SlideShare una empresa de Scribd logo
1 de 37
O
Op
pe
e a
a o
on
ns
s M
Ma
an
na
ag
ge
em
me
en
n
Project Management
Chapter 9
•Project Planning
•Project Scheduling
•Project Control
•CPM/PERT
•Probabilistic Activity Times
•Microsoft Project
• Project Crashing and Time-Cost
Trade-off
9-451
Lecture Outline
Project Management Process
9-453
Project Management Pr
(cont.)
• Objective
• Scope
• Contract requirements
• Schedules
• Resources
• Personnel
• Control
• Risk and problem analysis
9-455
Project Elements
Project Team and Project Manager
• Project team
• made up of individuals from various areas and
departments within a company
• Matrix organization
• a team structure with members from functional
areas, depending on skills required
• Project manager
• most important member of project team
9-456
Project Team and Proje
Scope Statement and Work
•Scope statement
• a document that provides an understanding,
justification, and expected result of a project
•Statement of work
• written description of objectives of a project
•Work breakdown structure (WBS)
• breaks down a project into components,
subcomponents, activities, and tasks
9-457
Scope Statement and
Breakdown Structure
•Steps
• Define activities
• Sequence
• Techniques
Gantt chart
CPM/PERT
•
•
activities
• Estimate
Microsoft Project
•
time
• Develop schedule
9-461
Project Scheduling
• Graph or bar chart with a bar for each
project activity that shows passage of
time
• Provides visual display of project
schedule
• Slack
• amount of time an activity can be delayed
without delaying the project
9-462
Gantt Chart
• Time management
• Cost management
• Quality management
• Performance management
• Earned Value Analysis
• a standard procedure for numerically measuring a
project’s progress, forecasting its completion date and
cost and measuring schedule and budget variation
• Communication
• Enterprise project management
9-464
Project Control
• Critical Path Method (CPM)
• DuPont & Remington-Rand (1956)
• Deterministic task times
• Activity-on-node network construction
• Project Evaluation and Review Technique
(PERT)
• US Navy, Booz, Allen & Hamilton
• Multiple task time estimates; probabilistic
• Activity-on-arrow network construction
9-465
CPM/PERT
• Activity-on-node (AON)
• nodes represent activities,
and arrows show
precedence relationships
Activity-on-arrow (AOA)
•
• arrows represent activities
and nodes are events for
points in time
Event
• completion or beginning
of an activity in a project
Dummy
• two or more activities
cannot share same start
and end nodes
•
•
9-466
Node
1 2 3
Branch
Project Network
AOA Project Network for
Lay Dummy
house work
3 1
Design house Order and
financing materials paint carpet
9-467
3
foundation
2 0 Build Finish
1 2 4 3
6 1
7
and obtain receive Select 1 1 Select
5
AOA Project Network
a House
Concurrent Activities
Lay
Dummy
2 0
2 3
2 4
Order material
9-468
Lay foundation 3
foundation
1
Order material
(a) Incorrect precedence (b) Correct precedence
relationship relationship
Concurrent Activiti
AON Network for House
Finish work
3
2
1 1
and obtain
5 1
Select carpet
1
1
Select paint
materials
9-469
Start
Lay foundations Build house
2 4
7
3
Design house
3 6
financing
Order and receive
AON Network for H
Building Project
4
2
1 1
5 1
1
3 + 2 + 3 + 1 = 9 months
through a network
3 + 2 + 1 + 1 + 1 = 8 months
3 + 1 + 3 + 1 = 8 months
completion time
3 + 1 + 1 + 1 + 1 = 7 months
9-470
Start
Critical Path
2 3
7
3
3 6
1
A: 1-2-4-7 • Critical path
B: 1-2-5-6-7 • Longest path
C: 1-3-4-7 • Minimum project
D: 1-3-5-6-7
Finish at 9 months
3
2
1 1
5 1
1
Start at 3 months
9-471
Start
Start at 5 months
2 4
7 Finish
3
3 6
1 Start at 6 months
Activity Start Times
• Earliest start time (ES)
• earliest time an activity can start
• ES = maximum EF of immediate predecessors
Forward pass
•
• starts at beginning of CPM/PERT network
determine earliest activity times
Earliest finish time (EF)
