SlideShare una empresa de Scribd logo
1 de 21
Project Schedule and Earned
Value Analysis
Ahmed Badr
Version 01
13 Jan 2014
6/21/2016 Project Management 1
Project Schedule
• MS Project Presentation
• https://www.youtube.com/watch?v=7WsfuvHegxE
• http://www.slideshare.net/khem13/ms-project-presentation-
9034496
6/21/2016 Project Managment 2
Three key values
• Total Budget
• BCWS
• The budgeted cost of individual tasks as they are scheduled in the project plan, based on the costs of the resources that are
assigned to those tasks, plus any fixed costs that are associated with the tasks. This is the budgeted cost of work scheduled
(BCWS). BCWS is the baseline cost up to the status date that you choose. Budgeted cost values are stored in the baseline
fields, or, if you saved multiple baselines, in the Baseline1 through Baseline10 fields.
• PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled
• ACWP
• The actual cost that is required to complete all or some portion of the tasks, up to the status date. This is the actual
cost of work performed (ACWP). Normally, Microsoft Office Project 2007 correlates the actual costs with the actual
work.
• AC or ACWP = Hourly Rate * Total Hours Spent
• BCWP
• The value of the work that is performed by the status date, measured in currency. This is literally the value earned by
the work performed and is called the budgeted cost of work performed (BCWP). This value is calculated for each
individual task, but is analyzed at an aggregate level (typically at the project level).
• EV or BCWP = Baselined Cost * % Complete Actual
6/21/2016 Project Managment 3
Cost Variance %
• Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)
• Or
• Cost Variance (CV) = BCWP - ACWP
Cost Variance
• Cost Variance % indicates how much over or under budget the project is in terms
of percentage.
• CV % = Cost Variance (CV) / Earned Value (EV)
• Or
• CV % = CV / BCWP
6/21/2016 Project Managment 4
Cost Performance Indicator (CPI)
• Cost Performance Indicator is an index showing the efficiency of the
utilization of the resources on the project. Cost Performance Indicator
can be calculated using the following formula:
• CPI = Earned Value (EV) / Actual Cost (AC)
• Or
• CPI = BCWP / ACWP
6/21/2016 Project Managment 5
Schedule Variance
• Schedule Variance indicates how much ahead or behind schedule the
project is.
• Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)
• Or
• Schedule Variance (SV) = BCWP - BCWS
Schedule Variance %
• Schedule Variance % indicates how much ahead or behind schedule
the project is in terms of percentage.
• SV % = Schedule Variance (SV) / Planned Value (PV)
• Or
• SV % = SV / BCWS
6/21/2016 Project Managment 6
Schedule Performance Indicator (SPI)
• Schedule Performance Indicator is an index showing the efficiency of
the time utilized on the project. Schedule Performance Indicator can
be calculated using the following formula:
• SPI = Earned Value (EV) / Planned Value (PV)
• Or
• SPI = BCWP / BCWS
6/21/2016 Project Managment 7
To Complete Schedule Performance Indicator
(TSPI)
• To Complete Schedule Performance Indicator is an index showing the
efficiency at which the remaining time on the project should be
utilized. This can be calculated using the following formula:
• TSPI = ( Total Budget - EV ) / ( Total Budget - PV )
• Or
• TSPI = ( Total Budget - BCWP ) / ( Total Budget - BCWS )
6/21/2016 Project Managment 8
MS Project - Earned Value
• Tables
• Entry – Resources Sheet - Cost
• On the View menu, point to Table, and then click More Tables
• In the Tables list, click Earned Value, Earned Value Cost Indicators, or Earned Value
Schedule Indicators, and then click Apply.
• Create Baseline
• Set “advanced” options to calculate based in which baseline
• And set the Earned Value Calculation method
• Reports
• Use the Earned Value Over Time report to view a chart that plots AC (actual cost of
work performed), planned value (budgeted cost of work scheduled), and earned
value (budgeted cost of work performed) over time. To generate this report, on the
Report menu, click Visual Reports. Click Earned Value Over Time and then click View
6/21/2016 Project Managment 9
6/21/2016 Project Managment 10
Plan-Track-Analyze
6/21/2016 Project Managment 11
6/21/2016 Project Managment 12
6/21/2016 Project Managment 13
Earned Value over Time Report
6/21/2016 Project Managment 14
Project Forecast
• Budget At Completion (BAC)
• Budget At Completion (BAC) is the total budget allocated to the
project.
• Budget At Completion (BAC) is generally plotted over time. Say like
periods of reporting (Monthly, Weekly, etc.)
• BAC is used to compute the Estimate At Completion (EAC), explained
in next section.
• BAC is also used to compute the TCPI and TSPI.
• BAC = Baseline Effort-hours * Hourly Rate
6/21/2016 Project Managment 15
Estimate To Complete (ETC)
• Estimate To Complete (ETC) is the estimated cost required to
complete the remainder of the project.
• Estimate To Complete (ETC) is calculated and applied when the past
estimating assumptions become invalid and a need for fresh
estimates arises.
• ETC is used to compute the Estimation At Completion (EAC).
6/21/2016 Project Managment 16
Estimate At Completion (EAC)
• Estimate At Completion (EAC) is the estimated cost of the project at the
end of the project.
• There are three methods to calculate EAC:
• Variances are Typical - This method is used when the variances at the current stage
are typical and are not expected to occur in the future.
• Past Estimating Assumptions are not valid - This method is used when the past
estimating assumptions are not valid and fresh estimates are applied to the project.
• Variances will be present in the future - This method is used when the assumption is
that the current variances will continue to be present in the future.
• The formulas for calculation of the three methods are as given below:
• AC + (BAC - EV)
• AC + ETC (Estimate To Complete)
• AC + (BAC- EV) / CPI
6/21/2016 Project Managment 17
Variance At Completion (VAC)
• Variance At completion (VAC) is the variance on the total budget at the end
of the project.
• This is the difference between what the project was originally expected
(baselined) to cost, versus what the it is now expected to cost.
• VAC = BAC – EAC
• % Completed Planned
• The percentage of work which was planned to be completed by the Reporting Date.
This is calculated using the following formula:
• % Completed Planned = PV / BAC
• % Completed Actual
• The percentage of work which was actually completed by the Reporting Date. This is
calculated using the following formula:
• % Completed Actual = AC / EAC
6/21/2016 Project Managment 18
Earned Value Focuses on
• % Completed Planned
• The percentage of work which was planned to be completed by the Reporting
Date. This is calculated using the following formula:
• % Completed Planned = PV / BAC
• % Completed Actual
• The percentage of work which was actually completed by the Reporting Date.
This is calculated using the following formula:
• % Completed Actual = AC / EAC
6/21/2016 Project Managment 19
Plan-Track-Analyze-Forecast
6/21/2016 Project Managment 20
Forecast after Change Status Day
6/21/2016 Project Managment 21

