NESMA Input (Contract/
BOQ/Dwgs. /Others
PROJECT AWARDED SAPMT Input
(WAR / SNS)
Planning Requirements
SCOPE DEFINITION
SCHEDULE DEVELOPMENT RESOURCE & COST PLANNING
PROGRAMME PLANNING DEVELOPMENT
Contract Schedule
Prepared
Project Director
Approval
NO
Submission of Contract Schedule to SAPMT/
KAUST
YES
Programme
Review by
SAPMT
NO
SAPMT Approval
Comments by
SAPMT
Freezing of the Programme
(Contract Schedule /
Baseline)
YES
MONITORING the PERFORMANCE
(Planning/Scheduling Department)
Critical Analysis Forecasting &
Highlighting of Expected and/or Current
Delays
SCOPE CHANGES
Identify Changes
Create Analysis:
Impact of Changes to
Current Baseline
Schedule
Validation of Delays
for Extention of Time
Procedures
Include Changes
Track Changed
Works
Claim Resolution:
Variation Orders
(Cost Claims)
Reconciliation
Change in
Methodology
Addition/Deletion of
Works
Change in Cost
(New Items)
Output from Project Engineers &
Construction Managers:
Current Status of Project
Project Variables
Risk Management
Input /Output from
Subcontractors
Output from Other Departments
Actual Daily Manpower
Time Sheets
Actual Engineering &
Procurement Status
Actual Quantities
Production
Internal Reports &
Preparation of Invoices
Submission to NESMA
External Reports &
Invoicing (Sales Job
Orders)
Submission to SAPMT
Submission of
Subcontract
Agreement to SAPMT
Project Closeout /Lessons
Learned
Coordination &
Inputs from Cost/
Estimation
Department
Prepare New
Schedule
Performance Reporting, Compiling &
Submission (Daily, Weekly & Monthly
External & Internal Reports)
Input /Output from Planning
Department
Progress Summaries
Schedule Updates
Look Ahead Schedule
KEY
Input/output from
Planning Department
Input/output from Other
Department
Input/output from SAPMT
PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES
CONTRACT NO. 66000028921
PROJECT PLANNING FLOW CHART
PROJECT
COMPLETION
Prepared by:
Allan C. Leyte
Lead Scheduling Engineer
NESMA & PARTNERS
APPROVED
BASELINE
SCHEDULE
DESIGN DEVELOPMENT
SUB PROGRAMME
(Drawing & Design
Revisions)
FULL LOADING of
Manpower/Cost to the
Approved Baseline
PROGRESS DATA
GATHERING
PROCUREMENT
SCHEDULE SUB
PROGRAMME (Long Lead
Items, IAP Lead time & Site
Delivery Inspections)
DELAY TRACKING
IMPACT OF
CHANGING
EVENTS
PROGRESS
MONITORING
PROGRESS
REPORTING
SITE
INSTRUCTIONS
VARIATION ORDERS
INTEGRATION TO
APPROVED BASELINE
SUBMISSION OF FULL
RESOURCE LOADING ON
APPROVED BASELINE
SUBMISSION OF AGREED
REPORTING FORMAT
SUBMISSION OF DAILY,
WEEKLY& MONTHLY
PROGRESS REPORT
SUBMISSION OF DELAY
NARRATIVE REPORTS,
CATCH-UP SCHEDULE
PLAN & IMPACT ANALYSIS
DELAY &
DISTRUPTION
PROTOCOL
ANALYSIS
SUBMISSION OF REVISED
SCHEDULE AND/OR
EXTENSION OF TIME
PROCEDURES
SUBMISSION OF COST
CLAIM & RESOLUTION
PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES
CONTRACT NO. 66000028921
CONSTRUCTION SCHEDULING DEVELOPMENT
SCHEDULING PROCESS
*MINIMUM LEVEL OF REQUIREMENTS
INPUT OUTPUT
PLAN ORGANIZE COMMUNICATE
Prepared by:
Allan C. Leyte
Lead Scheduling Engineer
NESMA & PARTNERS
PLANNING & SCHEDULING
SCHEDULINGPLANNING
INPUT
CONTRACT DOCUMENTS
(CONTRACT, DRAWING &
OTHERS)
SAPMT/CONSULTANT
(WAR, SNS, EIL)
CONSTRUCTIBILITY
ANALYSIS
METHOD
STATEMENT
PROJECT
EXECUTION PLAN
From CONSTRUCTION/
OPERATION DEPARTMENT
FORENSIC SITE
INVESTIGATION &
ANALYSIS
From QUANTITY SURVEY
DEPARTMENT
BILL OF QUANTITIES
From ESTIMATION/COST
ENGINEERING
DEPARTMENT
BALANCING of
PROJECT
CONSTRAINTS
SCOPE
RESOURCES
VALUE
ENGINEERING
OPTIMIZE SCHEDULE
OPTIMIZE QUALITY
STAKEHOLDERS
CLIENTS (SAPMT &
KAUST)
NESMA PROJECT
MANAGEMENT TEAM
CONSULTANTS & 3rd
PARTY INSPECTORS
SUBCONS & SUPPLIERS
PROJECT
VARIABLES
PHYSICAL SITE
CONDITION
CONSTRUCTION
METHODOLOGIES
FUNDINGS
LABOR & EQUIPMENT
AGREEMENTS
MATERIAL DELIVERY &
STORAGE
OUTPUT/
DELIVERABLES
SCHEDULE SCOPE OF WORK
WORKBREAKDOWN
STRUCTURE
DEFINED PROJECT GOAL
PERIODIC FORECAST
INPUT
SCHEDULE SCOPE OF
WORK
WORKBREAKDOWN
STRUCTURE
SCHEDULING
SPECIFICATIONS From
SAPTMT
COST ESTIMATES & BILL
OF QUANTITIES
CREATING
SCHEDULE
ACTIVITY DEFINITIONS
DURATIONS
WBS
CALENDARS
CODINGS
CREATING RELATIONSHIP
LOGIC TIE
QUALITY ANALYSIS
MILESTONES &
COMPLIANCE
RELATIONSHIPS
COST/RESOURCES LOADING
RESOURCE FLOW
CASH FLOW
LEAD/LAG TIME
CONSTRAINTS
MAINTAINING
SCHEDULE OUTPUT
TRACKING PROGRESS
RECORD INPUT & LOGIC
CHANGES
ACTUAL UPDATES
CHANGE MANAGEMENT
IDENTIFY CHANGES
INCLUDE CHANGES
TRACK CHANGES
SCHEDULE ACCELERATION
CHANGES IN METHODS
CHANGES IN DURATIONS
WHAT IF PROCEDURES
SEEKING FEEDBACK
PROJECT REVIEW
CLIENTS OVERVIEW OF
THE PROJECT
ACTUAL SITE
PERFORMANCE
PERFORMANCE TRACKING
SCHEDULE
PERFORMANCE
EARNED VALUE
CONTROL LEVEL
SCHEDULES
PROGRESS REPORTING
CRITICAL PATH ANALYSIS
FORECASTS
MANAGEMENT SUMMARIES
RECOVERY PLAN (IN CASE
OF SLIPPAGES)
EXTENSION OF TIME
PROCEDURES
IMPACT OF
CHANGING EVENTS
SITE INSTRUCTIONS
VARIATION ORDERS
PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES
CONTRACT NO. 66000028921
BASELINE PLAN (CLAUSE
14.1 PROGRAMME)
Prepared by:
Allan C. Leyte
Lead Scheduling Engineer
NESMA & PARTNERS

