REPORT ON
“GENERATION OF THERMAL POWER”
AT
NTPC DADRI




                   BY-ADITYA GUPTA
                     ECE 4Th year
About NTPC
• NTPC, the largest power Company in India, was
  setup in 1975 to accelerate power development
  in the country.
• NTPC has installed capacity of 29,394 MW.
• It has 15 coal based power stations (23,395 MW)
• 7 gas based power stations (3,955 MW)
• 4 power stations in Joint Ventures (1,794 MW).
• The company has power generating facilities in
  all major regions of the country.
• It plans to be a 75,000 MW company by 2017.
Generation of Electricity
• Prime mover coupled to
  Alternator
• Prime mover is driven by
  energy obtained from various
  sources such as
• burning of fuel
• pressure of water
• Force of wind etc.

                                 Fig. Fundamental of generation of Electricity
Thermal Power Plant
• A generating station which converts heat energy of coal combustion
  into electrical energy is known as a steam power station.
• Steam is produced in the boiler by utilizing the heat of coal
  combustion. The steam is then expanded in the steam turbine and is
  condensed in a condenser to be fed into the boiler again. The steam
  turbine drives the alternator which converts mechanical energy of the
  turbine into electrical energy.
WORKING OF STEAM POWER
           PLANT
 • Coal is burnt in a boiler ,which converts water into steam.
 • The steam is expanded in a turbine used to drive alternator.
 • The steam expanded is condensed in a condenser to be feed into the
     boiler again.
 • The entire arrangement of steam power plant can be divided into :
a. fuel and ash plant.
b. air and fuel gas plant.
c. feed water and steam plant.
d. cooling water plant.
The most important constituents of a steam power station
are:

     a. Steam generating equipment
     b. Condenser
     c. Prime mover
     d. Cooling towers
     e. Electrical equipment

Steam generating equipment includes:
 •   Boiler
 •   Boiler furnace
 •   Superheater
 •   Economiser
 •   Air Pre-heater
Boiler
A boiler is closed vessel in which water is converted into steam by
utilising the heat of coal combustion.
Steam boilers are broadly classified into following two types:
(a) Water tube boilers (b) Fire tube boilers


In a water tube boiler, water flows through the tubes and the hot gases
of combustion flow over these tubes. Water-tube boilers are used for
high-pressure boilers
In a fire tube boiler, the hot products of combustion pass through the
 tubes surrounded by water.




• The heated water then rises into the steam drum. Here, saturated
  steam is drawn off the top of the drum. The steam will reenter the
  furnace in through a superheater in order to become superheated.
  Superheated steam is used in driving turbines. Since water droplets can
  severely damage turbine blades, steam is superheated to 730°F
  (390°C) or higher in order to ensure that there is no water entrained in
  the steam.
Super heater

• A device which removes last traces of
  moisture.
• It helps in reduction in requirement of
  steam quantity.
• steam being dry reduces the mechanical
  resistance of turbine.
• No corrosion at the turbine blades.
Economiser and Air Pre-heater
• They are such devices which recover the
  heat from the flue gases on their way to
  chimney and raise the temperature of feed
  water.
• Economiser raises boiler efficiency.
• Air Pre-heaters recover the heat from the
  flue gases leaving the economiser and
  heat the incoming air required for
  combustion
Condenser
• Which condenses the steam at the exhaust of
  turbine.
• It creates a very low pressure at the exhaust of
  turbine, this helps in converting heat energy of
  steam into mechanical energy in the prime
  mover.
• The condensed steam can be used as feed
  water to the boiler.
Prime Mover (i.e. Turbine)
A steam turbine is a mechanical device that extracts thermal energy
from pressurized steam, and converts it into mechanical energy.
About 86% of all electric generation in the world is by use of steam
turbines.
It has almost completely replaced the reciprocating piston steam
engine.




   BOILER                                        GENERATOR

                                     STEAM TURBINE
Cooling Towers

• Remove heat from the
  water discharged from
  the condenser so that the
  water can be discharged
  to the river or re
  circulated and reused.
• Air can be circulated in
  the cooling towers
  through natural draft and
  mechanical draft.
Electrical Equipments
Alternator
An alternator is coupled to a steam turbine and converts mechanical
energy of the turbine into electrical energy.
It may be hydrogen or air cooled.
The necessary excitation is provided by means of main and pilot exciters
directly coupled to the alternator shaft.
Transformers
(a) main step-transformers, which steps-up generated voltage
transmission of power
(b) station transformers, general purpose
(c) auxiliary transformers, which supply to individual unit-auxiliaries.
Switchgear
which locates fault on the system and isolate faulty part from healthy
section.
It contains circuit breakers, relays, switches and other control devices.
Coal Handling Plant Details
• Source of coal = Piparwar Mines North Karanpur (Jharkhand)
• Location = Near Ranchi
• Distance = 1200 Kms.
• Type of coal = F-grade (Washed)
• E grade (Raw)
• Coal requirement = 13,000 MT/Day
• ( 04 rakes )
Ash Handling Technique

• A natural result from the burning of fossil fuels,
  particularly coal, is the emission of flyash. Ash is mineral
  matter present in the fuel. For a pulverized coal unit, 60-
  80% of ash leaves with the flue gas.

