SlideShare una empresa de Scribd logo
1 de 23
STANI MEMORIAL COLLEGE OF
ENGINEERING & TECHNOLOGY
(APPROVED BY AICTE, MINISTRY OF HRD,GOVT. OF INDIA & AFFILIATED TO RTU, KOTA)
PHAGI, JAIPUR -303005
A PRESENTATION OF SUMMER VACATION TRAINING IN “NTPC”
BARH, PATNA
SUBMITED BY - AJEET KUMAR
NTPC BARH
NTPC OVERVIEW
 NTPC Limited (Formerly National Thermal Power Corporation) is the largest
power generation company in India and was founded on November 7,
1975.
 Contributing 26% of country’s entire power generation, it has placed itself
in the Nav - Ratan companies of Indian government and hence is the
public sector company.
 The total installed capacity of the company is 31134 MW
 NTPC has been operating its plants at high efficiency levels. Although the
company has 18.79% of the total national capacity it contributes 28.60%
of total power generation due to its focus on high efficiency.
 The company has set a future goal of having 75000 MW by 2017.
Beneficiary state
The states & UTs of Northern & Western regions and state of Bihar
 Coal before fixing in the furnace is
Pulverized.coal pulverization is required in
the whole system process not just in terms of
furnace performance and heat rate but in
terms of mechanical reliability and integrity
of furnace.
 Flame is established in the furnace
Using the LDO(light diesel oil).LDO is
atomized by applying arc to it.
 Coal+air- Co2+CO+Sox+MOx+heat+ASH
Here CO2-heat carrier
CO-Acidic, danger to tubes(less air)
MOX,SOX-Acidic formation in water
bodies and atmosphere.
 To avoid the gases CO,MOX,SOX a ratio is maintained between air and coal of 1:6.It also ensures
proper combustion.The water is purified(DM water) before injunction in the furnace to prevent
choking of pipes due to the scale formation.
1.BOILER
2.TURBINES
3.COOLING WATER PUMP
4.CONDENSER
5.DEAREATOR
6.REHEATER
7.AIR PREHEATER
8.PRECIPITATOR
9.ECONOMISER
10.COOLING TOWER
11.TRANSMISSION LINES(3 PHASE)
12.UNIT TRANSFORMERS(3 PHASE)
13.ELECTRIC GENERATORS(3 PHASE)
14.CONDENSATE EXTRACTION
PUMP
15. Steam governor valve
16. FEED HEATER
17.COAL CONVEYOR
18.COAL HOPPER
19.FORCED DRAUGHT FAN
20.FLUE GAS
Boiler is a rectangular furnace about 50 feet on side and 130 feet tall. theirs walls
are made of high pressure steel tubes about 2.3 inches in diameter which circulates
DM water to be converted into steam. The thermal radiation heats water and
changes to steam. Steam is sent to the turbine .The efficiency and technology of
boiler vary according to the operational pressures.
1. Operational pressure>221 KSC---%n=42.45%-----super critical boiler
2. 175KSC <Operational pressure<221 KSC---%n=38.42%----- critical boiler
3. Operational pressure<175KSC---%n=38%-----sub critical boiler
The turbine generator consists of a series of steam turbines interconnected to each
other and generators on a common shaft.
It pumps the water from the cooling tower which goes to the condenser.
The steam coming out from the Low Pressure Turbine
(a little above its boiling pump) is brought into thermal
contact with cold water (pumped in from the cooling
tower) in the condenser, where it condenses rapidly
back into water, creating near Vacuum-like conditions
inside the condenser chest.
A deareator is a device for air removal and used to remove
dissolved gases (an alternate would be the use of water
treatment chemicals) from boiler feed water to make it
noncorrosive.
Reheater is a heater which is used to raise the
temperature of steam which has fallen from the
intermediate pressure turbine.
The purpose of the air preheater is to recover the heat from
the boiler flue gas which increases the thermal efficiency
of the boiler by reducing the useful heat lost in the flue
gas.
An Electrostatic precipitator (ESP) is a particulate device that
removes particles from a flowing gas (such as air) using the force of
an induced electrostatic charge.
 General Voltage Level
LT – 415 V
HT – 11KV & 3.3 KV
EHT – 400KV
 Voltage generation level (NTPC Barh)
stage 1 – 24.5kv
stage 2 – 21.5kv
 voltage level ( power plant)
5.5kv, 11kv, 132kv,400kv
Switchyard is considered as the HEART of the Power Plant. Power generated can be worthy only if it is
successfully transmitted and received by its consumers. Switchyard plays a very important role as a junction
between the generation and transmission. It is a junction, which carries the generated power to its destination (i.e.
consumers).
Outdoor equipments
1. Bus bar
2. Lightening Arrester
3. Wavetrap
4. Breaker
5. Capacitive voltage transformer
6. Earthingrod
7. Current transformer
8. Potential transformer
9. Lightening Mask
Indoor equipments
1. Relays
2. Control panels’
3. Circuit breakers
1. Bus bar
In electrical power distribution, a busbar is a strip or
bar of copper, brass or aluminium that conducts electricity
within a switchboard, distribution board, substation,
battery bank, or other electrical apparatus.
PICTORIAL VIEW OF BUS BAR
A lightning arrester is a device used on electrical
power systems and telecommunications systems to
protect the insulation and conductors of the system
from the damaging effects of lightning. The typical
lightning arrester has a high-voltage terminal and a
ground terminal.
2.lightning arrester
PICTORIAL VIEW OF LIGHTNING ARRESTER
3.wave trap