Más contenido relacionado

La actualidad más candente

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Valueconstructioninside
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budgetharwoodr
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeAhmed Elsayed
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)Maintenance Connection
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementPraveen Malik, PMP
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value ManagementKristine Hejna
 

La actualidad más candente (20)

Earned value management
Earned value managementEarned value management
Earned value management
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project Management
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value Management
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 

Similar a Earned value 01

Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptvitumbikokhoswe1
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseVladimir Vujovic
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptxAhmedKayed6
 

Similar a Earned value 01 (20)

EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 

Último

2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 

Último (20)

2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 

Earned value 01

  • 1. Project Schedule and Earned Value Analysis Ahmed Badr Version 01 13 Jan 2014 6/21/2016 Project Management 1
  • 2. Project Schedule • MS Project Presentation • https://www.youtube.com/watch?v=7WsfuvHegxE • http://www.slideshare.net/khem13/ms-project-presentation- 9034496 6/21/2016 Project Managment 2
  • 3. Three key values • Total Budget • BCWS • The budgeted cost of individual tasks as they are scheduled in the project plan, based on the costs of the resources that are assigned to those tasks, plus any fixed costs that are associated with the tasks. This is the budgeted cost of work scheduled (BCWS). BCWS is the baseline cost up to the status date that you choose. Budgeted cost values are stored in the baseline fields, or, if you saved multiple baselines, in the Baseline1 through Baseline10 fields. • PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled • ACWP • The actual cost that is required to complete all or some portion of the tasks, up to the status date. This is the actual cost of work performed (ACWP). Normally, Microsoft Office Project 2007 correlates the actual costs with the actual work. • AC or ACWP = Hourly Rate * Total Hours Spent • BCWP • The value of the work that is performed by the status date, measured in currency. This is literally the value earned by the work performed and is called the budgeted cost of work performed (BCWP). This value is calculated for each individual task, but is analyzed at an aggregate level (typically at the project level). • EV or BCWP = Baselined Cost * % Complete Actual 6/21/2016 Project Managment 3
  • 4. Cost Variance % • Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC) • Or • Cost Variance (CV) = BCWP - ACWP Cost Variance • Cost Variance % indicates how much over or under budget the project is in terms of percentage. • CV % = Cost Variance (CV) / Earned Value (EV) • Or • CV % = CV / BCWP 6/21/2016 Project Managment 4
  • 5. Cost Performance Indicator (CPI) • Cost Performance Indicator is an index showing the efficiency of the utilization of the resources on the project. Cost Performance Indicator can be calculated using the following formula: • CPI = Earned Value (EV) / Actual Cost (AC) • Or • CPI = BCWP / ACWP 6/21/2016 Project Managment 5
  • 6. Schedule Variance • Schedule Variance indicates how much ahead or behind schedule the project is. • Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV) • Or • Schedule Variance (SV) = BCWP - BCWS Schedule Variance % • Schedule Variance % indicates how much ahead or behind schedule the project is in terms of percentage. • SV % = Schedule Variance (SV) / Planned Value (PV) • Or • SV % = SV / BCWS 6/21/2016 Project Managment 6
  • 7. Schedule Performance Indicator (SPI) • Schedule Performance Indicator is an index showing the efficiency of the time utilized on the project. Schedule Performance Indicator can be calculated using the following formula: • SPI = Earned Value (EV) / Planned Value (PV) • Or • SPI = BCWP / BCWS 6/21/2016 Project Managment 7
  • 8. To Complete Schedule Performance Indicator (TSPI) • To Complete Schedule Performance Indicator is an index showing the efficiency at which the remaining time on the project should be utilized. This can be calculated using the following formula: • TSPI = ( Total Budget - EV ) / ( Total Budget - PV ) • Or • TSPI = ( Total Budget - BCWP ) / ( Total Budget - BCWS ) 6/21/2016 Project Managment 8
