SlideShare una empresa de Scribd logo
1 de 1
Descargar para leer sin conexión
The 9 Key Elements
of
Successful
Plant Commissioning
Element 4
- PRE-COMMISSIONING -
What is Pre-Commissioning?
Pre-Commissioning Activities (Examples)
Pre-Commissioning Sequence (Example)
RFC
Licensor
Vendor Specialists
Pre-Commissioning Additional Records
Pre-Commissioning Test Records
Pre-Commissioning Checklists
Pre-Commissioning Procedures (Examples)
The term Pre-Commissioning is used for activities
after construction completion, such as cleaning,
catalyst loading, dry-runs and checks within the
systems in order to prepare these items/systems for
the next step - commissioning.
Pre-Commissioning activities can be done after or as
well before mechanical completion (MC).
API Recommended Practice 1FSC
"Group of energized and static tests that constitute
verification that the equipment or component is
fabricated, installed, cleaned, and tested in
accordance with the design and ready for
commissioning."
Also: "static commissioning"
Flushing, blowing and drying activities
Chemical cleaning
Final inspection and closing of vessels and tanks
Final reinstatement of systems or sub-systems
Air tightness “Leak” testing of systems
Lubricants application
Pre-commissioning “Run-in” of major rotating
equipment and electrical motors
Installation of filters
Packing of distillation columns
Loading of catalyst and molecular sieve beds
Refractory dry-out (if possible - mostly
commissioning activity)
Vendor and factory acceptance testing
Instrument, electrical and motor loop testing
Punchlisting (ongoing process)
1. Power and control system (electrical sub-stations)
2. Building power, HVAC, fire & gas protection
3. DCS and PLC systems and instrumentation
4. Raw water and fire fighting systems
5. Waste water treatment systems
6. Oily sewer / clean sewer systems and chemical
sewers & neutralization pits
7. Service water / potable water / cooling water
systems
8. Instrument air / plant air and regeneration air
systems
9. Water treatment systems, demineralization units
and boiler water system
10. Nitrogen system
11. Flare system
12. Plant safety equipment and fire & gas detection
13. Fuel gas and fuel oil system
14. Slop systems
15. Flushing oil system
16. Boiler systems with steam & condensate
networks
17. Amine, aromatics and caustic drain systems
18. Feed & product storage systems
19. Product & feed systems
20. Sour water treatment section and chemical
handling treatment section
21. Amine treatment section
22. All process systems in order of “priority”
Milestone "Ready For Commissioning"
Pre-Commissioning activities are completed and the
systems are ready to commence commissioning.
API Recommended Practice 1FSC
Protocol
"Minor milestone in project when pre-commissioning
activities for a discipline (electrical, instrumentation,
mechanical, piping, etc.) are essentially complete
and ready to commence commissioning."
Final inspection of “critical” equipment installation
Supervision of catalyst and chemical loading
For major items of rotating machinery, major utility
systems and special electrical and instrument control
equipment
Package unitsRequest for mechanical completion acceptance
Mechanical completion certificate
Release for pre-commissioning notice
Punchlist report of outstanding punch points
Pre-commissioning activity test records are prepared
to record the satisfactory completion of various
system preparation tasks & activities.
Cleaning
Chemical cleaning
Drying
Air tightness test
Loading of catalysts
Blinds list
Performance Indicators
Construction QA/QC documentation
Systems punchlist (commissioning punch)
Piping pre-commissioning activities
Stationary equipment pre-commissioning activities
Rotating equipment pre-commissioning activities
Instrumentation pre-commissioning activities
Tightness tests
ReportingTotal / Completed / Remaining
Many different checklists for different types of
equipment
To record the inspection and status of equipment
items within the plant
To conform readiness for commissioning
Often to be witnessed by client, PMC & licensor
Spectacle blind installation checks
Non-return valve internals installation checks
Thermal refractory lining installation checks
Mechanical interlock checks
Fitting of all locks on valves
Packing of a distillation or scrubbing column
Packing a reactor with catalyst
Installation of filter medium and cartridges
Air blowing
Steam blowing
Water flushing
Chemical cleaning
Tightness test
Cooling water passivation
Mechanical test run of pumps
NOTE: All slip blinds or spectacle plates utilized
must be given a suitable tail or handle so immediate
identification can be made in the field.