Más contenido relacionado

La actualidad más candente

BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
Russell and Dawson
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
Duncan Smith
 

La actualidad más candente (20)

BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
 
Construction Design And Management Regulations (Cdm2007) Presentation
Construction Design And Management Regulations (Cdm2007) PresentationConstruction Design And Management Regulations (Cdm2007) Presentation
Construction Design And Management Regulations (Cdm2007) Presentation
 
MTECH BIM project case study
MTECH BIM project case studyMTECH BIM project case study
MTECH BIM project case study
 
BIM Execution Plan (BXP)- What, Why, When and How
BIM Execution Plan (BXP)- What, Why, When and HowBIM Execution Plan (BXP)- What, Why, When and How
BIM Execution Plan (BXP)- What, Why, When and How
 
BIM Execution plan
BIM  Execution  planBIM  Execution  plan
BIM Execution plan
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
Revit Keyboard Shortcuts .pdf
Revit Keyboard Shortcuts .pdfRevit Keyboard Shortcuts .pdf
Revit Keyboard Shortcuts .pdf
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Price adjustment and escalation
Price adjustment and escalationPrice adjustment and escalation
Price adjustment and escalation
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained  Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 

Destacado

PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
Allan Leyte
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Allan Leyte
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
Harish Mahavar
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
Dexter Ng
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
Hamdija Velagic
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
Soh Shing
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 

Destacado (20)

PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Business Plan of Smoothy Juice Company
Business Plan of Smoothy Juice CompanyBusiness Plan of Smoothy Juice Company
Business Plan of Smoothy Juice Company
 
Project on construction of 3 block house report
Project on construction of 3 block house reportProject on construction of 3 block house report
Project on construction of 3 block house report
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project report
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Building services
Building servicesBuilding services
Building services
 
PMBOK fifth edition data flow diagram by english
PMBOK fifth edition data flow diagram by englishPMBOK fifth edition data flow diagram by english
PMBOK fifth edition data flow diagram by english
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Similar a Visio-Planning FlowChart-3

Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
Nermeen gerges
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning Engineer
MD TAUSIF ASLAM
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
Sankar Sundaram PMP
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
Goutama Bachtiar
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)
ngiyari
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
Dwayne Davis
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
Sajith Nair
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17
Deborah Hines
 
Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4
mrbaseball
 

Similar a Visio-Planning FlowChart-3 (20)

Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning Engineer
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Project controls function
Project controls functionProject controls function
Project controls function
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)
 
RINAL_PATEL
RINAL_PATELRINAL_PATEL
RINAL_PATEL
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
 
Vignesh Nagarajan CV
Vignesh Nagarajan CVVignesh Nagarajan CV
Vignesh Nagarajan CV
 
Brian Nicholls resume 2016-08-11
Brian Nicholls resume   2016-08-11Brian Nicholls resume   2016-08-11
Brian Nicholls resume 2016-08-11
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
JakeA_resume Oct14
JakeA_resume Oct14JakeA_resume Oct14
JakeA_resume Oct14
 
DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17 DHines Planner Scheduler Materials 3-1-17
DHines Planner Scheduler Materials 3-1-17
 
CV Asif Rashid
CV Asif Rashid CV Asif Rashid
CV Asif Rashid
 
Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4
 

Más de Allan Leyte

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
Allan Leyte
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
Allan Leyte
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
Allan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
Allan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
Allan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
Allan Leyte
 

Más de Allan Leyte (16)

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Wreport
WreportWreport
Wreport
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

