Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
1. ORIENTAL ENTERPRISES
MIC BUSINESS & RECREATION BLDG
SUMMARY of WORKS
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Late
Start
Late
Finish
MHRS
MIC BUSINESS & RECREATION BLDG
PRELIMINARIES & GENERAL MATTERS
PROJECT MILESTONE
PRELIMINARIES
ML1000 Commencement Order to Proceed 0 01MAY11 01MAY11 0
ML1010 OE Receive IFC Drawings 0 01MAY11 01MAY11 0
ML1020 Completion of Project 0 31OCT12 31OCT12 0
ML1030 Site Safety Induction of Workers&Kick Off 0 09MAY11 09MAY11 0
GENERAL MATTERS
PRELIMINARIES
GM1000 Site Handover to Orientals 1 01MAY11 01MAY11 01MAY11 01MAY11 0
GM1010 OE recieve Contract Documents 1 01MAY11 01MAY11 01MAY11 01MAY11 0
GM1020 Collect Building Permit & Approvals 1 01MAY11 01MAY11 01MAY11 01MAY11 0
GM1030 OE Receive Downpayment 7 01MAY11 08MAY11 01MAY11 08MAY11 0
MOBILIZATION
PRELIMINARIES
MO1000 Project Mobilization 6 02MAY11 08MAY11 02MAY11 08MAY11 0
MO1010 Site Survey Works & Construction 471 02MAY11 31OCT12 02MAY11 31OCT12 0
MO1020 Construction of Temp Facil, Site 36 09MAY11 19JUN11 08JUN11 19JUL11 1,875
ENGINEERING & PROCUREMENT
+ SHOP DRAWING SUBMITTALS & APPROVALS
90 24MAY11 05SEP11 19JUL12 31OCT12 0
+ MATERIAL SUBMITTALS & APPROVALS
60 02MAY11 10JUL11 11DEC11 18FEB12 0
+ LONG LEAD ITEMS
150 26MAY11 16NOV11 04JAN12 05AUG12 0
+ STEEL WORKS DESIGN & FABRICATION
103 01MAY11 28AUG11 04JUL12 31OCT12 0
MAIN RECREATION CLUB ZONE 1
+ CONSTRUCTION OF ZONE 1 BUILDING
404 09MAY11 21AUG12 09MAY11 31OCT12 122,239
+ BASEMENT
170 09MAY11 22NOV11 10DEC11 31OCT12 27,131
2011 2012
APRM J J A S O N D J F M A M J J A S O N DJAN
Commencement Order to Proceed
OE Receive IFC Drawings
Completion of Project
Site Safety Induction of Workers&Kick Off Meetng
Site Handover to Orientals
OE recieve Contract Documents
Collect Building Permit & Approvals
OE Receive Downpayment
Project Mobilization
Site Survey
Construction of Temp Facil, Site Store&Hoarding
2. Sheet 2 of 2
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Late
Start
Late
Finish
MHRS
MAIN RECREATION CLUB ZONE 2
+ CONSTRUCTION OF ZONE 2 BUILDING
283 27SEP11 21AUG12 02JAN12 31OCT12 107,218
MAIN RECREATION CLUB ZONE 3
+ CONSTRUCTION OF ZONE 3 BUILDING
254 31OCT11 21AUG12 05FEB12 31OCT12 108,981
EXTERNAL WORKS & INFRASTRUCTURE
+ EXTERNAL WORKS
465 09MAY11 31OCT12 08AUG11 31OCT12 32,074
+ SWIMMING POOL
232 05JUL11 31MAR12 05FEB12 31OCT12 38,476
+ TENNIS COURT
127 01DEC11 26APR12 06JUN12 31OCT12 10,763
+ CHILLER COMPOUND
116 24NOV11 07APR12 30MAY12 31OCT12 5,735
+ GUARD HOUSE
89 22OCT11 01FEB12 26JUN12 31OCT12 2,442
+ SECURITY OFFICE
89 15NOV11 26FEB12 21JUL12 31OCT12 2,324
FENCING WORKS
+ CONCRETE FENCE WORKS
84 20JUN12 25SEP12 26JUL12 31OCT12 8,603
HAND-OVER & CLOSE OUT
+ CONSTRUCTION OF ZONE 1 BUILDING
28 18AUG12 18SEP12 06SEP12 31OCT12 850
+ CONSTRUCTION OF ZONE 2 BUILDING
28 01SEP12 02OCT12 20SEP12 31OCT12 850
+ CONSTRUCTION OF ZONE 3 BUILDING
24 19SEP12 16OCT12 04OCT12 31OCT12 850
2011 2012
APRM J J A S O N D J F M A M J J A S O N DJAN
Sheet 2 of 2
4. Sheet 2 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
STEEL WORKS DESIGN & FABRICATION
STEEL FABRICATION PHASE
FAB1000 Submission of Steel Structural Design 14 01MAY11 16MAY11 0
FAB1010 Approval of Steel Structural Design Drawings 6 17MAY11 23MAY11 0
FAB1020 Submission of Steel Design Connection 12 24MAY11 06JUN11 0
FAB1030 Approval of Steel Design for Fabrication 6 07JUN11 13JUN11 0
FAB1040 Provide Steel Build Design 60 14JUN11 22AUG11 0
FAB1050 Fabrication of Steel Structure 60 14JUN11 22AUG11 0
FAB1060 Delivery of Structural Steel to Site 15 11AUG11 28AUG11 0
MAIN RECREATION CLUB ZONE 1
CONSTRUCTION OF ZONE 1 BUILDING
MILESTONE
A01-0010 Completion of Superstructures 0 30NOV11 0
A01-0020 Completion of Finishes 0 08JAN12 0
A01-0030 Completion of MEPD-HVAC 0 21AUG12 0
SITE PREPARATION, EXCAVATION & EARTHWORKS
A01-1000 Excavation 15 09MAY11 25MAY11 1,051 m3
A01-1010 Disposal of Surplus Exc. Materials 10 23MAY11 02JUN11 1,499 m3
SUBSTRUCTURE WORKS
A01-1020 Blinding below Foundation 6 16MAY11 22MAY11 30 m3
A01-1030 Water Proofing to Foundation 7 18MAY11 25MAY11 405 m2
A01-1040 Rebar Installation to Isolated Footing 6 19MAY11 25MAY11 27,678 kg
A01-1050 Formworks for Footings 6 23MAY11 29MAY11 861 m2
A01-1060 Casting for Isolated Footing 5 28MAY11 01JUN11 161 m3
A01-1070 Backfilling Around Foundation 8 31MAY11 08JUN11 388 m3
A01-1080 Rebar for Column Stumps 5 31MAY11 05JUN11 21,145 kg
A01-1090 Formworks for Column Stumps 5 02JUN11 07JUN11 155 m2
A01-1100 Casting for Column Stumps 3 06JUN11 08JUN11 29 m3
A01-1120 Bitumenous Concrete Protection 9 09JUN11 19JUN11 564 m2
A01-1130 Backfilling by Layer to Below Ground Beam 4 12JUN11 15JUN11 129 m3
A01-1140 Blinding to below Ground beam 5 13JUN11 18JUN11 38 m3
A01-1150 Rebar for Ground Beam 15 14JUN11 30JUN11 45,728 kg
A01-1160 Formworks for Ground Beam 15 16JUN11 03JUL11 1,423 m2
A01-1170 Casting for Ground Beam 6 30JUN11 06JUL11 266 m3
A01-1180 Backfilling to below Ground Slab 3 03JUL11 05JUL11 129 m3
A01-1190 Blinding to below Ground Slab 7 05JUL11 12JUL11 430 m3
A01-1200 Water proofing to Ground Slab 6 06JUL11 12JUL11 5,728 m2
A01-1210 Fabric Reinforcement A252mesh to Ground 9 07JUL11 17JUL11 5,728 m2
A01-1220 Casting of Ground Slab 9 10JUL11 19JUL11 879 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Submission of Steel Structural Design Drawing
Approval of Steel Structural Design Drawings
Submission of Steel Design Connection Details
Approval of Steel Design for Fabrication
Provide Steel Build Design Module(BOM)Erection
Fabrication of Steel Structure
Delivery of Structural Steel to Site
Completion of Superstructures
Completion of Finishes
Completion of MEPD-HVAC
Excavation
Disposal of Surplus Exc. Materials
Blinding below Foundation
Water Proofing to Foundation
Rebar Installation to Isolated Footing
Formworks for Footings
Casting for Isolated Footing
Backfilling Around Foundation
Rebar for Column Stumps
Formworks for Column Stumps
Casting for Column Stumps
Bitumenous Concrete Protection
Backfilling by Layer to Below Ground Beam
Blinding to below Ground beam
Rebar for Ground Beam
Formworks for Ground Beam
Casting for Ground Beam
Backfilling to below Ground Slab
Blinding to below Ground Slab
Water proofing to Ground Slab
Fabric Reinforcement A252mesh to Ground Slab
Casting of Ground Slab
Sheet 2 of 25
5. Sheet 3 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SUPERSTRUCTURE-CONCRETE WORKS
GROUND FLOOR
A01-1230 Rebar for Ground Floor Column 12 31MAY11 13JUN11 18,394 kg
A01-1240 Formworks for Ground Floor Column 12 04JUN11 16JUN11 572 m2
A01-1250 Casting for Ground Floor Column 4 15JUN11 19JUN11 107 m3
A01-1311 Hollow Core Slab Installation 12 20AUG11 01SEP11 2,374 m2
A01-1260 Staircase & Lintel Formworks GF 12 22AUG11 04SEP11 32 m2
A01-1270 Staircase & Lintel Rebars GF 12 25AUG11 07SEP11 1,031 kg
A01-1312 Hollow Core Slab Toppings 12 30AUG11 12SEP11 2,374 m2
A01-1280 Stair Case & Lintel Beams Casting GF 9 06SEP11 15SEP11 6 m3
FIRST FLOOR
A01-1290 Formworks for First Floor Beam,Slab& Corbel 12 24JUL11 06AUG11 893 m2
A01-1300 Rebar for First Floor Beam & Corbel 12 27JUL11 09AUG11 28,709 kg
A01-1310 Casting for First Floor Beam & Corbel 6 06AUG11 11AUG11 167 m3
A01-1350 Rebar for First Floor Column 12 09AUG11 22AUG11 18,394 kg
A01-1360 Formworks for First Floor Column 12 13AUG11 25AUG11 572 m2
A01-1370 Casting for First Floor Column 4 24AUG11 28AUG11 107 m3
A01-1320 Staircase & Lintel Formworks FF 12 03SEP11 15SEP11 32 m2
A01-1330 Staircase & Lintel Rebars FF 12 06SEP11 19SEP11 1,031 kg
A01-1361 Incline Roof Formworks GF 21 10SEP11 03OCT11 797 m2
A01-1362 Incline Roof Rebars GF 20 13SEP11 05OCT11 25,615 kg
A01-1340 Stair Case & Lintel Beams Casting FF 9 18SEP11 27SEP11 6 m3
A01-1363 Incline Roof Casting GF 14 04OCT11 19OCT11 149 m3
ROOF
A01-1470 Formworks for Roof Slab & Beam 12 31AUG11 13SEP11 893 m2
A01-1480 Rebar for Roof Slab & Beam 12 04SEP11 17SEP11 28,709 kg
A01-1490 Casting for Roof Floor Slab & Beam 6 15SEP11 21SEP11 167 m3
A01-1500 Incline Roof Formworks RF 21 27OCT11 20NOV11 797 m2
A01-1510 Incline Roof Rebars RF 21 31OCT11 23NOV11 25,615 kg
A01-1520 Incline Roof Casting RF 9 21NOV11 30NOV11 149 m3
STEEL STRUCTURAL WORKS
ROOF
A01-1570 Mero Space Frame Installation & Supports 21 12OCT11 05NOV11 2,542 m2
A01-1571 Purlin & isulation Installation 21 02NOV11 26NOV11 2,542 m2
A01-1572 Roof Sandwich Panel Cladding 15 14NOV11 30NOV11 2,542 m2
A01-1573 Inclined wall Cladding 35 18DEC11 26JAN12 1 item
MASONRY WORKS
GROUND FLOOR
A01-1530 Block Works for Ground Floor 26 22AUG11 20SEP11 1,945 m2
A01-1540 Plastering for Ground Floor 26 29AUG11 27SEP11 3,956 m2
FIRST FLOOR
A01-1550 Block Works for First Floor 21 04SEP11 27SEP11 1,945 m2
A01-1560 Plastering for First Floor 21 11SEP11 04OCT11 3,956 m2
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Rebar for Ground Floor Column
Formworks for Ground Floor Column
Casting for Ground Floor Column
Hollow Core Slab Installation
Staircase & Lintel Formworks GF
Staircase & Lintel Rebars GF
Hollow Core Slab Toppings
Stair Case & Lintel Beams Casting GF
Formworks for First Floor Beam,Slab& Corbel
Rebar for First Floor Beam & Corbel
Casting for First Floor Beam & Corbel
Rebar for First Floor Column
Formworks for First Floor Column
Casting for First Floor Column
Staircase & Lintel Formworks FF
Staircase & Lintel Rebars FF
Incline Roof Formworks GF
Incline Roof Rebars GF
Stair Case & Lintel Beams Casting FF
Incline Roof Casting GF
Formworks for Roof Slab & Beam
Rebar for Roof Slab & Beam
Casting for Roof Floor Slab & Beam
Incline Roof Formworks RF
Incline Roof Rebars RF
Incline Roof Casting RF
Mero Space Frame Installation & Supports
Purlin & isulation Installation
Roof Sandwich Panel Cladding
Inclined wall Cladding
Block Works for Ground Floor
Plastering for Ground Floor
Block Works for First Floor
Plastering for First Floor
Sheet 3 of 25
6. Sheet 4 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
ROOF
A01-1590 Block Works for Roof Parapet Wall 9 19SEP11 28SEP11 1,945 m2
A01-1600 Plastering for Roof Parapet 12 22SEP11 05OCT11 3,956 m2
A01-1610 Roof Plint Construction 21 07NOV11 30NOV11 1 item
ROOFING WORKS
ROOF
A01-1620 Thermal Isulation & Proofing Roof Floor 21 07NOV11 30NOV11 2,661 m2