Más contenido relacionado

La actualidad más candente

HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTING
Paul Sumal
 

La actualidad más candente (20)

World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Basics of Different Types of Compressors
Basics of Different Types of CompressorsBasics of Different Types of Compressors
Basics of Different Types of Compressors
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and design
 
GAS TURBINE MAJOR INSPECTION
GAS TURBINE MAJOR INSPECTIONGAS TURBINE MAJOR INSPECTION
GAS TURBINE MAJOR INSPECTION
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
NDT for Boilers
NDT for BoilersNDT for Boilers
NDT for Boilers
 
HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTING
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
Hydrotest
HydrotestHydrotest
Hydrotest
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptx
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
Boiler operation (2)
Boiler operation (2)Boiler operation (2)
Boiler operation (2)
 
Storage Tank Safety
Storage Tank SafetyStorage Tank Safety
Storage Tank Safety
 
Heavy equipments in construction
Heavy equipments in constructionHeavy equipments in construction
Heavy equipments in construction
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 

Destacado

Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
ptetang
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
Murilo Juchem
 
Building maintenance management in malaysia
Building maintenance management in malaysiaBuilding maintenance management in malaysia
Building maintenance management in malaysia
Nur Zakaria
 
Introduction to building services part 2
Introduction to building services part 2Introduction to building services part 2
Introduction to building services part 2
Noorule Inie Osman
 

Destacado (20)

Design of piping_systems_-_mw_kellogg
Design of piping_systems_-_mw_kelloggDesign of piping_systems_-_mw_kellogg
Design of piping_systems_-_mw_kellogg
 
Commercial Building Services
Commercial Building ServicesCommercial Building Services
Commercial Building Services
 
Commercial - Industrial mechanical aspects
Commercial - Industrial mechanical aspectsCommercial - Industrial mechanical aspects
Commercial - Industrial mechanical aspects
 
Clamp a type
Clamp a typeClamp a type
Clamp a type
 
Welded steel pipe 10.10.07
Welded steel pipe 10.10.07Welded steel pipe 10.10.07
Welded steel pipe 10.10.07
 
Pipe Clamp Design, Application & Installation - November
Pipe Clamp Design, Application & Installation - NovemberPipe Clamp Design, Application & Installation - November
Pipe Clamp Design, Application & Installation - November
 
The Design Secrets of Slide Plates & Pipe Rollers Webinar
The Design Secrets of Slide Plates & Pipe Rollers WebinarThe Design Secrets of Slide Plates & Pipe Rollers Webinar
The Design Secrets of Slide Plates & Pipe Rollers Webinar
 
Pipe Clamps Webinar
Pipe Clamps WebinarPipe Clamps Webinar
Pipe Clamps Webinar
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 
Building Maintenance Solutions
Building Maintenance SolutionsBuilding Maintenance Solutions
Building Maintenance Solutions
 
Quality Assurance Plan
Quality Assurance PlanQuality Assurance Plan
Quality Assurance Plan
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
 
Buildings Maintenance Issues
Buildings Maintenance IssuesBuildings Maintenance Issues
Buildings Maintenance Issues
 
cswip-3-1-quiz
 cswip-3-1-quiz cswip-3-1-quiz
cswip-3-1-quiz
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
Welding iv
Welding   ivWelding   iv
Welding iv
 
Building maintenance management in malaysia
Building maintenance management in malaysiaBuilding maintenance management in malaysia
Building maintenance management in malaysia
 
PIPE SYSTEMS1
PIPE SYSTEMS1PIPE SYSTEMS1
PIPE SYSTEMS1
 
Building Services
Building ServicesBuilding Services
Building Services
 
Introduction to building services part 2
Introduction to building services part 2Introduction to building services part 2
Introduction to building services part 2
 

Similar a Mind map the_9_key_elements_video_05_pre-commissioning

Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
wan saiful arini
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
Ronie Chu
 
Leak Detection And Repair
Leak Detection And RepairLeak Detection And Repair
Leak Detection And Repair
Ashutosh Soni
 
Eng Ahmed Mostafa Helmy_ Instruments Engineer
Eng Ahmed Mostafa Helmy_ Instruments EngineerEng Ahmed Mostafa Helmy_ Instruments Engineer
Eng Ahmed Mostafa Helmy_ Instruments Engineer
Ahmed Helmy
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
ankur sood
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
ankur sood
 

Similar a Mind map the_9_key_elements_video_05_pre-commissioning (20)

Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Leak Detection And Repair
Leak Detection And RepairLeak Detection And Repair
Leak Detection And Repair
 
Efficiency environment and innovation
Efficiency environment and innovationEfficiency environment and innovation
Efficiency environment and innovation
 
Pre commissioning Instrument Engineer
Pre commissioning Instrument EngineerPre commissioning Instrument Engineer
Pre commissioning Instrument Engineer
 
Control Loop Foundation - Batch And Continous Processes
Control Loop Foundation - Batch And Continous ProcessesControl Loop Foundation - Batch And Continous Processes
Control Loop Foundation - Batch And Continous Processes
 
SeptiTech STAAR Denitrification Wastewater Presentation
SeptiTech STAAR Denitrification Wastewater PresentationSeptiTech STAAR Denitrification Wastewater Presentation
SeptiTech STAAR Denitrification Wastewater Presentation
 
SeptiTech STAAR (Standard/Denite) Filter Systems
SeptiTech STAAR (Standard/Denite) Filter SystemsSeptiTech STAAR (Standard/Denite) Filter Systems
SeptiTech STAAR (Standard/Denite) Filter Systems
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
 