Wave Traps are used at sub-stations using Power Line
Carrier Communication (PLCC). PLCC is used to
transmit communication and control information at a
high frequency over the power lines..
4 .Breaker
A circuit breaker is an automatically operated
electrical switch designed to protect an electrical
circuit from damage caused by overload or short
circuit. Its basic function is to detect a fault condition
and interrupt current flow.
Depending on the arc quenching medium being used C.B.s can be categorizedinto various
types. In BSTPP for 400 KV/132 KV switchyard only one type is being used
ACB (Air break circuit breaker):-
operated as well asarc quenched through air.
BOCB (Bulk oil circuit breaker):-
arc quenching done through oil(Aerosol fluid oil).
MOCB (Minimum oil circuit breaker):-
arc quenching done through oil(Aerosol fluid oil).
ABCB (Air Blast Circuit Breaker):-
arc quenching done by blast of air
SF6 circuit breaker:-
arc quenching done through SF6 gas.
A capacitor voltage transformer (CVT), or
capacitance-coupled voltage transformer (CCVT), is
a transformer used in power systems to step down
extra high voltage signals and provide a low voltage
signal.
5. CAPACITIVE VOLTAGE TRANSFORMER
6.CURRENT TRANSFORMER
The current transformer is a step up transformer , it
means current is stepped down to a very low value
(generally 1 A or 5 A) so that it can be used for
measuring and protection purposes .
Current Transformer is used for basically two major functions: -
1 .Metering
which means current measurement.
2. Protection
such as over current protection, overload earth faultprotection, Bus-bar protection, Bus
differential protection.CT is typically described by its current ratio from primary to secondary.
ISOLATOR
An isolator is one, which can break an electrical circuit when the circuit is to beswitched on
no load. These are normally used in various circuits for the purposes of isolating a certain
portion when required for maintenance etc.
In BSTPP there are two switchyards:-
(i) 400KV SWITCHYARD
(ii) 132KV SWITCHYARD
.400 KV SWITCHYARD
There are total 22 bay in 400 KV switchyard. A Bay is basically
a way for the incoming power from generator as well as
outgoing power for distribution.
 5 Bay for each generating transformer
 3 Bay for ICT(Inter Connecting Transformer)
 2 Bay for PATNA line
 2 Bay for KAHALGAON line
 2 Bay for BALIA line
 7 for FUTURE line
 1 Bay for SHUNT REACTOR
There are four main buses in 400 KV switchyard.
 Main bus – 1& 2
 Main bus – 3&4
132 KV SWITCHYARD
There are total 11 Bay in 132 KV switchyard.
 3 Bay for ICT (Inter Connecting Transformer)
 5 Bay for S.T (Station Transformer)
 2 Bay for MST (Miscellaneous Service Transformer)
 1 Bay for Bus Coupler
There are two main buses in 132 KV switchyard.
 Main bus - 1
 Main bus - 2
It is a static machine which increases or decreases the AC voltage without changing the frequency of the supply. It is a
device that:
 Transfers electric power from one circuit to another.
 It accomplishes this by electromagnetic induction.
 In this the two electric circuits are in mutual inductive influence of each other.
WORKING PRINCIPLE: It works on FARADAY‟S LAW OF ELECTROMAGNETIC INDUCTION (self or
mutual induction depending on the type of transformer).
CLASSIFICATION:
(I) ACCORDING TO THE CORE: a) Core type transformer b) shell type transformer c) Berry type transformer
(II) ACCORDING TO PHASES: a) 1phase transformer b) 3phase transformer
(III) ACCORDING TO THE PURPOSE FOR WHICH USED : a) Distribution transformer b) Transmission
transformer c) Generator transformer d) Station transformer e) Unit Auxiliary transformer (UAT)
GENERATING TRANSFORMER:-
A generating transformer is a single – phase power transformer(3 single phase units shall form a
bank) . Generating Transformer steps–up the generated voltage of 24 KV by alternator to a higher
voltage of 400 KV (hence, working as a step-up Transformer).This voltage of 400 KV is then
transmitted to Switchyard
INTER CONNECTING TRANSFORMER:-
An ICT is a 3-phase auto transformer used to interconnect 400 KV switchyard and 132 KV switchyard
STATION TRANSFORMER:-
Station Transformer is used only for initializing the start-up of the station (Main Plant).It
is very beneficial during emergency situations such as tripping of Units, shut-down etc. Station
transformers is used to start Station auxiliaries a which are required for generating services such as
coal and ash handling system, lighting system, water purifying system etc
UNIT TRANSFORMER
The Unit Auxiliary Transformer is the Power Transformer that
provides power to the auxiliary equipment of a power
generating station during its normal operation.
MISCELLANEOUS SERVICE TRANSFORMER
Miscellaneous service transformer are used to supply
miscellaneous loads of plant. It is a two winding
transformer connected to 132 KV switchyard
GENERATOR SPECIFICATIONS-
KVA 247000
Pf 0.85
Volts of stator 15750
Amperes of stator 9050
Volts of rotor 310
Amperes of rotor 2600
Rpm 3000
Hz 50
Phase 3
Connection YY
Coolant water(stator)&hydrogen(rotor)
Gas pressure 3.5kg/cm-sq.
Insulation class B
Turbo generators are used in thermal power stations because of the steam energy to mechanical energy
conversion, turbo generators are more efficient.
Summer Training Report Ntpc barh (ajeet)