  • 9. MS Project - Earned Value • Tables • Entry – Resources Sheet - Cost • On the View menu, point to Table, and then click More Tables • In the Tables list, click Earned Value, Earned Value Cost Indicators, or Earned Value Schedule Indicators, and then click Apply. • Create Baseline • Set “advanced” options to calculate based in which baseline • And set the Earned Value Calculation method • Reports • Use the Earned Value Over Time report to view a chart that plots AC (actual cost of work performed), planned value (budgeted cost of work scheduled), and earned value (budgeted cost of work performed) over time. To generate this report, on the Report menu, click Visual Reports. Click Earned Value Over Time and then click View 6/21/2016 Project Managment 9
  • 14. Earned Value over Time Report 6/21/2016 Project Managment 14
  • 15. Project Forecast • Budget At Completion (BAC) • Budget At Completion (BAC) is the total budget allocated to the project. • Budget At Completion (BAC) is generally plotted over time. Say like periods of reporting (Monthly, Weekly, etc.) • BAC is used to compute the Estimate At Completion (EAC), explained in next section. • BAC is also used to compute the TCPI and TSPI. • BAC = Baseline Effort-hours * Hourly Rate 6/21/2016 Project Managment 15
  • 16. Estimate To Complete (ETC) • Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project. • Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises. • ETC is used to compute the Estimation At Completion (EAC). 6/21/2016 Project Managment 16
  • 17. Estimate At Completion (EAC) • Estimate At Completion (EAC) is the estimated cost of the project at the end of the project. • There are three methods to calculate EAC: • Variances are Typical - This method is used when the variances at the current stage are typical and are not expected to occur in the future. • Past Estimating Assumptions are not valid - This method is used when the past estimating assumptions are not valid and fresh estimates are applied to the project. • Variances will be present in the future - This method is used when the assumption is that the current variances will continue to be present in the future. • The formulas for calculation of the three methods are as given below: • AC + (BAC - EV) • AC + ETC (Estimate To Complete) • AC + (BAC- EV) / CPI 6/21/2016 Project Managment 17
  • 18. Variance At Completion (VAC) • Variance At completion (VAC) is the variance on the total budget at the end of the project. • This is the difference between what the project was originally expected (baselined) to cost, versus what the it is now expected to cost. • VAC = BAC – EAC • % Completed Planned • The percentage of work which was planned to be completed by the Reporting Date. This is calculated using the following formula: • % Completed Planned = PV / BAC • % Completed Actual • The percentage of work which was actually completed by the Reporting Date. This is calculated using the following formula: • % Completed Actual = AC / EAC 6/21/2016 Project Managment 18
  • 19. Earned Value Focuses on • % Completed Planned • The percentage of work which was planned to be completed by the Reporting Date. This is calculated using the following formula: • % Completed Planned = PV / BAC • % Completed Actual • The percentage of work which was actually completed by the Reporting Date. This is calculated using the following formula: • % Completed Actual = AC / EAC 6/21/2016 Project Managment 19
  • 21. Forecast after Change Status Day 6/21/2016 Project Managment 21

Notas del editor

  1. http://www.tutorialspoint.com/earn_value_management/cost_variance.htm
  2. The formula mentioned above gives the efficiency of the project team in utilizing the time allocated for the project. SPI value above 1 indicates project team is very efficient in utilizing the time allocated to the project. SPI value below 1 indicates project team is less efficient in utilizing the time allocated to the project.
  3. https://support.office.com/en-us/article/Analyze-project-performance-with-earned-value-analysis-29efe3a3-dc4d-4e3f-833b-08c3b4599a04
  4. EVM (Earn Value Management) and MS PROJECT 2010 http://ntrajkovski.com/2012/04/06/evm-earn-value-management-and-ms-project-2010/
  5. For the second way of calculating the EAC, assumed I needed 500 LE to complete the project