• earliest time an activity can finish
• earliest start time plus activity time
• EF= ES + t
to
•
9-473
Activity Scheduling
Activity Scheduling (cont.)
• Latest start time (LS)
• Latest time an activity can start without delaying
critical path time
• LS= LF - t
• Latest finish time (LF)
• latest time an activity can be completed without
delaying critical path time
• LF = minimum LS of immediate predecessors
Backward pass
• Determines latest activity times by starting at the
of CPM/PERT network and working forward
•
end
9-475
Activity Scheduling (
timates
• Beta distribution
• a probability distribution traditionally used in
CPM/PERT
Mean (expected time): t =
b - a
6
9-478
a + 4m + b
6
2
Variance: 2 =
where
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate
Probabilistic Time Es
Equipment testing
installation
1 4
debugging
training
development
Manual 1,4,7
2 3,7,11
Start
System
changeover
3 6 System
9-480
Project Network with Probabilistic
Time Estimates: Example
Equipment
and modification
6,8,10 2,4,12 System Final
System
8 10
testing
3,6,9
5 11
Finish
Position 2,3,4 9 1,10,13
recruiting
Job Training 2,4,6
1,3,5 3,4,5 testing
Orientation
7
2,2,2
Activity Time Estimates
2 3 6 9 6 1.00
11 1 10 13 9 4.00
9-481
TIME ESTIMA
TES (WKS) MEAN TIME VARIANCE
ACTIVITY a m b t б2
1 6 8 10 8 0.44
3 1 3 5 3 0.44
4 2 4 12 5 2.78
5 2 3 4 3 0.11
6 3 4 5 4 0.11
7 2 2 2 2 0.00
8 3 7 11 7 1.78
9 2 4 6 4 0.44
10 1 4 7 4 1.00
Activity Time Estim
11 9 4.00 16 25 16 25 0
9-482
Activity Early, Late Times,
and Slack
ACTIVITY t б ES EF LS LF S
1 8 0.44 0 8 1 9 1
2 6 1.00 0 6 0 6 0
3 3 0.44 0 3 2 5 2
4 5 2.78 8 13 16 21 8
5 3 0.11 6 9 6 9 0
6 4 0.11 3 7 5 9 2
7 2 0.00 3 5 14 16 11
8 7 1.78 9 16 9 16 0
9 4 0.44 9 13 12 16 3
10 4 1.00 13 17 21 25 8
6
9-483
4 12 16
9 16 25
Earliest, Latest, and Slack
1 0 8 4 8 13
8 1 9 5 16 21
Critical Path
10 13 17
8 9 16
1 0 3
Start 2 0 6 Finish
7 9 16
0 6
5 6 9 11 16 25
3 0 3
3 2 5
3 6 9 9 9 13
6 3 7
4 5 9
7 3 5
2 14 16
2 б2
2 + б5
2 б8
2 б11
2
= + +
9-484
Total project variance
= 1.00 + 0.11 + 1.78 + 4.00
= 6.89 weeks
Z =
9-486
Probabilistic Network Analysis
Determine probability that project is
completed within specified time
x -
where
= tp = project mean time
= project standard deviation
x = proposed project time
Z = number of standard deviations x
is from mean
• Crashing
• reducing project time by expending additional
resources
• Crash time
• an amount of time an activity is reduced
• Crash cost
• cost of reducing activity time
• Goal
• reduce project duration at minimum cost
9-500
Project Crashing
Project Network for Building
12
8
1 4
5 4
4
9-501
2 4
7
12
3 6
4
Project Network for
a House
Crash cost
Slope = crash cost per week
$3,000 –
–
9-502
Normal Time and Cost
vs. Crash Time and Cost
$7,000 –
$6,000 –
$5,000 – Crashed activity
$4,000 –
Normal activity
Normal cost
$2,000 –
$1,000 – Crash time Normal time
| | | | | | |
0 2 4 6 8 10 12 14 Weeks
ple
$75,000 $110,700
9-503
TOTAL
NORMAL CRASH ALLOWABLE CRASH
TIME TIME NORMAL CRASH CRASH TIME COST PER
ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK
1 12 7 $3,000 $5,000 5 $400
2 8 5 2,000 3,500 3 500
3 4 3 4,000 7,000 1 3,000
4 12 9 50,000 71,000 3 7,000
5 4 1 500 1,100 3 200
6 4 1 500 1,100 3 200
7 4 3 15,000 22,000 1 7,000
Project Crashing: Exam
36 weeks
$700
12
8
$3000
$200
$7000
$500
$700
12
8
7
31 weeks
$2000
9-504
$500 $7000
2 4
7
1 4
12
$400 3 6
4 5 4
4 $200
Project Duration:
FROM …
TO…
2 4
7
1 4
$400 3 6
4 5 4
4 $200
$3000
$200
Project Duration:
Additional Cost:
Time-Cost Relationship
• Crashing costs increase as project
duration decreases
• Indirect costs increase as project
duration increases
• Reduce project length as long as
crashing costs are less than indirect
costs
9-505
Time-Cost Relation
Total project cost
9-506
Cost
($)
Time-Cost Tradeoff
Minimum cost = optimal project time
Indirect cost
Direct cost
Crashing Time
Project duration