Más contenido relacionado

La actualidad más candente

132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction reportSumit Singh
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptaryan5808
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)Asafak Husain
 
presentation on power grid system
presentation on power grid systempresentation on power grid system
presentation on power grid systemrahul123gupta
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdfSagarRana91
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONSwatantra SwAt
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training pptShubham Patel
 
Summer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfSummer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfAbhisheksamal22
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
ELECTRIC HEATING AND HEATING METHODS
ELECTRIC HEATING AND HEATING METHODSELECTRIC HEATING AND HEATING METHODS
ELECTRIC HEATING AND HEATING METHODSDeepjyoti Patowary
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATIONPower System Operation
 

La actualidad más candente (20)

NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
 
presentation on power grid system
presentation on power grid systempresentation on power grid system
presentation on power grid system
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Summer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfSummer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdf
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
PGVCL TRAINING REPORT
PGVCL TRAINING REPORTPGVCL TRAINING REPORT
PGVCL TRAINING REPORT
 
ELECTRIC HEATING AND HEATING METHODS
ELECTRIC HEATING AND HEATING METHODSELECTRIC HEATING AND HEATING METHODS
ELECTRIC HEATING AND HEATING METHODS
 
Structure of power system
Structure of power systemStructure of power system
Structure of power system
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
 

Destacado

NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORTAnkur Pal
 
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAINING
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAININGAmit Sharma 2012UGMEL127 INDUSTRIAL TRAINING
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAININGAmit Sharma
 
Ntpc LNCT training report (autosaved)
Ntpc LNCT training report (autosaved)Ntpc LNCT training report (autosaved)
Ntpc LNCT training report (autosaved)Ankit Kumar
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALMilind Punj
 
4 week summer training report
4 week summer training report4 week summer training report
4 week summer training reportanand bhatnagar
 
Contract Procurement Management Report of Ntpc
Contract Procurement Management Report of  NtpcContract Procurement Management Report of  Ntpc
Contract Procurement Management Report of Ntpc1988chandan
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTARVIND NEGI
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineeringYogesh Jadoun
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Vocational training in NTPC
Vocational training in NTPCVocational training in NTPC
Vocational training in NTPCMohindra
 