A01-1630 Protective Chip &Pre cast Slab Cover at Roof 21 01DEC11 25DEC11 2,661 m2
A01-1631 Water Proofing to Incline Roof 21 18DEC11 10JAN12 1,483 m2
FLOOR, WALL & CEILING FINISH
GROUND FLOOR
A01-1640 Floor Screeding Ground Floor 12 15SEP11 28SEP11 1,381 m2
A01-1650 Non Slip Porcelain Floor Tiling Works 18 27SEP11 17OCT11 388 m2
A01-1660 Stair & Ramp Tiling works 12 27SEP11 10OCT11 65 m2
A01-1670 Ceramic Floor Tiling Works 18 03OCT11 23OCT11 320 m2
A01-1680 Carpet Tiling Works 12 09OCT11 22OCT11 1,014 m2
A01-1690 Granite Tiling Works 6 11OCT11 17OCT11 524 m2
A01-1700 Wood Tiling Works 15 11OCT11 27OCT11 85 m2
A01-1710 Epoxy paint Finish 15 11OCT11 27OCT11 635 m2
A01-1730 Gypsum Board Suspended Ceiling 15 17OCT11 02NOV11 1,526 m2
A01-1720 Moisture Resistant Suspended Ceiling 15 22OCT11 07NOV11 1,065 m2
FIRST FLOOR
A01-1740 Floor Screeding First Floor 12 25SEP11 08OCT11 1,381 m2
A01-1750 Non Slip Porcelain Floor Tiling Works 12 05OCT11 18OCT11 388 m2
A01-1760 Ceramic FloorTiling Works 18 19OCT11 08NOV11 320 m2
A01-1770 Carpet Tiling Works 12 19OCT11 01NOV11 1,014 m2
A01-1780 Granite Tiling Works 6 19OCT11 25OCT11 524 m2
A01-1830 Gypsum Board Suspended Ceiling 15 19OCT11 05NOV11 1,526 m2
A01-1820 Moisture Resistant Suspended Ceiling 15 23OCT11 08NOV11 1,065 m2
A01-1790 Wood Tiling Works 15 26OCT11 12NOV11 85 m2
A01-1800 Steps & Stairs Tiling works 6 26OCT11 01NOV11 65 m2
A01-1810 Epoxy paint Finish 15 26OCT11 12NOV11 635 m2
A01-1811 Ceramic Wall Tiling Works 21 26OCT11 19NOV11 1,437 m2
JOINERY & CARPENTRY
A01-1940 Timber Frames Installation 35 12OCT11 21NOV11 96 no
A01-1960 Bulkhead & Linings 21 19OCT11 12NOV11 265 m
A01-1970 Vanity Countertops Installation 21 23OCT11 15NOV11 22 m
A01-1980 Modular Wall System Panels 35 23OCT11 01DEC11 129 m2
A01-1081 Partition Wall System Panels 35 30OCT11 08DEC11 216 m2
A01-1950 Timber Doors Installation & Ironmongries 35 22NOV11 01JAN12 96 no
A01-1951 Equipment Furnishings 35 22NOV11 01JAN12 1 item
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Block Works for Roof Parapet Wall
Plastering for Roof Parapet
Roof Plint Construction
Thermal Isulation & Proofing Roof Floor
Protective Chip &Pre cast Slab Cover at Roof Top
Water Proofing to Incline Roof
Floor Screeding Ground Floor
Non Slip Porcelain Floor Tiling Works
Stair & Ramp Tiling works
Ceramic Floor Tiling Works
Carpet Tiling Works
Granite Tiling Works
Wood Tiling Works
Epoxy paint Finish
Gypsum Board Suspended Ceiling
Moisture Resistant Suspended Ceiling
Floor Screeding First Floor
Non Slip Porcelain Floor Tiling Works
Ceramic FloorTiling Works
Carpet Tiling Works
Granite Tiling Works
Gypsum Board Suspended Ceiling
Moisture Resistant Suspended Ceiling
Wood Tiling Works
Steps & Stairs Tiling works
Epoxy paint Finish
Ceramic Wall Tiling Works
Timber Frames Installation
Bulkhead & Linings
Vanity Countertops Installation
Modular Wall System Panels
Partition Wall System Panels
Timber Doors Installation & Ironmongries
Equipment Furnishings
Sheet 4 of 25
7. Sheet 5 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
METAL & ALUMINUM WORKS
A01-2000 Aluminum Door& Sliding Doors Installation 21 05OCT11 29OCT11 23 no
A01-2020 Aluminum Window Installation 15 16OCT11 01NOV11 16 no
A01-2010 Metal Doors Installation 12 25OCT11 07NOV11 16 no
A01-1990 Decorative Circular Colum Install 21 27OCT11 20NOV11 10 no
A01-2030 Miscellaneous Steel Works 12 08NOV11 21NOV11 1 item
PAINTING & DECORATING
A01-2050 Interior Painting Works 45 09OCT11 29NOV11 10,553 m2
A01-2040 Exterior Paint Finishings 36 18OCT11 28NOV11 3,880 m2
A01-2060 Snagging & Punchlisting 6 02JAN12 08JAN12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
SUBSTRUCTURE
A01-2070 UnderGround Sanitary & Rainwater Pipe 10 04JUL11 14JUL11 882 m
GROUND FLOOR
A01-2080 Hot & Cold Domestic Pipe Installation 24 12SEP11 09OCT11 206 m
A01-2100 Fire Fighting Pipes 18 19SEP11 09OCT11 399 m
A01-2090 Sanitary Pipe Installation Rise above floor 9 28SEP11 08OCT11 24 m
A01-2120 Isolating & Alarm Valve Installation 6 03OCT11 09OCT11 5 no
A01-2110 Floor Clean out Drains & traps 12 09OCT11 22OCT11 54 no
A01-2101 LPG Pipes 18 10OCT11 30OCT11 122 m
A01-2130 Water Circulating Pump Installation 6 17NOV11 23NOV11 3 no
A01-2140 Fire Hose Reel Cabinet Installation 12 17NOV11 30NOV11 2 no
A01-2150 Sanitary Fixtures Installation 21 17NOV11 11DEC11 123 no
A01-2160 Fire Fighting Equipment Installation 35 24NOV11 03JAN12 40 no
A01-2170 Water Fountain & Sauna system 21 28NOV11 21DEC11 1 item
FIRST FLOOR
A01-2180 Hot & Cold Domestic Pipe Installation 24 25SEP11 22OCT11 206 m
A01-2190 Fire Fighting Pipes 18 02OCT11 22OCT11 399 m
A01-2200 Sanitary Pipe Installation Rise above floor 9 09OCT11 18OCT11 24 m
A01-2210 Isolating & Alarm Valve Installation 6 16OCT11 22OCT11 5 no
A01-2220 Floor Clean out Drains & traps 12 19OCT11 01NOV11 54 no
A01-2230 Fire Hose Reel Cabinet Installation 12 17NOV11 30NOV11 2 no
A01-2240 Sprinkler System Installation 12 17NOV11 30NOV11 660 no
A01-2260 Sanitary Fixtures Installation 12 17NOV11 30NOV11 123 no
A01-2250 Fire Fighting Equipment Installation 12 24NOV11 07DEC11 40 no
ROOF
A01-2360 Rain Water Pipe Installation 12 06OCT11 19OCT11 144 m
A01-2400 Precommissioning For Plumbing 6 11AUG12 16AUG12 1 item
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Aluminum Door& Sliding Doors Installation
Aluminum Window Installation
Metal Doors Installation
Decorative Circular Colum Install
Miscellaneous Steel Works
Interior Painting Works
Exterior Paint Finishings
Snagging & Punchlisting
UnderGround Sanitary & Rainwater Pipe Install
Hot & Cold Domestic Pipe Installation
Fire Fighting Pipes
Sanitary Pipe Installation Rise above floor
Isolating & Alarm Valve Installation
Floor Clean out Drains & traps
LPG Pipes
Water Circulating Pump Installation
Fire Hose Reel Cabinet Installation
Sanitary Fixtures Installation
Fire Fighting Equipment Installation
Water Fountain & Sauna system
Hot & Cold Domestic Pipe Installation
Fire Fighting Pipes
Sanitary Pipe Installation Rise above floor
Isolating & Alarm Valve Installation
Floor Clean out Drains & traps
Fire Hose Reel Cabinet Installation
Sprinkler System Installation
Sanitary Fixtures Installation
Fire Fighting Equipment Installation
Rain Water Pipe Installation
Precommissioning For Plumbing
Sheet 5 of 25
8. Sheet 6 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
ELECTRICAL WORKS
SUBSTRUCTURE
A01-2410 Underground Electrical Sleeve Installation 10 04JUL11 14JUL11 1 item
GROUND FLOOR
A01-2430 Earthing Conductor Installation 6 05SEP11 11SEP11 1 item
A01-2420 MDB & DB Enclosure to Wall 12 12SEP11 25SEP11 9 no
A01-2440 Electrical Conduiting, Cable Tray Works 21 26SEP11 19OCT11 308 m
A01-2450 Cable Pulling, Wiring & Termination 21 27SEP11 20OCT11 308 m
A01-2480 Data TV BMS&Security Sys. Installation 12 12OCT11 25OCT11 12 no
A01-2490 Fire Alarm System Installation 12 17OCT11 30OCT11 98 no
A01-2500 Telephone&ComputerSystem Installation 12 20OCT11 02NOV11 1 item
A01-2520 MV Panel, CBank & CBreaker 21 24OCT11 16NOV11 2 no
A01-2460 DB & SMDB Installation 9 17NOV11 27NOV11 9 no
A01-2470 Wall & Ceiling Mount Outlets 15 24NOV11 11DEC11 254 no
A01-2510 Lighting Fixture Installation 12 01DEC11 14DEC11 507 no
FIRST FLOOR
A01-2530 MDB & DB Enclosure to Wall 12 25SEP11 08OCT11 9 no
A01-2540 Electrical Conduiting, Cable Tray Works 21 09OCT11 01NOV11 308 m
A01-2550 Cable Pulling, Wiring & Termination 21 10OCT11 02NOV11 308 m
A01-2570 MV Panel, CBank & CBreaker 12 23OCT11 05NOV11 2 no
A01-2580 Data TV BMS&Security Sys. Installation 12 25OCT11 07NOV11 12 no
A01-2600 Telephone&ComputerSystem Installation 12 03NOV11 16NOV11 1 item
A01-2560 DB & SDDB Installation 9 17NOV11 27NOV11 9 no
A01-2590 Wall & Ceiling Mount Outlets 15 24NOV11 11DEC11 254 no
A01-2610 Fire Alarm System Installation 12 28NOV11 11DEC11 98 no
A01-2620 Lighting Fixture Installation 12 01DEC11 14DEC11 507 no
A01-2630 Earthing & Grounding Equipments & 6 08DEC11 14DEC11 1 item
A01-2750 Precommissioning Electrical & Low Current 10 08AUG12 19AUG12 1 item
HVAC WORKS
GROUND FLOOR
A01-2760 GI Duct works with Thermal Insulation 21 29SEP11 23OCT11 1,813 m2
A01-2770 Circular Duct & Isulation 15 06OCT11 23OCT11 69 m
A01-2780 Volume Control & fire Damper Installation 15 17NOV11 04DEC11 5 no
A01-2790 Supply & Return Air Diffussers 15 17NOV11 04DEC11 374 no
A01-2800 Exhaust Fans Installation 12 24NOV11 07DEC11 6 no
A01-2810 Split A/C installation 9 08DEC11 18DEC11 6 no
FIRST FLOOR
A01-2820 GI Duct works with Thermal Insulation 21 02OCT11 25OCT11 1,813 m2
A01-2830 Circular duct & Isulation 15 09OCT11 25OCT11 69 m
A01-2840 Volume Control & fire Damper Installation 15 09OCT11 25OCT11 5 no
A01-2850 Supply & Return Air Diffussers 15 09OCT11 25OCT11 374 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Underground Electrical Sleeve Installation
Earthing Conductor Installation
MDB & DB Enclosure to Wall
Electrical Conduiting, Cable Tray Works
Cable Pulling, Wiring & Termination
Data TV BMS&Security Sys. Installation
Fire Alarm System Installation
Telephone&ComputerSystem Installation
MV Panel, CBank & CBreaker
DB & SMDB Installation
Wall & Ceiling Mount Outlets
Lighting Fixture Installation
MDB & DB Enclosure to Wall
Electrical Conduiting, Cable Tray Works
Cable Pulling, Wiring & Termination
MV Panel, CBank & CBreaker
Data TV BMS&Security Sys. Installation
Telephone&ComputerSystem Installation
DB & SDDB Installation
Wall & Ceiling Mount Outlets
Fire Alarm System Installation
Lighting Fixture Installation
Earthing & Grounding Equipments & Connection
Precommissioning Electrical & Low Current
GI Duct works with Thermal Insulation
Circular Duct & Isulation
Volume Control & fire Damper Installation
Supply & Return Air Diffussers
Exhaust Fans Installation
Split A/C installation
GI Duct works with Thermal Insulation
Circular duct & Isulation
Volume Control & fire Damper Installation
Supply & Return Air Diffussers
Sheet 6 of 25
9. Sheet 7 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A01-2860 Exhaust Fans Installation 12 23OCT11 05NOV11 6 no
A01-2831 Chilled Water Pipe installation 15 26OCT11 12NOV11 438 m
A01-2870 Split A/C installation 9 08DEC11 18DEC11 6 no
A01-2940 Condenser Pipe drainage Installation 6 14NOV11 20NOV11 1 item
A01-2950 AHU unit Installation 18 18DEC11 07JAN12 6 no