Más contenido relacionado

Similar a Aminullah Assagaf_P7-Ch.9_Project management-32.pptx

chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsGovadaDhana
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...Siddharth Modi
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 

Similar a Aminullah Assagaf_P7-Ch.9_Project management-32.pptx (20)

chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Network scheduling
Network scheduling Network scheduling
Network scheduling
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Schedule Training
Schedule TrainingSchedule Training
Schedule Training
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
 
C10 project management
C10 project managementC10 project management
C10 project management
 
C10 project management
C10 project managementC10 project management
C10 project management
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 

Más de Aminullah Assagaf

Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf
 
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf
 
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf
 
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf
 
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf
 
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf
 
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf
 
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf
 
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptx
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptxAminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptx
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptxAminullah Assagaf
 

Más de Aminullah Assagaf (20)

Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pptx
 
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 22_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdfAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pdf
 
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptxAminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
Aminullah Assagaf_Regresi Lengkap 21_11 April 2024.pptx
 
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
Aminullah Assagaf_Regresi Lengkap 20_10 April 2024_Inc. Data panel & Perbandi...
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
 
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
Aminullah Assagaf_Regresi Lengkap 19_8 Nov 2023_Inc. Data panel & Perbandinga...
 
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K12-14_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K10-11_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.pptAminullah Assagaf_K6-7_29 Oktober 2024.ppt
Aminullah Assagaf_K6-7_29 Oktober 2024.ppt
 
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K8-9_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].pptAminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
Aminullah Assagaf_K4-5_Manj Oprs dan Prod_2021 [Autosaved].ppt
 
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.pptAminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
Aminullah Assagaf_K1-3_Manj Oprs dan Prod_2024.ppt
 
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptxAminullah Assagaf_P6-Ch.8_Human resources-32.pptx
Aminullah Assagaf_P6-Ch.8_Human resources-32.pptx
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
 
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptxAminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
Aminullah Assagaf_P4-Ch.6_Processes and technology-32.pptx
 
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptxAminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
Aminullah Assagaf_P3-Ch.4-5_Product Design & Srvice Design.pptx
 
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptxAminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
Aminullah Assagaf_P2-Ch.2-3_Operations Strategy & Qualittty Mangt.pptx
 
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptx
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptxAminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptx
Aminullah Assagaf_P1-Ch.1_ Introduction & Suppl Ch Mng_32.pptx
 