Destacado (16)

NTPC PROJECT..
NTPC PROJECT..NTPC PROJECT..
NTPC PROJECT..
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAINING
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAININGAmit Sharma 2012UGMEL127 INDUSTRIAL TRAINING
Amit Sharma 2012UGMEL127 INDUSTRIAL TRAINING
 
Ntpc LNCT training report (autosaved)
Ntpc LNCT training report (autosaved)Ntpc LNCT training report (autosaved)
Ntpc LNCT training report (autosaved)
 
Main proj
Main projMain proj
Main proj
 
NTPC Report
NTPC ReportNTPC Report
NTPC Report
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
Ntpc
NtpcNtpc
Ntpc
 
4 week summer training report
4 week summer training report4 week summer training report
4 week summer training report
 
Contract Procurement Management Report of Ntpc
Contract Procurement Management Report of  NtpcContract Procurement Management Report of  Ntpc
Contract Procurement Management Report of Ntpc
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORT
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Vocational training in NTPC
Vocational training in NTPCVocational training in NTPC
Vocational training in NTPC
 

Similar a Summer Training Report Ntpc barh (ajeet)

NTPC Barh Training Report .pptx
NTPC Barh Training Report .pptxNTPC Barh Training Report .pptx
NTPC Barh Training Report .pptxRahulRaj598351
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationSaumyadip Moitra
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)shovandey07
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation Madeen Kumar
 
Ppt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distributionPpt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distributionSuvamSahu2
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalPiyush Dwivedi
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdfSinghJi18
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPURsahid raja khan
 

Similar a Summer Training Report Ntpc barh (ajeet) (20)

Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
NTPC Barh Training Report .pptx
NTPC Barh Training Report .pptxNTPC Barh Training Report .pptx
NTPC Barh Training Report .pptx
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
Ppt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distributionPpt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distribution
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electrical
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf220kvgss-180808104033 (1).pdf
220kvgss-180808104033 (1).pdf
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
Electrostatic Precipitator
Electrostatic Precipitator Electrostatic Precipitator
Electrostatic Precipitator
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
ntpc
ntpcntpc
ntpc
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 

Último

DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamUiPathCommunity
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Zilliz
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 

Último (20)

DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 

Summer Training Report Ntpc barh (ajeet)

