0.06352 – 0.907*0.0508 2 ] = 0.03663 m Shell side mass flow rate m ; ∆H = m*Cp*∆T Here coolant used is dowtherm Q because operating temperature is 523 K and dowtherm Q is stable up to 603 K ( Properties from dowtherm Q product technical data) Properties of dowtherm Q Cp = 1811 J/Kg K Viscosity µ = 1.28 x 10-3 pa.sec Thermal conductivity K = 0.1156 W/mK ∆T= 60 K m = 2445180.91/(1811 x 60) = 22.5 Kg/s Density = 927.6 Kg/ m3 Circulation rate qv = (22.5/927.6) = 0.024 m3 /sec
  • 6. 28 Shell inside diameter, Ds : Db =d0 (Nt /K1 )1/n1 K1 = 0.319 and n1 = 2.142 Db = 50.8(340/0.319)1/2.142 = 1.315m Let clearance between shell internal dia and bundle (Db), Db = 15 mm Let Ds= 1.315 + 0.015 m = 1.330 m Baffle spacing Bs= 0.4Ds = 0.4 x 1.33 = 0.532m Shell side flow area As = (Pt-d0)DsBs/Pt = (0.0635-0.0508)/0.0635(1.330 x 0.532) = 0.1416 m2 Gs = m/As = 22.5 / 0.1416 = 158.83 kg/m2 sec Reynolds number, Re = deGs/µ = 0.03669 x 158.83 / 0.00128 = 4545.36 Prandlt number, Pr = Cp µ/K
  • 7. 29 = 1811 x 0.00128 / 0.1156 = 20.05 (h0 de/k)= 0.027 Re0.8 Pr0.3 From calculation h0 = 150.50 W/m2 K Overall heat transfer coefficient U0 ; 1/ U0 =1/h0+1/h0d +d0 ln(d0 /di)/2Kw+d0 l/di hid +d0 l/di hi =1/150.50 + 1/5000 + {0.0508 ln(0.0508/0.04328)}/(2*16) + (0.0508/0.04328)*(1/5000) + 0.0508/(0.04328 x 49.78) U0 = 37.06 W/m2 K Shell side pressure drop Ps =8 Jf(Ds/de)(L/Bs)(ρsus 2 /2) Jf = 0.07 from Jf vs Nre graph [11] us= Gs/ρs = 158.83 / 927.6 = 0.171 m/sec = 8*0.07 x (1.330/0.03663) x (14/0.5323) x ( 985.728 x 0.0692 /2) = 7335.7 Pa Tube Side pressure drop Pt =8 Jf(L/di)(ρsus 2 /2) Jf = 0.03 from Jf vs Nre graph [11] =8 x 0.03 x (14/0.04328) x (14.95 x 0.8022 )/2 = 0.3760672 KPa Pressure drop across the bed Blake – plummer equation ! =" 1.75(1 # $)%& ' $*+, " P = 18.07 KPa
  • 8. 30 Total tube side pressure drop Pt = 18.45 KPa 5.1.1 Mechanical Design of reactor Shell and tube type reactor [6] (a) Shell side Material carbon steel - (Corrosion allowance- 3mm) Number of passes – 1 Fluid – dowtherm Q Working pressure – 0.3 N/mm2 Design pressure – 0.33 N/mm2 Inlet temperature – 25 0 C Outlet temperature – 85 0 C Segmental baffles (25% cut ) with tie rods and spacers Maximum allowable stress - 80 N/mm2 Shell thickness; [6] ts =PD/(2fJ+P) = 0.33 x 1400/((2 x 80 x 0.85)+0.33) + 3 mm = 6.38 mm Nozzle thickness (diameter -75mm) tn=PD/(2fJ-P) = 0.33 x 75/( 2 x 80 – 0.33) = 0.155 mm + 3 mm = 3.155 mm Head Head thickness (th) = PCrW/2fJ Crown radius = 1400 mm Knuckle radius = 140 mm