A01-2951 ACCU Refrigeration unit Installation 18 22DEC11 11JAN12 3 no
A01-2960 Precommissioning For HVAC 12 08AUG12 21AUG12 1 item
A01-2970 Installation of Passenger Lift 45 09OCT11 29NOV11 3 no
A01-2980 Installation of Lift Door & Control Panels 21 20NOV11 13DEC11 1 no
A01-2990 Precommissioning of Lift 12 08AUG12 21AUG12 1 item
B01-0010 Completion of Structures 0 22NOV11 0
B01-1000 Excavation of Basement 35 09MAY11 18JUN11 3,518 m3
B01-1010 Disposal of Surplus Exc. Materials 12 13JUN11 26JUN11 1 item
B01-1020 Blinding below Foundation 18 08JUN11 28JUN11 55 m3
B01-1030 Water Proofing to Foundation 15 11JUN11 27JUN11 1,228 m2
B01-1040 Rebar Installation to Isolated Footing 15 15JUN11 02JUL11 85,955 kg
B01-1050 Formworks for Footings 15 19JUN11 05JUL11 2,675 m2
B01-1060 Casting for Isolated Footing 6 29JUN11 05JUL11 500 m3
B01-1070 Backfilling Around Foundation 8 03JUL11 11JUL11 600 m3
B01-1080 Rebar for Retaining Wall & Neck Column 15 03JUL11 19JUL11 22,348 kg
B01-1090 Formworks for Retaining Wall & Neck Column 15 05JUL11 21JUL11 696 m2
B01-1120 Bitumenous Concrete Protection 9 12JUL11 21JUL11 11,247 m2
B01-1100 Casting for Retaining Wall & Neck Column 12 19JUL11 01AUG11 130 m3
B01-1130 Backfilling by Layer to Below Ground Beam 4 21JUL11 25JUL11 400 m3
B01-1140 Blinding to below Ground beam 5 23JUL11 27JUL11 37 m3
B01-1150 Rebar for Ground Beam 6 24JUL11 30JUL11 16,847 kg
B01-1160 Formworks for Ground Beam 6 26JUL11 01AUG11 524 m2
B01-1170 Casting for Ground Beam 4 31JUL11 03AUG11 98 m3
B01-1200 Formworks to Service Corridor Slab 6 07AUG11 13AUG11 2,017 m2
B01-1210 Rebar to Service Corridor 9 08AUG11 17AUG11 136 m2
B01-1220 Casting of Service Corridor Slab 9 10AUG11 20AUG11 377 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Exhaust Fans Installation
Chilled Water Pipe installation
Split A/C installation
Condenser Pipe drainage Installation
AHU unit Installation
ACCU Refrigeration unit Installation
Precommissioning For HVAC
Installation of Passenger Lift
Installation of Lift Door & Control Panels
Precommissioning of Lift
Completion of Structures
Excavation of Basement
Disposal of Surplus Exc. Materials
Blinding below Foundation
Water Proofing to Foundation
Rebar Installation to Isolated Footing
Formworks for Footings
Casting for Isolated Footing
Backfilling Around Foundation
Rebar for Retaining Wall & Neck Column
Formworks for Retaining Wall & Neck Column
Bitumenous Concrete Protection
Casting for Retaining Wall & Neck Column
Backfilling by Layer to Below Ground Beam
Blinding to below Ground beam
Rebar for Ground Beam
Formworks for Ground Beam
Casting for Ground Beam
Formworks to Service Corridor Slab
Rebar to Service Corridor
Casting of Service Corridor Slab
Sheet 7 of 25
10. Sheet 8 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SUPERSTRUCTURE-CONCRETE WORKS
GROUND FLOOR
B01-1230 Rebar for Ground Floor Column 12 03JUL11 16JUL11 18,394 kg
B01-1240 Formworks for Ground Floor Column 12 06JUL11 19JUL11 572 m2
B01-1250 Casting for Ground Floor Column 4 18JUL11 21JUL11 107 m3
B01-1251 Rebar for Beams & Corbels 21 17AUG11 10SEP11 28,709 kg
B01-1252 Formworks for Beams & Corbels 21 21AUG11 13SEP11 893 m2
B01-1253 Casting for Beams & Corbels 6 11SEP11 17SEP11 167 m3
STEEL STRUCTURAL WORKS
GROUND FLOOR
B01-1270 Installation of Mero Steel Space Frame 24 27SEP11 24OCT11 2,000 m2
B01-1280 Purlin & isulation Installation 21 09OCT11 01NOV11 2,000 m2
B01-1283 Roof Sandwich Panel Cladding 21 30OCT11 22NOV11 2,000 m2
MAIN RECREATION CLUB ZONE 2
CONSTRUCTION OF ZONE 2 BUILDING
MILESTONE
A02-0010 Completion of Superstructures 0 23FEB12 0
A02-0020 Completion of Finishes 0 23JUN12 0
A02-0030 Completion of MEPD-HVAC Services 0 21AUG12 0
SITE PREPARATION, EXCAVATION & EARTHWORKS
A02-1000 Excavation 15 27SEP11 13OCT11 1,051 m3
A02-1010 Disposal of Surplus Exc. Materials 10 11OCT11 22OCT11 1,449 item
SUBSTRUCTURE WORKS
A02-1020 Blinding below Foundation 6 04OCT11 10OCT11 30 m3
A02-1030 Water Proofing to Foundation 7 06OCT11 13OCT11 405 m2
A02-1040 Rebar Installation to Isolated Footing 6 08OCT11 13OCT11 27,678 kg
A02-1050 Formworks for Footings 6 11OCT11 17OCT11 861 m2
A02-1060 Casting for Isolated Footing 5 16OCT11 20OCT11 161 m3
A02-1070 Backfilling Around Foundation 8 19OCT11 27OCT11 388 m3
A02-1080 Rebar for Neck Columns 5 19OCT11 24OCT11 21,145 kg
A02-1090 Formworks for Neck Column 5 22OCT11 26OCT11 155 m2
A02-1100 Casting for Neck Column 3 25OCT11 27OCT11 29 m3
A02-1120 Bitumenous Concrete Protection 9 29OCT11 07NOV11 564 m2
A02-1130 Backfilling by Layer to Below Ground Beam 4 31OCT11 03NOV11 129 m3
A02-1140 Blinding to below Ground beam 5 01NOV11 06NOV11 38 m3
A02-1150 Rebar for Ground Beam 15 02NOV11 19NOV11 45,728 kg
A02-1160 Formworks for Ground Beam 15 05NOV11 21NOV11 1,423 m2
A02-1170 Casting for Ground Beam 6 19NOV11 24NOV11 879 m3
A02-1180 Backfilling to below Ground Slab 3 21NOV11 23NOV11 129 m3
A02-1190 Blinding to below Ground Slab 7 23NOV11 30NOV11 430 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Rebar for Ground Floor Column
Formworks for Ground Floor Column
Casting for Ground Floor Column
Rebar for Beams & Corbels
Formworks for Beams & Corbels
Casting for Beams & Corbels
Installation of Mero Steel Space Frame System
Purlin & isulation Installation
Roof Sandwich Panel Cladding
Completion of Superstructures
Completion of Finishes
Completion of MEPD-HVAC Services
Excavation
Disposal of Surplus Exc. Materials
Blinding below Foundation
Water Proofing to Foundation
Rebar Installation to Isolated Footing
Formworks for Footings
Casting for Isolated Footing
Backfilling Around Foundation
Rebar for Neck Columns
Formworks for Neck Column
Casting for Neck Column
Bitumenous Concrete Protection
Backfilling by Layer to Below Ground Beam
Blinding to below Ground beam
Rebar for Ground Beam
Formworks for Ground Beam
Casting for Ground Beam
Backfilling to below Ground Slab
Blinding to below Ground Slab
Sheet 8 of 25
11. Sheet 9 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A02-1200 Water proofing to Ground Slab 6 24NOV11 30NOV11 5,728 m2
A02-1210 Fabric Reinforcement A252mesh to Ground 9 26NOV11 05DEC11 5,728 m2
A02-1220 Casting of Ground Slab 9 28NOV11 07DEC11 879 m3
SUPERSTRUCTURE-CONCRETE WORKS
GROUND FLOOR
A02-1230 Rebar for Ground Floor Column 12 19OCT11 01NOV11 36,788 kg
A02-1240 Formworks for Ground Floor Column 12 23OCT11 05NOV11 1,144 m2
A02-1250 Casting for Ground Floor Column 4 03NOV11 07NOV11 214 m3
A02-1281 Precast Pergola structure 14 25DEC11 09JAN12 1 no
A02-1251 Hollow Core Slab Installation 12 30JAN12 12FEB12 2,374 kg
A02-1260 Staircase & Lintel Formworks GF 12 30JAN12 12FEB12 64 m2
A02-1270 Staircase & Lintel Rebars GF 12 02FEB12 15FEB12 1,031 kg
A02-1254 Hollow Core Slab Toppings 12 09FEB12 22FEB12 2,374 m2
A02-1280 Stair Case & Lintel Beams Casting GF 9 14FEB12 23FEB12 6 m3
ROOF
A02-1470 Formworks for Roof Beam & Corbel 12 25DEC11 07JAN12 1,786 m2
A02-1480 Rebar for Roof Beam & Corbel 12 28DEC11 10JAN12 57,418 kg
A02-1490 Casting for Roof Floor Beam & Corbel 4 09JAN12 12JAN12 334 m3
A02-1500 Parapet Roof Formworks RF 12 30JAN12 12FEB12 32 m2
A02-1510 Parapet Roof Rebars RF 12 02FEB12 15FEB12 1,031 kg
A02-1520 Parapet Roof Casting RF 9 14FEB12 23FEB12 6 m3
STEEL STRUCTURAL WORKS
ROOF
A02-1550 Mero Space Frame Installation & Supports 21 12MAR12 04APR12 2,542 m2
A02-1551 Purlin & isulation Installation 21 02APR12 25APR12 2,542 kg
A02-1552 Roof Sandwich Panel Cladding 15 14APR12 30APR12 2,442 m3
MASONRY WORKS
GROUND FLOOR
A02-1530 Block Works for Ground Floor 26 30JAN12 28FEB12 3,890 m2
A02-1540 Plastering for Ground Floor 26 06FEB12 06MAR12 7,912 m2
ROOF
A02-1590 Block Works for Roof Parapet Wall 9 12JAN12 22JAN12 1,945 m2
A02-1600 Plastering for Roof Parapet 35 16JAN12 25FEB12 3,956 m2
A02-1610 Roof Plint Construction 21 31JAN12 23FEB12 1 item
ROOFING WORKS
ROOF
A02-1620 Thermal Isulation & Proofing Roof Floor 21 31JAN12 23FEB12 2,661 m2
A02-1630 Protective Chip &Pre cast Slab Cover at Roof 21 04MAR12 27MAR12 2,661 m2
FLOOR, WALL & CEILING FINISH
GROUND FLOOR
A02-1640 Floor Screeding Ground Floor 21 23FEB12 18MAR12 2,762 m2
A02-1650 Non Slip Porcelain Floor Tiling Works 12 06MAR12 19MAR12 776 m2
A02-1660 Stair & Ramp Tiling works 12 06MAR12 19MAR12 130 m2
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Water proofing to Ground Slab
Fabric Reinforcement A252mesh to Ground Slab
Casting of Ground Slab
Rebar for Ground Floor Column
Formworks for Ground Floor Column
Casting for Ground Floor Column
Precast Pergola structure
Hollow Core Slab Installation
Staircase & Lintel Formworks GF
Staircase & Lintel Rebars GF
Hollow Core Slab Toppings
Stair Case & Lintel Beams Casting GF
Formworks for Roof Beam & Corbel
Rebar for Roof Beam & Corbel
Casting for Roof Floor Beam & Corbel
Parapet Roof Formworks RF
Parapet Roof Rebars RF
Parapet Roof Casting RF
Mero Space Frame Installation & Supports
Purlin & isulation Installation
Roof Sandwich Panel Cladding
Block Works for Ground Floor
Plastering for Ground Floor
Block Works for Roof Parapet Wall
Plastering for Roof Parapet
Roof Plint Construction
Thermal Isulation & Proofing Roof Floor
Protective Chip &Pre cast Slab Cover at Roof Top
Floor Screeding Ground Floor
Non Slip Porcelain Floor Tiling Works
Stair & Ramp Tiling works
Sheet 9 of 25
12. Sheet 10 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A02-1670 Ceramic Floor Tiling Works 18 11MAR12 31MAR12 640 m2
A02-1680 Carpet Tiling Works 12 18MAR12 31MAR12 2,028 m2
A02-1690 Wood Tiling Works 6 20MAR12 26MAR12 170 m2
A02-1700 Granite Tiling Works 15 20MAR12 05APR12 1,048 m2
A02-1710 Epoxy paint Finish 15 20MAR12 05APR12 1,270 m2
A02-1720 Moisture Resistant Suspended Ceiling 21 25MAR12 17APR12 2,130 m2
A02-1730 Gypsum Board Suspended Ceiling 21 25MAR12 17APR12 3,052 m2
JOINERY & CARPENTRY
A02-1940 Timber Door Jamb Installation 35 21MAR12 30APR12 96 no
A02-1970 Bulkhead & Linings 21 21MAR12 14APR12 265 no
A02-1960 Vanity Countertops Installation 21 28MAR12 21APR12 22 no
A02-1980 Modular Wall System Panels 35 28MAR12 07MAY12 129 no
A02-1981 Partition Wall System Panels 35 04APR12 14MAY12 216 m2
A02-1950 Timber Door & Ironmongries Installation 35 01MAY12 10JUN12 96 no
A02-1951 Equipment Furnishings 35 01MAY12 10JUN12 1 item
METAL & ALUMINUM WORKS