Heating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC QualificationHeating Ventilation and Air Conditioner HVAC Qualification
Heating Ventilation and Air Conditioner HVAC Qualification
 
TOC.pptx
TOC.pptxTOC.pptx
TOC.pptx
 
Eng Ahmed Mostafa Helmy_ Instruments Engineer
Eng Ahmed Mostafa Helmy_ Instruments EngineerEng Ahmed Mostafa Helmy_ Instruments Engineer
Eng Ahmed Mostafa Helmy_ Instruments Engineer
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Facility & Equipment Quality System Outline
Facility & Equipment Quality System OutlineFacility & Equipment Quality System Outline
Facility & Equipment Quality System Outline
 
Principle of Validation and Qualification
Principle of Validation and QualificationPrinciple of Validation and Qualification
Principle of Validation and Qualification
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit Breakers
 
076 circuit breaker install 1.0
076 circuit breaker install 1.0076 circuit breaker install 1.0
076 circuit breaker install 1.0
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 

Último

FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Dipal Arora
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 

Último (20)

Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 

Mind map the_9_key_elements_video_05_pre-commissioning

  • 1. The 9 Key Elements of Successful Plant Commissioning Element 4 - PRE-COMMISSIONING - What is Pre-Commissioning? Pre-Commissioning Activities (Examples) Pre-Commissioning Sequence (Example) RFC Licensor Vendor Specialists Pre-Commissioning Additional Records Pre-Commissioning Test Records Pre-Commissioning Checklists Pre-Commissioning Procedures (Examples) The term Pre-Commissioning is used for activities after construction completion, such as cleaning, catalyst loading, dry-runs and checks within the systems in order to prepare these items/systems for the next step - commissioning. Pre-Commissioning activities can be done after or as well before mechanical completion (MC). API Recommended Practice 1FSC "Group of energized and static tests that constitute verification that the equipment or component is fabricated, installed, cleaned, and tested in accordance with the design and ready for commissioning." Also: "static commissioning" Flushing, blowing and drying activities Chemical cleaning Final inspection and closing of vessels and tanks Final reinstatement of systems or sub-systems Air tightness “Leak” testing of systems Lubricants application Pre-commissioning “Run-in” of major rotating equipment and electrical motors Installation of filters Packing of distillation columns Loading of catalyst and molecular sieve beds Refractory dry-out (if possible - mostly commissioning activity) Vendor and factory acceptance testing Instrument, electrical and motor loop testing Punchlisting (ongoing process) 1. Power and control system (electrical sub-stations) 2. Building power, HVAC, fire & gas protection 3. DCS and PLC systems and instrumentation 4. Raw water and fire fighting systems 5. Waste water treatment systems 6. Oily sewer / clean sewer systems and chemical sewers & neutralization pits 7. Service water / potable water / cooling water systems 8. Instrument air / plant air and regeneration air systems 9. Water treatment systems, demineralization units and boiler water system 10. Nitrogen system 11. Flare system 12. Plant safety equipment and fire & gas detection 13. Fuel gas and fuel oil system 14. Slop systems 15. Flushing oil system 16. Boiler systems with steam & condensate networks 17. Amine, aromatics and caustic drain systems 18. Feed & product storage systems 19. Product & feed systems 20. Sour water treatment section and chemical handling treatment section 21. Amine treatment section 22. All process systems in order of “priority” Milestone "Ready For Commissioning" Pre-Commissioning activities are completed and the systems are ready to commence commissioning. API Recommended Practice 1FSC Protocol "Minor milestone in project when pre-commissioning activities for a discipline (electrical, instrumentation, mechanical, piping, etc.) are essentially complete and ready to commence commissioning." Final inspection of “critical” equipment installation Supervision of catalyst and chemical loading For major items of rotating machinery, major utility systems and special electrical and instrument control equipment Package unitsRequest for mechanical completion acceptance Mechanical completion certificate Release for pre-commissioning notice Punchlist report of outstanding punch points Pre-commissioning activity test records are prepared to record the satisfactory completion of various system preparation tasks & activities. Cleaning Chemical cleaning Drying Air tightness test Loading of catalysts Blinds list Performance Indicators Construction QA/QC documentation Systems punchlist (commissioning punch) Piping pre-commissioning activities Stationary equipment pre-commissioning activities Rotating equipment pre-commissioning activities Instrumentation pre-commissioning activities Tightness tests ReportingTotal / Completed / Remaining Many different checklists for different types of equipment To record the inspection and status of equipment items within the plant To conform readiness for commissioning Often to be witnessed by client, PMC & licensor Spectacle blind installation checks Non-return valve internals installation checks Thermal refractory lining installation checks Mechanical interlock checks Fitting of all locks on valves Packing of a distillation or scrubbing column Packing a reactor with catalyst Installation of filter medium and cartridges Air blowing Steam blowing Water flushing Chemical cleaning Tightness test Cooling water passivation Mechanical test run of pumps NOTE: All slip blinds or spectacle plates utilized must be given a suitable tail or handle so immediate identification can be made in the field.