  • 9. 31 W=1/4(3+ (Rc/R1)1/2 ) = 1/4(3 + (1400/140)1/2 ) = 1.54 th = 0.33 x 1400 x 1.54 / (2 x 0.85 x 80) + 3mm = 8.23mm Transverse Baffles Spacing between baffles= 0.4Ds = 0.4 x 1.4 = 0.56m Thickness of baffles = 5mm Tube Side [6] Tube and tube sheet material - stainless steel Number of tubes – 340 Outside diameter – 50.8 mm Length – 14m Tube pitch - 0.0635m Working pressure – 1.5 N/mm2 Design pressure – 1.65 N/mm2 Inlet temperature – 2500 C Outlet temperature - 2500 C Permissible stress – 74.5 N/mm2 tf =PD0/(2fJ+P) = 1.65 x 50.8 / (2 x 74.5 x 0.85 + 1.65) = 0.65 mm No corrosion allowance, since the tubes are of stainless steel. Design of Gasket and Bolt Size [6] Gasket material – flat metal jacketed, asbestos fill (iron or soft steel) Gasket factor, m= 3.75 Minimum design stress = 52.4 N/mm2
  • 10. 32 Basic gasket seating width – b 0 Internal dia. Of Gasket – 1400 mm Do/Di = ((Y-Pm)/(Y-P(m+1)))0.5 = ((52.4 – 0.33 x 3.75)/(52.4 – 0.33 x 4.75))0.5 = 1.0032 Do = 1.4045 m N = (1.4045-1400)/2 = 0.0022648mm use 35mm b0 = ½N = 0.0175mm G= (1.4045+1400)/2 = 1.4022m Effective Gasket seating width, b= 0.5b0 1/2 = 2.09 mm Bolts Minimum bolt load at atm. Condition, Wm1 = 3.14bGYa = 3.14 x 2.09 x 1402.2 x 52.4 = 483360.87 N At operating condition, Wm2=3.14(2b)GmP+3.14G2 P = 3.14 x 2 x 2.09 x 1402.2 x 3.75 x 0.33 +3.14 x 1402.22 x 0.33 = 532176.24 N Wm1 < Wm2 so Wm2 is controlling load Number of bolts = 1402.2/(2.5*10) = 56 Am2= 532176.24/80 = 6652.203 mm2
  • 11. 33 Diameter of bolts = [(Am2/no. of bolts) x 3.14/4]1/2 = [(6652.203)/56 x (4/3.14)]1/2 =12.29 mm Bolt area, Ab = 2 x 3.14 x YaGN/fa = 2 x 3.14 x 52.48 x 1402.2 x 35 / 80 =202204.36 mm2 Pitch of bolts = 4.75*18 = 85.6 mm Pitch circle dia.= (85.6*56)/3.14 =1526.62mm Flange Thickness, K= 1/[0.3+1.5WmhG/HG] = 1/[0.3 + 1.5 x 532176.24 x 62.52136 /( 509382.1 X 1402.2)] = 2.7 tf = G(p/kf)1/2 +c = 1402.2 x (0.33/2.7/80) ½ + 3 = 70.62 mm 5.2 Heat exchanger Design For heat exchanger tube side is waste water and shell side is cooling water is used. Here we assume over all heat transfer coefficient (U) is 800 W/m2 K.In table 5.1 tube side and shell side fluid inlet, outlet temperature and mass flowrate values given. [11] Table 5.2: tube side and shell side flowrate and temperature tube side shell side flow rate(Kg/sec) 0.6714 6.12 inlet temperature(K) 401 308 outlet temperature(K) 310 318
  • 12. 34 U=800 W/m2 K (assumed) [11] LMTD= [(401-318)-(310-308)/ln((401-318)/(310-308))] = 21.74 K Q = 256454.44 J/sec Q = UA(LMTD) A=256454.44/(800 x 21.74) = 14.74 m2 Material of construction (MOC) of tube = Stainless steel Tube OD = 0.02 m Tube ID = 0.016 m Length of tube (L) = 5 m Area of tube = ∏ x ID x L = ∏ x (0.04328) x 5 = 0.303 m2 Total number of tube required N = total area / area of tube = 14.74/0.303 = 49 Tube side heat transfer coefficient Cross section area = n x (∏/4) x ID2 = 49 x (∏/4) x (0.016)2 = 0.0098 m2 Velocity (u) = 0.000692/0.0098 = 0.0706 m/sec