A02-2000 Aluminum Door Installation 12 14MAR12 27MAR12 23 no
A02-1990 Decorative Circular Columns 12 18MAR12 31MAR12 10 no
A02-2020 Aluminum Window Installation 15 25MAR12 10APR12 16 no
A02-2030 Metal Doors Installation 12 29MAR12 11APR12 16 no
A02-2010 Miscellaneous Steel works 12 03APR12 16APR12 1 item
PAINTING & DECORATING
A02-2040 Exterior Paint Finishings 36 21MAR12 01MAY12 3,880 m2
A02-2050 Interior Painting Works 45 25APR12 16JUN12 10,553 m2
A02-2060 Snagging & Punchlisting 6 17JUN12 23JUN12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
SUBSTRUCTURE
A02-2070 UnderGround Sanitary & Rainwater Pipe 10 22NOV11 03DEC11 882 m
GROUND FLOOR
A02-2080 Hot & Cold Domestic Pipe Installation 24 20FEB12 18MAR12 412 m
A02-2100 Fire Fighting Pipes 18 27FEB12 18MAR12 798 m
A02-2101 LPG Pipes 18 27FEB12 18MAR12 122 m
A02-2090 Sanitary Pipe Installation Rise above floor 9 07MAR12 17MAR12 48 m
A02-2120 Isolating & Alarm Valve Installation 6 12MAR12 18MAR12 10 no
A02-2110 Floor Clean out Drains & traps 12 18MAR12 31MAR12 108 no
A02-2140 Fire Hose Reel Cabinet Installation 12 19MAR12 01APR12 4 no
A02-2160 Fire Fighting Equipment Installation 12 26MAR12 08APR12 80 no
A02-2170 Sprinkler System Installation 6 29MAR12 04APR12 660 no
A02-2150 Sanitary Fixtures Installation 21 01APR12 24APR12 246 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Ceramic Floor Tiling Works
Carpet Tiling Works
Wood Tiling Works
Granite Tiling Works
Epoxy paint Finish
Moisture Resistant Suspended Ceiling
Gypsum Board Suspended Ceiling
Timber Door Jamb Installation
Bulkhead & Linings
Vanity Countertops Installation
Modular Wall System Panels
Partition Wall System Panels
Timber Door & Ironmongries Installation
Equipment Furnishings
Aluminum Door Installation
Decorative Circular Columns
Aluminum Window Installation
Metal Doors Installation
Miscellaneous Steel works
Exterior Paint Finishings
Interior Painting Works
Snagging & Punchlisting
UnderGround Sanitary & Rainwater Pipe Install
Hot & Cold Domestic Pipe Installation
Fire Fighting Pipes
LPG Pipes
Sanitary Pipe Installation Rise above floor
Isolating & Alarm Valve Installation
Floor Clean out Drains & traps
Fire Hose Reel Cabinet Installation
Fire Fighting Equipment Installation
Sprinkler System Installation
Sanitary Fixtures Installation
Sheet 10 of 25
13. Sheet 11 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
ROOF
A02-2360 Rain Water Pipe Installation 12 30JAN12 12FEB12 144 m
A02-2400 Precommissioning For Plumbing 6 11AUG12 16AUG12 1 item
ELECTRICAL WORKS
SUBSTRUCTURE
A02-2410 Underground Electrical Sleeve Installation 10 22NOV11 03DEC11 1 item
GROUND FLOOR
A02-2420 MDB & DB Enclosure to Wall 12 13FEB12 26FEB12 18 no
A02-2430 Earthing Conductor Installation 6 13FEB12 19FEB12 1 item
A02-2440 Electrical Conduiting, Cable Tray Works 21 27FEB12 21MAR12 616 m
A02-2450 Cable Pulling, Wiring & Termination 21 28FEB12 22MAR12 616 item
A02-2460 DB & SMDB Installation 9 06MAR12 15MAR12 18 no
A02-2480 Data TV BMS&Security Sys. Installation 12 14MAR12 27MAR12 24 no
A02-2490 Fire Alarm System Installation 12 19MAR12 01APR12 196 no
A02-2470 Wall & Ceiling Mount Outlets 15 22MAR12 08APR12 508 no
A02-2500 Telephone&ComputerSystem Installation 12 22MAR12 04APR12 1 item
A02-2520 MV Panel, CBank & CBreaker 21 26MAR12 18APR12 4 no
A02-2510 Lighting Fixture Installation 12 29MAR12 11APR12 1,014 no
A02-2750 Precommissioning Electrical & Low Current 12 08AUG12 21AUG12 1 item
HVAC WORKS
GROUND FLOOR
A02-2760 GI Duct works with Thermal Insulation 21 08MAR12 01APR12 3,626 m2
A02-2770 Circular Duct & Isulation 15 15MAR12 01APR12 138 m
A02-2780 Volume Control & fire Damper Installation 15 15MAR12 01APR12 10 no
A02-2790 Supply & Return Air Diffussers 15 15MAR12 01APR12 748 no
A02-2800 Exhaust Fans Installation 12 22MAR12 04APR12 12 no
A02-2771 Chilled Water Pipe installation 15 02APR12 18APR12 438 m
A02-2810 Split A/C installation 18 05APR12 25APR12 12 no
ROOF
A02-2940 Condenser Pipe drainage Installation 6 07FEB12 13FEB12 1 item
A02-2950 AHU unit Installation 21 12MAR12 04APR12 12 no
A02-2951 ACCU Refrigeration unit Installation 18 19APR12 09MAY12 6 no
A02-2960 Precommissioning For HVAC 12 08AUG12 21AUG12 0 item
MAIN RECREATION CLUB ZONE 3
CONSTRUCTION OF ZONE 3 BUILDING
MILESTONE
A03-0010 Completion of Superstructures 0 28MAR12 0
A03-0020 Completion of Finishes 0 26JUL12 0
A03-0030 Completion of MEPD-HVAC Services 0 21AUG12 0
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Rain Water Pipe Installation
Precommissioning For Plumbing
Underground Electrical Sleeve Installation
MDB & DB Enclosure to Wall
Earthing Conductor Installation
Electrical Conduiting, Cable Tray Works
Cable Pulling, Wiring & Termination
DB & SMDB Installation
Data TV BMS&Security Sys. Installation
Fire Alarm System Installation
Wall & Ceiling Mount Outlets
Telephone&ComputerSystem Installation
MV Panel, CBank & CBreaker
Lighting Fixture Installation
Precommissioning Electrical & Low Current
GI Duct works with Thermal Insulation
Circular Duct & Isulation
Volume Control & fire Damper Installation
Supply & Return Air Diffussers
Exhaust Fans Installation
Chilled Water Pipe installation
Split A/C installation
Condenser Pipe drainage Installation
AHU unit Installation
ACCU Refrigeration unit Installation
Precommissioning For HVAC
Completion of Superstructures
Completion of Finishes
Completion of MEPD-HVAC Services
Sheet 11 of 25
14. Sheet 12 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SITE PREPARATION, EXCAVATION & EARTHWORKS
A03-1000 Excavation 15 31OCT11 16NOV11 1,051 m3
A03-1010 Disposal of Surplus Exc. Materials 10 14NOV11 24NOV11 1,449 item
SUBSTRUCTURE WORKS
A03-1020 Blinding below Foundation 6 07NOV11 13NOV11 30 m3
A03-1030 Water Proofing to Foundation 7 09NOV11 16NOV11 405 m2
A03-1040 Rebar Installation to Isolated Footing 6 10NOV11 16NOV11 27,678 kg
A03-1050 Formworks for Footings 6 14NOV11 20NOV11 861 m2
A03-1060 Casting for Isolated Footing 5 19NOV11 23NOV11 161 m3
A03-1070 Backfilling Around Foundation 8 22NOV11 30NOV11 388 m3
A03-1080 Rebar for Neck Columns 5 22NOV11 27NOV11 21,145 kg
A03-1090 Formworks for Neck Column 5 24NOV11 29NOV11 155 m2
A03-1100 Casting for Neck Column 3 28NOV11 30NOV11 29 m3
A03-1110 Bitumenous Concrete Protection 9 01DEC11 11DEC11 564 m2
A03-1120 Backfilling by Layer to Below Ground Beam 4 04DEC11 07DEC11 129 m3
A03-1130 Blinding to below Ground beam 5 05DEC11 10DEC11 38 m3
A03-1140 Rebar for Ground Beam 15 06DEC11 22DEC11 45,728 kg
A03-1150 Formworks for Ground Beam 15 08DEC11 25DEC11 1,423 m2
A03-1160 Casting for Ground Beam 6 22DEC11 28DEC11 879 m3
A03-1170 Backfilling to below Ground Slab 3 25DEC11 27DEC11 129 m3
A03-1180 Blinding to below Ground Slab 7 27DEC11 03JAN12 430 m3
A03-1190 Water proofing to Ground Slab 6 28DEC11 03JAN12 5,728 m2
A03-1200 Fabric Reinforcement A252mesh to Ground 9 29DEC11 08JAN12 5,728 m2
A03-1210 Casting of Ground Slab 9 01JAN12 10JAN12 879 m3
SUPERSTRUCTURE-CONCRETE WORKS
GROUND FLOOR
A03-1220 Rebar for Ground Floor Column 12 22NOV11 05DEC11 36,788 kg
A03-1230 Formworks for Ground Floor Column 12 26NOV11 08DEC11 1,144 m2
A03-1240 Casting for Ground Floor Column 4 07DEC11 11DEC11 214 m3
A03-1250 Hollow Core Slab Installation 12 04MAR12 17MAR12 2,374 kg
A03-1260 Staircase & Lintel Formworks GF 12 04MAR12 17MAR12 64 m2
A03-2110 Precast Pergola structure 14 04MAR12 19MAR12 1 no
A03-1270 Staircase & Lintel Rebars GF 12 07MAR12 20MAR12 1,031 kg
A03-1280 Hollow Core Slab Toppings 12 14MAR12 27MAR12 2,374 m2
A03-1290 Stair Case & Lintel Beams Casting GF 9 19MAR12 28MAR12 6 m3
ROOF
A03-1300 Formworks for Roof Beam & Corbel 12 28JAN12 09FEB12 1,786 m2
A03-1310 Rebar for Roof Beam & Corbel 12 31JAN12 13FEB12 57,418 kg
A03-1320 Casting for Roof Floor Beam & Corbel 4 12FEB12 15FEB12 334 m3
A03-1330 Parapet Roof Formworks RF 12 04MAR12 17MAR12 32 m2
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Excavation
Disposal of Surplus Exc. Materials
Blinding below Foundation
Water Proofing to Foundation
Rebar Installation to Isolated Footing
Formworks for Footings
Casting for Isolated Footing
Backfilling Around Foundation
Rebar for Neck Columns
Formworks for Neck Column
Casting for Neck Column
Bitumenous Concrete Protection
Backfilling by Layer to Below Ground Beam
Blinding to below Ground beam
Rebar for Ground Beam
Formworks for Ground Beam
Casting for Ground Beam
Backfilling to below Ground Slab
Blinding to below Ground Slab
Water proofing to Ground Slab
Fabric Reinforcement A252mesh to Ground Slab
Casting of Ground Slab
Rebar for Ground Floor Column
Formworks for Ground Floor Column
Casting for Ground Floor Column
Hollow Core Slab Installation
Staircase & Lintel Formworks GF
Precast Pergola structure
Staircase & Lintel Rebars GF
Hollow Core Slab Toppings
Stair Case & Lintel Beams Casting GF
Formworks for Roof Beam & Corbel
Rebar for Roof Beam & Corbel
Casting for Roof Floor Beam & Corbel
Parapet Roof Formworks RF
Sheet 12 of 25
15. Sheet 13 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A03-1340 Parapet Roof Rebars RF 12 07MAR12 20MAR12 1,031 kg
A03-1350 Parapet Roof Casting RF 9 19MAR12 28MAR12 6 m3
STEEL STRUCTURAL WORKS
A03-1360 Mero Space Frame Installation & Supports 21 15APR12 08MAY12 2,542 m2
A03-1370 Purlin & isulation Installation 21 06MAY12 29MAY12 2,542 kg
A03-1380 Roof Sandwich Panel Cladding 15 17MAY12 03JUN12 2,442 m3
MASONRY WORKS
GROUND FLOOR
A03-1390 Block Works for Ground Floor 26 04MAR12 02APR12 3,890 m2
A03-1400 Plastering for Ground Floor 26 11MAR12 09APR12 7,912 m2
ROOF
A03-1410 Block Works for Roof Parapet Wall 9 15FEB12 25FEB12 1,945 m2
A03-1420 Plastering for Roof Parapet 12 19FEB12 03MAR12 3,956 m2
A03-1430 Roof Plint Construction 21 05MAR12 28MAR12 1 item
ROOFING WORKS
ROOF
A03-1440 Thermal Isulation & Proofing Roof Floor 21 05MAR12 28MAR12 2,661 m2
A03-1450 Protective Chip &Pre cast Slab Cover at Roof 21 29MAR12 22APR12 2,661 m2
FLOOR, WALL & CEILING FINISH
GROUND FLOOR
A03-1460 Floor Screeding Ground Floor 21 28MAR12 21APR12 2,762 m2
A03-1470 Non Slip Porcelain Floor Tiling Works 12 09APR12 22APR12 776 m2
A03-1480 Stair & Ramp Tiling works 12 09APR12 22APR12 130 m2
A03-1490 Ceramic Floor Tiling Works 18 14APR12 03MAY12 640 m2
A03-1500 Carpet Tiling Works 12 21APR12 03MAY12 2,028 m2