  • 1. STANI MEMORIAL COLLEGE OF ENGINEERING & TECHNOLOGY (APPROVED BY AICTE, MINISTRY OF HRD,GOVT. OF INDIA & AFFILIATED TO RTU, KOTA) PHAGI, JAIPUR -303005 A PRESENTATION OF SUMMER VACATION TRAINING IN “NTPC” BARH, PATNA SUBMITED BY - AJEET KUMAR
  • 3. NTPC OVERVIEW  NTPC Limited (Formerly National Thermal Power Corporation) is the largest power generation company in India and was founded on November 7, 1975.  Contributing 26% of country’s entire power generation, it has placed itself in the Nav - Ratan companies of Indian government and hence is the public sector company.  The total installed capacity of the company is 31134 MW  NTPC has been operating its plants at high efficiency levels. Although the company has 18.79% of the total national capacity it contributes 28.60% of total power generation due to its focus on high efficiency.  The company has set a future goal of having 75000 MW by 2017.
  • 4.
  • 5. Beneficiary state The states & UTs of Northern & Western regions and state of Bihar
  • 6.  Coal before fixing in the furnace is Pulverized.coal pulverization is required in the whole system process not just in terms of furnace performance and heat rate but in terms of mechanical reliability and integrity of furnace.  Flame is established in the furnace Using the LDO(light diesel oil).LDO is atomized by applying arc to it.  Coal+air- Co2+CO+Sox+MOx+heat+ASH Here CO2-heat carrier CO-Acidic, danger to tubes(less air) MOX,SOX-Acidic formation in water bodies and atmosphere.  To avoid the gases CO,MOX,SOX a ratio is maintained between air and coal of 1:6.It also ensures proper combustion.The water is purified(DM water) before injunction in the furnace to prevent choking of pipes due to the scale formation.
  • 7. 1.BOILER 2.TURBINES 3.COOLING WATER PUMP 4.CONDENSER 5.DEAREATOR 6.REHEATER 7.AIR PREHEATER 8.PRECIPITATOR 9.ECONOMISER 10.COOLING TOWER 11.TRANSMISSION LINES(3 PHASE) 12.UNIT TRANSFORMERS(3 PHASE) 13.ELECTRIC GENERATORS(3 PHASE) 14.CONDENSATE EXTRACTION PUMP 15. Steam governor valve 16. FEED HEATER 17.COAL CONVEYOR 18.COAL HOPPER 19.FORCED DRAUGHT FAN 20.FLUE GAS
  • 8. Boiler is a rectangular furnace about 50 feet on side and 130 feet tall. theirs walls are made of high pressure steel tubes about 2.3 inches in diameter which circulates DM water to be converted into steam. The thermal radiation heats water and changes to steam. Steam is sent to the turbine .The efficiency and technology of boiler vary according to the operational pressures. 1. Operational pressure>221 KSC---%n=42.45%-----super critical boiler 2. 175KSC <Operational pressure<221 KSC---%n=38.42%----- critical boiler 3. Operational pressure<175KSC---%n=38%-----sub critical boiler The turbine generator consists of a series of steam turbines interconnected to each other and generators on a common shaft. It pumps the water from the cooling tower which goes to the condenser.
  • 9. The steam coming out from the Low Pressure Turbine (a little above its boiling pump) is brought into thermal contact with cold water (pumped in from the cooling tower) in the condenser, where it condenses rapidly back into water, creating near Vacuum-like conditions inside the condenser chest. A deareator is a device for air removal and used to remove dissolved gases (an alternate would be the use of water treatment chemicals) from boiler feed water to make it noncorrosive.
  • 10. Reheater is a heater which is used to raise the temperature of steam which has fallen from the intermediate pressure turbine. The purpose of the air preheater is to recover the heat from the boiler flue gas which increases the thermal efficiency of the boiler by reducing the useful heat lost in the flue gas. An Electrostatic precipitator (ESP) is a particulate device that removes particles from a flowing gas (such as air) using the force of an induced electrostatic charge.
  • 11.  General Voltage Level LT – 415 V HT – 11KV & 3.3 KV EHT – 400KV  Voltage generation level (NTPC Barh) stage 1 – 24.5kv stage 2 – 21.5kv  voltage level ( power plant) 5.5kv, 11kv, 132kv,400kv
  • 12. Switchyard is considered as the HEART of the Power Plant. Power generated can be worthy only if it is successfully transmitted and received by its consumers. Switchyard plays a very important role as a junction between the generation and transmission. It is a junction, which carries the generated power to its destination (i.e. consumers). Outdoor equipments 1. Bus bar 2. Lightening Arrester 3. Wavetrap 4. Breaker 5. Capacitive voltage transformer 6. Earthingrod 7. Current transformer 8. Potential transformer 9. Lightening Mask Indoor equipments 1. Relays 2. Control panels’ 3. Circuit breakers
  • 13. 1. Bus bar In electrical power distribution, a busbar is a strip or bar of copper, brass or aluminium that conducts electricity within a switchboard, distribution board, substation, battery bank, or other electrical apparatus. PICTORIAL VIEW OF BUS BAR A lightning arrester is a device used on electrical power systems and telecommunications systems to protect the insulation and conductors of the system from the damaging effects of lightning. The typical lightning arrester has a high-voltage terminal and a ground terminal. 2.lightning arrester PICTORIAL VIEW OF LIGHTNING ARRESTER