  • 13. 35 Density = 969.972 Kg/m3 Viscosity = 0.000345 Pa.sec hi = 4200(1.35 + 0.02t)u0.8 /ID0.2 = 4200 (1.35 + 0.02 x 82.5) (0.0706)0.8 /(0.016)0.2 = 3466.1561 Shell side Water flow rate = 6.12 Kg/sec Pitch (P) = 1.25 x OD = 1.25 x 0.02 = 0.025 m Equivalent diameter de = 1.1/d0 (Pt – 0.907 d0 2 ) = 1.1/0.02[0.0252 – 0.907*0.022 ] = 0.0144 m Shell inside diameter, Ds : Db =d0 (Nt /K1 )1/n1 K1 = 0.319 and n1 = 2.142 Db = 0.02(49/0.319)1/2.142 = 0.21 m Let clearance between shell internal dia and bundle (Db), Db = 15 mm Let Ds= 0.21 + 0.015 m = 0.225 m Baffle spacing Bs= 0.4Ds = 0.4 x 0.225 = 0.09 m
  • 14. 36 Shell side flow area As = (Pt-d0)DsBs/Pt = (0.025-0.02)/0.025(0.225 x 0.09) = 0.00405 m2 Gs = m/As = 6.12 / 0.00405 = 1530 kg/m2 s Reynolds number, Re = deGs/µ = 0.0144 x 1530 / 0.000853 = 25815.515 Prandlt number, Pr = Cp µ/K = 4184 x 0.000853 / 0.610 = 5.85 (h0 de/k)= 0.023 Re0.8 Pr0.3 From calculation h0 = 5594.0996 W/m2 K Overall heat transfer coefficient U0 ; 1/ U0 =1/h0+1/h0d +d0 ln(d0 /di)/2Kw+d0 l/di hid +d0 l/di hi =1/5594.0996 + 1/5000 + {0.02 ln(0.02/0.016)}/(2*16) + (0.02/0.016) x (1/5000) + 0.02/(0.016 x 3466.1561) U0 = 1648.18 W/m2 K Shell side pressure drop Ps =8 Jf(Ds/de)(L/Bs)(ρsus 2 /2) Jf = 0.03 us= Gs/ρs = 1530 / 1000 = 1.53 m/sec = 8 x 0.07 x (0.225/0.0144) x (5/0.09) x (1000 x 1.532 /2) = 234.28 KPa
  • 15. 37 Tube Side pressure drop Pt = (8Jf(L/di) + 2.5)(ρtut 2 /2) = ( 8 x 0.008 x (5/0.016) + 2.5)(969.69 x 0.0712 /2) = 54.99 Pa 5.2.1 Mechanical Design for heat exchanger Shell and tube type heat exchanger [6] (a) Shell side Material carbon steel - (Corrosion allowance- 3mm) Number of passes – 1 Fluid – water Working pressure – 0.4 N/mm2 Design pressure – 0.44 N/mm2 Inlet temperature – 25 0 C Outlet temperature – 85 0 C Segmental baffles (25% cut ) with tie rods and spacers Shell thickness; ts =PD/(2fJ+P) = 0.44 x 300/((2 x 80 x 0.85)+0.44) + 3 mm = 3.96 mm Nozzle thickness (diameter -75mm) tn=PD/(2fJ-P) = 0.44 x 75/( 2 x 80 – 0.44) = 0.21 mm + 3 mm = 3.21 mm Head Head thickness (th) = PCrW/2fJ Crown radius = 300 mm Knuckle radius = 30 mm
  • 16. 38 W=1/4(3+ (Rc/R1)1/2 ) = 1/4(3 + (300/30)1/2 ) = 1.54 th = 0.44 x 300 x 1.54 / (2 x 0.85 x 80) + 3mm = 4.49 mm Transverse Baffles Spacing between baffles= 0.4Ds = 0.4 x 0.3 = 0.12 m Thickness of baffles = 5mm Tube Side Tube and tube sheet material - stainless steel Number of tubes – 49 Outside diameter – 20 mm Length – 5 m Tube pitch - 0.025 m Working pressure – 0.5 N/mm2 Design pressure – 0.55 N/mm2 Inlet temperature – 1280 C Outlet temperature - 370 C Permissible stress – 74.5 N/mm2 tf =PD0/(2fJ+P) = 0.55 x 20 / (2 x 74.5 x 0.85 + 0.55) = 0.086 mm No corrosion allowance, since the tubes are of stainless steel. Design of Gasket and Bolt Size [6] Gasket material – flat metal jacketed, asbestos fill (iron or soft steel) Gasket factor, m= 3.75