A03-1510 Wood Tiling Works 6 23APR12 29APR12 170 m2
A03-1520 Granite Tiling Works 15 23APR12 09MAY12 1,048 m2
A03-1530 Epoxy paint Finish 15 23APR12 09MAY12 1,270 m2
A03-1540 Moisture Resistant Suspended Ceiling 21 28APR12 21MAY12 2,130 m2
A03-1550 Gypsum Board Suspended Ceiling 21 28APR12 21MAY12 3,052 m2
JOINERY & CARPENTRY
A03-1560 Timber Door Jamb Installation 35 24APR12 03JUN12 96 no
A03-1570 Bulkhead & Linings 21 24APR12 17MAY12 265 no
A03-1580 Vanity Countertops Installation 21 01MAY12 24MAY12 22 no
A03-1590 Modular Wall System Panels 35 01MAY12 10JUN12 129 no
A03-1600 Partition Wall System Panels 35 08MAY12 17JUN12 216 m2
A03-1610 Timber Door & Ironmongries Installation 35 04JUN12 14JUL12 96 no
A03-1620 Equipment Furnishings 35 04JUN12 14JUL12 1 item
METAL & ALUMINUM WORKS
A03-1630 Decorative Circular Columns 12 25MAR12 07APR12 10 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Parapet Roof Rebars RF
Parapet Roof Casting RF
Mero Space Frame Installation & Supports
Purlin & isulation Installation
Roof Sandwich Panel Cladding
Block Works for Ground Floor
Plastering for Ground Floor
Block Works for Roof Parapet Wall
Plastering for Roof Parapet
Roof Plint Construction
Thermal Isulation & Proofing Roof Floor
Protective Chip &Pre cast Slab Cover at Roof Top
Floor Screeding Ground Floor
Non Slip Porcelain Floor Tiling Works
Stair & Ramp Tiling works
Ceramic Floor Tiling Works
Carpet Tiling Works
Wood Tiling Works
Granite Tiling Works
Epoxy paint Finish
Moisture Resistant Suspended Ceiling
Gypsum Board Suspended Ceiling
Timber Door Jamb Installation
Bulkhead & Linings
Vanity Countertops Installation
Modular Wall System Panels
Partition Wall System Panels
Timber Door & Ironmongries Installation
Equipment Furnishings
Decorative Circular Columns
Sheet 13 of 25
16. Sheet 14 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A03-1640 Metal Doors Installation 12 05APR12 18APR12 16 no
A03-1650 Aluminum Door Installation 12 17APR12 30APR12 23 no
A03-1660 Aluminum Window Installation 15 28APR12 14MAY12 16 no
A03-1670 Miscellaneous Steel works 12 07MAY12 20MAY12 1 item
PAINTING & DECORATING
A03-1680 Exterior Paint Finishings 36 24APR12 04JUN12 3,880 m2
A03-1690 Interior Painting Works 45 29MAY12 19JUL12 10,553 m2
A03-1700 Snagging & Punchlisting 6 21JUL12 26JUL12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
SUBSTRUCTURE
A03-1710 UnderGround Sanitary & Rainwater Pipe 10 26DEC11 05JAN12 882 m
GROUND FLOOR
A03-1820 Rain Water Pipe Installation 12 04MAR12 17MAR12 144 m
A03-1720 Hot & Cold Domestic Pipe Installation 24 25MAR12 21APR12 412 m
A03-1730 Fire Fighting Pipes 18 01APR12 21APR12 798 m
A03-1740 LPG Pipes 18 01APR12 21APR12 122 m
A03-1750 Sanitary Pipe Installation Rise above floor 9 10APR12 19APR12 48 m
A03-1760 Isolating & Alarm Valve Installation 6 15APR12 21APR12 10 no
A03-1770 Floor Clean out Drains & traps 12 21APR12 03MAY12 108 no
A03-1780 Fire Hose Reel Cabinet Installation 12 22APR12 05MAY12 4 no
A03-1790 Fire Fighting Equipment Installation 12 29APR12 12MAY12 80 no
A03-1800 Sprinkler System Installation 6 02MAY12 08MAY12 660 no
A03-1810 Sanitary Fixtures Installation 21 05MAY12 28MAY12 246 no
A03-1830 Precommissioning For Plumbing 6 11AUG12 16AUG12 1 item
ELECTRICAL WORKS
SUBSTRUCTURE
A03-1840 Underground Electrical Sleeve Installation 10 26DEC11 05JAN12 1 item
GROUND FLOOR
A03-1850 MDB & DB Enclosure to Wall 12 18MAR12 31MAR12 18 no
A03-1860 Earthing Conductor Installation 6 18MAR12 24MAR12 1 item
A03-1870 Electrical Conduiting, Cable Tray Works 21 01APR12 24APR12 616 m
A03-1880 Cable Pulling, Wiring & Termination 21 02APR12 25APR12 616 item
A03-1890 DB & SMDB Installation 9 09APR12 18APR12 18 no
A03-1900 Data TV BMS&Security Sys. Installation 12 17APR12 30APR12 24 no
A03-1910 Fire Alarm System Installation 12 22APR12 05MAY12 196 no
A03-1920 Wall & Ceiling Mount Outlets 15 25APR12 12MAY12 508 no
A03-1930 Telephone&ComputerSystem Installation 12 25APR12 08MAY12 1 item
A03-1940 MV Panel, CBank & CBreaker 21 29APR12 22MAY12 4 no
A03-1950 Lighting Fixture Installation 12 02MAY12 15MAY12 1,014 no
A03-2521 Installation on Transformer 21 15MAY12 07JUN12 4 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Metal Doors Installation
Aluminum Door Installation
Aluminum Window Installation
Miscellaneous Steel works
Exterior Paint Finishings
Interior Painting Works
Snagging & Punchlisting
UnderGround Sanitary & Rainwater Pipe Install
Rain Water Pipe Installation
Hot & Cold Domestic Pipe Installation
Fire Fighting Pipes
LPG Pipes
Sanitary Pipe Installation Rise above floor
Isolating & Alarm Valve Installation
Floor Clean out Drains & traps
Fire Hose Reel Cabinet Installation
Fire Fighting Equipment Installation
Sprinkler System Installation
Sanitary Fixtures Installation
Precommissioning For Plumbing
Underground Electrical Sleeve Installation
MDB & DB Enclosure to Wall
Earthing Conductor Installation
Electrical Conduiting, Cable Tray Works
Cable Pulling, Wiring & Termination
DB & SMDB Installation
Data TV BMS&Security Sys. Installation
Fire Alarm System Installation
Wall & Ceiling Mount Outlets
Telephone&ComputerSystem Installation
MV Panel, CBank & CBreaker
Lighting Fixture Installation
Installation on Transformer
Sheet 14 of 25
17. Sheet 15 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
A03-2522 Installation of Switch gear 21 02JUN12 25JUN12 1 no
A03-2523 Installation on Standby Generator 21 05JUN12 28JUN12 1 no
A03-1960 Precommissioning Electrical & Low Current 12 08AUG12 21AUG12 1 item
HVAC WORKS
GROUND FLOOR
A03-1970 GI Duct works with Thermal Insulation 21 11APR12 05MAY12 3,626 m2
A03-1980 Circular Duct & Isulation 15 18APR12 05MAY12 138 m
A03-1990 Volume Control & fire Damper Installation 15 18APR12 05MAY12 10 no
A03-2000 Supply & Return Air Diffussers 15 18APR12 05MAY12 748 no
A03-2010 Exhaust Fans Installation 12 25APR12 08MAY12 12 no
A03-2020 Chilled Water Pipe installation 15 06MAY12 22MAY12 438 m
A03-2030 Split A/C installation 18 09MAY12 29MAY12 12 no
ROOF
A03-2040 Condenser Pipe drainage Installation 6 12MAR12 18MAR12 1 item
A03-2050 AHU unit Installation 21 15APR12 08MAY12 12 no
A03-2060 ACCU Refrigeration unit Installation 18 23MAY12 12JUN12 6 no
A03-2070 Precommissioning For HVAC 12 08AUG12 21AUG12 1 item
EXTERNAL WORKS & INFRASTRUCTURE
EXTERNAL WORKS
MILESTONE
HARD LANDSCAPING
EXT1051 Completion of External MEP-Qtel Works 0 09AUG12 0
EXT1050 Completion of Infrastructure 0 31OCT12 0
EXTERNAL SERVICES
HARD LANDSCAPING
EXT1000 Site Preparation/Strip Surface to 150mm 236 09MAY11 07FEB12 20,125 m2
EXT1001 Filling of Imported materials incl compaction 236 06JUN11 06MAR12 37,888 m2
EXT1002 Sub grade filling & Compaction 236 11JUL11 10APR12 16,211 m2
EXT1010 Road Kerb Installation 160 19DEC11 21JUN12 5,159 m
EXT1030 Block Paving works 120 02APR12 19AUG12 4,977 m2
EXT1020 Asphalt Paving Works & Bitrumen Tack Coat 60 20JUN12 28AUG12 16,211 m2
EXT1021 Shade Parking Installation 60 08JUL12 15SEP12 6 no
EXTERNAL QGEWC & DRAINAGE
EXP1020 Incoming Water Pipe Trench, Laying&Backfill 35 30JAN12 10MAR12 1,959 m
EXP1030 Water Manholes Construction 26 05MAR12 03APR12 1 no
EXP1050 Surface Water Drainage uPVC, 35 11MAR12 19APR12 180 m
EXP1060 Manholes & Storm GullysConstruction 15 15APR12 01MAY12 158 no
EXP1070 Incoming Fire Fighting Pipings 35 21APR12 30MAY12 1,025 m
EXP1080 Isolating Valves on Concrete Boxes 15 26MAY12 11JUN12 12 no
EXP1040 Installation of Hydrants & Breaching Inlets 15 08JUL12 24JUL12 14 no
EXP1090 Approval to Attach to External Water Service 14 25JUL12 09AUG12 1 item
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Installation of Switch gear
Installation on Standby Generator
Precommissioning Electrical & Low Current
GI Duct works with Thermal Insulation
Circular Duct & Isulation
Volume Control & fire Damper Installation
Supply & Return Air Diffussers
Exhaust Fans Installation
Chilled Water Pipe installation
Split A/C installation
Condenser Pipe drainage Installation
AHU unit Installation
ACCU Refrigeration unit Installation
Precommissioning For HVAC
Completion of External MEP-Qtel Works
Completion of Infrastructure
Site Preparation/Strip Surface to 150mm
Filling of Imported materials incl compaction
Sub grade filling & Compaction
Road Kerb Installation
Block Paving works
Asphalt Paving Works & Bitrumen Tack Coat
Shade Parking Installation
Incoming Water Pipe Trench, Laying&Backfill
Water Manholes Construction
Surface Water Drainage uPVC, Laying&Backfill
Manholes & Storm GullysConstruction
Incoming Fire Fighting Pipings
Isolating Valves on Concrete Boxes
Installation of Hydrants & Breaching Inlets
Approval to Attach to External Water Service
Sheet 15 of 25
18. Sheet 16 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
EXTERNAL ELECTRICAL
EXE1000 Main Cable Trench, Laying & backfill 60 06FEB12 15APR12 4,536 m
EXE1001 Street Light Cabling & fiber Optic Laying 60 12MAR12 20MAY12 5,273 m
EXE1010 Installation of External Street Lighting 35 16APR12 26MAY12 281 no
EXE1020 Electrical Manholes 35 16APR12 26MAY12 82 no
EXE1030 Approval Attach Electrical to External Service 14 23JUL12 07AUG12 1 item
EXTERNAL Q-TEL WORKS
EXQ1000 Qtel Upvc Duct laying & backfill 60 12MAR12 20MAY12 940 m
EXQ1020 JRC Manholes 35 16APR12 26MAY12 15 no
EXQ1030 Approval Attach Qtel to External Service 14 27MAY12 11JUN12 1 item
IRRIGATION WORKS
IRR1001 Irrigation Incoming Main Pipe Works 35 19MAY12 27JUN12 1,021 m
IRR1002 Manholes, Cabling & trenching works Works 21 28JUN12 22JUL12 59 no
IRR1000 Irrigation Pipe Trench, Lay & Backfill 21 29AUG12 22SEP12 2,450 m
IRR1010 Installation of Coupling & isolating valves 14 19SEP12 04OCT12 43 no
IRR1020 Installation of Popup Sprayers 6 03OCT12 09OCT12 504 no
SOFT LANDSCAPING
SOF1000 Installation & Spreading of Sweet Soil 21 03OCT12 27OCT12 7,860 m2
SOF1010 Planting & Greening 25 03OCT12 31OCT12 1 item
SWIMMING POOL
SITE PREPARATION, EXCAVATION & EARTHWORKS
SP1010 Excavation of Swimming Pool 45 05JUL11 25AUG11 12,974 m3
SP1020 Disposal of Surplus Exc. Materials 18 16AUG11 05SEP11 12,634 m3
SUBSTRUCTURE WORKS
SP1030 Blinding below Foundation 18 11AUG11 31AUG11 100 m3
SP1040 Water Proofing to Foundation 35 14AUG11 22SEP11 1,338 m2
SP1050 Rebar Installation to Foundation 35 18AUG11 27SEP11 113,036 kg