Último

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 

Último (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 

Aminullah Assagaf_P7-Ch.9_Project management-32.pptx

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.
  • 6. O Op pe e a a o on ns s M Ma an na ag ge em me en n Project Management Chapter 9
  • 7. •Project Planning •Project Scheduling •Project Control •CPM/PERT •Probabilistic Activity Times •Microsoft Project • Project Crashing and Time-Cost Trade-off 9-451 Lecture Outline
  • 9. • Objective • Scope • Contract requirements • Schedules • Resources • Personnel • Control • Risk and problem analysis 9-455 Project Elements
  • 10. Project Team and Project Manager • Project team • made up of individuals from various areas and departments within a company • Matrix organization • a team structure with members from functional areas, depending on skills required • Project manager • most important member of project team 9-456 Project Team and Proje
  • 11. Scope Statement and Work •Scope statement • a document that provides an understanding, justification, and expected result of a project •Statement of work • written description of objectives of a project •Work breakdown structure (WBS) • breaks down a project into components, subcomponents, activities, and tasks 9-457 Scope Statement and Breakdown Structure
  • 12. •Steps • Define activities • Sequence • Techniques Gantt chart CPM/PERT • • activities • Estimate Microsoft Project • time • Develop schedule 9-461 Project Scheduling
  • 13. • Graph or bar chart with a bar for each project activity that shows passage of time • Provides visual display of project schedule • Slack • amount of time an activity can be delayed without delaying the project 9-462 Gantt Chart
  • 14. • Time management • Cost management • Quality management • Performance management • Earned Value Analysis • a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation • Communication • Enterprise project management 9-464 Project Control
  • 15. • Critical Path Method (CPM) • DuPont & Remington-Rand (1956) • Deterministic task times • Activity-on-node network construction • Project Evaluation and Review Technique (PERT) • US Navy, Booz, Allen & Hamilton • Multiple task time estimates; probabilistic • Activity-on-arrow network construction 9-465 CPM/PERT
  • 16. • Activity-on-node (AON) • nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) • • arrows represent activities and nodes are events for points in time Event • completion or beginning of an activity in a project Dummy • two or more activities cannot share same start and end nodes • • 9-466 Node 1 2 3 Branch Project Network
  • 17. AOA Project Network for Lay Dummy house work 3 1 Design house Order and financing materials paint carpet 9-467 3 foundation 2 0 Build Finish 1 2 4 3 6 1 7 and obtain receive Select 1 1 Select 5 AOA Project Network a House
  • 18. Concurrent Activities Lay Dummy 2 0 2 3 2 4 Order material 9-468 Lay foundation 3 foundation 1 Order material (a) Incorrect precedence (b) Correct precedence relationship relationship Concurrent Activiti
  • 19. AON Network for House Finish work 3 2 1 1 and obtain 5 1 Select carpet 1 1 Select paint materials 9-469 Start Lay foundations Build house 2 4 7 3 Design house 3 6 financing Order and receive AON Network for H Building Project
  • 20. 4 2 1 1 5 1 1 3 + 2 + 3 + 1 = 9 months through a network 3 + 2 + 1 + 1 + 1 = 8 months 3 + 1 + 3 + 1 = 8 months completion time 3 + 1 + 1 + 1 + 1 = 7 months 9-470 Start Critical Path 2 3 7 3 3 6 1 A: 1-2-4-7 • Critical path B: 1-2-5-6-7 • Longest path C: 1-3-4-7 • Minimum project D: 1-3-5-6-7
  • 21. Finish at 9 months 3 2 1 1 5 1 1 Start at 3 months 9-471 Start Start at 5 months 2 4 7 Finish 3 3 6 1 Start at 6 months Activity Start Times
  • 22. • Earliest start time (ES) • earliest time an activity can start • ES = maximum EF of immediate predecessors Forward pass • • starts at beginning of CPM/PERT network determine earliest activity times Earliest finish time (EF) • earliest time an activity can finish • earliest start time plus activity time • EF= ES + t to • 9-473 Activity Scheduling