• Two emission control devices for flyash are the fabric
  filters and electrostatic precipitators.

• Electrostatic precipitators have collection efficiency of
  99%, but do not work well for flyash with a high electrical
  resistivity (as commonly results from combustion of low-
  sulfur coal). In addition, the designer must avoid
  allowing unburned gas to enter the electrostatic
  precipitator since the gas could be ignited.
Top View of ESP Schematic Diagram       Side view of ESP Schematic Diagram



 • The fluegas laden with flyash is sent through pipes having negatively
   charged plates which give the particles a negative charge. The particles
   are then routed past positively charged plates, or grounded plates, which
   attract the now negatively-charged ash particles.
 • The particles stick to the positive plates until they are collected. The air
   that leaves the plates is then clean from harmful pollutants.
Coal Ash can be used in:

•   Construction of embankments and fills
•   Construction of road in sub-base
•   Manufacture of cement
•   Manufacture of bricks/blocks
•   Filling as flowable fill material
•   Agriculture as soil amendment/source of
    essential plant nutrients
Ntpc dadri ppt

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

Training report on thermal power plant
Training report on thermal power plantTraining report on thermal power plant
Training report on thermal power plant
 
COAL HANDLING DIVISION/PLANT, ANPARA
COAL HANDLING DIVISION/PLANT, ANPARACOAL HANDLING DIVISION/PLANT, ANPARA
COAL HANDLING DIVISION/PLANT, ANPARA
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training report
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
ntpc dadri
ntpc dadri ntpc dadri
ntpc dadri
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
ntpc anta training report
ntpc anta training reportntpc anta training report
ntpc anta training report
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 

Similar a Ntpc dadri ppt

thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPC
richa khatri
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharma
Prakash Sharma
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
Rashmi Nimje
 

Similar a Ntpc dadri ppt (20)

Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02
 
Presentation sai,varun.
Presentation sai,varun.Presentation sai,varun.
Presentation sai,varun.
 
thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPC
 
Richappt
RichapptRichappt
Richappt
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharma
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Emam training
Emam training Emam training
Emam training
 
Ntpc2
Ntpc2Ntpc2
Ntpc2
 
Steam plan
Steam planSteam plan
Steam plan
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 
Thermal Power Station
Thermal Power StationThermal Power Station
Thermal Power Station
 
Ppt aman
Ppt amanPpt aman
Ppt aman
 
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Thermal Power Plant (Bathinda) PPT
Thermal Power Plant (Bathinda) PPTThermal Power Plant (Bathinda) PPT
Thermal Power Plant (Bathinda) PPT
 
KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptx
 
PPT ON THERMAL POWER PLANT (POLLUTION CONTROLLED)
PPT ON THERMAL POWER PLANT (POLLUTION  CONTROLLED)PPT ON THERMAL POWER PLANT (POLLUTION  CONTROLLED)
PPT ON THERMAL POWER PLANT (POLLUTION CONTROLLED)
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 