SP1060 Formworks for Footings 35 22AUG11 01OCT11 279 m2
SP1070 Casting for Trenches & Pool Slab 12 28SEP11 11OCT11 742 m3
SP1080 Backfilling Around Foundation 12 02OCT11 15OCT11 340 m3
SP1090 Rebar for Retaining Wall & Trench Wall 21 02OCT11 25OCT11 85,158 kg
SP1100 Formworks for Retaining Wall & Trench Wall 21 09OCT11 01NOV11 3,822 m2
SP1120 Casting for Retaining Wall & Trench Wall 12 30OCT11 12NOV11 549 m3
SP1110 Bitumenous Concrete Protection 12 06NOV11 19NOV11 2,190 m2
SP1130 Backfilling by Layer to Below Ground Beam 12 08NOV11 21NOV11 68 m3
SP1140 Blinding to below Ground beam 12 09NOV11 22NOV11 2,009 m3
SP1150 Mesh Rebar for Ground Slab 12 16NOV11 29NOV11 2,009 m2
SP1160 Formworks for Ground Beam & S.Slab 12 19NOV11 01DEC11 435 m2
SP1170 Casting for Ground Beam & S.Slab 6 29NOV11 05DEC11 256 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Main Cable Trench, Laying & backfill
Street Light Cabling & fiber Optic Laying
Installation of External Street Lighting
Electrical Manholes
Approval Attach Electrical to External Service
Qtel Upvc Duct laying & backfill
JRC Manholes
Approval Attach Qtel to External Service
Irrigation Incoming Main Pipe Works
Manholes, Cabling & trenching works Works
Irrigation Pipe Trench, Lay & Backfill
Installation of Coupling & isolating valves
Installation of Popup Sprayers
Installation & Spreading of Sweet Soil
Planting & Greening
Excavation of Swimming Pool
Disposal of Surplus Exc. Materials
Blinding below Foundation
Water Proofing to Foundation
Rebar Installation to Foundation
Formworks for Footings
Casting for Trenches & Pool Slab
Backfilling Around Foundation
Rebar for Retaining Wall & Trench Wall
Formworks for Retaining Wall & Trench Wall
Casting for Retaining Wall & Trench Wall
Bitumenous Concrete Protection
Backfilling by Layer to Below Ground Beam
Blinding to below Ground beam
Mesh Rebar for Ground Slab
Formworks for Ground Beam & S.Slab
Casting for Ground Beam & S.Slab
Sheet 16 of 25
19. Sheet 17 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SUPERSTRUCTURE-CONCRETE WORKS
SP1210 Rebar for Structural Support Column 12 02OCT11 15OCT11 1,523 kg
SP1220 Formworks for Structural Support Column 12 05OCT11 18OCT11 53 m2
SP1230 Casting for Structural Support Column 4 17OCT11 20OCT11 10 m3
SP1240 Hollow core Slab Installation 21 15DEC11 08JAN12 1,137 m2
SP1250 Hollow core slab Tapping works 21 19DEC11 11JAN12 1,137 m2
STEEL STRUCTURAL WORKS
SP1270 Tensile Fabric Shader Installation 24 04MAR12 31MAR12 426 m2
FLOOR, WALL & CEILING FINISH
SP1330 Floor Screeding Ground Floor 26 03JAN12 01FEB12 3,298 m2
SP1340 Vetrified CeramicTiling Works 24 15JAN12 11FEB12 2,198 m2
SP1350 Mosaic Floor & Wall Tiling Works 18 29JAN12 18FEB12 936 m2
PLUMBING, DRAINAGE & FIRE PROTECTION
SP1370 UnderGround Pool Piping 10 08NOV11 19NOV11 1 item
SP1390 Piping works & support 24 09JAN12 05FEB12 1 item
SP1430 Check Valve Installation 6 30JAN12 05FEB12 1 item
SP1450 Pool Equipment Installation 35 06FEB12 17MAR12 47 no
SP1490 Precommissioning For Plumbing 6 18MAR12 24MAR12 1 item
ELECTRICAL WORKS
SP1510 Electrical Conduiting, Cable Tray Works 21 13FEB12 07MAR12 1 item
SP1520 Cable Pulling, Wiring & Termination 21 14FEB12 08MAR12 1 item
SP1540 Electrical Control Panel works 12 29FEB12 13MAR12 1 no
SP1550 Precommissioning Electrical Panel 12 14MAR12 27MAR12 1 item
TENNIS COURT
SITE PREPARATION, EXCAVATION & EARTHWORKS
TEN1000 Excavation 6 01DEC11 07DEC11 671 m3
TEN1010 Disposal of Surplus Excavated Material 3 08DEC11 11DEC11 91 m3
SUBSTRUCTURE WORKS
TEN1020 Concrete Blinding 4 08DEC11 12DEC11 247 m3
TEN1030 Waterproofing & Dampproofing 3 12DEC11 14DEC11 3,294 m2
TEN1040 Rebar for Footings 3 15DEC11 18DEC11 1,767 kg
TEN1050 Formworks for Isolated Footings 3 17DEC11 19DEC11 67 m2
TEN1060 Casting of Footings 2 19DEC11 20DEC11 19 m3
TEN1070 Rebar for Neck Column 3 20DEC11 22DEC11 279 kg
TEN1080 Formworks for Neck Column 3 21DEC11 24DEC11 36 m2
TEN1090 Casting for Neck Column 2 24DEC11 25DEC11 3 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Rebar for Structural Support Column
Formworks for Structural Support Column
Casting for Structural Support Column
Hollow core Slab Installation
Hollow core slab Tapping works
Tensile Fabric Shader Installation
Floor Screeding Ground Floor
Vetrified CeramicTiling Works
Mosaic Floor & Wall Tiling Works
UnderGround Pool Piping
Piping works & support
Check Valve Installation
Pool Equipment Installation
Precommissioning For Plumbing
Electrical Conduiting, Cable Tray Works
Cable Pulling, Wiring & Termination
Electrical Control Panel works
Precommissioning Electrical Panel
Excavation
Disposal of Surplus Excavated Material
Concrete Blinding
Waterproofing & Dampproofing
Rebar for Footings
Formworks for Isolated Footings
Casting of Footings
Rebar for Neck Column
Formworks for Neck Column
Casting for Neck Column
Sheet 17 of 25
20. Sheet 18 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
TEN1100 Bitumenoues Concrete Protection 6 25DEC11 31DEC11 169 m2
TEN1110 Rebar for Ground Beam 3 26DEC11 28DEC11 2,790 kg
TEN1120 Formworks for Ground Beam 3 29DEC11 01JAN12 249 m2
TEN1130 Casting of Ground Beam 2 02JAN12 03JAN12 30 m3
TEN1140 Backfilling Below Ground Slab 8 05JAN12 14JAN12 35 m3
TEN1141 Thickning Bed for tennis Court 12 19FEB12 03MAR12 12 m2
TEN1150 Mesh Rebars for Ground slab 12 19FEB12 03MAR12 1,075 m2
TEN1160 Casting Ground slab 6 29FEB12 06MAR12 460 m3
SUPERSTRUCTURE-CONCRETE WORKS
TEN1170 Rebar for Tennis Court Column 6 04JAN12 10JAN12 188 kg
TEN1180 Formworks for Tennis Court Column 6 08JAN12 14JAN12 52 m2
TEN1190 Casting for Tennis Court Column 4 14JAN12 17JAN12 4 m3
TEN1200 Formworks for Tennis Court beams & tiers 18 18JAN12 07FEB12 574 m2
TEN1210 Rebar for Tennis Court beams & tiers 18 21JAN12 09FEB12 8,225 kg
TEN1220 Casting of Tennis Court beams & tiers 6 08FEB12 14FEB12 175 m3
FLOOR, WALL & CEILING FINISH
TEN1250 Tennis Court Green Set Installation 14 29FEB12 15MAR12 2,720 m2
TEN1260 Seats & Miscellaneous works 15 14MAR12 31MAR12 1 item
METAL & ALUMINUM WORKS
TEN1270 Fencing Works 21 17MAR12 09APR12 322 m
TEN1280 Wooden Flatform 6 03APR12 09APR12 4 no
TEN1310 Snagging & Punch Listing 6 10APR12 16APR12 1 item
ELECTRICAL WORKS
TEN1360 Installation of Electrical Duct Sleeve 2 09JAN12 10JAN12 1 item
TEN1370 SMDB enclosure to Wall 12 17MAR12 29MAR12 1 no
TEN1380 Cable pulling, Termination 12 19MAR12 01APR12 1 item
TEN1390 Elec.,Tel.&FireAlarm Conduiting,Trunking 12 31MAR12 12APR12 193 m
TEN1400 Installation of DB 6 14APR12 19APR12 1 no
TEN1410 Installation of Street Lighting Fixtures 3 21APR12 23APR12 12 no
TEN1430 Precommissioning of Electrical at T. Court 3 24APR12 26APR12 1 item
CHILLER COMPOUND
SITE PREPARATION, EXCAVATION & EARTHWORKS
PRT1000 Excavation 6 24NOV11 30NOV11 109 m3
PRT1010 Disposal of Surplus Excavated Material 3 01DEC11 04DEC11 96 m3
SUBSTRUCTURE WORKS
PRT1020 Concrete Blinding 4 01DEC11 05DEC11 17 m2
PRT1030 Waterproofing & Dampproofing 3 05DEC11 07DEC11 17 m2
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Bitumenoues Concrete Protection
Rebar for Ground Beam
Formworks for Ground Beam
Casting of Ground Beam
Backfilling Below Ground Slab
Thickning Bed for tennis Court
Mesh Rebars for Ground slab
Casting Ground slab
Rebar for Tennis Court Column
Formworks for Tennis Court Column
Casting for Tennis Court Column
Formworks for Tennis Court beams & tiers
Rebar for Tennis Court beams & tiers
Casting of Tennis Court beams & tiers
Tennis Court Green Set Installation
Seats & Miscellaneous works
Fencing Works
Wooden Flatform
Snagging & Punch Listing
Installation of Electrical Duct Sleeve
SMDB enclosure to Wall
Cable pulling, Termination
Elec.,Tel.&FireAlarm Conduiting,Trunking Works
Installation of DB
Installation of Street Lighting Fixtures
Precommissioning of Electrical at T. Court
Excavation
Disposal of Surplus Excavated Material
Concrete Blinding
Waterproofing & Dampproofing
Sheet 18 of 25
21. Sheet 19 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
PRT1040 Rebar for Footings 3 06DEC11 08DEC11 1,080 kg
PRT1050 Formworks for Isolated Footings 3 07DEC11 10DEC11 19 m2
PRT1060 Casting of Footings 2 10DEC11 11DEC11 4 m3
PRT1070 Rebar for Column Stump 3 11DEC11 13DEC11 540 kg
PRT1080 Formworks for Column Stump 3 12DEC11 14DEC11 16 m2
PRT1090 Casting for Column Stump 2 14DEC11 15DEC11 2 m3
PRT1100 Bitumenoues Concrete Protection 6 15DEC11 21DEC11 115 m2
PRT1110 Rebar for Ground Beam 3 17DEC11 19DEC11 6,750 kg
PRT1120 Formworks for Ground Beam 3 20DEC11 22DEC11 55 m2
PRT1130 Casting of Ground Beam 2 24DEC11 25DEC11 25 m3
PRT1140 Backfilling Below Ground Slab 8 27DEC11 04JAN12 13 m3
PRT1150 Rebars for SOG & Equipment Foundations 4 17JAN12 21JAN12 197 m2
PRT1160 Casting SOG & Equipment Foundation 2 21JAN12 22JAN12 82 m3
SUPERSTRUCTURE-CONCRETE WORKS
PRT1170 Rebar for Chiller Room Column 3 26DEC11 28DEC11 2,160 kg
PRT1180 Formworks for Chiller Room Column 3 29DEC11 01JAN12 64 m2
PRT1190 Casting for Chiller Room Column 2 02JAN12 03JAN12 8 m3
PRT1200 Formworks for Chiller Room Roof Slab 6 04JAN12 10JAN12 60 m2
PRT1210 Rebar for Chiller Room Roof Slab 6 07JAN12 12JAN12 1,620 kg
PRT1220 Casting of Chiller Room Roof Slab 2 11JAN12 12JAN12 6 m3
MASONRY WORKS
PRT1230 Blockworks for Chiller Room 6 17JAN12 23JAN12 175 m2
PRT1240 Plastering for Chiller Room 9 19JAN12 29JAN12 469 m2
ROOFING WORKS
PRT1250 Roof Water Proofing Works 9 21JAN12 30JAN12 27 m2
PRT1260 Roof Drain & Rain Water Pipe Installation 6 21JAN12 26JAN12 12 m
METAL & ALUMINUM WORKS
PRT1300 Aluminum Gate 3 02FEB12 05FEB12 2 no
PRT1310 Fire Rated Door 4 06FEB12 09FEB12 1 no
PAINTING & DECORATING
PRT1320 Painting for External walls 15 30JAN12 15FEB12 208 m2
PRT1330 Painting for Internal walls 6 11FEB12 16FEB12 261 m2
PRT1490 Snagging & Punch Listing 6 18FEB12 23FEB12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
PRT1340 Installation of Under Ground Pipes 3 31DEC11 02JAN12 1 item
PRT1350 Installation of Valve manhole 6 24JAN12 30JAN12 1 no
PRT1380 Installation oTrapped Sump pit 12 31JAN12 13FEB12 1 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Rebar for Footings
Formworks for Isolated Footings
Casting of Footings
Rebar for Column Stump
Formworks for Column Stump
Casting for Column Stump
Bitumenoues Concrete Protection
Rebar for Ground Beam