  • 17. 39 Minimum design stress = 52.4 N/mm2 Basic gasket seating width – b 0 Internal dia. Of Gasket – 300 mm Do/Di = ((Y-Pm)/(Y-P(m+1)))0.5 = ((52.4 – 0.44 x 3.75)/(52.4 – 0.44 x 4.75))0.5 = 1.0043 Do = 301.29 m N = (301.29 - 300)/2 = 0.502 mm use 35mm b0 = ½N = 0.0175 m G= (301.29 + 300)/2 = 300.65 mm Effective Gasket seating width, b= 0.5b0 1/2 = 2.09 mm Bolts Minimum bolt load at atm. Condition, Wm1 = 3.14bGYa = 3.14 x 2.09 x 300.65 x 52.4 = 103635.28 N At operating condition, Wm2=3.14(2b)GmP+3.14G2 P = 3.14 x 2 x 2.09 x 300.65 x 3.75 x 0.44 +3.14 x 301.652 x 0.44 = 131402.52 N Wm1 < Wm2 so Wm2 is controlling load Number of bolts= 300.65/(2.5*10) = 12
  • 18. 40 Am2= 131402.52/80 = 1642.53 mm2 Diameter of bolts= [(Am2/no. of bolts) x 3.14/4]1/2 = [(1642.53)/12 x (4/3.14)]1/2 =13.19 mm Bolt area, Ab = 2 x 3.14 x YaGN/fa = 2 x 3.14 x 52.48 x 300.65 x 35 / 80 = 43350.36 mm2 Pitch of bolts = 4.75*18 = 85.6 mm Pitch circle dia.= (85.6*12)/3.14 = 327.13 mm Flange Thickness, K= 1/[0.3+1.5WmhG/HG] = 1/[0.3 + 1.5 x 131402.52 x 13.4 /( 31221.65 X 300.65)] = 1.75 tf = G(p/kf)1/2 +c = 300.65 x (0.44/1.75/80) ½ + 3 = 23.99 mm Use 24 mm 5.3 Distillation column Design: Operating pressure at top = 1 atm = 101.325 KPa Reflux ratio = 3.49 Number of plates = 40 Distillation molar rate D = 0.0327 Kmol/sec Liquid molar rate L= D x R = 0.0327 x 3.49 = 0.114 Kmol/sec
  • 19. 41 Vapor molar rate = D x (R + 1) = 0.0327 x (3.49 + 1) = 0.1468 Kmol/sec Vapor density ρv = 3.91 Kg/m3 Liquid density ρl = 653.64 Kg/m3 Vapor and liquid flowrate is given in table 5.2 Table 5.3: vapor and liquid flowrate vapor liquid molar flow rate 0.1468 0.1141 mass rate 10.8649 8.4451 vol. rate 2.7750 0.0129 Vload = Q [ρv / (ρl - ρv)]0.5 = 2.77 [ 3.91/(653.64 – 3.91)]0.5 = 0.2154 m3 /sec q = 0.0129 m3 /sec Single pass Dt = 1.7 m (from graph of Vload and liquid flowrate) System factor S = 1 Flooding factor = 0.8 ( 80 % flooding) Flow path length L = 0.75 x Dt / number of pass = 0.75 x 1.7 / 1 = 1.275 m C* = 0.125 C = S x C* = 1 x 0.125 = 0.125 Aamin = [ vapor load + 1.36qL]/ (C x F) = [ 0.2154 + 1.36 x 0.0129 x 1.275 ]/(0.125 x 0.8) = 2.37 m2