Ntpc dadri ppt

  • 1. REPORT ON “GENERATION OF THERMAL POWER” AT NTPC DADRI BY-ADITYA GUPTA ECE 4Th year
  • 2. About NTPC • NTPC, the largest power Company in India, was setup in 1975 to accelerate power development in the country. • NTPC has installed capacity of 29,394 MW. • It has 15 coal based power stations (23,395 MW) • 7 gas based power stations (3,955 MW) • 4 power stations in Joint Ventures (1,794 MW). • The company has power generating facilities in all major regions of the country. • It plans to be a 75,000 MW company by 2017.
  • 3. Generation of Electricity • Prime mover coupled to Alternator • Prime mover is driven by energy obtained from various sources such as • burning of fuel • pressure of water • Force of wind etc. Fig. Fundamental of generation of Electricity
  • 4. Thermal Power Plant • A generating station which converts heat energy of coal combustion into electrical energy is known as a steam power station. • Steam is produced in the boiler by utilizing the heat of coal combustion. The steam is then expanded in the steam turbine and is condensed in a condenser to be fed into the boiler again. The steam turbine drives the alternator which converts mechanical energy of the turbine into electrical energy.
  • 5. WORKING OF STEAM POWER PLANT • Coal is burnt in a boiler ,which converts water into steam. • The steam is expanded in a turbine used to drive alternator. • The steam expanded is condensed in a condenser to be feed into the boiler again. • The entire arrangement of steam power plant can be divided into : a. fuel and ash plant. b. air and fuel gas plant. c. feed water and steam plant. d. cooling water plant.
  • 6. The most important constituents of a steam power station are: a. Steam generating equipment b. Condenser c. Prime mover d. Cooling towers e. Electrical equipment Steam generating equipment includes: • Boiler • Boiler furnace • Superheater • Economiser • Air Pre-heater
  • 7. Boiler A boiler is closed vessel in which water is converted into steam by utilising the heat of coal combustion. Steam boilers are broadly classified into following two types: (a) Water tube boilers (b) Fire tube boilers In a water tube boiler, water flows through the tubes and the hot gases of combustion flow over these tubes. Water-tube boilers are used for high-pressure boilers
  • 8. In a fire tube boiler, the hot products of combustion pass through the tubes surrounded by water. • The heated water then rises into the steam drum. Here, saturated steam is drawn off the top of the drum. The steam will reenter the furnace in through a superheater in order to become superheated. Superheated steam is used in driving turbines. Since water droplets can severely damage turbine blades, steam is superheated to 730°F (390°C) or higher in order to ensure that there is no water entrained in the steam.
  • 9. Super heater • A device which removes last traces of moisture. • It helps in reduction in requirement of steam quantity. • steam being dry reduces the mechanical resistance of turbine. • No corrosion at the turbine blades.
  • 10. Economiser and Air Pre-heater • They are such devices which recover the heat from the flue gases on their way to chimney and raise the temperature of feed water. • Economiser raises boiler efficiency. • Air Pre-heaters recover the heat from the flue gases leaving the economiser and heat the incoming air required for combustion
  • 11. Condenser • Which condenses the steam at the exhaust of turbine. • It creates a very low pressure at the exhaust of turbine, this helps in converting heat energy of steam into mechanical energy in the prime mover. • The condensed steam can be used as feed water to the boiler.
  • 12. Prime Mover (i.e. Turbine) A steam turbine is a mechanical device that extracts thermal energy from pressurized steam, and converts it into mechanical energy. About 86% of all electric generation in the world is by use of steam turbines. It has almost completely replaced the reciprocating piston steam engine. BOILER GENERATOR STEAM TURBINE
  • 13. Cooling Towers • Remove heat from the water discharged from the condenser so that the water can be discharged to the river or re circulated and reused. • Air can be circulated in the cooling towers through natural draft and mechanical draft.
  • 14. Electrical Equipments Alternator An alternator is coupled to a steam turbine and converts mechanical energy of the turbine into electrical energy. It may be hydrogen or air cooled. The necessary excitation is provided by means of main and pilot exciters directly coupled to the alternator shaft. Transformers (a) main step-transformers, which steps-up generated voltage transmission of power (b) station transformers, general purpose (c) auxiliary transformers, which supply to individual unit-auxiliaries. Switchgear which locates fault on the system and isolate faulty part from healthy section. It contains circuit breakers, relays, switches and other control devices.
  • 15. Coal Handling Plant Details • Source of coal = Piparwar Mines North Karanpur (Jharkhand) • Location = Near Ranchi • Distance = 1200 Kms. • Type of coal = F-grade (Washed) • E grade (Raw) • Coal requirement = 13,000 MT/Day • ( 04 rakes )
  • 16. Ash Handling Technique • A natural result from the burning of fossil fuels, particularly coal, is the emission of flyash. Ash is mineral matter present in the fuel. For a pulverized coal unit, 60- 80% of ash leaves with the flue gas. • Two emission control devices for flyash are the fabric filters and electrostatic precipitators. • Electrostatic precipitators have collection efficiency of 99%, but do not work well for flyash with a high electrical resistivity (as commonly results from combustion of low- sulfur coal). In addition, the designer must avoid allowing unburned gas to enter the electrostatic precipitator since the gas could be ignited.
  • 17. Top View of ESP Schematic Diagram Side view of ESP Schematic Diagram • The fluegas laden with flyash is sent through pipes having negatively charged plates which give the particles a negative charge. The particles are then routed past positively charged plates, or grounded plates, which attract the now negatively-charged ash particles. • The particles stick to the positive plates until they are collected. The air that leaves the plates is then clean from harmful pollutants.