  • 14. 3.wave trap Wave Traps are used at sub-stations using Power Line Carrier Communication (PLCC). PLCC is used to transmit communication and control information at a high frequency over the power lines.. 4 .Breaker A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. Its basic function is to detect a fault condition and interrupt current flow.
  • 15. Depending on the arc quenching medium being used C.B.s can be categorizedinto various types. In BSTPP for 400 KV/132 KV switchyard only one type is being used ACB (Air break circuit breaker):- operated as well asarc quenched through air. BOCB (Bulk oil circuit breaker):- arc quenching done through oil(Aerosol fluid oil). MOCB (Minimum oil circuit breaker):- arc quenching done through oil(Aerosol fluid oil). ABCB (Air Blast Circuit Breaker):- arc quenching done by blast of air SF6 circuit breaker:- arc quenching done through SF6 gas.
  • 16. A capacitor voltage transformer (CVT), or capacitance-coupled voltage transformer (CCVT), is a transformer used in power systems to step down extra high voltage signals and provide a low voltage signal. 5. CAPACITIVE VOLTAGE TRANSFORMER 6.CURRENT TRANSFORMER The current transformer is a step up transformer , it means current is stepped down to a very low value (generally 1 A or 5 A) so that it can be used for measuring and protection purposes .
  • 17. Current Transformer is used for basically two major functions: - 1 .Metering which means current measurement. 2. Protection such as over current protection, overload earth faultprotection, Bus-bar protection, Bus differential protection.CT is typically described by its current ratio from primary to secondary. ISOLATOR An isolator is one, which can break an electrical circuit when the circuit is to beswitched on no load. These are normally used in various circuits for the purposes of isolating a certain portion when required for maintenance etc.
  • 18. In BSTPP there are two switchyards:- (i) 400KV SWITCHYARD (ii) 132KV SWITCHYARD .400 KV SWITCHYARD There are total 22 bay in 400 KV switchyard. A Bay is basically a way for the incoming power from generator as well as outgoing power for distribution.  5 Bay for each generating transformer  3 Bay for ICT(Inter Connecting Transformer)  2 Bay for PATNA line  2 Bay for KAHALGAON line  2 Bay for BALIA line  7 for FUTURE line  1 Bay for SHUNT REACTOR There are four main buses in 400 KV switchyard.  Main bus – 1& 2  Main bus – 3&4 132 KV SWITCHYARD There are total 11 Bay in 132 KV switchyard.  3 Bay for ICT (Inter Connecting Transformer)  5 Bay for S.T (Station Transformer)  2 Bay for MST (Miscellaneous Service Transformer)  1 Bay for Bus Coupler There are two main buses in 132 KV switchyard.  Main bus - 1  Main bus - 2
  • 19. It is a static machine which increases or decreases the AC voltage without changing the frequency of the supply. It is a device that:  Transfers electric power from one circuit to another.  It accomplishes this by electromagnetic induction.  In this the two electric circuits are in mutual inductive influence of each other. WORKING PRINCIPLE: It works on FARADAY‟S LAW OF ELECTROMAGNETIC INDUCTION (self or mutual induction depending on the type of transformer). CLASSIFICATION: (I) ACCORDING TO THE CORE: a) Core type transformer b) shell type transformer c) Berry type transformer (II) ACCORDING TO PHASES: a) 1phase transformer b) 3phase transformer (III) ACCORDING TO THE PURPOSE FOR WHICH USED : a) Distribution transformer b) Transmission transformer c) Generator transformer d) Station transformer e) Unit Auxiliary transformer (UAT)
  • 20. GENERATING TRANSFORMER:- A generating transformer is a single – phase power transformer(3 single phase units shall form a bank) . Generating Transformer steps–up the generated voltage of 24 KV by alternator to a higher voltage of 400 KV (hence, working as a step-up Transformer).This voltage of 400 KV is then transmitted to Switchyard INTER CONNECTING TRANSFORMER:- An ICT is a 3-phase auto transformer used to interconnect 400 KV switchyard and 132 KV switchyard STATION TRANSFORMER:- Station Transformer is used only for initializing the start-up of the station (Main Plant).It is very beneficial during emergency situations such as tripping of Units, shut-down etc. Station transformers is used to start Station auxiliaries a which are required for generating services such as coal and ash handling system, lighting system, water purifying system etc
  • 21. UNIT TRANSFORMER The Unit Auxiliary Transformer is the Power Transformer that provides power to the auxiliary equipment of a power generating station during its normal operation. MISCELLANEOUS SERVICE TRANSFORMER Miscellaneous service transformer are used to supply miscellaneous loads of plant. It is a two winding transformer connected to 132 KV switchyard
  • 22. GENERATOR SPECIFICATIONS- KVA 247000 Pf 0.85 Volts of stator 15750 Amperes of stator 9050 Volts of rotor 310 Amperes of rotor 2600 Rpm 3000 Hz 50 Phase 3 Connection YY Coolant water(stator)&hydrogen(rotor) Gas pressure 3.5kg/cm-sq. Insulation class B Turbo generators are used in thermal power stations because of the steam energy to mechanical energy conversion, turbo generators are more efficient.