  • 20. 42 U* = 0.170 m/sec U* = 0.007(ρl - ρv)0.5 = 0.007 x (653.64 – 3.91) = 0.178 m/sec U* = 0.008 x (Ts (ρl - ρv)) 0.5 = 0.008 x ( 0.457 (653.64 – 3.91)) 0.5 = 0.137 m/sec Use smallest value U* = 0.137 m/sec u = U* x S = 0.137 x 1 = 0.137 m/sec Admin = q/(u x f) = 0.0129/(0.137 x 0.8) = 0.1171 m2 Admin < 0.11 x Aa 0.1171 < 0.11 x 0.1171 m2 0.1171 < 0.2607 m2 Admin = 2 x 0.1171 = 0.2342 m2 At = Aamin + 2 Admin = 2.37 + 2 x 0.2342 = 2.84 m2 Atmin = 1.28 Vload /(0.8 x 0.125) = 1.28 x 0.2154/ (0.8 x 0.125) = 2.75 m2 At > Atmin Take At = 2.84 m2
  • 21. 43 Diameter = (At x 4 / 3.14)0.5 = (2.84 x 4 / 3.14)0.5 = 1.9 m Ad/(AtN) = 0.2342/(2.84 x 1) = 0.0823 Weir length Lw/Dt = 0.657 Lw = 0.657 x 1.9 = 1.25 m Weir hight H/ Dt = 0.12 H = 0.12 x 1.9 = 0.228 m Number of valve units Assume 120-175 units/ m2 active area Active area = 2.37 m2 Number of units = 285 to 417 units/plate Assume Number of units = 350 units/plate Holes area = 350/845 = 0.4142 m2 Pressure drop Tray MOC – MS density = 7700 kg/m3 Thickness of tray = 14 gauge = 0.188cm Type of valve V4 K1 = 2.73 K2 = 13.6 ∆Pdry = 0.135 tn (ρm /ρl) + K1Vn 2 (ρv /ρl) = 0.135 (0.188)(7700/653.64) + 2.73 (6.692 )(3.91/653.64) = 1.032 cm liquid
  • 22. 44 ∆Pdry = K2Vn 2 (ρv /ρl) = 13.6 (6.692 )(3.91/653.64) = 3.65 cm liquid ∆Pt = ∆Pdry + 55.4(q/Lw)0.67 + 0.04hw = 3.65 + 55.4(0.0129/1.25)0.67 + 0.04 x 50 = 8.44 cm liquid = 0.076 psi Hde = 55.4(q/Lw)0.67 + 0.1 hw + (∆Pt + 1.66)( ρl / (ρl - ρv)) = 55.4(0.0129/1.25)0.67 + 0.1 x 50 + (8.44 + 1.66)(653.64/(653.64-3.91)) = 17.96 cm liquid < 0.6 TS %Flooding = Vload / (0.78ATC) = 0.2154 / (0.78 x 2.84 x0.125) = 77.60% 5.3.1 Mechanical design of distillation column Mechanical design of distillation column including support. [14] Operating pressure = 101.325 Kpa Design pressure = 1.1 x 101.325 = 111.45 Kpa = 0.11145 N/mm2 Design temperature = 423 K MOC = carbon steel Diameter = 1900 mm Thickness of the column tc = PD/(2fJ - P) = 0.44 x 300/((2 x 80 x 0.85) - 0.44) + 3 mm = 3.065 mm But take 8mm Head Torispherical head [6] Head thickness (th) = PCrW/2fJ Crown radius = 1900 mm
  • 23. 45 Knuckle radius = 190 mm W=1/4(3+ (Rc/R1)1/2 ) = 1/4(3 + (1900/190)1/2 ) = 1.54 th = 0.11145 x 1900 x 1.54 / (2 x 0.85 x 80) + 3mm = 5.39 mm Use 8 mm same as column diameter Total vessel dead load !=("!+0.8#$ )%&' = 1.15 x 3.14 x 1.9 x (19 + 0.8 x 1.9) x 0.008 x 7700 x 9.81 = 119736.89 N Column support design Skirt diameter = 1900mm Stress due to dead load Fds = W/(D + t)t = 119736.89/(3.14 x (1900 + t) x t) Stress due to wind load Fws = 11071.56/(3.14 x (1900 + t) x t) Total compressive stess = Fds + Fws Maximum stress = 0.125Et/D = Fds + Fws E = 190 N/mm2 By solving this t = 41.42 mm So take thickness 45 mm For this thickness Fcompressive < Fs Ftensile < Fs