Formworks for Ground Beam
Casting of Ground Beam
Backfilling Below Ground Slab
Rebars for SOG & Equipment Foundations
Casting SOG & Equipment Foundation
Rebar for Chiller Room Column
Formworks for Chiller Room Column
Casting for Chiller Room Column
Formworks for Chiller Room Roof Slab
Rebar for Chiller Room Roof Slab
Casting of Chiller Room Roof Slab
Blockworks for Chiller Room
Plastering for Chiller Room
Roof Water Proofing Works
Roof Drain & Rain Water Pipe Installation
Aluminum Gate
Fire Rated Door
Painting for External walls
Painting for Internal walls
Snagging & Punch Listing
Installation of Under Ground Pipes
Installation of Valve manhole
Installation oTrapped Sump pit
Sheet 19 of 25
22. Sheet 20 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
PRT1470 Precommissioning of Plumbing at Chiller Rm 3 14FEB12 16FEB12 1 item
ELECTRICAL WORKS
PRT1390 Installation of Electrical Duct Sleeve 2 31DEC11 01JAN12 1 item
PRT1400 SMB Board& Isolators enclosure to Wall 12 22JAN12 04FEB12 2 no
PRT1410 Cable pulling, Termination 12 24JAN12 06FEB12 1 item
PRT1420 Elec.,Tel.&FireAlarm Conduiting,Trunking 12 05FEB12 18FEB12 1 item
PRT1430 Installation of DB 6 19FEB12 25FEB12 2 no
PRT1461 Installation of Fire Alarm System 3 19FEB12 21FEB12 5 no
PRT1460 Installation of Lighting Fixtures & switches 3 11MAR12 13MAR12 8 no
PRT1480 Precommissioning of Electrical at Chiller Rm 3 25MAR12 27MAR12 1 item
HVAC WORKS
PRT1501 Installation of Pressurization Unit 12 16FEB12 29FEB12 1 no
PRT1440 Ducting works 12 26FEB12 10MAR12 1 item
PRT1450 Installation of Chiller Pumps 12 11MAR12 24MAR12 1 no
PRT1500 Installation of ACU 1138Kw 12 21MAR12 03APR12 3 no
PRT1455 Precommissioning of HVAC at Chiller Rm 3 04APR12 07APR12 1 item
GUARD HOUSE
SITE PREPARATION, EXCAVATION & EARTHWORKS
GH1000 Excavation 6 22OCT11 27OCT11 15 m3
GH1010 Disposal of Surplus Excavated Material 3 29OCT11 31OCT11 5 m3
SUBSTRUCTURE WORKS
GH1020 Concrete Blinding 4 29OCT11 01NOV11 10 m2
GH1030 Waterproofing & Dampproofing 3 01NOV11 03NOV11 10 m2
GH1040 Rebar for Footings 3 02NOV11 05NOV11 330 kg
GH1050 Formworks for Footings 3 03NOV11 06NOV11 14 m2
GH1060 Casting of Footings 2 06NOV11 07NOV11 4 m3
GH1070 Rebar for Concrete Neck Column 3 07NOV11 09NOV11 750 kg
GH1080 Formworks for Neck Column 3 08NOV11 10NOV11 11 m2
GH1090 Casting for Neck Column 2 10NOV11 12NOV11 4 m3
GH1100 Rebar for Ground Beam 6 13NOV11 19NOV11 1,020 kg
GH1110 Bitumenoues Concrete Protection 6 13NOV11 19NOV11 32 m2
GH1120 Formworks for Ground Beam 6 15NOV11 21NOV11 20 m2
GH1130 Casting of Ground Beam 2 21NOV11 22NOV11 10 m3
GH1140 Backfilling to reach below Ground Slab 8 24NOV11 03DEC11 10 m3
GH1150 Square mesh A393 for Guard Room 4 15DEC11 19DEC11 21 m2
GH1160 Casting Ground Slab Base Guard Room 2 19DEC11 20DEC11 4 m3
SUPERSTRUCTURE-CONCRETE WORKS
GH1170 Rebar for Guard House Column 3 23NOV11 26NOV11 343 kg
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Precommissioning of Plumbing at Chiller Rm
Installation of Electrical Duct Sleeve
SMB Board& Isolators enclosure to Wall
Cable pulling, Termination
Elec.,Tel.&FireAlarm Conduiting,Trunking Works
Installation of DB
Installation of Fire Alarm System
Installation of Lighting Fixtures & switches
Precommissioning of Electrical at Chiller Rm
Installation of Pressurization Unit
Ducting works
Installation of Chiller Pumps
Installation of ACU 1138Kw
Precommissioning of HVAC at Chiller Rm
Excavation
Disposal of Surplus Excavated Material
Concrete Blinding
Waterproofing & Dampproofing
Rebar for Footings
Formworks for Footings
Casting of Footings
Rebar for Concrete Neck Column
Formworks for Neck Column
Casting for Neck Column
Rebar for Ground Beam
Bitumenoues Concrete Protection
Formworks for Ground Beam
Casting of Ground Beam
Backfilling to reach below Ground Slab
Square mesh A393 for Guard Room
Casting Ground Slab Base Guard Room
Rebar for Guard House Column
Sheet 20 of 25
23. Sheet 21 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
GH1180 Formworks for Guard House Column 3 27NOV11 29NOV11 25 m2
GH1190 Casting for Guard House Column 2 30NOV11 01DEC11 2 m3
GH1200 Formworks for Guard Room Roof Slab 6 03DEC11 08DEC11 32 m2
GH1210 Rebar for Guard Room Roof Slab 6 05DEC11 11DEC11 1,245 kg
GH1220 Casting of Guard Room Roof Slab 2 10DEC11 11DEC11 8 m3
GH1230 Construction of Parapet Wall 4 19DEC11 22DEC11 1 m3
MASONRY WORKS
GH1240 200mm Solid Blockworks 5 12NOV11 16NOV11 32 m2
GH1250 Blockworks for Guard Room 6 15DEC11 21DEC11 90 m2
GH1260 Plastering for Guard Room 6 18DEC11 24DEC11 170 m2
ROOFING WORKS
GH1270 Roof Water Proofing Works 9 24DEC11 02JAN12 10 m2
GH1280 Roof Drain & Rain Water Pipe Installation 3 24DEC11 26DEC11 1 item
FLOOR, WALL & CEILING FINISH
GH1340 Suspended Metal Ceiling 3 25DEC11 27DEC11 4 m2
GH1350 Aluminum Window Installation 3 25DEC11 27DEC11 2 no
GH1290 Ceramic Tiles to Floor 3 28DEC11 31DEC11 19 m2
GH1310 Ceramic Tile to Wall 4 01JAN12 04JAN12 20 m2
GH1320 Steps to entrance 6 01JAN12 07JAN12 4 m2
GH1330 Installation of Timber Doors 4 01JAN12 04JAN12 2 no
PAINTING & DECORATING
GH1370 Painting for External walls 12 25DEC11 07JAN12 75 m2
GH1380 Painting for Internal walls 6 05JAN12 11JAN12 90 m2
GH1390 Snagging & Punch Listing 6 12JAN12 18JAN12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
GH1400 Installation of Under Ground Drainage Pipes 3 28NOV11 30NOV11 24 m
GH1410 Hot & Cold Water Distribution System 3 22DEC11 25DEC11 32 m
GH1420 Vent Pipe Installation 3 26DEC11 28DEC11 29 m
GH1430 Installation of Isulating Valves & angle valves 6 26DEC11 01JAN12 12 no
GH1440 Installation of CO & Rodding eyes 3 31DEC11 02JAN12 4 no
GH1450 Installation of Water Heater 4 02JAN12 05JAN12 1 no
GH1460 Installation of Sanitary Fixtures 12 12JAN12 25JAN12 5 no
GH1470 Installation of Floor Drains 3 19JAN12 22JAN12 4 no
GH1480 Precommissioning of Plumbing at Guard 6 26JAN12 01FEB12 1 item
ELECTRICAL WORKS
GH1490 Installation of Electrical Duct Sleeve 2 28NOV11 29NOV11 40 m
GH1500 Distribution Board enclosure to Wall 6 20DEC11 26DEC11 1 no
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Formworks for Guard House Column
Casting for Guard House Column
Formworks for Guard Room Roof Slab
Rebar for Guard Room Roof Slab
Casting of Guard Room Roof Slab
Construction of Parapet Wall
200mm Solid Blockworks
Blockworks for Guard Room
Plastering for Guard Room
Roof Water Proofing Works
Roof Drain & Rain Water Pipe Installation
Suspended Metal Ceiling
Aluminum Window Installation
Ceramic Tiles to Floor
Ceramic Tile to Wall
Steps to entrance
Installation of Timber Doors
Painting for External walls
Painting for Internal walls
Snagging & Punch Listing
Installation of Under Ground Drainage Pipes
Hot & Cold Water Distribution System
Vent Pipe Installation
Installation of Isulating Valves & angle valves
Installation of CO & Rodding eyes
Installation of Water Heater
Installation of Sanitary Fixtures
Installation of Floor Drains
Precommissioning of Plumbing at Guard House
Installation of Electrical Duct Sleeve
Distribution Board enclosure to Wall
Sheet 21 of 25
24. Sheet 22 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
GH1530 Wiring,Cable pulling&Termination 7 22DEC11 29DEC11 1 item
GH1510 Elec.,Tel.&FireAlarm Conduiting,Trunking 7 27DEC11 03JAN12 40 m
GH1520 Installation of DB 6 04JAN12 10JAN12 1 no
GH1540 Installation of Wall Mount Outlet & 3 11JAN12 14JAN12 16 no
GH1560 Installation of Ceiling Lighting Fixtures 3 15JAN12 17JAN12 1 no
GH1570 Fire Alarm System Installtion 3 15JAN12 17JAN12 11 no
GH1580 Tel Data& TV outlet point Installation 3 18JAN12 21JAN12 5 no
GH1590 Precommissioning of Electrical at Guard Hse 6 22JAN12 28JAN12 1 item
HVAC WORKS
GH1600 Installation of Flexible pipe & Isulation 3 22DEC11 25DEC11 1 item
GH1610 Installtion of AC wall Accesories & Wirings 3 04JAN12 07JAN12 2 no
GH1620 Installation of Exhaust Fan System 6 08JAN12 14JAN12 1 no
GH1630 Installation of Split AC at Guard Hse 3 15JAN12 17JAN12 2 no
GH1650 Precommissioning of HVAC at Guard House 6 18JAN12 24JAN12 1 item
SECURITY OFFICE
SITE PREPARATION, EXCAVATION & EARTHWORKS
SO1000 Excavation 6 15NOV11 21NOV11 18 m3
SO1001 Disposal of Surplus Excavated Material 3 22NOV11 24NOV11 8 m3
SUBSTRUCTURE WORKS
SO1002 Concrete Blinding 4 22NOV11 26NOV11 10 m2
SO1003 Waterproofing & Dampproofing 3 26NOV11 28NOV11 9 m2
SO1004 Rebar for Footings 3 27NOV11 29NOV11 330 kg
SO1005 Formworks for Footings 3 28NOV11 30NOV11 14 m2
SO1006 Casting of Footings 2 30NOV11 01DEC11 4 m3
SO1007 Rebar for Concrete Neck Column 3 01DEC11 04DEC11 650 kg
SO1008 Formworks for Neck Column 3 03DEC11 05DEC11 11 m2
SO1009 Casting for Neck Column 2 05DEC11 06DEC11 3 m3
SO1010 Rebar for Ground Beam 6 07DEC11 13DEC11 1,020 kg
SO1011 Bitumenoues Concrete Protection 6 07DEC11 13DEC11 32 m2
SO1012 Formworks for Ground Beam 6 10DEC11 15DEC11 20 m2
SO1013 Casting of Ground Beam 2 15DEC11 17DEC11 10 m3
SO1014 Backfilling to reach below Ground Slab 8 19DEC11 27DEC11 10 m3
SO1015 Square mesh A393 for Security Off. 4 09JAN12 12JAN12 9 m2
SO1016 Casting Ground Slab Base Security Off. 2 12JAN12 14JAN12 3 m3
SUPERSTRUCTURE-CONCRETE WORKS
SO1017 Rebar for Security Off. Column 3 18DEC11 20DEC11 255 kg
SO1018 Formworks for Security Off. Column 3 21DEC11 24DEC11 25 m2
SO1019 Casting for Security Off. Column 2 25DEC11 26DEC11 2 m3
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Wiring,Cable pulling&Termination
Elec.,Tel.&FireAlarm Conduiting,Trunking Works
Installation of DB
Installation of Wall Mount Outlet & Receptacles
Installation of Ceiling Lighting Fixtures
Fire Alarm System Installtion
Tel Data& TV outlet point Installation
Precommissioning of Electrical at Guard Hse
Installation of Flexible pipe & Isulation
Installtion of AC wall Accesories & Wirings
Installation of Exhaust Fan System
Installation of Split AC at Guard Hse
Precommissioning of HVAC at Guard House
Excavation
Disposal of Surplus Excavated Material
Concrete Blinding
Waterproofing & Dampproofing
Rebar for Footings
Formworks for Footings
Casting of Footings
Rebar for Concrete Neck Column
Formworks for Neck Column
Casting for Neck Column
Rebar for Ground Beam
Bitumenoues Concrete Protection
Formworks for Ground Beam
Casting of Ground Beam
Backfilling to reach below Ground Slab
Square mesh A393 for Security Off.