  • 23. Activity Scheduling (cont.) • Latest start time (LS) • Latest time an activity can start without delaying critical path time • LS= LF - t • Latest finish time (LF) • latest time an activity can be completed without delaying critical path time • LF = minimum LS of immediate predecessors Backward pass • Determines latest activity times by starting at the of CPM/PERT network and working forward • end 9-475 Activity Scheduling (
  • 24. timates • Beta distribution • a probability distribution traditionally used in CPM/PERT Mean (expected time): t = b - a 6 9-478 a + 4m + b 6 2 Variance: 2 = where a = optimistic estimate m = most likely time estimate b = pessimistic time estimate Probabilistic Time Es
  • 25. Equipment testing installation 1 4 debugging training development Manual 1,4,7 2 3,7,11 Start System changeover 3 6 System 9-480 Project Network with Probabilistic Time Estimates: Example Equipment and modification 6,8,10 2,4,12 System Final System 8 10 testing 3,6,9 5 11 Finish Position 2,3,4 9 1,10,13 recruiting Job Training 2,4,6 1,3,5 3,4,5 testing Orientation 7 2,2,2
  • 26. Activity Time Estimates 2 3 6 9 6 1.00 11 1 10 13 9 4.00 9-481 TIME ESTIMA TES (WKS) MEAN TIME VARIANCE ACTIVITY a m b t б2 1 6 8 10 8 0.44 3 1 3 5 3 0.44 4 2 4 12 5 2.78 5 2 3 4 3 0.11 6 3 4 5 4 0.11 7 2 2 2 2 0.00 8 3 7 11 7 1.78 9 2 4 6 4 0.44 10 1 4 7 4 1.00 Activity Time Estim
  • 27. 11 9 4.00 16 25 16 25 0 9-482 Activity Early, Late Times, and Slack ACTIVITY t б ES EF LS LF S 1 8 0.44 0 8 1 9 1 2 6 1.00 0 6 0 6 0 3 3 0.44 0 3 2 5 2 4 5 2.78 8 13 16 21 8 5 3 0.11 6 9 6 9 0 6 4 0.11 3 7 5 9 2 7 2 0.00 3 5 14 16 11 8 7 1.78 9 16 9 16 0 9 4 0.44 9 13 12 16 3 10 4 1.00 13 17 21 25 8
  • 28. 6 9-483 4 12 16 9 16 25 Earliest, Latest, and Slack 1 0 8 4 8 13 8 1 9 5 16 21 Critical Path 10 13 17 8 9 16 1 0 3 Start 2 0 6 Finish 7 9 16 0 6 5 6 9 11 16 25 3 0 3 3 2 5 3 6 9 9 9 13 6 3 7 4 5 9 7 3 5 2 14 16
  • 29. 2 б2 2 + б5 2 б8 2 б11 2 = + + 9-484 Total project variance = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks
  • 30. Z = 9-486 Probabilistic Network Analysis Determine probability that project is completed within specified time x - where = tp = project mean time = project standard deviation x = proposed project time Z = number of standard deviations x is from mean
  • 31. • Crashing • reducing project time by expending additional resources • Crash time • an amount of time an activity is reduced • Crash cost • cost of reducing activity time • Goal • reduce project duration at minimum cost 9-500 Project Crashing
  • 32. Project Network for Building 12 8 1 4 5 4 4 9-501 2 4 7 12 3 6 4 Project Network for a House
  • 33. Crash cost Slope = crash cost per week $3,000 – – 9-502 Normal Time and Cost vs. Crash Time and Cost $7,000 – $6,000 – $5,000 – Crashed activity $4,000 – Normal activity Normal cost $2,000 – $1,000 – Crash time Normal time | | | | | | | 0 2 4 6 8 10 12 14 Weeks
  • 34. ple $75,000 $110,700 9-503 TOTAL NORMAL CRASH ALLOWABLE CRASH TIME TIME NORMAL CRASH CRASH TIME COST PER ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK 1 12 7 $3,000 $5,000 5 $400 2 8 5 2,000 3,500 3 500 3 4 3 4,000 7,000 1 3,000 4 12 9 50,000 71,000 3 7,000 5 4 1 500 1,100 3 200 6 4 1 500 1,100 3 200 7 4 3 15,000 22,000 1 7,000 Project Crashing: Exam
  • 35. 36 weeks $700 12 8 $3000 $200 $7000 $500 $700 12 8 7 31 weeks $2000 9-504 $500 $7000 2 4 7 1 4 12 $400 3 6 4 5 4 4 $200 Project Duration: FROM … TO… 2 4 7 1 4 $400 3 6 4 5 4 4 $200 $3000 $200 Project Duration: Additional Cost:
  • 36. Time-Cost Relationship • Crashing costs increase as project duration decreases • Indirect costs increase as project duration increases • Reduce project length as long as crashing costs are less than indirect costs 9-505 Time-Cost Relation
  • 37. Total project cost 9-506 Cost ($) Time-Cost Tradeoff Minimum cost = optimal project time Indirect cost Direct cost Crashing Time Project duration