Visio-Planning FlowChart-3

  • 1. NESMA Input (Contract/ BOQ/Dwgs. /Others PROJECT AWARDED SAPMT Input (WAR / SNS) Planning Requirements SCOPE DEFINITION SCHEDULE DEVELOPMENT RESOURCE & COST PLANNING PROGRAMME PLANNING DEVELOPMENT Contract Schedule Prepared Project Director Approval NO Submission of Contract Schedule to SAPMT/ KAUST YES Programme Review by SAPMT NO SAPMT Approval Comments by SAPMT Freezing of the Programme (Contract Schedule / Baseline) YES MONITORING the PERFORMANCE (Planning/Scheduling Department) Critical Analysis Forecasting & Highlighting of Expected and/or Current Delays SCOPE CHANGES Identify Changes Create Analysis: Impact of Changes to Current Baseline Schedule Validation of Delays for Extention of Time Procedures Include Changes Track Changed Works Claim Resolution: Variation Orders (Cost Claims) Reconciliation Change in Methodology Addition/Deletion of Works Change in Cost (New Items) Output from Project Engineers & Construction Managers: Current Status of Project Project Variables Risk Management Input /Output from Subcontractors Output from Other Departments Actual Daily Manpower Time Sheets Actual Engineering & Procurement Status Actual Quantities Production Internal Reports & Preparation of Invoices Submission to NESMA External Reports & Invoicing (Sales Job Orders) Submission to SAPMT Submission of Subcontract Agreement to SAPMT Project Closeout /Lessons Learned Coordination & Inputs from Cost/ Estimation Department Prepare New Schedule Performance Reporting, Compiling & Submission (Daily, Weekly & Monthly External & Internal Reports) Input /Output from Planning Department Progress Summaries Schedule Updates Look Ahead Schedule KEY Input/output from Planning Department Input/output from Other Department Input/output from SAPMT PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES CONTRACT NO. 66000028921 PROJECT PLANNING FLOW CHART PROJECT COMPLETION Prepared by: Allan C. Leyte Lead Scheduling Engineer NESMA & PARTNERS
  • 2. APPROVED BASELINE SCHEDULE DESIGN DEVELOPMENT SUB PROGRAMME (Drawing & Design Revisions) FULL LOADING of Manpower/Cost to the Approved Baseline PROGRESS DATA GATHERING PROCUREMENT SCHEDULE SUB PROGRAMME (Long Lead Items, IAP Lead time & Site Delivery Inspections) DELAY TRACKING IMPACT OF CHANGING EVENTS PROGRESS MONITORING PROGRESS REPORTING SITE INSTRUCTIONS VARIATION ORDERS INTEGRATION TO APPROVED BASELINE SUBMISSION OF FULL RESOURCE LOADING ON APPROVED BASELINE SUBMISSION OF AGREED REPORTING FORMAT SUBMISSION OF DAILY, WEEKLY& MONTHLY PROGRESS REPORT SUBMISSION OF DELAY NARRATIVE REPORTS, CATCH-UP SCHEDULE PLAN & IMPACT ANALYSIS DELAY & DISTRUPTION PROTOCOL ANALYSIS SUBMISSION OF REVISED SCHEDULE AND/OR EXTENSION OF TIME PROCEDURES SUBMISSION OF COST CLAIM & RESOLUTION PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES CONTRACT NO. 66000028921 CONSTRUCTION SCHEDULING DEVELOPMENT SCHEDULING PROCESS *MINIMUM LEVEL OF REQUIREMENTS INPUT OUTPUT PLAN ORGANIZE COMMUNICATE Prepared by: Allan C. Leyte Lead Scheduling Engineer NESMA & PARTNERS
  • 3. PLANNING & SCHEDULING SCHEDULINGPLANNING INPUT CONTRACT DOCUMENTS (CONTRACT, DRAWING & OTHERS) SAPMT/CONSULTANT (WAR, SNS, EIL) CONSTRUCTIBILITY ANALYSIS METHOD STATEMENT PROJECT EXECUTION PLAN From CONSTRUCTION/ OPERATION DEPARTMENT FORENSIC SITE INVESTIGATION & ANALYSIS From QUANTITY SURVEY DEPARTMENT BILL OF QUANTITIES From ESTIMATION/COST ENGINEERING DEPARTMENT BALANCING of PROJECT CONSTRAINTS SCOPE RESOURCES VALUE ENGINEERING OPTIMIZE SCHEDULE OPTIMIZE QUALITY STAKEHOLDERS CLIENTS (SAPMT & KAUST) NESMA PROJECT MANAGEMENT TEAM CONSULTANTS & 3rd PARTY INSPECTORS SUBCONS & SUPPLIERS PROJECT VARIABLES PHYSICAL SITE CONDITION CONSTRUCTION METHODOLOGIES FUNDINGS LABOR & EQUIPMENT AGREEMENTS MATERIAL DELIVERY & STORAGE OUTPUT/ DELIVERABLES SCHEDULE SCOPE OF WORK WORKBREAKDOWN STRUCTURE DEFINED PROJECT GOAL PERIODIC FORECAST INPUT SCHEDULE SCOPE OF WORK WORKBREAKDOWN STRUCTURE SCHEDULING SPECIFICATIONS From SAPTMT COST ESTIMATES & BILL OF QUANTITIES CREATING SCHEDULE ACTIVITY DEFINITIONS DURATIONS WBS CALENDARS CODINGS CREATING RELATIONSHIP LOGIC TIE QUALITY ANALYSIS MILESTONES & COMPLIANCE RELATIONSHIPS COST/RESOURCES LOADING RESOURCE FLOW CASH FLOW LEAD/LAG TIME CONSTRAINTS MAINTAINING SCHEDULE OUTPUT TRACKING PROGRESS RECORD INPUT & LOGIC CHANGES ACTUAL UPDATES CHANGE MANAGEMENT IDENTIFY CHANGES INCLUDE CHANGES TRACK CHANGES SCHEDULE ACCELERATION CHANGES IN METHODS CHANGES IN DURATIONS WHAT IF PROCEDURES SEEKING FEEDBACK PROJECT REVIEW CLIENTS OVERVIEW OF THE PROJECT ACTUAL SITE PERFORMANCE PERFORMANCE TRACKING SCHEDULE PERFORMANCE EARNED VALUE CONTROL LEVEL SCHEDULES PROGRESS REPORTING CRITICAL PATH ANALYSIS FORECASTS MANAGEMENT SUMMARIES RECOVERY PLAN (IN CASE OF SLIPPAGES) EXTENSION OF TIME PROCEDURES IMPACT OF CHANGING EVENTS SITE INSTRUCTIONS VARIATION ORDERS PROJECT: KAUST ARAMCO GENERAL CONSTRUCTION SERVICES CONTRACT NO. 66000028921 BASELINE PLAN (CLAUSE 14.1 PROGRAMME) Prepared by: Allan C. Leyte Lead Scheduling Engineer NESMA & PARTNERS