Casting Ground Slab Base Security Off.
Rebar for Security Off. Column
Formworks for Security Off. Column
Casting for Security Off. Column
Sheet 22 of 25
25. Sheet 23 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SO1020 Formworks for Security Off. Roof Slab 6 27DEC11 02JAN12 32 m3
SO1021 Rebar for Security Off.Roof Slab 6 29DEC11 04JAN12 1,245 kg
SO1022 Casting of Security Off. Roof Slab 2 03JAN12 04JAN12 8 m3
SO1023 Construction of Parapet Wall 4 12JAN12 16JAN12 1 m3
MASONRY WORKS
SO1024 200mm Solid Blockworks 5 06DEC11 11DEC11 32 m2
SO1025 Blockworks for Security Off. 6 09JAN12 15JAN12 90 m2
SO1026 Plastering for Security Off. 6 11JAN12 17JAN12 170 m2
ROOFING WORKS
SO1027 Roof Water Proofing Works 9 17JAN12 26JAN12 10 m2
SO1028 Roof Drain & Rain Water Pipe Installation 3 17JAN12 19JAN12 1 item
FLOOR, WALL & CEILING FINISH
SO1029 Suspended Metal Ceiling 3 18JAN12 21JAN12 4 m2
SO1030 Aluminum Window Installation 3 18JAN12 21JAN12 2 no
SO1031 Ceramic Tiles to Floor 3 22JAN12 24JAN12 10 m2
SO1032 Ceramic Tile to Wall 4 25JAN12 29JAN12 10 m2
SO1033 Steps to entrance 6 25JAN12 31JAN12 2 m3
SO1034 Installation of Timber Doors 4 25JAN12 29JAN12 2 no
PAINTING & DECORATING
SO1035 Painting for External walls 12 18JAN12 31JAN12 75 m2
SO1036 Painting for Internal walls 6 30JAN12 05FEB12 90 m2
SO1037 Snagging & Punch Listing 6 06FEB12 12FEB12 1 item
PLUMBING, DRAINAGE & FIRE PROTECTION
SO1038 Installation of Under Ground Drainage Pipes 3 22DEC11 25DEC11 24 m
SO1039 Hot & Cold Water Distribution System 3 16JAN12 18JAN12 32 m
SO1040 Vent Pipe Installation 3 19JAN12 22JAN12 29 m
SO1041 Installation of Isulating Valves & angle valves 6 19JAN12 25JAN12 2 no
SO1042 Installation of CO & Rodding eyes 3 24JAN12 26JAN12 4 no
SO1043 Installation of Water Heater 4 26JAN12 30JAN12 1 no
SO1044 Installation of Sanitary Fixtures 12 06FEB12 19FEB12 5 no
SO1045 Installation of Floor Drains 3 13FEB12 15FEB12 4 no
SO1046 Precommissioning of Plumbing at Security 6 20FEB12 26FEB12 1 item
ELECTRICAL WORKS
SO1047 Installation of Electrical Duct Sleeve 2 22DEC11 24DEC11 40 m
SO1048 Distribution Board enclosure to Wall 6 14JAN12 19JAN12 1 no
SO1051 Wiring,Cable pulling&Termination 7 16JAN12 23JAN12 1 item
SO1049 Elec.,Tel.&FireAlarm Conduiting,Trunking 7 21JAN12 28JAN12 40 m
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Formworks for Security Off. Roof Slab
Rebar for Security Off.Roof Slab
Casting of Security Off. Roof Slab
Construction of Parapet Wall
200mm Solid Blockworks
Blockworks for Security Off.
Plastering for Security Off.
Roof Water Proofing Works
Roof Drain & Rain Water Pipe Installation
Suspended Metal Ceiling
Aluminum Window Installation
Ceramic Tiles to Floor
Ceramic Tile to Wall
Steps to entrance
Installation of Timber Doors
Painting for External walls
Painting for Internal walls
Snagging & Punch Listing
Installation of Under Ground Drainage Pipes
Hot & Cold Water Distribution System
Vent Pipe Installation
Installation of Isulating Valves & angle valves
Installation of CO & Rodding eyes
Installation of Water Heater
Installation of Sanitary Fixtures
Installation of Floor Drains
Precommissioning of Plumbing at Security Off.
Installation of Electrical Duct Sleeve
Distribution Board enclosure to Wall
Wiring,Cable pulling&Termination
Elec.,Tel.&FireAlarm Conduiting,Trunking Works
Sheet 23 of 25
26. Sheet 24 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
SO1050 Installation of DB 6 29JAN12 04FEB12 1 no
SO1052 Installation of Wall Mount Outlet & 3 05FEB12 07FEB12 5 no
SO1054 Installation of Ceiling Lighting Fixtures 3 08FEB12 11FEB12 11 no
SO1055 Fire Alarm System Installtion 3 08FEB12 11FEB12 5 no
SO1056 Tel Data& TV outlet point Installation 3 12FEB12 14FEB12 5 no
SO1057 Precommissioning of Electrical at Security 6 15FEB12 21FEB12 1 item
HVAC WORKS
SO1058 Installation of Flexible pipe & Isulation 3 16JAN12 18JAN12 1 item
SO1059 Installtion of AC wall Accesories & Wirings 3 29JAN12 31JAN12 4 no
SO1060 Installation of Exhaust Fan System 6 01FEB12 07FEB12 4 no
SO1061 Installation of Split AC at Guard Hse 3 08FEB12 11FEB12 4 no
SO1063 Precommissioning of HVAC at Security Off. 6 12FEB12 18FEB12 1 item
FENCING WORKS
CONCRETE FENCE WORKS
SITE PREPARATION, EXCAVATION & EARTHWORKS
FENCING
EXF1000 Excavation 16 20JUN12 08JUL12 518 m3
EXF1010 Disposal of Surplus Excavated Material 6 09JUL12 15JUL12 454 m3
SUBSTRUCTURE WORKS
FENCING
EXF1020 Concrete Blinding 9 01JUL12 10JUL12 81 m3
EXF1030 Waterproofing & Dampproofing 9 04JUL12 14JUL12 539 m2
EXF1040 Rebar for Footings 9 11JUL12 21JUL12 3,604 kg
EXF1050 Formworks for Isolated Footings 9 18JUL12 28JUL12 102 m2
EXF1060 Casting of Footings 6 22JUL12 28JUL12 34 m3
EXF1070 Rebar for Column Shaft 3 23JUL12 25JUL12 424 kg
EXF1080 Formworks for Column Shaft 3 24JUL12 26JUL12 49 m2
EXF1090 Casting for Column Shaft 2 26JUL12 28JUL12 4 m3
EXF1100 Bitumenoues Concrete Protection 6 28JUL12 02AUG12 172 m2
EXF1110 Rebar for Ground Beam 3 29JUL12 31JUL12 1,908 kg
EXF1120 Formworks for Ground Beam 3 01AUG12 04AUG12 172 m2
EXF1130 Casting of Ground Beam 2 05AUG12 06AUG12 18 m3
EXF1140 Backfilling Works 8 08AUG12 16AUG12 64 m3
SUPERSTRUCTURE-CONCRETE WORKS
FENCING
EXF1170 Rebar for Column 6 07AUG12 13AUG12 2,014 kg
EXF1180 Formworks for Column 6 11AUG12 16AUG12 354 m2
EXF1190 Casting for Column 4 15AUG12 19AUG12 19 m3
MASONRY WORKS
FENCING
EXF1230 Blockworks to Wall & Boulder 18 20AUG12 09SEP12 1,411 m2
EXF1240 Plastering for Wall & Boulder 18 22AUG12 11SEP12 1,162 m2
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
Installation of DB
Installation of Wall Mount Outlet & Receptacles
Installation of Ceiling Lighting Fixtures
Fire Alarm System Installtion
Tel Data& TV outlet point Installation
Precommissioning of Electrical at Security Off.
Installation of Flexible pipe & Isulation
Installtion of AC wall Accesories & Wirings
Installation of Exhaust Fan System
Installation of Split AC at Guard Hse
Precommissioning of HVAC at Security Off.
Excavation
Disposal of Surplus Excavated Material
Concrete Blinding
Waterproofing & Dampproofing
Rebar for Footings
Formworks for Isolated Footings
Casting of Footings
Rebar for Column Shaft
Formworks for Column Shaft
Casting for Column Shaft
Bitumenoues Concrete Protection
Rebar for Ground Beam
Formworks for Ground Beam
Casting of Ground Beam
Backfilling Works
Rebar for Column
Formworks for Column
Casting for Column
Blockworks to Wall & Boulder
Plastering for Wall & Boulder
Sheet 24 of 25
27. Sheet 25 of 25
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
QTY UNIT
METAL & ALUMINUM WORKS
FENCING
EXF1270 External Fencing 18 29AUG12 18SEP12 62 m
EXF1271 Steel Gate Installation & Automatic Barrier 18 29AUG12 18SEP12 10 no
PAINTING & DECORATING
FENCING
EXF1290 Painting for External walls 6 12SEP12 18SEP12 1,162 m2
EXF1310 Snagging & Punch Listing 6 19SEP12 25SEP12 1 item
HAND-OVER & CLOSE OUT
CONSTRUCTION OF ZONE 1 BUILDING
PLUMBING, DRAINAGE & FIRE PROTECTION
A01-3000 Final Testing for Plumbing, Fire fighting 12 18AUG12 30AUG12 1 item
ELECTRICAL WORKS
A01-3010 Final Testing for Electrical &Low Current 12 22AUG12 04SEP12 1 item
DEMOBILIZATION & REMOVAL of TEMP. FACILITIES
A01-3020 Demobilization, Punch listing & Clean-up 12 05SEP12 18SEP12 1 item
CONSTRUCTION OF ZONE 2 BUILDING
PLUMBING, DRAINAGE & FIRE PROTECTION
A02-3000 Final Testing for Plumbing, Fire fighting 12 01SEP12 13SEP12 1 item
ELECTRICAL WORKS
A02-3010 Final Testing for Electrical &Low Current 12 05SEP12 18SEP12 1 item
DEMOBILIZATION & REMOVAL of TEMP. FACILITIES
A02-3020 Demobilization, Punch listing & Clean-up 12 19SEP12 02OCT12 1 item
CONSTRUCTION OF ZONE 3 BUILDING
PLUMBING, DRAINAGE & FIRE PROTECTION
A03-2080 Final Testing for Plumbing, Fire fighting 12 19SEP12 02OCT12 1 item
ELECTRICAL WORKS
A03-2090 Final Testing for Electrical &Low Current 12 19SEP12 02OCT12 1 item
DEMOBILIZATION & REMOVAL of TEMP. FACILITIES
A03-2100 Demobilization, Punch listing & Clean-up 12 03OCT12 16OCT12 1 item
2011 2012
A MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT N
External Fencing
Steel Gate Installation & Automatic Barrier
Painting for External walls
Snagging & Punch Listing
Final Testing for Plumbing, Fire fighting system
Final Testing for Electrical &Low Current System
Demobilization, Punch listing & Clean-up
Final Testing for Plumbing, Fire fighting system
Final Testing for Electrical &Low Current System
Demobilization, Punch listing & Clean-up
Final Testing for Plumbing, Fire fighting system
Final Testing for Electrical &Low Current System
Demobilization, Punch listing & Clean-up
Sheet 25 of 25
28. Annexure-1B
MIC BUSINESS & RECREATION COMPLEX
LOCATION & ZONING
MIC BUSINESS & RECREATION COMPLEX- PACKAGE 1
ZONE 3
ZONE 1
ZONE 2
BASEMENT
SWMG. POOL
Page 1 of 1
29. Project Start 1MAY11
Project Finish 31OCT12*
Data Date 1MAY11
Plot Date 13APR11
(c) Primavera Systems, Inc.
Schedule dates
Date ApprovedCheckedRevision
ORIENTAL ENTERPRISES
MIC BUSINESS & RECREATION COMPLEX
OVER ALL PEAK MONTHLY MANPOWER
MC02 Sheet 1 of 1
0
40
80
120
160
200
240
280
MAY
2011
JUN JUL AUG SEP OCT NOV DEC JAN
2012
FEB MAR APR MAY JUN JUL AUG SEP OCT
57
104
132
200
251
249
177
186
189
227
215
167
92
49
43
33
12
132
30. Project Start 1MAY11
Project Finish 31OCT12*
Data Date 1MAY11
Plot Date 13APR11
(c) Primavera Systems, Inc.
Schedule dates
MANPOWER PEAK SUMMARY PROFILE
Date ApprovedCheckedRevision
MIC BUSINESS & RECREATION COMPLEX
ORIENTALS ENTERPRISES
PEAK RESOURCE PROFILE
Sheet 1 of 1
0
20
40
60
80
100
120
140
160
180
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
CIVIL & STRUCTURAL WORKERS
0
2
4
6
8
10
12
14
16
18
20
22
24
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
PLUMBERS
0
4
8
12
16
20
24
28
32
36
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
ELECTRICIANS
0
4
8
12
16
20
24
28
32
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
HVAC INSTALLERS
0
10
20
30
40
50
60
70
80
90
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
SPECIALTY FINISHERS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
MAY
2011
JUL SEP NOV JAN
2012
MAR MAY JUL SEP
Months
PeakMan/Day
LANDSCAPERS & EXTERNAL SERVICES